Road Name: Barack Obama Road Layer Tested :Fill, First Layer Testing Date: 11/18/2019
Location:0+020 - 0+080km, LHS & RHS Material Source : Bunju A Samped & Tested by: Jointly
Contractor Consultant
Tested by: Checked by: Approved by:
Signature: Signature: Signature
Date: Date: Date:
Contractor Consultant
CONSTRUCTION OF NEW SELANDER BRIDGE AND ITS
GS Engineering and CONNECTING ROADS Yooshin Engineering
Construction Corporation Cooperation In
Association with Afrisa
Contr.No. TRD/HQ/1007/2018/19
Contractor Consultant
Tested by: Checked by: Approved by:
Signature: Signature: Signature
Date: Date: Date: