You are on page 1of 276

Rate_Analysis_Dhanusha_Civil_2075/076 Page 1 of 276

A - SITE PREPARATION WORK

Cutting of tree, branch & log etc. (12-30 cm. girth above
1.01 A1 (1-1A) 1.00 mtr. From G.L.) with lead upto 15 mtr. Nos. 78.00 89.70
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.130 Nos. 600.00 78.00
Total 78.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 11.70
Grand Total 89.70

Cutting of tree, branch & log etc. (31-60 cm. girth above
1.02 A1 (1-1B) 1.00 mtr. From G.L.) with lead upto 15 mtr. Nos. 234.00 269.10
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.390 Nos. 600.00 234.00
Total 234.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 35.10
Grand Total 269.10

Cutting of tree, branch & log etc. (61-120 cm. girth above
1.03 A1 (1-1C) 1.00 mtr. From G.L.) with lead upto 15 mtr. Nos. 588.00 676.20
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.980 Nos. 600.00 588.00
Total 588.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 88.20
Grand Total 676.20

Removing of tree root (12-30 cm. girth above 1.00 mtr.


1.04 A2 (1-2A) From G.L.) with lead upto 15 mtr. Nos. 240.00 276.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.400 Nos. 600.00 240.00
Total 240.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 36.00
Grand Total 276.00

Removing of tree root (31-60 cm. girth above 1.00 mtr.


1.05 A2 (1-2B) From G.L.) with lead upto 15 mtr. Nos. 318.00 365.70

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.530 Nos. 600.00 318.00
Total 318.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 47.70
Grand Total 365.70

Removing of tree root (61-120 cm. girth above 1.00 mtr.


1.06 A2 (1-2C) From G.L.) with lead upto 15 mtr. Nos. 1,512.00 1,738.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 2.520 Nos. 600.00 1,512.00
Total 1,512.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 226.80
Grand Total 1,738.80

Cutting of grass, taking of root & brocken of uplecutting


1.07 A3 of raised soil & site leveling with all complete Sqm. 13.80 15.87

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.230 Nos. 600.00 138.00
Total 138.00
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 20.70
Grand Total 158.70

Surface dressing work with cutting of raised soil & filling


1.08 A4 the ditches. sqm. 6.00 6.90

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.010 Nos. 600.00 6.00
Total 6.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 0.90
Grand Total 6.90

B - EARTH & SAND WORK

Earth work excavation in foundation in clay & silty soft soil


2.01 B1 (2-1) lead upto 10 mtr. & lift 1.5 mtr. Cum. 432.60 497.49
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.700 Nos. 600.00 420.00
Materials T & P 3 % of labour 12.60
Total 432.60
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 64.89

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 2 of 276
Rate analysis for : 1.00 Cum.
Grand Total 497.49

Earth work excavation in foundation in clay & soft murram


2.02 B1 (2-2) stone (30 cm.) hard soil lead upto 10 mtr. & lift 1.5 mtr. Cum. 494.40 568.56

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.800 Nos. 600.00 480.00
Materials T & P 3 % of labour 14.40
Total 494.40
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 74.16
Grand Total 568.56

Earth filling work in every 15-15 cm. layer with watering &
2.03 B2 (2-25A) lead upto 1o.00 mtr. & proper manual compaction. Cum. 300.00 345.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.500 Nos. 600.00 300.00
Total 300.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 45.00
Grand Total 345.00

Earth filling (Earth transported from 5 Km. surronding)


2.04 B2 (2-25A) work in every 15-15 cm. layer with watering & proper Cum. 765.55 880.38
manual compaction.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.500 Nos. 600.00 300.00
Mud 1.500 Cum. 309.00 463.50
Materials
Water 5.000 Ltr. 0.41 2.05
Total 765.55
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 114.83
Grand Total 880.38

Earth filling work in every 15-15 cm. layer without watering


2.05 B2 (2-25B) & proper manual compaction. Cum. 150.00 172.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.250 Nos. 600.00 150.00
Total 150.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 22.50
Grand Total 172.50

Earth filling (Earth transported from 5 Km. surronding)


2.06 B2 (2-25B) work in every 15-15 cm. layer without watering & proper Cum. 551.70 634.45
manual compaction.

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.250 Nos. 600.00 150.00
Materials Mud 1.300 Cum. 309.00 401.70
Total 551.70
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 82.75
Grand Total 634.45

Sand filling work with watering & proper manual


2.07 B3 (2-42A) compaction. Cum. 1,343.02 1,544.47

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.700 Nos. 600.00 420.00
Sand local 1.100 Cum. 837.25 920.97 with tax
Materials
Water 5.000 Cum. 0.41 2.05
Total 1,343.02
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 201.45
Grand Total 1,544.47

Gravel Sand mixed (agg-50% + sand 50%) filling work with


2.08 B3 (2-42B) proper manual compaction. Cum. 2,158.56 2,482.34

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.750 Nos. 600.00 450.00
Materials Gravel (sand mixed) 1.100 Cum. 1,553.24 1,708.56 with tax
Total 2,158.56
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 323.78
Grand Total 2,482.34

Pumping of water from foundation or trench


2.09 B4 (2-34) Hrs 35.34 40.65

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Water pump 0.500 Hour 353.49 176.74
Total 176.74
Rate analysis for : 5000.00 Ltr. 15 % Contractor overhead 26.51
Grand Total 203.25

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 3 of 276

Compaction of filled earth by 8-10 M.T. roller in 20/20 cm


2.11 B5 layer Cum. 15.48 17.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Equipment Road roller 8-10 M.T. 1.670 Hour 927.00 1,548.09
Total 1,548.09
Rate analysis for : 100.00 Cum. 15 % Contractor overhead 232.21
Grand Total 1,780.30

Compaction of filled earth by 1.00 M.T. Hand roller in 20/20


2.12 B5 cm layer Cum. 5.16 5.93

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 53.000 Nos 600.00 31,800.00
Equipment Road hand roller 1.00 M.T. 1.670 Hour 309.00 516.03
Total 516.03
Rate analysis for : 100.00 Cum. 15 % Contractor overhead 77.40
Grand Total 593.43

Earth work excavation in foundation in SOFT SOIL(USED 0.80


2.13 B7 CUM. CAPACITY Hydraulic EXCAVATOR) Cum. 48.79 56.10

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1248 Ltr. 114.33 14.26
Equipment Hydraulic Excavator 0.80 Cum. 0.0104 Hour 3,320.72 34.53
Total 48.79
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 7.31
Grand Total 56.10

Earth work excavation in foundation in HARD SOIL USED 0.80


2.14 B7 CUM. CAPACITY Hydraulic EXCAVATOR) Cum. 58.64 67.43

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1500 Ltr. 114.33 17.14
Equipment Hydraulic Excavator 0.80 Cum. 0.0125 Hour 3,320.72 41.50
Total 58.64
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 8.79
Grand Total 67.43

Earth work excavation in foundation in HARD Rock Used 0.80


2.15 B7 Cum capecity Hydraulic excavator Cum. 80.70 92.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.2064 Ltr. 114.33 23.59
Equipment Hydraulic Excavator 0.80 Cum. 0.0172 Hour 3,320.72 57.11
Total 80.70
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 12.10
Grand Total 92.80

Earth work excavation in foundation in SOFT SOILUsed


2.16 B7 1.32Cum capecity Hydraulic excavator Cum. 139.11 159.97

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1380 Ltr. 729.58 100.68
Hydraulic Excavator 1.32 Cum. 0.0069 Hour 5,570.24 38.43
Total 139.11
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 20.86
Grand Total 159.97

Earth work excavation in foundation in HARD SOIL Used


2.17 B7 1.32Cum capecity Hydraulic excavator Cum. 169.36 194.76

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1680 Ltr. 729.58 122.57
Hydraulic Excavator 1.32 Cum. 0.0084 Hour 5,570.24 46.79
Total 169.36
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 25.40
Grand Total 194.76

C - MASONRY WORK

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement
3.01 Cum. 11,283.04 12,975.49
5-2A) sand mortar in G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled ( for Scaffolding ) 0.200 Nos. 600.00 120.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.130 M.T. 18,025.00 2,343.25 transportation
Materials
Sand 0.270 Cum. 837.25 226.05
Water 150.000 Ltr. 0.41 61.50
Scaffolding material 3 % of Scaffolding labour 3.60
Total 11,283.04
Rate analysis for : 1.00 Cum.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 4 of 276

Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,692.45


Grand Total 12,975.49

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement
3.02 Cum. 11,592.04 13,330.84
5-2B) sand mortar in F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled 0.700 Nos. 600.00 420.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.130 M.T. 18,025.00 2,343.25 transportation
Materials
Sand 0.270 Cum. 837.25 226.05
Water 150.000 Ltr. 0.41 61.50
Scaffolding material 3 % of Scaffolding labour 12.60
Total 11,592.04
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,738.80
Grand Total 13,330.84

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement
3.03 Cum. 12,024.64 13,828.33
5-2B) sand mortar in S. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled 1.400 Nos. 600.00 840.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.130 M.T. 18,025.00 2,343.25 transportation
Materials
Sand 0.270 Cum. 837.25 226.05
Water 150.000 Ltr. 0.41 61.50
Scaffolding material 3 % of Scaffolding labour 25.20
Total 12,024.64
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,803.69
Grand Total 13,828.33

C2( 5-1-B2 & First class chimney brick masonry work in (1:4) cement
3.04 Cum. 10,742.47 12,353.84
5-2A) sand mortar in G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled ( for Scaffolding ) 0.200 Nos. 600.00 120.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.100 M.T. 18,025.00 1,802.50 transportation
Materials
Sand 0.280 Cum. 837.25 234.43
Water 130.000 Ltr. 0.41 53.30
Scaffolding material 3 % of Scaffolding labour 3.60
Total 10,742.47
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,611.37
Grand Total 12,353.84

C25-1-B2 & First class chimney brick masonry work in (1:4) cement
3.05 Cum. 11,051.47 12,709.19
5-2B) sand mortar in F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled 0.700 Nos. 600.00 420.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.100 M.T. 18,025.00 1,802.50 transportation
Materials
Sand 0.280 Cum. 837.25 234.43
Water 130.000 Ltr. 0.41 53.30
Scaffolding material 3 % of Scaffolding labour 12.60
Total 11,051.47
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,657.72
Grand Total 12,709.19

C2(5-1-B2 & First class chimney brick masonry work in (1:4) cement
3.06 Cum. 11,484.07 13,206.68
5-2B) sand mortar in S. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled 1.400 Nos. 600.00 840.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.100 M.T. 18,025.00 1,802.50 transportation
Materials
Sand 0.280 Cum. 837.25 234.43
Water 130.000 Ltr. 0.41 53.30
Scaffolding material 3 % of Scaffolding labour 25.20
Total 11,484.07
Rate analysis for : 1.00 Cum.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 5 of 276

Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,722.61


Grand Total 13,206.68

C2(5-1-B3 & First class chimney brick masonry work in (1:6) cement
3.07 Cum. 10,206.16 11,737.08
5-2A) sand mortar in G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.5000 Nos. 900.00 1,350.00
Labour Unskilled 2.2000 Nos. 600.00 1,320.00
Unskilled ( for Scaffolding ) 0.2000 Nos. 600.00 120.00
Brick chimney 474.0000 Nos. 12.36 5,858.64
with
Cement 0.0700 M.T. 18,025.00 1,261.75 transportation
Materials
Sand 0.3000 Cum. 837.25 251.17
Water 100.0000 Ltr. 0.41 41.00
3 % of Scaffolding labour 3.60
Total 10,206.16
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,530.92
Grand Total 11,737.08

C2(5-1-B3 & First class chimney brick masonry work in (1:6) cement
3.08 Cum. 10,515.16 12,092.43
5-2B) sand mortar in F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled 0.700 Nos. 600.00 420.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.070 M.T. 18,025.00 1,261.75 transportation
Materials
Sand 0.300 Cum. 837.25 251.17
Water 100.000 Ltr. 0.41 41.00
Scaffolding material 3 % of Scaffolding labour 12.60
Total 10,515.16
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,577.27
Grand Total 12,092.43

C2( 5-1-B3 & First class chimney brick masonry work in (1:6) cement
3.09 Cum. 10,947.76 12,589.92
5-2B) sand mortar in S F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour Unskilled 2.200 Nos. 600.00 1,320.00
Unskilled 1.400 Nos. 600.00 840.00
Brick chimney 474.000 Nos. 12.36 5,858.64
with
Cement 0.070 M.T. 18,025.00 1,261.75 transportation
Materials
Sand 0.300 Cum. 837.25 251.17
Water 100.000 Ltr. 0.41 41.00
Scaffolding material 3 % of Scaffolding labour 25.20
Total 10,947.76
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,642.16
Grand Total 12,589.92

C2(5-1-B6 & First class chimney brick masonry work in mud mortar in
3.10 Cum. 8,073.02 9,283.97
5-2A) G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour Unskilled 1.700 Nos. 600.00 1,020.00
Unskilled 0.200 Nos. 600.00 120.00
Brick chimney 474.000 Nos. 12.36 5,858.64
Mud 0.420 Cum. 309.00 129.78
Materials
Water 100.000 Ltr. 0.41 41.00
Scaffolding material 3 % of Scaffolding labour 3.60
Total 8,073.02
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,210.95
Grand Total 9,283.97

C2( 5-1-B6 & First class chimney brick masonry work in mud mortar in
3.11 Cum. 8,382.02 9,639.32
5-2B) F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour Unskilled 1.700 Nos. 600.00 1,020.00
Unskilled 0.700 Nos. 600.00 420.00
Brick chimney 474.000 Nos. 12.36 5,858.64
Mud 0.420 Cum. 309.00 129.78
Materials
Water 100.000 Ltr. 0.41 41.00
Scaffolding material 3 % of Scaffolding labour 12.60
Total 8,382.02
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,257.30
Grand Total 9,639.32

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 6 of 276

C2(5-1-B6 & First class chimney brick masonry work in mud mortar in
3.12 Cum. 8,814.62 10,136.81
5-2B) S. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour Unskilled 1.700 Nos. 600.00 1,020.00
Unskilled 1.400 Nos. 600.00 840.00
Brick chimney 474.000 Nos. 12.36 5,858.64
Mud 0.420 Cum. 309.00 129.78
Materials
Water 100.000 Ltr. 0.41 41.00
Scaffolding material 3 % of Scaffolding labour 25.20
Total 8,814.62
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,322.19
Grand Total 10,136.81

R.R. stone masonry work in cement sand (1:3) mortar


3.13 C6( 6-1-1A) Cum. 10,626.99 12,221.03

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 5.000 Nos. 600.00 3,000.00
Cement 0.194 M.T. 18,025.00 3,496.85
Sand 0.420 Cum. 837.25 351.64
Materials Stone block 1.000 Cum. 2,163.00 2,163.00
Stone bond 0.100 Cum. 2,163.00 216.30
Water 120.000 Ltr. 0.41 49.20
Total 10,626.99
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,594.04
Grand Total 12,221.03

3.14 C6( 6-1-1B) R.R. stone masonry work in cement sand (1:4) mortar Cum. 10,013.03 11,514.98
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 5.000 Nos. 600.00 3,000.00
Cement 0.159 M.T. 18,025.00 2,865.97
Sand 0.450 Cum. 837.25 376.76
Materials Stone block 1.000 Cum. 2,163.00 2,163.00
Stone bond 0.100 Cum. 2,163.00 216.30
Water 100.000 Ltr. 0.41 41.00
Total 10,013.03
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,501.95
Grand Total 11,514.98

3.15 C6( 6-1-1C) R.R. stone masonry work in cement sand (1:6) mortar Cum. 9,062.15 10,421.47
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 5.000 Nos. 600.00 3,000.00
Cement 0.106 M.T. 18,025.00 1,910.65
Sand 0.470 Cum. 837.25 393.50
Materials
Stone block 1.000 Cum. 2,163.00 2,163.00
Stone bond 0.100 Cum. 2,163.00 216.30
Water 70.000 Ltr. 0.41 28.70
Total 9,062.15
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,359.32
Grand Total 10,421.47

Aslar (Crused stone) stone masonry work in cement sand


3.14a C6( 6-1-1B) (1:4) mortar Cum. 10,013.03 11,514.98

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 5.000 Nos. 600.00 3,000.00
Cement 0.159 M.T. 18,025.00 2,865.97
Sand 0.450 Cum. 837.25 376.76
Materials
Stone bond 1.100 Cum. 2,163.00 2,379.30
Water 100.000 Ltr. 0.41 41.00
Total 10,013.03
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,501.95
Grand Total 11,514.98

3.15a C6( 6-1-1C) Aslar (Crused stone)stone masonry work in cement sand Cum. 9,062.15 10,421.47
Resources Level/Type(1:6) mortar Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00 1.50
Labour
Unskilled 5.000 Nos. 600.00 3,000.00 3.00
Cement 0.106 M.T. 18,025.00 1,910.65 0.04
Materials Sand 0.470 Cum. 837.25 393.50 0.42
Stone bond 1.100 Cum. 2,163.00 2,379.30 1.10
Water 70.000 Ltr. 0.41 28.70
Total 9,062.15
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,359.32
Grand Total 10,421.47

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 7 of 276

3.16 C6( 6-2-1) R.R. stone masonry work for dry wall Cum. 4,479.30 5,151.19
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 2.000 Nos. 600.00 1,200.00
Stone block 1.000 Cum. 2,163.00 2,163.00
Materials
Stone bond 0.100 Cum. 2,163.00 216.30
Total 4,479.30
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 671.89
Grand Total 5,151.19

3.17 C6( 6-2-2) R.R. stone masonry work in mud mortar Cum. 4,759.08 5,472.94
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 2.250 Nos. 600.00 1,350.00
Stone block 1.000 Cum. 2,163.00 2,163.00
Stone bond 0.100 Cum. 2,163.00 216.30
Materials
Mud 0.420 Cum. 309.00 129.78
Water 70.000 Ltr. 0.41 28.70
Total 4,759.08
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 713.86
Grand Total 5,472.94

3.18 C10( 6-5) Stone filling in trench with proper leveling Cum. 3,495.60 4,019.94
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 1.50 Nos. 600.00 900.00
Stone block 1.00 Cum. 2,163.00 2,163.00
Materials
Stone bond 0.20 Cum. 2,163.00 432.60
Total 3,495.60
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 524.34
Grand Total 4,019.94

D - CEMENT CONCRETE WORK

4.01 D1(7-2B) P.C.C. (1:4:8) work in foundation, wall (River bed) Cum. 7,807.48 8,978.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Cement 0.170 M.T. 18,025.00 3,064.25
Aggrigate 40 mm-River bed 0.650 Cum. 1,103.75 717.43
Materials Aggrigate 20 mm-River bed 0.240 Cum. 1,213.75 291.30
Sand 0.470 Cum. 837.25 393.50
Water 100.000 Ltr. 0.41 41.00
Total 7,807.48
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,171.12
Grand Total 8,978.60

4.02 D1(7-2C) P.C.C. (1:3:6) work in foundation, wall (River bed) Cum. 8,716.93 10,024.46
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Cement 0.220 M.T. 18,025.00 3,965.50
Aggrigate 40 mm-River bed 0.650 Cum. 1,103.75 717.43
Materials Aggrigate 20 mm-River bed 0.240 Cum. 1,213.75 291.30
Sand 0.470 Cum. 837.25 393.50
Water 120.000 Ltr. 0.41 49.20
Total 8,716.93
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,307.53
Grand Total 10,024.46

4.03 D1(7-2D) P.C.C. (1:2:4) work in foundation, wall (River bed) Cum. 10,487.55 12,060.68
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Cement 0.320 M.T. 18,025.00 5,768.00
Aggrigate 40 mm-River bed 0.520 Cum. 1,103.75 573.95
Aggrigate 20 mm-River bed 0.220 Cum. 1,213.75 267.02
Materials
Aggrigate 10 mm-River bed 0.110 Cum. 1,313.75 144.51
Sand 0.445 Cum. 837.25 372.57
Water 150.000 Ltr. 0.41 61.50
Total 10,487.55
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,573.13
Grand Total 12,060.68

P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (River bed)
4.04 D2(7-4A) Cum. 12,107.55 13,923.68
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 900.00 720.00
Labour
Unskilled 7.000 Nos. 600.00 4,200.00
Cement 0.320 M.T. 18,025.00 5,768.00
Aggrigate 40 mm-River bed 0.520 Cum. 1,103.75 573.95
Materials
-------------------Prepared by : -----------------Checked by : --------------------Approved by :
Rate_Analysis_Dhanusha_Civil_2075/076 Page 8 of 276

Aggrigate 20 mm-River bed 0.220 Cum. 1,213.75 267.02


Materials
Aggrigate 10 mm-River bed 0.110 Cum. 1,313.75 144.51
Sand 0.445 Cum. 837.25 372.57
Water 150.000 Ltr. 0.41 61.50
Total 12,107.55
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,816.13
Grand Total 13,923.68

P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (River


4.05 D2(7-4B) bed) Cum. 13,640.64 15,686.73

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 900.00 720.00
Labour
Unskilled 7.000 Nos. 600.00 4,200.00
Cement 0.400 M.T. 18,025.00 7,210.00
Aggrigate 20 mm-River bed 0.570 Cum. 1,213.75 691.83
Materials Aggrigate 10 mm-River bed 0.290 Cum. 1,313.75 380.98
Sand 0.425 Cum. 837.25 355.83
Water 200.000 Ltr. 0.41 82.00
Total 13,640.64
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,046.09
Grand Total 15,686.73

P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (River bed)
4.06 D2(7-4C) Cum. 17,446.76 20,063.77

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 900.00 720.00
Labour
Unskilled 7.000 Nos. 600.00 4,200.00
Cement 0.610 M.T. 18,025.00 10,995.25
Aggrigate 20 mm-River bed 0.640 Cum. 1,213.75 776.80
Materials Aggrigate 10 mm-River bed 0.210 Cum. 1,313.75 275.88
Sand 0.425 Cum. 837.25 355.83
Water 300.000 Ltr. 0.41 123.00
Total 17,446.76
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,617.01
Grand Total 20,063.77

P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall


4.07 D3(A) (River bed) Cum. 8,656.16 9,954.58

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.220 M.T. 18,025.00 3,965.50
Aggrigate 40 mm-River bed 0.650 Cum. 1,103.75 717.43
Aggrigate 20 mm-River bed 0.240 Cum. 1,213.75 291.30
Materials Sand 0.425 Cum. 837.25 355.83
Water 100.000 Ltr. 0.41 41.00
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29 Previous year
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 8,656.16
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,298.42
Grand Total 9,954.58

P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall


4.08 D3(B) (River bed) Cum. 10,453.45 12,021.46

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.320 M.T. 18,025.00 5,768.00
Aggrigate 40 mm-River bed 0.520 Cum. 1,103.75 573.95
Aggrigate 20 mm-River bed 0.330 Cum. 1,213.75 400.53
Materials Sand 0.445 Cum. 837.25 372.57
Water 130.000 Ltr. 0.41 53.30
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 10,453.45
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,568.01
Grand Total 12,021.46

P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,


4.09 D4(A) beam etc (River bed) Cum. 12,005.74 13,806.60

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 9 of 276

Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.400 M.T. 18,025.00 7,210.00
Aggrigate 20 mm-River bed 0.570 Cum. 1,213.75 691.83
Aggrigate 10 mm-River bed 0.290 Cum. 1,313.75 380.98
Materials Sand 0.425 Cum. 837.25 355.83
Water 200.000 Ltr. 0.41 82.00
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 12,005.74
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,800.86
Grand Total 13,806.60

P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab,


4.10 D4(B) beam etc (River bed) Cum. 15,811.86 18,183.63

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.610 M.T. 18,025.00 10,995.25
Aggrigate 20 mm-River bed 0.640 Cum. 1,213.75 776.80
Aggrigate 10 mm-River bed 0.210 Cum. 1,313.75 275.88
Materials Sand 0.425 Cum. 837.25 355.83
Water 300.000 Ltr. 0.41 123.00
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 15,811.86
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,371.77
Grand Total 18,183.63

P.C.C. (1:1:2) for R.C.C. work in slab (River bed) with micro
4.11 D(5) silica & super plasticiser Cum. 27,414.68 31,526.88

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.600 M.T. 18,025.00 10,815.00
Aggrigate 20 mm-River bed 0.825 Cum. 1,213.75 1,001.34
Sand 0.412 Cum. 837.25 344.94
Super plasticiser 12.000 Ltr. - -
Micro silica 40.000 Kg. 297.67 11,906.80
Materials Water 150.000 Ltr. 0.41 61.50
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Vibrator 0.250 Hour 294.58 73.64
Total 27,414.68
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 4,112.20
Grand Total 31,526.88

P.C.C. (1:4:8) work in foundation, wall (crushed or stone


4.12 D1(7-2B) ballast) Cum. 8,406.75 9,667.76

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Cement 0.170 M.T. 18,025.00 3,064.25
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 1,800.00 1,170.00
Materials Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 1,825.00 438.00
Sand Crusher 0.470 Cum. 837.25 393.50
Water 100.000 Ltr. 0.41 41.00
Total 8,406.75
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,261.01
Grand Total 9,667.76

P.C.C. (1:3:6) work in foundation, wall (crushed or stone


4.13 D1(7-2C) ballast) Cum. 9,316.20 10,713.63

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Cement 0.220 M.T. 18,025.00 3,965.50
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 1,800.00 1,170.00
Materials Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 1,825.00 438.00
Sand Crusher 0.470 Cum. 837.25 393.50
Water 120.000 Ltr. 0.41 49.20
Total 9,316.20
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,397.43

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 10 of 276
Rate analysis for : 1.00 Cum.
Grand Total 10,713.63

P.C.C. (1:2:4) work in foundation, wall (crushed or stone


4.14 D1(7-2D) ballast) Cum. 11,048.57 12,705.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Cement 0.320 M.T. 18,025.00 5,768.00
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 1,800.00 936.00
Aggrigate 20 mm-crushed/ballast stone 0.220 Cum. 1,825.00 401.50
Materials
Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 1,900.00 209.00
Sand Crusher 0.445 Cum. 837.25 372.57
Water 150.000 Ltr. 0.41 61.50
Total 11,048.57
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,657.28
Grand Total 12,705.85

P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (crushed or


4.15 D2(7-4A) stone ballast) Cum. 12,668.57 14,568.85
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 900.00 720.00
Labour
Unskilled 7.000 Nos. 600.00 4,200.00
Cement 0.320 M.T. 18,025.00 5,768.00
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 1,800.00 936.00
Aggrigate 20 mmcrushed/ballast stone 0.220 Cum. 1,825.00 401.50
Materials
Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 1,900.00 209.00
Sand Crusher 0.445 Cum. 837.25 372.57
Water 150.000 Ltr. 0.41 61.50
Total 12,668.57
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,900.28
Grand Total 14,568.85

P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (crushed


4.16 D2(7-4B) or stone ballast) Cum. 14,159.08 16,282.94

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 900.00 720.00
Labour
Unskilled 7.000 Nos. 600.00 4,200.00
Cement 0.400 M.T. 18,025.00 7,210.00
Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 1,825.00 1,040.25
Materials Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 1,900.00 551.00
Sand Crusher 0.425 Cum. 837.25 355.83
Water 200.000 Ltr. 0.41 82.00
Total 14,159.08
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,123.86
Grand Total 16,282.94

P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (crushed or


4.17 D2(7-4C) stone ballast) Cum. 17,961.08 20,655.24

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 900.00 720.00
Labour
Unskilled 7.000 Nos. 600.00 4,200.00
Cement 0.610 M.T. 18,025.00 10,995.25
Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 1,825.00 1,168.00
Materials Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 1,900.00 399.00
Sand Crusher 0.425 Cum. 837.25 355.83
Water 300.000 Ltr. 0.41 123.00
Total 17,961.08
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,694.16
Grand Total 20,655.24

P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall


4.18 D3(A) (crushed or stone ballast) Cum. 9,255.43 10,643.74

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.220 M.T. 18,025.00 3,965.50
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 1,800.00 1,170.00
Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 1,825.00 438.00
Materials Sand Crusher 0.425 Cum. 837.25 355.83
Water 100.000 Ltr. 0.41 41.00
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 9,255.43
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,388.31
Grand Total 10,643.74

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 11 of 276

P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall


4.19 D3(B) (crushed or stone ballast) Cum. 11,017.22 12,669.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.320 M.T. 18,025.00 5,768.00
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 1,800.00 936.00
Aggrigate 20 mm-crushed/ballast stone 0.330 Cum. 1,825.00 602.25
Materials Sand Crusher 0.445 Cum. 837.25 372.57
Water 130.000 Ltr. 0.41 53.30
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 11,017.22
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,652.58
Grand Total 12,669.80

P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,


4.20 D4(A) beam etc (crushed or stone ballast) Cum. 12,524.18 14,402.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.400 M.T. 18,025.00 7,210.00
Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 1,825.00 1,040.25
Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 1,900.00 551.00
Materials Sand Crusher 0.425 Cum. 837.25 355.83
Water 200.000 Ltr. 0.41 82.00
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 12,524.18
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,878.62
Grand Total 14,402.80

P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab,


4.21 D4(B) beam etc (crushed or stone ballast) Cum. 16,326.18 18,775.10

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.610 M.T. 18,025.00 10,995.25
Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 1,825.00 1,168.00
Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 1,900.00 399.00
Materials Sand Crusher 0.425 Cum. 837.25 355.83
Water 300.000 Ltr. 0.41 123.00
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29
Equipment
Vibrator 0.250 Hour 294.58 73.64
Total 16,326.18
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,448.92
Grand Total 18,775.10

P.C.C. (1:1:2) for R.C.C. work in slab (crushed or stone


4.22 D(5) ballast) with micro silica & super plasticiser Cum. 27,918.96 32,106.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Cement 0.600 M.T. 18,025.00 10,815.00
Aggrigate 20 mm-crushed/ballast stone 0.825 Cum. 1,825.00 1,505.62
Sand Crusher 0.412 Cum. 837.25 344.94
Super plasticiser 12.000 Ltr. - -
Micro silica 40.000 Kg. 297.67 11,906.80
Materials Water 150.000 Ltr. 0.41 61.50
Diesel 3.000 Ltr. 114.33 342.99
Petrol 0.100 Ltr. 131.84 13.18
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 508.82 305.29

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Materials

Rate_Analysis_Dhanusha_Civil_2075/076 Page 12 of 276

Vibrator 0.250 Hour 294.58 73.64


Total 27,918.96
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 4,187.84
Grand Total 32,106.80

Torsteel reinforcement bar for R.C.C. work with cutting,


4.23 D9(7-5) bending, binding & laying with all complete. Kg. 116.77 134.29

Resources Level/Type Quantity


Unit Rate Amount Remarks
Skilled 12.000
Nos. 900.00 10,800.00
Labour
Unskilled 12.000
Nos. 600.00 7,200.00
TOR/TMT reinforcement bar 1.050
M.T. 92,700.00 97,335.00
Materials
Binding wire 10.000
Kg. 144.20 1,442.00
Total 116,777.00
Rate analysis for : 1.00 MT 15 % Contractor overhead 17,516.55
Grand Total 134,293.55
E - FORM & PROPS WORK

Form work shuttering & centering (COLUMN) with (USED


5.01 E1(8-3A) LOCAL WOOD) all complete. Sqm. 1,139.42 1,310.34

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.748 Nos. 900.00 3,373.20 Scrap
Labour
Unskilled 5.622 Nos. 600.00 3,373.20 value .75x.526/
Wood Local 0.070 Cum. 61,800.00 4,326.00 6= 0.07
Materials
Killa 2.500 Kg. 128.75 321.87
Total 11,394.27
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,709.14
Grand Total 13,103.41

Form work shuttering & centering (COLUMN) with (USED


5.02 E2(51B) PLY WOOD) all complete. Sqm. 612.11 703.93

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.574 Nos. 900.00 1,416.60
Labour
Unskilled 2.361 Nos. 600.00 1,416.60
Ply board 19 mm thick 0.693 Sqm. 1,349.71 935.34
Wood Local 0.019 Cum. 61,800.00 1,174.20
Materials
MS Black pipe(MNB 50-M) 0.540 Nos. 1,586.20 856.54

Killa 2.500 Kg. 128.75 321.87


Total 6,121.15
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 918.17
Grand Total 7,039.32

Form work shuttering & centering (BEAM-0.30 Mtr) with


5.03 E3(8-4A) (USED LOCAL WOOD) all complete. Sqm. 1,184.78 1,362.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 4.000 Nos. 900.00 3,600.00
Labours
Unskilled 6.000 Nos. 600.00 3,600.00
Wood Local 0.070 Cum. 61,800.00 4,326.00
Materials
Killa 2.500 Kg. 128.75 321.87
Total 11,847.87
Rate analysis for : 10.00 Sqm. 15 % Contractor Overhead 1,777.18
Grand Total 13,625.05

Form work shuttering & centering (BEAM-0.30-0.80 Mtr)


5.04 E4(8-4B) with (USED LOCAL WOOD) all complete. Sqm. 945.08 1,086.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.670 Nos. 900.00 2,403.00
Labours
Unskilled 4.000 Nos. 600.00 2,400.00
Wood Local 0.070 Cum. 61,800.00 4,326.00
Materials
Killa 2.500 Kg. 128.75 321.87
Total 9,450.87
Rate analysis for : 10.00 Sqm. 15 % Contractor Overhead 1,417.63
Grand Total 10,868.50

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 13 of 276

Form work shuttering & centering (COLUMN) with (USED


5.05 E5(51A) PLY WOOD) all complete. Sqm. 1,287.21 1,480.29

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.670 Nos. 900.00 2,403.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Ply board 19 mm thick 1.650 Sqm. 1,236.00 2,039.40
Wood Local 0.040 Cum. 61,800.00 2,472.00
Materials
MS Black pipe(MNB 50-M) 2.040 Nos. 1,586.20 3,235.84 0.40*5.10
Killa 2.500 Kg. 128.75 321.87
Total 12,872.11
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,930.81
Grand Total 14,802.92

Form work shuttering & centering with MS pipe (prop),


5.06 E6(8-4A) plyboard for slab etc Sqm. 1,044.44 1,201.11

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 17.200 Nos. 900.00 15,480.00
Labours
Unskilled 25.700 Nos. 600.00 15,420.00

Ply board 19 mm thick 16.500 Sqm. 1,236.00 20,394.00


Wood Local 0.232 Cum. 61,800.00 14,337.60
Materials 4.40*5.10
MS Black pipe(MNB 50-M) 22.440 Nos. 1,586.20 35,594.32

Killa 25.000 Kg. 128.75 3,218.75


Total 104,444.67
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 15,666.70
Grand Total 120,111.37

gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
1.6875x1.1x0.75/6= 0.232
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
100x1.1x0.9/6=16.5
M kfO{k M !% k6s;Dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
88/15x0.75 =4.4
gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
0.155/6x0.75=0.019
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
4.62/6x0.90=0.693
M kmnfd] af]N6 M !% k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
10.68/15x0.75=0.54
sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
33.33/6*0.75=4.16*0.0254=0.105
sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
2.03/6*0.75=0.25375

Form work shuttering & centering with Bamboo, plyboard


5.06(A) E6(8-4A) for slab etc Sqm. 554.52 637.70

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.560 Nos. 900.00 9,504.00 60% of17.2
Labours
Unskilled 10.380 Nos. 600.00 6,228.00 60% of17.3
Ply board 19 mm thick 16.500 Sqm. 1,236.00 20,394.00
Wood Local 0.232 Cum. 61,800.00 14,337.60
Materials
Bamboo 6.250 Nos. 283.25 1,770.31 6.25
Killa 25.000 Kg. 128.75 3,218.75
Total 55,452.66
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 8,317.89
Grand Total 63,770.55

gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
1.6875x1.1x0.75/6= 0.232
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
100x1.1x0.9/6=16.5
af; M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
(100*3/6)/6*0.75 =6.25

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 14 of 276

5.07 E12(8-13A) Trench work open type form work (up to 1.50 Mtr.) Sqm. 225.45 259.27

Resources Quantity Unit Rate Amount Remarks


Level/Type
Skilled 0.250 Nos. 900.00 225.00
Labours
Unskilled 0.250 Nos. 600.00 150.00
0.105
Wood Local Cum. 61,800.00 6,489.00
Materials
0.25375
Wood Local Cum. 61,800.00 15,681.75
Total 22,545.75
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 3,381.86

Grand Total 25,927.61


=

5.08 E12(8-13B) Trench work open type form work ( 1.50 to 3.00 Mtr.) Sqm. 232.20 267.03
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 900.00 450.00
Labours
Unskilled 1.000 Nos. 600.00 600.00
Wood Local 0.105 Cum. 61,800.00 6,489.00 4.16*0.0254
Materials
Wood Local 0.25375 Cum. 61,800.00 15,681.75
Total 23,220.75
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 3,483.11
Grand Total 26,703.86

5.09 E13(8-13C) Trench work open type form work (above 3.00 Mtr.) Sqm. 241.20 277.38
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labours
Unskilled 1.750 Nos. 600.00 1,050.00
Wood Local 0.105 Cum. 61,800.00 6,489.00 4.16*0.0254
Materials
Wood Local 0.25375 Cum. 61,800.00 15,681.75
Total 24,120.75
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 3,618.11
Grand Total 27,738.86

gf]6 M !Æ j/fj/ @=%$ ;]=dL= kmn]ssf] lx;fj ul/Psf] sf7x? ^ k6s;Dd k|of]u u/L;s]kl5 @%Ü d"No afFsL x'g] u/L lx;fj ul/Psf]]_
F - ROOFING WORK

26 (H) 0.41 mm thick colored C.G.I. sheet roofing work


6.01 F1( 9-1) Sqm. 1,688.56 1,941.85
(65kg/bandal)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 26 (H) 0.41 mm thick Plane 12.000 Sqm. 1,145.87 13,750.44
Materials Nutbolt 8 mm. 30.000 Nos. 20.60 618.00
J-hook 25.000 Nos. 23.17 579.25
Bitumen washer 55.000 Nos. 3.60 198.00
Total 16,885.69
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,532.85
Grand Total 19,418.54

=
26 (H) 0.41mm thick plane C.G.I. sheet roofing work
6.02 F1( 9-1) (62kg/bandal) Sqm. 1,446.52 1,663.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 26 (H) 0.41 mm thick Plane 12.000 Sqm. 944.17 11,330.00
Nutbolt 8 mm. 30.000 Nos. 20.60 618.00
Materials
J-hook 25.000 Cum. 23.17 579.25
Bitumen washer 55.000 Nos. 3.60 198.00
Total 14,465.25
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,169.79
Grand Total 16,635.04

26 (L) 0.35mm thick plane C.G.I. sheet roofing work


6.03 F1( 9-1) Sqm. 1,276.56 1,468.05
(55kg/bandal)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 26 (L) 0.35 mm thick Plane 12.000 Sqm. 802.54 9,630.44
Nutbolt 8 mm. 30.000 Nos. 20.60 618.00
Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 15 of 276

Materials
J-hook 25.000 Nos. 23.17 579.25
Bitumen washer 55.000 Nos. 3.60 198.00
Total 12,765.69
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,914.85
Grand Total 14,680.54

26 (H) 0.41 mm thick colour C.G.I. sheet roofing work


6.04 F3( 9-1) Sqm. 1,688.56 1,941.85
(65kg/bandal)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 26 (H) 0.41 mm thick coloured 12.000 Sqm. 1,145.87 13,750.44
Nutbolt 8 mm. 30.000 Nos. 20.60 618.00
Materials
J-hook 25.000 Nos. 23.17 579.25
Bitumen washer 55.000 Nos. 3.60 198.00
Total 16,885.69
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,532.85
Grand Total 19,418.54

26 (L) 0.35mm thick colour C.G.I. sheet roofing work


6.05 F3( 9-1) (62kg/bandal) Sqm. 1,474.84 1,696.06

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 26 (L) 0.35 mm thick colour 12.000 Sqm. 967.76 11,613.16
Nutbolt 8 mm. 30.000 Nos. 20.60 618.00
Materials
J-hook 25.000 Nos. 23.17 579.25
Bitumen washer 55.000 Nos. 3.60 198.00
Total 14,748.41
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,212.26
Grand Total 16,960.67

28 (H) G.I. plane ridge cover


6.08 F2( 9-2) Rmtr. 608.24 699.47

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.000 Nos. 900.00 1,800.00
Labour
Unskilled 3.000 Nos. 600.00 1,800.00
CGI Ridge Cover 12.000 Rmtr.. 202.70 2,432.40
Materials
Nutbolt L.S. 50.00
Total 6,082.40
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 912.36
Grand Total 6,994.76

6.09 F4( 9-2) 26 (L) C.G.I. colour ridge cover Rmtr. 770.40 885.96
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.000 Nos. 900.00 1,800.00
Labour
Unskilled 3.000 Nos. 600.00 1,800.00
CGI Ridge Cover colour 12.000 Rmtr.. 337.84 4,054.08
Materials
Nutbolt L.S. 50.00
Total 7,704.08
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,155.61
Grand Total 8,859.69

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 16 of 276

6.11 F5 28 (H) 0.31 mm thick plane G.I. sheet roofing work Rmtr. 1,190.31 1,368.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 28(H) 0.31 mm thick plane 12.000 Sqm. 729.58 8,755.00
J-hook 30.000 Nos. 23.17 695.10
Materials
Nut bolt 8 mm 25.000 Nos. 20.60 515.00
Bitumen washer 55.000 Nos. 3.60 198.00
Total 11,903.10
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,785.47
Grand Total 13,688.57

6.12 F5 26 (L) 0.35 mm thick plane G.I. sheet roofing work Rmtr. 1,277.85 1,469.53

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 26 (L) 0.35 mm thick plain 12.000 Sqm. 802.54 9,630.44
J-hook 30.000 Nos. 23.17 695.10
Materials
Nut bolt 8 mm 25.000 Nos. 20.60 515.00
Bitumen washer 55.000 Nos. 3.60 198.00
Total 12,778.54
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,916.78
Grand Total 14,695.32

6.13 F6 26 (H) 0.41 mm thick Colour G.I. sheet roofing work Rmtr. 1,729.40 1,988.81

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
CGI sheet 26 (H) 0.41 mm thick
colour 12.000 Sqm. 1,145.87 13,750.44
Materials J-hook 30.000 Nos. 23.17 695.10
Nut bolt 8 mm 25.000 Nos. 36.42 910.50
Bitumen washer 55.000 Nos. 3.60 198.00
Total 17,294.04
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 2,594.11
Grand Total 19,888.15

6.14 F6 26 (M) 0.38 mm thick Colour G.I. sheet roofing work Rmtr. 1,603.33 1,843.83

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
GI sheet 26 (M) 0.38 mm thick Colour 12.000 Sqm. 1,073.77 12,885.24
J-hook 30.000 Nos. 23.17 695.10
Materials
Nut bolt 8 mm 25.000 Nos. 20.60 515.00
Bitumen washer 55.000 Nos. 3.60 198.00
Total 16,033.34
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 2,405.00
Grand Total 18,438.34

150 mm breadth upto 450 mm G. I. plane sheet Gutter


6.16 F7 fixing work with 3x40 mm M.S. bracke,t nut bolt & Rmtr. 1,133.10 1,303.06
washer .
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.750 Nos. 900.00 1,575.00
Labour
Unskilled 2.000 Nos. 600.00 1,200.00
G. I. plane sheet Gutter 0.50mm thick 13.500 Rmtr 208.37 2,812.99
M.S. bracket 3*40 mm 32.000 Nos. 143.17 4,581.44
Materials
Nut bolt 48.000 Nos. 20.60 988.80
Bitumen washer 48.000 Nos. 3.60 172.80
Total 11,331.03
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,699.65
Grand Total 13,030.68

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 17 of 276

150 mm breadth upto 450 mm G. I. colour sheet Gutter


6.17 F7 fixing work with 3x40 mm M.S. bracke,t nut bolt & Rmtr. 1,189.20 1,367.59
washer .
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.750 Nos. 900.00 1,575.00
Labour
Unskilled
G. I.Colour plane sheet Gutter 2.000 Nos. 600.00 1,200.00
0.50mm thick 13.500 Rmtr 249.93 3,374.05
M.S. bracket 3*40 mm 32.000 Nos. 143.17 4,581.44
Materials
Nut bolt 48.000 Nos. 20.60 988.80
Bitumen washer 48.000 Nos. 3.60 172.80
Total 11,892.09
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,783.81
Grand Total 13,675.90

6.18 F10( 9-6) Clay tile roofing work Rmtr. 576.75 663.26
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 1.500 Nos. 600.00 900.00
Materials Clay tile 125.000 Nos. 35.34 4,417.50
Total 5,767.50
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 865.13
Grand Total 6,632.63

6.19 F11( 9-7) Clay tile ridge cover Rmtr. 366.36 421.31
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 0.500 Nos. 600.00 300.00
Materials Clay tile ridge cover 80.000 Nos. 36.42 2,913.60
Total 3,663.60
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 549.54
Grand Total 4,213.14

6.20 F12( 9-8) 100 mm lime concrete (1:1:3) work Sqm. 1,198.94 1,378.79
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 12.000 Nos. 600.00 7,200.00
Brick Aggrigate 1.250 Cum. 2,575.00 3,218.75
Materials White lime 1.500 Kg. 23.56 35.34
Surkhee 0.400 Cum. 463.50 185.40
Total 11,989.49
Rate analysis for : 10.00 Sqm.. 15 % Contractor overhead 1,798.42
Grand Total 13,787.91

6.21 F13( 9-9A) 80 mm thick khar roof with bamboo frame Sqm. 2,513.66 2,890.70
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 1.500 Nos. 600.00 900.00
Khar 83.000 Bundle 128.75 10,686.25
Bamboo 30.000 Nos. 283.25 8,497.50
Materials
Dori 3.500 Kg. 175.10 612.85
Chattai 12.000 Sqm. 257.50 3,090.00
Total 25,136.60
Rate analysis for : 10.00 Sqm.. 15 % Contractor overhead 3,770.49
Grand Total 28,907.09

6.22 F13( 9-9B) 150 mm thick khar roof with bamboo frame Sqm. 3,891.80 4,475.57
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 1.500 Nos. 600.00 900.00
Khar 166.000 Bundle 128.75 21,372.50
Bamboo 40.000 Nos. 283.25 11,330.00
Materials
Dori 5.000 Kg. 175.10 875.50
Chattai 12.000 Sqm. 257.50 3,090.00
Total 38,918.00
Rate analysis for : 10.00 Sqm.. 15 % Contractor overhead 5,837.70
Grand Total 44,755.70

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 18 of 276

6.23 F14 1.20 mm thick fiber glass corgated sheet roofing work Sqm. 1,576.71 1,813.22
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.250 Nos. 600.00 750.00
Fiber glass 1.20 mm thick corgated 12.000 Sqm. 1,052.66 12,631.92
Nutbolt 8 mm. 30.000 Nos. 20.60 618.00
Materials
J-hook 25.000 Nos. 23.17 579.25
Bitumen washer 55.000 Nos. 3.60 198.00
Total 15,767.17
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,365.08
Grand Total 18,132.25

6.24 F15 1.20 mm thick fiber glass ridge cover Rmtr. 1,130.57 1,300.15
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.00 Nos. 900.00 1,800.00
Labour
Unskilled
Fiber glass 1.20 mm thick ridge cover 3.00 Nos. 600.00 1,800.00
(0.60m width) 12.00 Rmtr. 637.98 7,655.70
Materials
Nutbolt L.S. 50.00
Total 11,305.70
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,695.85
Grand Total 13,001.55

Readymade colour concrete tile laying work on cement


6.25 F18 Sqm. 715.12 822.39
sand (1:4) screeding
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 2.000 Nos. 600.00 1,200.00
Cement 0.024 M.T. 463.50 11.12
Sand Crusher 0.090 Cum. 837.25 75.35
Materials
Readymade colour concrete tile
I,,bambai,cadbari design floor
tile(10"x10"x1.5"=40.00rs 175.000 Nos. 28.37 4,964.75
Total 7,151.22
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,072.68
Grand Total 8,223.90

6.26 F19( 10-17) Making and fixing of Sal wood beam, lintel, etc Cum. 287,416.00 330,528.40
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 17.650 Nos. 900.00 15,885.00
Labour
Unskilled 1.760 Nos. 600.00 1,056.00
Wood Sal 1.050 Cum. 257,500.00 270,375.00
Materials
Killas L.S. 100.00
Total 287,416.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 43,112.40
Grand Total 330,528.40

6.27 F20(10-19) Making and fixing of 25 mm sal wood eaves board Sqm. 7,228.53 8,312.80
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.430 Nos. 900.00 1,287.00
Labour
Unskilled 0.143 Nos. 600.00 85.80
Wood Sal 0.275 Cum. 257,500.00 70,812.50
Materials
Killas L.S. 100.00
Total 72,285.30
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 10,842.79
Grand Total 83,128.09

6.28 F22 2 mm thick UPVC roofing sheet roofing work Sqm. - -


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 1.000 Nos. 600.00 600.00
UPVC roofing sheet 2 mm thick 12.000 Sqm. - -
Materials Clip 14.000 Nos. 59.74 836.36
Self Taping Screw 3" 28.000 Nos. 8.75 245.00
Total -
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead -
Grand Total -

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 19 of 276

6.29 F23 3 mm thick UPVC roofing sheet roofing work Sqm. 2,164.55 2,489.23
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 1.000 Nos. 600.00 600.00
UPVC roofing sheet 3 mm thick 12.000 Sqm. 1,551.18 18,614.16
Materials Clip 14.000 Nos. 59.74 836.36
Self Taping Screw 3" 28.000 Nos. 8.75 245.00
Total 21,645.52
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 3,246.83
Grand Total 24,892.35

G - DOOR & WINDOW WORK

7.01 G1(10-1) Sal wood works for chaukhats with all complete. Cum. 320,911.36 369,048.06
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 34.000 Nos. 900.00 30,600.00
Labour
Unskilled 3.400 Nos. 600.00 2,040.00
Wood Sal 1.100 Nos. 257,500.00 283,250.00
Materials Hold fast 92.000 Nos. 51.50 4,738.00
pech killas 184.000 Nos. 1.54 283.36
Total 320,911.36
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 48,136.70
Grand Total 369,048.06

7.02 G1(10-1) Local wood works for chaukhats with all complete. Cum. 105,641.36 121,487.56
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 34.000 Nos. 900.00 30,600.00
Labour
Unskilled 3.400 Nos. 600.00 2,040.00
Wood Local 1.100 Nos. 61,800.00 67,980.00
Materials Hold fast 92.000 Nos. 51.50 4,738.00
pech killas 184.000 Nos. 1.54 283.36
Total 105,641.36
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 15,846.20
Grand Total 121,487.56

38 mm thick sal wood fully paneled shutter fixing work with all
7.03 G2(10-2) complete. Size of shutter 1.07 x 1.982 =2.114 Sqm. Sqm. 16,031.36 18,436.06

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 1.000 Nos. 600.00 600.00
Wood Sal 0.084 Cum. 257,500.00 21,630.00
Hinge 100 mm 6.000 Nos. 36.05 216.30
Towerbolt 150 mm. 1.000 Nos. 92.70 92.70
Materials Towerbolt 300 mm. 1.000 Nos. 216.30 216.30
Lockingset 250-300mm. 1.000 Nos. 1,648.00 1,648.00
Handle 2.000 Nos. 206.00 412.00
Pech killas L.S. 75.00
Total 33,890.30
Rate analysis for : 2.114 Sqm. 15 % Contractor overhead 5,083.54
Grand Total 38,973.84

38 x 75 mm thick sal wood frame with 4 mm thick fully glazed


7.04 G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 10,392.49 11,951.37
1.22 =2.23 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 9.000 Nos. 900.00 8,100.00
Labour
Unskilled 0.900 Nos. 600.00 540.00
Wood Sal 0.049 Cum. 257,500.00 12,617.50
Glass 4 mm thick-Plane 1.085 Sqm. 885.80 961.09
Hinge 75 mm 8.000 Nos. 27.81 222.48
Materials
Towerbolt 100 mm. 4.000 Nos. 61.80 247.20
Handle 2.000 Nos. 206.00 412.00
Pech killas L.S. 75.00
Total 23,175.27
Rate analysis for : 2.23 Sqm. 15 % Contractor overhead 3,476.29
Grand Total 26,651.56

38 x 75 mm thick sal wood frame with 3 mm thick fully glazed


7.04a G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 10,342.38 11,893.73
1.22 =2.23 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 9.000 Nos. 900.00 8,100.00
Labour
Unskilled 0.900 Nos. 600.00 540.00
Wood Sal 0.049 Cum. 257,500.00 12,617.50
Glass 3 mm thick-Plane 1.085 Sqm. 782.80 849.33
Hinge 75 mm 8.000 Sqm. 27.81 222.48
Materials
Towerbolt 100 mm. 4.000 Cum. 61.80 247.20

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 20 of 276
Materials
Handle 2.000 Nos. 206.00 412.00
Pech killas L.S. 75.00
Total 23,063.51
Rate analysis for : 2.23 Sqm. 15 % Contractor overhead 3,459.52
Grand Total 26,523.03

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 21 of 276

38 x 75 mm thick Gamhair wood frame with 4 mm thick fully


7.05 G3(10-4) glazed shutter fixing work with all complete. Size of shutter Sqm. 6,028.99 6,933.33
1.829 x 1.22 =2.23 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 9.000 Nos. 900.00 8,100.00
Labour
Unskilled 0.900 Nos. 600.00 540.00
Wood Gamhair 0.049 Cum. 58,916.00 2,886.88
Glass 4 mm thick-Plane 1.085 Sqm. 885.80 961.09
Hinge 75 mm 8.000 Nos. 27.81 222.48
Materials
Towerbolt 100 mm. 4.000 Nos. 61.80 247.20
Handle 2.000 Nos. 206.00 412.00
Pech killas L.S. 75.00
Total 13,444.65
Rate analysis for : 2.23 Sqm. 15 % Contractor overhead 2,016.69
Grand Total 15,461.34

38 mm thick sal wood frame with 4 mm thick commercial


7.06 G4(10-7) plywood (bothside) flush shutter fixing with all comolete. Sqm. 8,376.67 9,633.17
Size of shutter 1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 7.000 Nos. 900.00 6,300.00
Labour
Unskilled 0.700 Nos. 600.00 420.00
Wood Sal 0.0346 Cum. 257,500.00 8,909.50
Ply wood 4 mm thick commercial 4.650 Sqm. 381.10 1,772.11
Hinge 100 mm 3.000 Nos. 36.05 108.15
Materials
Towerbolt 150 mm. 2.000 Nos. 92.70 185.40
Mortice lock(Brass) 1.000 Nos. 1,060.48 1,060.48
Pech killas L.S. 50.00
Total 18,805.64
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,820.84
Grand Total 21,626.48

38 mm thick sal wood frame with 3 mm thick TEAK


plywood (Both side ) flush shutter fixing with all comolete.
7.07 G4(10-8) Size of shutter 1.092 x 2.058 =2.245 Sqm. Sqm. 8,174.00 9,400.10

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 900.00 6,300.00
Labour
Unskilled 0.700 Nos. 600.00 420.00
Wood Sal 0.0346 Cum. 257,500.00 8,909.50
Ply wood 4 mm thick Teak 2.325 Sqm. 566.50 1,317.11
Hinge 100 mm 3.000 Nos. 36.05 108.15
Materials
Towerbolt 150 mm. 2.000 Nos. 92.70 185.40
Mortice lock(Brass) 1.000 Nos. 1,060.48 1,060.48
Pech killas L.S. 50.00
Total 18,350.64
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,752.59
Grand Total 21,103.23

38 mm thick sal wood frame with 26 Bwg G.I. plane sheet


7.08 G4(10-9) (bothside) shutter fixing with all comolete. Size of shutter Sqm. 8,546.66 9,828.66
1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 7.000 Nos. 900.00 6,300.00
Labour
Unskilled 0.700 Nos. 600.00 420.00
Wood Sal 0.0346 Cum. 257,500.00 8,909.50
GI plane sheet 26 gauge 4.650 Sqm. 613.70 2,853.72
Hinge 100 mm 3.000 Nos. 36.05 108.15
Materials Towerbolt 150 mm. 2.000 Nos. 92.70 185.40
Handle 1.000 Nos. 206.00 206.00
Lockingset 250 mm. 1.000 Nos. 154.50 154.50
Pech killas L.S. 50.00
Total 19,187.27
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,878.09
Grand Total 22,065.36

38 mm thick sal wood frame with 24 Bwg G.I. mosquito


7.09 G4(10-10) proof & Expanded metal net net shutter fixing with all Sqm. 7,075.02 8,136.27
comolete. Size of shutter 1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.000 Nos. 900.00 4,500.00
Labour
Unskilled 0.500 Nos. 600.00 300.00
Wood Sal 0.026 Cum. 257,500.00 6,695.00
Mosquito proof net 2.130 Sqm. 1,390.50 2,961.76
Expanded metal 2.130 Sqm. 182.10 387.87
Hinge 100 mm 3.000 Nos. 36.05 108.15
Materials
Towerbolt 150 mm. 2.000 Nos. 92.70 185.40
Handle 2.000 Nos. 206.00 412.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Materials Rate_Analysis_Dhanusha_Civil_2075/076 Page 22 of 276

Door spring 1.000 Nos. 283.25 283.25


Pech killas L.S. 50.00
Total 15,883.43
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,382.51
Grand Total 18,265.94

38 mm thick sal wood frame with 24 Bwg G.I. mosquito


7.10 G4(10-10) proof net shutter fixing with all comolete. Size of shutter Sqm. 6,902.25 7,937.59
1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.000 Nos. 900.00 4,500.00
Labour
Unskilled 0.500 Nos. 600.00 300.00
Wood Sal 0.026 Cum. 257,500.00 6,695.00
Mosquito proof net 18 mess good(steel)
quality 2.130 Sqm. 1,390.50 2,961.76
Hinge 100 mm 3.000 Nos. 36.05 108.15
Materials
Towerbolt 150 mm. 2.000 Nos. 92.70 185.40
Handle 2.000 Nos. 206.00 412.00
Door spring 1.000 Nos. 283.25 283.25
Pech killas L.S. 50.00
Total 15,495.56
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,324.33
Grand Total 17,819.89

7.11 G5(10-11B) 4 mm thick plane glass fixing work with wooden listies. Sqm. 990.24 1,138.77
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.060 Nos. 900.00 54.00
Labour
Unskilled 0.006 Nos. 600.00 3.60
Glass 4 mm thick-Plane 1.000 Sqm. 885.80 885.80
Materials Wooden listies ½" 4.050 Rmtr. 7.86 31.84
Killas L.S. 15.00
Total 990.24
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 148.53
Grand Total 1,138.77

7.12 G5(10-11B) 26 Bwg plane sheet fixing work with wooden listies. Sqm. 745.49 857.31
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.060 Nos. 900.00 54.00
Labour
Unskilled 0.006 Nos. 600.00 3.60
GI plane sheet 26 gauge 1.000 Sqm. 613.70 613.70
Materials Wooden listies ¾" 4.050 Sqm. 14.62 59.19
Killas L.S. 15.00
Total 745.49
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 111.82
Grand Total 857.31

7.13 G6(10-12) 4 mm thick ply wood fixing work with wooden listies. Sqm. 541.07 622.23
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.060 Nos. 900.00 54.00
Labour
Unskilled 0.006 Nos. 600.00 3.60
Ply wood 4 mm thick commercial 1.050 Sqm. 381.10 400.15
Materials Wooden listies 1" 4.050 Sqm. 16.87 68.32
Killas L.S. 15.00
Total 541.07
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 81.16
Grand Total 622.23

7.14 G5(10-11B) Mosquito proof net fixing work with wooden listies. Sqm. 1,522.29 1,750.63
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.060 Nos. 900.00 54.00
Labour
Unskilled 0.006 Nos. 600.00 3.60
Mosquito proof net 1.000 Sqm. 1,390.50 1,390.50
Materials Wooden listies ¾" 4.050 Rmtr. 14.62 59.19
Killas L.S. 15.00
Total 1,522.29
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 228.34
Grand Total 1,750.63

Mosquito proof & Expanded metal net fixing work with


7.15 G5(10-11B) wooden listies. Sqm. 1,713.52 1,970.54

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.060 Nos. 900.00 54.00
Labour
Unskilled 0.006 Nos. 600.00 3.60
Mosquito proof net 1.000 Sqm. 1,390.50 1,390.50
Expanded metal 1.000 Sqm. 182.10 182.10
Materials
Wooden listies 1" 4.050 Rmtr. 16.87 68.32
Killas L.S. 15.00
Total 1,713.52
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 257.02
Grand Total 1,970.54

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 23 of 276

False ceiling of 6 mm thick commerical plywood with 50


7.16 10-16-A mm x 75 mm size local wood frame of box size 0.600 x Sqm. 3,811.20 4,382.88
0.900 m and fixing of wooden listy in joints
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 23.000 Nos. 900.00 20,700.00
Labour
Unskilled 2.300 Nos. 600.00 1,380.00
Wood Local 0.450 Cum. 61,800.00 27,810.00
Ply wood 6 mm thick commercial 37.500 Sqm. 566.50 21,243.75
Materials
Wooden listies 1½" 100.000 Rmtr. 641.69 64,169.00 L.S.
Killas Kg. 531.97 300.00 L.S.
Total 135,602.75
Rate analysis for : 35.58 Sqm. 15 % Contractor overhead 20,340.41
Grand Total 155,943.16

Torsteel reinforcement bar fixing work in window frame


7.17 G7(10-21) with all complete, Kg. 127.33 146.43

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 20.00 Nos. 900.00 18,000.00
Labour
Unskilled 20.00 Nos. 600.00 12,000.00
Materials TOR/TMT reinforcement bar 1.05 M.T. 92,700.00 97,335.00
Total 127,335.00
Rate analysis for : 1.00 M.T. 15 % Contractor overhead 19,100.25
Grand Total 146,435.25

38 x100mm thick sal wood frame with 12 mm thick


G8(10-3 & commercial plywood paneled & one side 4 mm thick Teak
7.18 plywood paneled shutter fixing with all comolete. Size of Sqm. 8,701.12 10,006.28
10-7)
shutter 1.092 x 2.058 =2.245 Sqm.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 900.00 6,300.00
Labour
Unskilled 0.700 Nos. 600.00 420.00
Wood Sal 0.0346 Cum. 257,500.00 8,909.50
Ply wood 12 mm thick commercial 1.900 Sqm. 587.10 1,115.49
Ply wood 4 mm thick Teak 1.900 Sqm. 566.50 1,076.35
Wooden listies ¾" 7.434 Rmtr. 14.62 108.65
Materials Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 36.05 108.15
Towerbolt 150 mm. 2.000 Nos. 92.70 185.40
Mortice lock(Brass) 1.000 Nos. 1,060.48 1,060.48
Pech killas L.S. 50.00
Total 19,534.02
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,930.10
Grand Total 22,464.12

38 x100mm thick sal wood frame with 12 mm thick


G9(10-3 & commercial plywood paneled & both side 4 mm thick Teak
7.19 plywood paneled shutter fixing with all comolete. Size of Sqm. 9,228.96 10,613.30
10-7)
shutter 1.092 x 2.058 =2.245 Sqm.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 900.00 6,300.00
Labour
Unskilled 0.700 Nos. 600.00 420.00
Wood Sal 0.0346 Cum. 257,500.00 8,909.50
Ply wood 12 mm thick commercial 1.900 Sqm. 587.10 1,115.49
Ply wood 4 mm thick Teak 3.800 Sqm. 566.50 2,152.70
Wooden listies ¾" 14.868 Rmtr. 14.62 217.31
Materials Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 36.05 108.15
Towerbolt 150 mm. 2.000 Nos. 92.70 185.40
Mortice lock(Brass) 1.000 Nos. 1,060.48 1,060.48
Pech killas L.S. 50.00
Total 20,719.03
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 3,107.85
Grand Total 23,826.88

38 x100mm thick sal wood frame with 12 mm thick water


G10(10-3 & proof plywood paneled & one side 4 mm thick Teak
7.20 plywood paneled shutter fixing with all comolete. Size of Sqm. 8,701.12 10,006.28
10-7)
shutter 1.092 x 2.058 =2.245 Sqm.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 900.00 6,300.00
Labour
Unskilled 0.700 Nos. 600.00 420.00
Wood Sal 0.0346 Cum. 257,500.00 8,909.50
Ply wood 12 mm thick water proof 1.900 Sqm. 587.10 1,115.49
Ply wood 4 mm thick Teak 1.900 Sqm. 566.50 1,076.35
Wooden listies ¾" 7.434 Rmtr. 14.62 108.65
Materials Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 36.05 108.15
Towerbolt 150 mm. 2.000 Nos. 92.70 185.40

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Materials Rate_Analysis_Dhanusha_Civil_2075/076 Page 24 of 276

Mortice lock(Brass) 1.000 Nos. 1,060.48 1,060.48


Pech killas L.S. 50.00
Total 19,534.02
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,930.10
Grand Total 22,464.12
H - FLOORING WORK

25 mm or 1" thick P.C.C. (1:2:4) work in floor with all


8.01 H1(11-1A) complete. Sqm. 389.18 447.56

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 1.500 Nos. 600.00 900.00
Cement 0.090 M.T. 18,025.00 1,622.25
Materials Sand 0.120 Cum. 837.25 100.47
Aggrigate 12 mm-River bed 0.230 Cum. 1,213.75 279.16
Total 3,891.88
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 583.78
Grand Total 4,475.66

38 mm or 1½" thick P.C.C. (1:2:4) work in floor with all


8.02 H1(11-1B) complete. Sqm. 525.59 604.42

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 900.00 1,125.00
Labour
Unskilled 2.000 Nos. 600.00 1,200.00
Cement 0.130 M.T. 18,025.00 2,343.25
Materials Sand 0.180 Cum. 837.25 150.70
Aggrigate 12 mm-River bed 0.360 Cum. 1,213.75 436.95
Total 5,255.90
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 788.38
Grand Total 6,044.28

50 mm or 2" thick P.C.C. (1:2:4) work in floor with all


8.03 H1(11-1C) complete. Sqm. 644.01 740.61

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 900.00 1,125.00
Labour
Unskilled 2.500 Nos. 600.00 1,500.00
Cement 0.170 M.T. 18,025.00 3,064.25
Materials Sand 0.230 Cum. 837.25 192.56
Aggrigate 20 mm-River bed 0.460 Cum. 1,213.75 558.32
Total 6,440.13
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 966.01
Grand Total 7,406.14

75 mm or 3" thick P.C.C. (1:2:4) work in floor with all


8.04 H1(11-1D) complete. Sqm. 872.15 1,002.97

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 900.00 1,125.00
Labour
Unskilled 3.000 Nos. 600.00 1,800.00
Cement 0.260 M.T. 18,025.00 4,686.50
Materials Sand 0.340 Cum. 837.25 284.66
Aggrigate 20 mm-River bed 0.680 Cum. 1,213.75 825.35
Total 8,721.51
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,308.22
Grand Total 10,029.73

25 mm thick mosaic flooring with 20 mm thick P.C.C.


8.05 H2(11-2) (1:2:4) & 5 mm thick white cement marble chips1:1 rubbing Sqm. 1,737.75 1,998.41
& polishing work with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.500 Nos. 900.00 2,250.00
Labour
Unskilled 16.000 Nos. 600.00 9,600.00
Cement 0.065 M.T. 18,025.00 1,171.62
Sand 0.088 Cum. 837.25 73.67
Aggrigate 12 mm-River bed 0.176 Cum. 1,213.75 213.62
White cement 0.061 M.T. 28,840.00 1,759.24
Materials Marble chips 3 mm 0.061 Cum. 17,510.00 1,068.11
Oxalic acid powder 0.365 Kg. 360.50 131.58
Main Polish 0.118 Kg. 515.00 60.77
Tarpaintain oil 0.538 Ltr. 226.60 121.91
Carborendam Stone 2.000 Nos. 463.50 927.00 L.S. 2 Nos.
Total 17,377.52
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 2,606.62
Grand Total 19,984.14

25 mm thick mosaic flooring with 19 mm thick cement


8.06 H3(11-3) sand plaster 1:2 & 6 mm thick white cement marble Sqm. 3,110.57 3,577.15
chips1:1 rubbing & polishing work with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 25 of 276

Skilled 3.500 Nos. 900.00 3,150.00


Labour
Unskilled 36.000 Nos. 600.00 21,600.00
Cement 0.121 M.T. 18,025.00 2,181.02
Sand crusher(local) 0.165 Cum. 837.25 138.14
White cement 0.069 M.T. 28,840.00 1,989.96
Marble chips 3 mm 0.047 Cum. 17,510.00 822.97
Materials
Oxalic acid powder 0.340 Kg. 360.50 122.57
Main Polish 0.118 Kg. 515.00 60.77
Tarpaintain oil 0.500 Ltr. 226.60 113.30
Carborendam Stone 2.000 Nos. 463.50 927.00 2 Nos.
Total 31,105.73
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,665.85
Grand Total 35,771.58

20 mm thick mosaic flooring with 12.5mm thick cement


8.07 H4(11-4) sand plaster 1:2 & 6 mm thick white cement marble Sqm. 3,133.42 3,603.44
chips1:1 rubbing & polishing work with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.500 Nos. 900.00 3,150.00
Labour
Unskilled 36.000 Nos. 600.00 21,600.00
Cement 0.089 M.T. 18,025.00 1,604.22
Sand crusher(local) 0.122 Cum. 837.25 102.14
White cement 0.089 M.T. 28,840.00 2,566.76
Marble chips 3 mm 0.061 Cum. 17,510.00 1,068.11
Materials
Oxalic acid powder 0.370 Kg. 360.50 133.38
Main Polish 0.118 Kg. 515.00 60.77
Tarpaintain oil 0.538 Ltr. 226.60 121.91
Carborendam Stone 2.000 Nos. 463.50 927.00 2 Nos.
Total 31,334.29
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,700.14
Grand Total 36,034.43

20 mm thick Terrazo tile paving with 20 mm thick cement


8.08 H5(11-5) sand mortar 1:4 rubbing & polishing work with all Sqm. 2,924.22 3,362.86
complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.000 Nos. 900.00 1,800.00
Labour
Unskilled 12.600 Nos. 600.00 7,560.00
Terrazo tile 20 mm thick 11.000 Sqm. 1,545.00 16,995.00
Cement 0.081 M.T. 18,025.00 1,460.02
Sand crusher(local) 0.220 Cum. 837.25 184.19
Materials Oxalic acid powder 0.370 Kg. 360.50 133.38
Main Polish 0.118 Kg. 515.00 60.77
Tarpaintain oil 0.538 Ltr. 226.60 121.91
Carborendam Stone 2.000 Nos. 463.50 927.00 2 Nos.
Total 29,242.27
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,386.34
Grand Total 33,628.61

15 mm thick marble tile 600x600 mm paving with 20 mm


8.09 11-6 thick cement sand mortar 1:2 rubbing & polishing work Sqm. 3,871.85 4,452.63
with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.000 Nos. 900.00 1,800.00
Labour
Unskilled 8.000 Nos. 600.00 4,800.00
Marble tile 15mm 11.000 Sqm. 2,575.00 28,325.00
Cement 0.133 M.T. 18,025.00 2,397.32
Sand crusher(local) 0.183 Cum. 837.25 153.21
Materials Oxalic acid powder 0.370 Kg. 360.50 133.38
Main Polish 0.118 Kg. 515.00 60.77
Tarpaintain oil 0.538 Ltr. 226.60 121.91
Carborendam Stone 2.000 Nos. 463.50 927.00 L.S. 2 Nos.
Total 38,718.59
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 5,807.78
Grand Total 44,526.37

Porcelain glazed /non glazed tile paving work in cement


8.10 H6(11-7) sand (1:4) mortar Sqm. 3,205.82 3,686.69

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 13.000 Nos. 900.00 11,700.00
Labour
Unskilled 4.500 Nos. 600.00 2,700.00
Porecelain glazed/non glazed tile 11.000 Sqm. 1,493.50 16,428.50
Cement 0.056 M.T. 18,025.00 1,009.40
Materials
Sand crusher(local) 0.152 Cum. 837.25 127.26
White cement 3.228 Kg. 28.84 93.09
Total 32,058.25
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,808.73
Grand Total 36,866.98

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 26 of 276

Spartik Non-glazed tile paving work in cement sand (1:4)


8.11 H6(11-7) mortar Sqm. 2,717.72 3,125.38

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 13.000 Nos. 900.00 11,700.00
Labour
Unskilled 4.500 Nos. 600.00 2,700.00
Spartik non glazed tile 11.000 Sqm. 1,049.77 11,547.47
Cement 0.056 M.T. 18,025.00 1,009.40
Materials
Sand crusher(local) 0.152 Cum. 837.25 127.26
White cement 3.228 Kg. 28.84 93.09
Total 27,177.22
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,076.58
Grand Total 31,253.80

Flat Brick paving in 1:6 & cement sand pointing in1:2 in


8.12 H12(11-12) joints Sqm. 989.86 1,138.34

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.250 Nos. 900.00 2,025.00
Labour
Unskilled 3.250 Nos. 600.00 1,950.00
Brick chimney 350.000 Nos. 12.36 4,326.00
Materials Cement 0.078 M.T. 18,025.00 1,405.95
Sand crusher(local) 0.229 Cum. 837.25 191.73
Total 9,898.68
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,484.80
Grand Total 11,383.48

Edge Brick paving in 1:6 & cement sand pointing in1:2 in


8.13 H13(11-13) joints Sqm. 1,178.06 1,354.77

Resources Level/Type Quantity Unit Rate Amount Remarks

Skilled 1.100 Nos. 900.00 990.00


Labour
Unskilled 1.800 Nos. 600.00 1,080.00

Brick chimney 580.000 Nos. 12.36 7,168.80


Materials Cement 0.121 M.T. 18,025.00 2,181.02
Sand crusher(local) 0.431 Cum. 837.25 360.85
Total 11,780.67
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,767.10
Grand Total 13,547.77

Dry flat Brick paving work


8.14 H15(11-15A) Sqm. 597.04 686.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 1.000 Nos. 600.00 600.00

Materials Brick chimney 350.000 Nos. 12.36 4,326.00


Sand crusher(local) 0.710 Cum. 837.25 594.44
Total 5,970.44
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 895.56
Grand Total 6,866.00

Dry flat Brick (Brick Bat ) paving work


8.15 H15(11-15A) Sqm. 380.74 437.85
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 900.00 450.00
Labour
Unskilled 1.000 Nos. 600.00 600.00
Brick Bat 350.000 Nos. 6.18 2,163.00 50% brick rate
Materials
Sand crusher(local) 0.710 Cum. 837.25 594.44
Total 3,807.44
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 571.11
Grand Total 4,378.55

Dry edge Brickpaving work


8.16 H15(11-15B) Sqm. 1,061.32 1,220.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 3.250 Nos. 600.00 1,950.00

Brick chimney 580.000 Nos. 12.36 7,168.80


Materials
Sand crusher(local) 0.710 Cum. 837.25 594.44
Total 10,613.24
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,591.98
Grand Total 12,205.22

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 27 of 276

Note : 1.00 Cum Brick bat=438 Brick

Dry edge Brick (Brick Bat ) paving work


8.17 H15(11-15B) Sqm. 702.88 808.31
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 3.250 Nos. 600.00 1,950.00

Brick Bat 580.000 Nos. 6.18 3,584.40 50% brick rate


Materials
Sand crusher(local) 0.710 Cum. 837.25 594.44
Total 7,028.84
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,054.32
Grand Total 8,083.16

8.18 H16( 11-16) Stone filling in floor with sand lead up to 30 mtr. Cum. 5,757.44 6,621.05
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Stone block 1.000 Cum. 2,163.00 2,163.00
Materials
Sand Local 0.710 Cum. 837.25 594.44
Total 5,757.44
Rate analysis for :1.00 Cum. 15 % Contractor overhead 863.61
Grand Total 6,621.05

Edge brick paving with sand packing in voids & cement


8.19 H17( 11-17) sand (1:3) flush pointing in top surface. Sqm. 1,144.22 1,315.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.000 Nos. 900.00 1,800.00
Labour
Unskilled 4.000 Nos. 600.00 2,400.00
Brick chimney 550.000 Cum. 12.36 6,798.00
Materials
cement 0.020 Cum. 18,025.00 360.50
Sand crusher(local) 0.100 Cum. 837.25 83.72
Total 11,442.22
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,716.33
Grand Total 13,158.55

Sand filling work


8.20 H19( 11-19A) Cum. 1,505.97 1,731.87
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 6.500 Nos. 900.00 5,850.00
Materials Sand crusher(local) 11.000 Cum. 837.25 9,209.75
Total 15,059.75
Rate analysis for :10.00 Cum. 15 % Contractor overhead 2,258.96
Grand Total 17,318.71

15-15 cm. Brick bat filling work.


8.21 H19( 11-19B) Cum. 913.59 1,050.63
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled 10.00 Nos. 900.00 9,000.00
Materials Brick bat 11.00 Cum. 12.36 135.96
Total 9,135.96
Rate analysis for :10.00 Cum. 15 % Contractor overhead 1,370.39
Grand Total 10,506.35

8.22 H20( 11-20) 3 mm thick neat cement punning work. Sqm. 245.89 282.77
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 1.000 Nos. 600.00 600.00
Materials Cement 53.200 Kg. 18.03 958.93
Total 2,458.93
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 368.83
Grand Total 2,827.76

25 mm thick Sal wood planking work with 50x75 mm sal


8.23 H21(11-21) wood frame in 600x600 mm Sqm. 11,484.75 13,207.46

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 6.500 Nos. 900.00 5,850.00
Labour
Unskilled 0.650 Nos. 600.00 390.00
Wood Sal 0.421 Cum. 257,500.00 108,407.50
Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 28 of 276

Materials
Killa L.S. 200.00
Total 114,847.50
Rate analysis for :10.00 Sqm.
15 % Contractor overhead 17,227.12
Grand Total 132,074.62

8.24 H24( 11-20) 3 mm thick neat Plaster of Paris punning work. Sqm. 269.64 310.09
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 1.000 Nos. 600.00 600.00
Materials Plaster of Paris 53.200 Kg. 22.49 1,196.46
Total 2,696.46
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 404.46
Grand Total 3,100.92

Clay tile(Machine Made) paving work in cement sand (1:4)


8.25 H25(11-7) mortar Sqm. 1,592.54 1,831.42

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 13.000 Nos. 900.00 11,700.00
Labour
Unskilled 4.500 Nos. 600.00 2,700.00
clay tile(Machine Made) 11.000 Sqm. 35.34 388.74
Materials Cement 0.056 M.T. 18,025.00 1,009.40
Sand crusher(local) 0.152 Cum. 837.25 127.26
Total 15,925.40
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 2,388.81
Grand Total 18,314.21

Granite 16mm thick paving with 20 mm thick cement sand


8.26 H26(11-6) mortar 1:2 rubbing & polishing work with all complete. Sqm. 6,197.35 7,126.95

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.000 Nos. 900.00 1,800.00
Labour
Unskilled 8.000 Nos. 600.00 4,800.00

Granite 16mm thick 11.000 Sqm. 3,952.72 43,479.92


Cement 0.133 M.T. 18,025.00 2,397.32

Sand crusher(local) 0.183 Cum. 837.25 153.21


Materials Oxalic acid powder 0.370 Kg. 360.50 133.38
Main Polish 0.118 Kg. 515.00 60.77

Tarpaintain oil 0.538 Ltr. 226.60 121.91


Carborendam Stone 2.000
Nos. 463.50 927.00 L.S. 2 Nos.
Equipment Unskilled 13.500
Nos. 600.00 8,100.00
Total 61,973.51
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 9,296.02
Grand Total 71,269.53
I - PLASTER & POINTING WORK

9.01 I1(12-1B) 12.5 mm. thick cement sand plaster work 1:3 on wall. Sqm. 327.37 376.47
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 900.00 10,800.00
Labour
Unskilled 16.000 Nos. 600.00 9,600.00

Materials Cement 0.625 M.T. 18,025.00 11,265.62


Sand crusher(local) 1.280 Cum. 837.25 1,071.68
Total 32,737.30
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,910.59
Grand Total 37,647.89

9.02 I1(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on wall. Sqm. 313.19 360.17
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 900.00 10,800.00
Labour
Unskilled 16.000 Nos. 600.00 9,600.00
Cement 0.538 M.T. 18,025.00 9,697.45
Materials
Sand crusher(local) 1.460 Cum. 837.25 1,222.38
Total 31,319.83
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,697.97
Grand Total 36,017.80

9.03 I1(12-1D) 12.5 mm. thick cement sand plaster work 1:6 on wall. Sqm. 286.00 328.90
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 900.00 10,800.00
Labour
Unskilled 16.000 Nos. 600.00 9,600.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 29 of 276

Cement 0.382 M.T. 18,025.00 6,885.55


Materials
Sand crusher(local) 1.570 Cum. 837.25 1,314.48
Total 28,600.03
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,290.00
Grand Total 32,890.03

9.04 I4(12-4A) 20 mm. thick cement sand plaster work 1:3 on wall etc. Sqm. 429.36 493.77
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 900.00 12,600.00
Labour
Unskilled 19.000 Nos. 600.00 11,400.00
Cement 0.960 M.T. 18,025.00 17,304.00
Materials
Sand crusher(local) 1.950 Cum. 837.25 1,632.63
Total 42,936.63
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,440.49
Grand Total 49,377.12

9.05 I4(12-4B) 20 mm. thick cement sand plaster work 1:4 on wall etc. Sqm. 404.42 465.08
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 900.00 12,600.00
Labour
Unskilled 19.000 Nos. 600.00 11,400.00
Cement 0.810 M.T. 18,025.00 14,600.25
Materials
Sand crusher(local) 2.200 Cum. 837.25 1,841.95
Total 40,442.20
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,066.33
Grand Total 46,508.53

9.06 I4(12-4C) 20 mm. thick cement sand plaster work1:6 on wall etc. Sqm. 362.41 416.78
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 900.00 12,600.00
Labour
Unskilled 19.000 Nos. 600.00 11,400.00
Cement 0.570 M.T. 18,025.00 10,274.25
Materials
Sand crusher(local) 2.350 Cum. 837.25 1,967.53
Total 36,241.78
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,436.26
Grand Total 41,678.04

9.07 I5(12-5) 25 mm. thick mud plaster on wall etc. Sqm. 343.28 394.78
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 20.000 Nos. 900.00 18,000.00
Labour
Unskilled 25.000 Nos. 600.00 15,000.00
Mud 3.000 Cum. 309.00 927.00
Materials Bhush 10.000 Kg. 15.45 154.50
Gobar 120.000 Kg. 2.06 247.20
Total 34,328.70
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,149.30
Grand Total 39,478.00

9.08 I5(12-6) 12.5 mm. thick mud plaster on wall etc. Sqm. 268.59 308.88
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 15.000 Nos. 900.00 13,500.00
Labour
Unskilled 20.000 Nos. 600.00 12,000.00
Mud 1.500 Cum. 309.00 463.50
Materials Bhush 50.000 Kg. 15.45 772.50
Gobar 60.000 Kg. 2.06 123.60
Total 26,859.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,028.94
Grand Total 30,888.54

9.09 I7(12-1B) 12.5 mm. thick cement sand plaster work (1:3 ) on ceilling Sqm. 378.37 435.12

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.000 Nos. 900.00 13,500.00
Labour
Unskilled 20.000 Nos. 600.00 12,000.00

Materials Cement 0.625 M.T. 18,025.00 11,265.62


Sand crusher(local) 1.280 Cum. 837.25 1,071.68
Total 37,837.30
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,675.59
Grand Total 43,512.89

9.10 I7(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on ceilling Sqm. 364.19 418.82
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 15.000 Nos. 900.00 13,500.00
Labour
Unskilled 20.000 Nos. 600.00 12,000.00
Cement 0.538 M.T. 18,025.00 9,697.45
Materials
Sand crusher(local) 1.460 Cum. 837.25 1,222.38
Total 36,419.83
Rate analysis for :100.00 Sqm.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 30 of 276

Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,462.97


Grand Total 41,882.80

Flush pointing works in 1:1 Cement sand mortar on Brick


9.11 I8(14-1A) masonry wall Sqm. 225.30 259.09

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.500 Nos. 900.00 9,450.00
Labour
Unskilled 12.000 Nos. 600.00 7,200.00
Cement 0.316 M.T. 18,025.00 5,695.90
Materials
Sand crusher(local) 0.220 Cum. 837.25 184.19
Total 22,530.09
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,379.51
Grand Total 25,909.60

Flush pointing works in 1:2 Cement sand mortar on Brick


9.12 I8(14-1B) masonry work Sqm. 206.78 237.79

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.500 Nos. 900.00 9,450.00
Labour
Unskilled 12.000 Nos. 600.00 7,200.00
Cement 0.210 M.T. 18,025.00 3,785.25
Materials
Sand crusher(local) 0.290 Cum. 837.25 242.80
Total 20,678.05
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,101.70
Grand Total 23,779.75

Flush pointing works in 1:3 Cement sand mortar on Brick


9.13 I8(14-1C) masonry wall Sqm. 197.11 226.68

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.500 Nos. 900.00 9,450.00
Labour
Unskilled 12.000 Nos. 600.00 7,200.00
Cement 0.155 M.T. 18,025.00 2,793.87
Materials
Sand crusher(local) 0.320 Cum. 837.25 267.92
Total 19,711.79
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,956.76
Grand Total 22,668.55

Rulled pointing works in 1:1 Cement sand mortar on Brick


9.14 I8(14-1A) masonry wall Sqm. 308.55 354.83

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.750 Nos. 900.00 14,175.00
Labour
Unskilled 18.000 Nos. 600.00 10,800.00
Cement 0.316 M.T. 18,025.00 5,695.90
Materials
Sand crusher(local) 0.220 Cum. 837.25 184.19
Total 30,855.09
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,628.26
Grand Total 35,483.35

Ruled pointing works in 1:2 Cement sand mortar on Brick


9.15 I8(14-1B) masonry work Sqm. 290.03 333.53

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.750 Nos. 900.00 14,175.00
Labour
Unskilled 18.000 Nos. 600.00 10,800.00
Cement 0.210 M.T. 18,025.00 3,785.25
Materials
Sand crusher(local) 0.290 Cum. 837.25 242.80
Total 29,003.05
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,350.45
Grand Total 33,353.50

Ruled pointing works in 1:3 Cement sand mortar on Brick


9.16 I8(14-1C) masonry wall Sqm. 280.36 322.42

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.750 Nos. 900.00 14,175.00
Labour
Unskilled 18.000 Nos. 600.00 10,800.00
Cement 0.155 M.T. 18,025.00 2,793.87
Materials
Sand crusher(local) 0.320 Cum. 837.25 267.92
Total 28,036.79
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,205.51
Grand Total 32,242.30

Flush/Rulled pointing works in 1:1 Cement sand mortar


9.17 I9(14-2A) on Stone masonry wall Sqm. 287.91 331.10
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 14.000 Nos. 600.00 8,400.00
Cement 0.612 M.T. 18,025.00 11,031.30
Materials
Sand crusher(local) 0.430 Cum. 837.25 360.01
Total 28,791.31
Rate analysis for :100.00 Sqm.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 31 of 276

Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,318.69


Grand Total 33,110.00

Flush/Rulled pointing works in 1:2 Cement sand mortar


9.18 I9(14-2B) on Stone masonry work Sqm. 252.31 290.16
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 14.000 Nos. 600.00 8,400.00
Cement 0.408 M.T. 18,025.00 7,354.20
Materials
Sand crusher(local) 0.570 Cum. 837.25 477.23
Total 25,231.43
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,784.71
Grand Total 29,016.14

Flush/Rulled pointing works in 1:3 Cement sand mortar


9.19 (14-2C) on Stone masonry work Sqm. 234.43 269.59

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 14.000 Nos. 600.00 8,400.00
Cement 0.306 M.T. 18,025.00 5,515.65
Materials
Sand crusher(local) 0.630 Cum. 837.25 527.46
Total 23,443.11
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,516.46
Grand Total 26,959.57

Flush/Rulled pointing works in 1:3 Cement sand mortar


9.20 I10(14-3) on Aslar Stone masonry work Sqm. 153.50 176.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 8.000 Nos. 900.00 7,200.00
Labour
Unskilled 10.000 Nos. 600.00 6,000.00
Cement 0.110 M.T. 18,025.00 1,982.75
Materials
Sand crusher(local) 0.200 Cum. 837.25 167.45
Total 15,350.20
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,302.53
Grand Total 17,652.73

1:3 Cement sand pointing on 450 mm x 450 mm flat stone


9.21 I11(14-4) paving joints. Sqm. 82.82 95.24

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.000 Nos. 900.00 4,500.00
Labour
Unskilled 5.000 Nos. 600.00 3,000.00
Cement 0.042 M.T. 18,025.00 757.05
Materials
Sand crusher(local) 0.030 Cum. 837.25 25.11
Total 8,282.16
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,242.32
Grand Total 9,524.48

1:1 Cement sand pointing on Teliya brick paving joints.


9.22 I12(14-5) Sqm. 177.87 204.55

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 10.000 Nos. 600.00 6,000.00
Cement 0.150 M.T. 18,025.00 2,703.75
Materials
Sand crusher(local) 0.100 Cum. 837.25 83.72
Total 17,787.47
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,668.12
Grand Total 20,455.59

9.23 (14-6) 3 mm thick Cement sand 1:1 flushing plaster Sqm. 212.48 244.36
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 10.000 Nos. 600.00 6,000.00
Cement 0.336 M.T. 18,025.00 6,056.40
Materials
Sand crusher(local) 0.230 Cum. 837.25 192.56
Total 21,248.96
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,187.34
Grand Total 24,436.30

9.24 I13(14-7) 3 mm thick lime flushing plaster Sqm. 150.03 172.54


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 10.000 Nos. 600.00 6,000.00
Materials White lime 0.160 Kg. 23.56 3.76
Total 15,003.76
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,250.56

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 32 of 276
Rate analysis for :100.00 Sqm.
Grand Total 17,254.32

9.25 I14(14-8) 3 mm thick Cement flushing plaster Sqm. 243.36 279.87


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 900.00 9,000.00
Labour
Unskilled 10.000 Nos. 600.00 6,000.00
Materials Cement 0.518 M.T. 18,025.00 9,336.95
Total 24,336.95
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,650.54
Grand Total 27,987.49

9.26 I15 20 mm thick Jhalar/pani patti making over cement plaster Sqm. 168.31 193.55
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.025 Nos. 900.00 22.50
Labour
Unskilled 0.010 Nos. 600.00 6.00
Cement 0.007 M.T. 18,025.00 126.17
Materials Sand crusher(local) 0.004 Cum. 837.25 3.34
Water proofing compound 0.100 Kg. 103.00 10.30
Total 168.31
Rate analysis for :1.00 Rmtr. 15 % Contractor overhead 25.24
Grand Total 193.55

25 mm thick roofing tile butta plaster in cement sand (1:4)


9.27 I16 work Sqm. 641.69 737.94

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour
25mm thick roofing tile butta plaster 1.000 Sqm 641.69 641.69
Materials
Total 641.69
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 96.25
Grand Total 737.94

2 mm thick plane white putting plaster work in wall


9.28 I17 &ceilling Sqm. 221.23 254.41

Resources Level/Type QuantityUnit Rate Amount Remarks


Skilled 1.000
Nos. 900.00 900.00
Labour
Unskilled 1.000
Nos. 600.00 600.00
Materials White patti plaster 10.640Kg. 66.95 712.34
Total 2,212.34
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 331.85
Grand Total 2,544.19
J - PAINTING WORK

Two coat white washing work on wall.


10.01 J1(13-1B) Sqm. 27.54 31.68

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 900.00 1,350.00
Labour
Unskilled 1.100 Nos. 600.00 660.00
White lime 22.000 Kg. 23.56 518.32
Materials
gum 0.880 Kg. 257.50 226.60
Total 2,754.92
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 413.23
Grand Total 3,168.15

10.02 J1(13-1B) Two coat white washing work on ceilling. Sqm. 32.57 37.46
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.875 Nos. 900.00 1,687.50 25% Add for
Labour
Unskilled 1.375 Nos. 600.00 825.00 ceilling
White lime 22.000 Kg. 23.56 518.32
Materials
gum 0.880 Kg. 257.50 226.60
Total 3,257.42
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 488.61
Grand Total 3,746.03

10.03 J1(13-1C) Three coat white washing work on wall. Sqm. 54.03 62.14
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.000 Nos. 900.00 2,700.00
Labour
Unskilled 2.700 Nos. 600.00 1,620.00
White lime 32.000 Kg. 23.56 753.92
Materials
gum 1.280 Kg. 257.50 329.60
Total 5,403.52
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 810.52
Grand Total 6,214.04

10.04 J1(13-1C) Three coat white washing work on ceilling. Sqm. 64.83 74.56
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.750 Nos. 900.00 3,375.00 25% Add for
Labour
Unskilled 3.375 Nos. 600.00 2,025.00 ceilling
White lime 32.000 Kg. 23.56 753.92
Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 33 of 276

Materials
gum 1.280 Kg. 257.50 329.60
Total 6,483.52
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 972.52
Grand Total 7,456.04

10.05 J2(13-2) white washing work in old surface. Sqm. 14.78 17.00
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 900.00 720.00
Labour
Unskilled 0.700 Nos. 600.00 420.00
White lime 10.000 Kg. 23.56 235.60
Materials
gum 0.400 Kg. 257.50 103.00
Total 1,478.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 221.79
Grand Total 1,700.39

10.06 J3(13-3AB) One coat distemper painting work over primer coat. Sqm. 103.10 118.57
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.00 Nos. 900.00 3,600.00
Labour
Unskilled 4.00 Nos. 600.00 2,400.00
Distemper primer 8.00 Ltr. 329.60 2,636.80
Materials
Distemper Powder 6.50 Kg. 257.50 1,673.75
Total 10,310.55
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,546.58
Grand Total 11,857.13

10.07 J3(13-3ABC) Two coat distemper painting work over primer coat. Sqm. 142.98 164.42
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.80 Nos. 900.00 5,220.00
Labour
Unskilled 5.80 Nos. 600.00 3,480.00
Distemper primer 8.00 Ltr. 329.60 2,636.80
Materials
Distemper Powder 11.50 Kg. 257.50 2,961.25
Total 14,298.05
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,144.70
Grand Total 16,442.75

10.08 J3(13-3B) One coat distemper painting work without primer coat. Sqm. 46.73 53.74
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.00 Nos. 900.00 1,800.00
Labour
Unskilled 2.00 Nos. 600.00 1,200.00
Materials Distemper washable 6.50 Kg. 257.50 1,673.75
Total 4,673.75
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 701.06
Grand Total 5,374.81

10.09 J3(13-3BC) Two coat distemper painting work without primer coat. Sqm. 86.61 99.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.80 Nos. 900.00 3,420.00
Labour
Unskilled 3.80 Nos. 600.00 2,280.00
Materials Distemper washable 11.50 Kg. 257.50 2,961.25
Total 8,661.25
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,299.18
Grand Total 9,960.43

10.10 J3(13-3AB) One coat weather proof painting work over primer coat. Sqm. 174.87 201.10
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.00 Nos. 900.00 3,600.00
Labour
Unskilled 4.00 Nos. 600.00 2,400.00
Weather proof primer 8.00 Ltr. 360.50 2,884.00
Materials
Weather proof paint 6.50 Kg. 1,323.55 8,603.07
Total 17,487.07
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,623.06
Grand Total 20,110.13

Two coat weather proof painting work over primer coat.


10.11 J3(13-3ABC) Sqm. 268.04 308.25
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.80 Nos. 900.00 5,220.00
Labour
Unskilled 5.80 Nos. 600.00 3,480.00
Weather proof primer 8.00 Ltr. 360.50 2,884.00
Materials
Weather proof paint 11.50 Kg. 1,323.55 15,220.82
Total 26,804.82
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,020.72
Grand Total 30,825.54

One coat weather proof painting work without primer coat.


10.12 J3(13-3B) Sqm. 116.03 133.43

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.00 Nos. 900.00 1,800.00
Labour

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 34 of 276

Labour
Unskilled 2.00Nos. 600.00 1,200.00
Materials Weather proof paint 6.50 Kg. 1,323.55 8,603.07
Total 11,603.07
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,740.46
Grand Total 13,343.53

Two coat weather proof painting work without primer coat.


10.13 J3(13-3BC) Sqm. 209.20 240.58

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.80 Nos. 900.00 3,420.00
Labour
Unskilled 3.80 Nos. 600.00 2,280.00
Materials Weather proof paint 11.50 Kg. 1,323.55 15,220.82
Total 20,920.82
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,138.12
Grand Total 24,058.94

One coat water proof cement paint painting work in old


10.14 J4(13-4A) surface Sqm. 56.40 64.86

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.70 Nos. 900.00 1,530.00
Labour
Unskilled 1.70 Nos. 600.00 1,020.00
Materials Water proof cement paint 30.00 Kg. 103.00 3,090.00
Total 5,640.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 846.00
Grand Total 6,486.00

Two coat water proof cement paint painting work in old


10.15 J4(13-4B) surface Sqm. 124.95 143.69

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.00 Nos. 900.00 4,500.00
Labour
Unskilled 5.00 Nos. 600.00 3,000.00
Materials Water proof cement paint 48.50 Kg. 103.00 4,995.50
Total 12,495.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,874.32
Grand Total 14,369.82

10.16 J4(13-4A) One coat white cement paint painting work . Sqm. 34.15 39.27
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.70 Nos. 900.00 1,530.00
Labour
Unskilled 1.70 Nos. 600.00 1,020.00
Materials White cement 30.00 Kg. 28.84 865.20
Total 3,415.20
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 512.28
Grand Total 3,927.48

10.17 J4(13-4B) Two coat white cement paint painting work . Sqm. 88.98 102.33
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.00 Nos. 900.00 4,500.00
Labour
Unskilled 5.00 Nos. 600.00 3,000.00
Materials White cement 48.50 Kg. 28.84 1,398.74
Total 8,898.74
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,334.81
Grand Total 10,233.55

One coat enamel painting work over primer coat in wooden


10.18 J5(13-5AB) surface. Sqm. 197.09 226.65

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 8.00 Nos. 900.00 7,200.00
Labour
Unskilled 5.00 Nos. 600.00 3,000.00
Enamel Primer 8.10 Ltr. 372.86 3,020.16
Materials
Enamel paint 9.00 Ltr. 721.00 6,489.00
Total 19,709.16
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,956.37
Grand Total 22,665.53

Two coat enamel painting work over primer coat in wooden


10.19 J5(13-5ABC) surface. Sqm. 302.93 348.37

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 12.00 Nos. 900.00 10,800.00
Labour
Unskilled 8.00 Nos. 600.00 4,800.00
Enamel Primer 8.10 Ltr. 372.86 3,020.16
Materials
Enamel paint 16.00 Ltr. 729.58 11,673.33
Total 30,293.49
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,544.02
Grand Total 34,837.51

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 35 of 276

One coat plastic emulsion painting work over primer coat.


10.20 J5(13-5AB) Sqm. 243.44 279.95

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 8.00 Nos. 900.00 7,200.00
Labour
Unskilled 5.00 Nos. 600.00 3,000.00
Enamel Primer 8.10 Ltr. 372.86 3,020.16
Materials
Plastic emulsion paint 9.00 Ltr. 1,236.00 11,124.00
Total 24,344.16
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,651.62
Grand Total 27,995.78

Two coat plastic emulsion painting work over primer coat.


10.21 J5(13-5AB) Sqm. 412.85 474.78

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 12.00 Nos. 900.00 10,800.00
Labour
Unskilled 8.00 Nos. 600.00 4,800.00
Enamel Primer 8.10 Ltr. 729.58 5,909.62
Materials
Plastic emulsion paint 16.00 Ltr. 1,236.00 19,776.00
Total 41,285.62
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,192.84
Grand Total 47,478.46

Two coat aluminium painting work over primer coat in metal


10.22 J6(13-6) surface. Sqm. 266.32 306.26
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.75 Nos. 900.00 9,675.00
Labour
Unskilled 10.75 Nos. 600.00 6,450.00
Red oxide Primer 8.10 Ltr. 401.70 3,253.77
Materials Aluminium paint 10.76 Ltr. 669.50 7,203.82
Sand paper 4.00 Nos. 12.36 49.44
Total 26,632.03
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,994.80
Grand Total 30,626.83

10.25 J7(13-8A) One coat double boiled Linseed oil painting work . Sqm. 39.27 45.16
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.00 Nos. 900.00 1,800.00
Labour
Unskilled 2.00 Nos. 600.00 1,200.00
Materials Linseed oil paint 6.00 Ltr. 154.50 927.00
Total 3,927.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 589.05
Grand Total 4,516.05

10.23 J7(13-8AB) Two coat double boiled Linseed oil painting work . Sqm. 76.99 88.54
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.00 Nos. 900.00 3,600.00
Labour
Unskilled 4.00 Nos. 600.00 2,400.00
Materials Linseed oil paint 11.00 Ltr. 154.50 1,699.50
Total 7,699.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,154.92
Grand Total 8,854.42

10.24 J8(13-9A) One coat varnish painting work . Sqm. 69.90 80.38
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.00 Nos. 900.00 2,700.00
Labour
Unskilled 2.00 Nos. 600.00 1,200.00
Materials Varnish paint 6.00 Ltr. 515.00 3,090.00
Total 6,990.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,048.50
Grand Total 8,038.50

10.25(A) J8(13-9AB) Two coat varnish painting work . Sqm. 134.65 154.84
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 6.00 Nos. 900.00 5,400.00
Labour
Unskilled 4.00 Nos. 600.00 2,400.00
Materials Varnish paint 11.00 Ltr. 515.00 5,665.00
Total 13,465.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,019.75
Grand Total 15,484.75

10.26 J9(13-10A) One coat Bitumen painting work . Sqm. 43.29 49.78
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.50 Nos. 900.00 1,350.00
Labour
Unskilled 1.00 Nos. 600.00 600.00
Materials Bitumen paint 7.00 Ltr. 339.90 2,379.30
Total 4,329.30
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 649.39
Grand Total 4,978.69

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 36 of 276

10.27 J9(13-10B) Two coat Bitumen painting work . Sqm. 75.28 86.58
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.50 Nos. 900.00 2,250.00
Labour
Unskilled 2.00 Nos. 600.00 1,200.00
Materials Bitumen paint 12.00 Ltr. 339.90 4,078.80
Total 7,528.80
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,129.32
Grand Total 8,658.12

10.28 J10(13-11) Three coat chapra painting work . Sqm. 165.17 189.94
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.00 Nos. 900.00 9,000.00
Labour
Unskilled 5.00 Nos. 600.00 3,000.00
Chapra paint 2.00 Kg. 610.58 1,221.16
Materials
Sprit 10.00 Ltr. 329.60 3,296.00
Total 16,517.16
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,477.57
Grand Total 18,994.73

10.29 J11(13-4C) One coat RED OXIDE painting work . Sqm. 146.01 167.91
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.70 Nos. 900.00 1,530.00
Labour
Unskilled 1.70 Nos. 600.00 1,020.00
Materials Red oxide paint 30.00 Kg. 401.70 12,051.00
Total 14,601.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,190.15
Grand Total 16,791.15

10.30 J11(13-4C) Two coat RED OXIDE painting work . Sqm. 247.32 284.42
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.50 Nos. 900.00 3,150.00
Labour
Unskilled 3.50 Nos. 600.00 2,100.00
Materials Red oxide paint 48.50 Kg. 401.70 19,482.45
Total 24,732.45
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,709.86
Grand Total 28,442.31

One coat water proof cement paint painting work in plastered


10.31 J12(13-12A) surface Sqm. 83.40 95.91

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.50 Nos. 900.00 3,150.00
Labour
Unskilled 3.50 Nos. 600.00 2,100.00
Materials Water proof cement paint 30.00 Kg. 103.00 3,090.00
Total 8,340.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,251.00
Grand Total 9,591.00

Two coat water proof cement paint painting work in plastered


10.32 J12(13-12AB) surface Sqm. 149.00 171.35

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 6.50 Nos. 900.00 5,850.00
Labour
Unskilled 6.50 Nos. 600.00 3,900.00
Materials Water proof cement paint 50.00 Kg. 103.00 5,150.00
Total 14,900.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,235.00
Grand Total 17,135.00

ENAMEL paint painting work over linceed oil in face brick wall
10.33 J15(5-5) Sqm. 205.38 236.18

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.538 Nos. 900.00 484.20
Labour
Unskilled 0.538 Nos. 600.00 322.80
Linseed oil paint 0.538 Ltr. 154.50 83.12
Materials
Enamel paint 1.614 Ltr. 721.00 1,163.69
Total 2,053.81
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 308.07
Grand Total 2,361.88

One coat enamel painting work without primer coat in wooden


10.34 J16(13-5B) surface. Sqm. 121.89 140.17

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.00 Nos. 900.00 4,500.00
Labour

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 37 of 276

Labour
Unskilled 2.00Nos. 600.00 1,200.00
Materials Enamel paint 9.00 Ltr. 721.00 6,489.00
Total 12,189.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,828.35
Grand Total 14,017.35

Two coat enamel painting work without primer coat in wooden


10.35 J17(13-5BC) surface. Sqm. 226.36 260.31

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 9.00 Nos. 900.00 8,100.00
Labour
Unskilled 5.00 Nos. 600.00 3,000.00
Materials Enamel paint 16.00 Ltr. 721.00 11,536.00
Total 22,636.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,395.40
Grand Total 26,031.40

One coat plastic emulsion painting work without primer coat.


10.36 J18(13-5B) Sqm. 168.24 193.47

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.00 Nos. 900.00 4,500.00
Labour
Unskilled 2.00 Nos. 600.00 1,200.00
Materials Plastic emulsion paint 9.00 Ltr. 1,236.00 11,124.00
Total 16,824.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,523.60
Grand Total 19,347.60

Two coat plastic emulsion painting work without primer coat.


10.37 J19(13-5BC) Sqm. 308.76 355.07

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 9.00 Nos. 900.00 8,100.00
Labour
Unskilled 5.00 Nos. 600.00 3,000.00
Materials Plastic emulsion paint 16.00 Ltr. 1,236.00 19,776.00
Total 30,876.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,631.40
Grand Total 35,507.40

One coat aluminium painting work without primer coat in


10.38 J20(13-6) metal surface. Sqm. 92.63 106.53
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.75 Nos. 900.00 3,375.00
Labour
Unskilled 3.75 Nos. 600.00 2,250.00
Aluminium paint 5.38 Ltr. 669.50 3,601.91
Materials
Sand paper 3.00 Nos. 12.36 37.08
Total 9,263.99
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,389.59
Grand Total 10,653.58

Two coat aluminium painting work without primer coat in


10.39 J21(13-6) metal surface. Sqm. 188.78 217.09
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 7.75 Nos. 900.00 6,975.00
Labour
Unskilled 7.75 Nos. 600.00 4,650.00
Aluminium paint 10.76 Ltr. 669.50 7,203.82
Materials
Sand paper 4.00 Nos. 12.36 49.44
Total 18,878.26
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,831.73
Grand Total 21,709.99

10.40 J22(13-7) One coat RED OXIDE painting work without primer coat Sqm. 93.09 107.06
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.33 Nos. 900.00 3,897.00
Labour
Unskilled 4.00 Nos. 600.00 2,400.00
Materials Red oxide paint 7.50 Ltr. 401.70 3,012.75
Total 9,309.75
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,396.46
Grand Total 10,706.21

10.41 J23(13-7) Two coat RED OXIDE painting work without primer coat Sqm. 186.28 214.22
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 8.67 Nos. 900.00 7,803.00
Labour
Unskilled 8.00 Nos. 600.00 4,800.00
Materials Red oxide paint 15.00 Ltr. 401.70 6,025.50
Total 18,628.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,794.27
Grand Total 21,422.77

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 38 of 276

10.44 J26 Two coat washable distemper painting work over primer coat. Sqm. 154.56 177.75
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.80 Nos. 900.00 5,220.00
Labour
Unskilled 5.80 Nos. 600.00 3,480.00
Distemper primer 8.00 Ltr. 329.60 2,636.80
Materials
Distemper washable 16.00 Kg. 257.50 4,120.00
Total 15,456.80
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,318.52
Grand Total 17,775.32
K - Damp proofing work

20 mm thick D.P.C. work in cement sand mortar in 1:2 with


11.01 K1(18-7) W.P.Compound. Sqm. 401.71 461.97

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.750 Nos. 900.00 675.00
Labour
Unskilled 0.800 Nos. 600.00 480.00
Cement 0.135 M.T. 18,025.00 2,433.37
Materials Sand crusher(local) 0.180 Cum. 837.25 150.70
W.P.Compound 2.700 Kg. 103.00 278.10
Total 4,017.17
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 602.57
Grand Total 4,619.74

25 mm thick D.P.C. work in cement concrete in 1:1½:3


11.02 K2(18-8) withwith W.P.Compound. Sqm. 433.25 498.24

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.0000 Nos. 900.00 900.00
Labour
Unskilled 1.2500 Nos. 600.00 750.00
Cement 0.1125 M.T. 18,025.00 2,027.81
Sand crusher(local) 0.1130 Cum. 837.25 94.60
Materials
Aggrigate 12 mm 0.2500 Cum. 1,313.75 328.43
W.P.Compound 2.2500 Kg. 103.00 231.75
Total 4,332.59
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 649.88
Grand Total 4,982.47

38 mm thick D.P.C. work in cement concrete in 1:2:4 with with


11.03 18-9 W.P.Compound. Sqm. 514.86 592.09

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 2.000 Nos. 600.00 1,200.00
Cement 0.120 M.T. 18,025.00 2,163.00
Sand crusher(local) 0.170 Cum. 837.25 142.33
Materials
Aggrigate 12 mm 0.340 Cum. 1,313.75 446.67
W.P.Compound 2.880 Kg. 103.00 296.64
Total 5,148.64
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 772.29
Grand Total 5,920.93

11.05 K4(18-11) 500 gauge polythine sheet laying work Sqm. 148.91 171.25
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.600 Nos. 900.00 540.00
Labour
Unskilled 0.600 Nos. 600.00 360.00
Materials Polythine sheet 500 gauge 11.000 Sqm. 53.56 589.16
Total 1,489.16
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 223.37
Grand Total 1,712.53

11.06 K5(18-12A) One layer tarfelt laying work. Sqm. 779.91 896.90
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 900.00 990.00
Labour
Unskilled 3.500 Nos. 600.00 2,100.00
Tarfelt 11.000 Sqm. 123.60 1,359.60
Bitumen 15.000 Kg. 144.20 2,163.00
Materials
Fire wood 60.000 Kg. 15.45 927.00
Sand crusher(local) 0.310 Cum. 837.25 259.54
Total 7,799.14
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,169.87
Grand Total 8,969.01

11.07 K5(18-12B) Two layer tarfelt laying work. Sqm. 1,264.97 1,454.72
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.300 Nos. 900.00 2,070.00
Labour
Unskilled 4.600 Nos. 600.00 2,760.00
Tarfelt 22.000 Sqm. 123.60 2,719.20
Bitumen 25.000 Kg. 144.20 3,605.00
Materials
Fire wood 80.000 Kg. 15.45 1,236.00
Sand crusher(local) 0.310 Cum. 837.25 259.54
Total 12,649.74
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,897.46
Grand Total 14,547.20

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 39 of 276

11.08 K6(18-13A) One layer damp proof grade tarfelt laying work. Sqm. 1,016.25 1,168.68
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.350 Nos. 900.00 2,115.00
Labour
Unskilled 4.600 Nos. 600.00 2,760.00
Damp proof grade tarfelt 11.000 Sqm. 149.96 1,649.56
Bitumen 17.000 Kg. 144.20 2,451.40
Materials
Fire wood 60.000 Kg. 15.45 927.00
Sand crusher(local) 0.310 Cum. 837.25 259.54
Total 10,162.50
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,524.37
Grand Total 11,686.87

11.09 K6(18-13B) Two layer damp proof grade tarfelt laying work. Sqm. 1,885.80 2,168.67
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.500 Nos. 900.00 3,150.00
Labour
Unskilled 11.700 Nos. 600.00 7,020.00
Damp proof grade tarfelt 22.000 Sqm. 149.96 3,299.12
Bitumen 27.000 Kg. 144.20 3,893.40
Materials
Fire wood 80.000 Kg. 15.45 1,236.00
Sand crusher(local) 0.310 Cum. 837.25 259.54
Total 18,858.06
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 2,828.70
Grand Total 21,686.76

Two coat elastocret cementious elastomeric water


11.10 K7 proofing work Sqm. 531.97 611.76

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.000 Nos. 900.00 -
Labour
Unskilled 0.000 Nos. 600.00 -
Materials lastocret cementious elastomeric water
proofing 1.000 Sqm. 531.97 531.97
Total 531.97
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 79.79
Grand Total 611.76

11.11 K8(18-14) One coat rain Crystallization seal paint or equivalent paint Sqm. 139.15 160.02
Resources Level/Type work. Quantity Unit Rate Amount Remarks
Skilled 0.000 Nos. 900.00 -
Labour
Unskilled 0.000 Nos. 600.00 -
Materials Crystallization seal 0.245 Sqm. 567.99 139.15
Total 139.15
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 20.87
Grand Total 160.02

Expansion Joint Works: - Chipping and laying thermocol


in the hole, masking tape on the thermocol and plaster
with mixing Perma Bond SBR or eqv. modified mortar up
11.12 0 to 40 mm wide and levelling all complete. Sqm. 7,139.54 8,210.47

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.000 Nos. 900.00 -
Labour
Unskilled 0.000 Nos. 600.00 -
Materials Expansion joint materials 1.000 sqm 7,139.54 7,139.54
Total 7,139.54
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 1,070.93
Grand Total 8,210.47

L - MAINTAINANCE & DISMANTLING WORK

Dismantling work of mud masonry wall & removing of


12.01 L1(19-1) material upto 10 mtr lead. Cum. 636.00 731.40

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 1.060 Nos. 600.00 636.00
Total 636.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 95.40
Grand Total 731.40

Dismantling work of cement masonry wall & removing of


12.02 L2(19-2) material upto 10 mtr lead. Cum. 1,272.00 1,462.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 2.120 Nos. 600.00 1,272.00
Total 1,272.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 190.80
Grand Total 1,462.80

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 40 of 276

Dismantling work of R.C.C. / R.B.C. & removing of material


12.03 L3(19-3) upto 10 mtr lead. Cum. 6,600.00 7,590.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 11.000 Nos. 600.00 6,600.00
Total 6,600.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 990.00
Grand Total 7,590.00

Dismantling work of P.C.C. / L.C.C. & removing of material


12.04 L4(19-4) upto 10 mtr lead. Cum. 2,400.00 2,760.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 4.000 Nos. 600.00 2,400.00
Total 2,400.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 360.00
Grand Total 2,760.00

Dismantling work of cement sand / lime surkhee plaster &


12.05 L5(19-5) removing of material upto 10 mtr lead. Sqm. 64.80 74.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.108 Nos. 600.00 64.80
Total 64.80
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 9.72
Grand Total 74.52

Dismantling work of tile roof & removing of all material wood,


12.06 L6(19-6) tile upto 10 mtr lead. Sqm. 97.20 111.78

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.054 Nos. 900.00 48.60
Labour
Unskilled 0.081 Nos. 600.00 48.60
Total 97.20
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 14.58
Grand Total 111.78

Wood preservative paint painting work


12.07 L7 Sqm. 409.41 470.82

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.22 Nos. 900.00 198.00
Labour
Unskilled 0.100 Nos. 600.00 60.00
Wood preservative paint 0.245 Ltr. 618.00 151.41
Total 409.41
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 61.41
Grand Total 470.82

Clearance work of old existing marble floor with Oxalic


12.08 L11 acid & carborendum stone Sqm.. 255.51 293.84

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 900.00 -
Labour
Unskilled 3.375 Nos. 600.00 2,025.00
Oxalic acid powder 0.185 Kg. 360.50 66.69 NCN 11-6
Materials
Carborendam Stone 1.000 Nos. 463.50 463.50 L.S.
Total 2,555.19
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 383.27
Grand Total 2,938.46

Clearance work of old existing parket & polishing work


12.09 L12 Sqm.. 202.50 232.87

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 900.00 -
Labour
Unskilled 3.375 Nos. 600.00 2,025.00
Sand paper Kg. 12.36 - L.S.
Materials
Main polish Nos. 515.00 - L.S.
Total 2,025.00
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 303.75
Grand Total 2,328.75

Clearance work of old existing mosaic floor with Oxalic


12.10 L13 acid , main polish , terpantain oil & carborendum stone Sqm.. 280.45 322.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 900.00 -
Labour
Unskilled 3.375 Nos. 600.00 2,025.00
Oxalic acid powder 0.370 Kg. 360.50 133.38
Main Polish 0.118 Kg. 515.00 60.77
Materials
Tarpaintain oil 0.538 Ltr. 226.60 121.91
Carborendam Stone 1.000 Nos. 463.50 463.50 L.S.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 41 of 276

Total 2,804.56
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 420.68
Grand Total 3,225.24

Clearance work of brick from mud masonry wall &


12.11 L14(A) stacking of brick for re-used Nos. 2.61 3.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.040 Nos. 900.00 36.00
Labour
Unskilled 3.900 Nos. 600.00 2,340.00
Equipment Pully, dori,gas cutter & gas etc 10% of Labour 237.60
Total 2,613.60
Rate analysis for : 1000.00 Nos. 15 % Contractor overhead 392.04
Grand Total 3,005.64

Clearance work of brick from cement masonry wall &


12.12 L14(C) stacking of brick for re-used Nos. 4.38 5.04

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.200 Nos. 900.00 1,080.00
Labour
Unskilled 4.850 Nos. 600.00 2,910.00
Equipment Pully, dori,gas cutter & gas etc 10% of Labour 399.00
Total 4,389.00
Rate analysis for : 1000.00 Nos. 15 % Contractor overhead 658.35
Grand Total 5,047.35

Clearance work of stone from cement masonry wall &


12.13 L15(B) stacking of stone for re-used Cum. 932.40 1,072.26

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.220 Nos. 900.00 198.00
Labour
Unskilled 1.150 Nos. 600.00 690.00
Equipment Pully, dori,gas cutter & gas etc 5% of Labour 44.40
Total 932.40
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 139.86
Grand Total 1,072.26

Clearance work of stone from mud masonry wall &


12.13a L15(B) stacking of stone for re-used Cum. 757.52 871.14

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.183 Nos. 900.00 165.00
Labour
Unskilled 0.927 Nos. 600.00 556.45
Equipment Pully, dori,gas cutter & gas etc 5% of Labour 36.07
Total 757.52
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 113.62
Grand Total 871.14

Dismantling work of R. C. C. barbed wire fencing work with


12.14 L19(A) earthwork excavation filling & leveling Sqm. 270.00 310.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 900.00 -
Labour
Unskilled 0.450 Nos. 600.00 270.00
Total 270.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 40.50
Grand Total 310.50

Dismantling work of IRON. barbed wire fencing work with


12.15 L19(B) earthwork excavation filling & leveling Sqm. 252.00 289.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 900.00 -
Labour
Unskilled 0.420 Nos. 600.00 252.00
Total 252.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 37.80
Grand Total 289.80

Dismantling work of WOODEN. barbed wire fencing work


12.16 L19(C) with earthwork excavation filling & leveling Sqm. 240.00 276.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 900.00 -
Labour
Unskilled 0.400 Nos. 600.00 240.00
Total 240.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 36.00
Grand Total 276.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 42 of 276

Dismantling work of M.S. bar from R.C.C./R.B.C.& stacking


12.17 L19(C) upto 10 mtr. Sqm. 810.00 931.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.100 Nos. 900.00 90.00
Labour
Unskilled 1.200 Nos. 600.00 720.00
Total 810.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 121.50
Grand Total 931.50

Dismantling work of Gavian work


12.18 L21 Sqm. 906.00 1,041.90

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 900.00 900.00
Labour
Unskilled 0.010 Nos. 600.00 6.00
Total 906.00
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 135.90
Grand Total 1,041.90

Dismantling work of cgi sheet roof & removing of all


12.19 L22 material wood, cgi sheet upto 10 mtr lead. Sqm. 48.30 55.54

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.027 Nos. 900.00 24.30
Labour
Unskilled 0.040 Nos. 600.00 24.00
Total 48.30
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 7.24
Grand Total 55.54

M - METAL, FENCING & RAILING WORK

3 x 20mm Metal Grill including manufacturing, fitting, painting


13.01 M1(24-1A) with Aluminium paint, sand papering all complete Sqm. 2,008.50 2,309.77

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Skilled - Nos. 900.00 -
Material MS grill 3*20 mm (15 kg/sqm) 150.000 Kg. 133.90 20,085.00
Total 20,085.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 3,012.75
Grand Total 23,097.75

4 x 20mm Metal Grill including manufacturing, fitting, painting


13.02 M2(24-1B) with Aluminium paint, sand papering all complete Sqm. 2,878.85 3,310.67

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Skilled - Nos. 900.00 -
Material MS grill 4.5*20 mm (21.5 kg/sqm) 215.000 Kg. 133.90 28,788.50
Total 28,788.50
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,318.27
Grand Total 33,106.77

12x12 mm solid core square rod M. S. grill with 4 x 20mm Metal


13.03 M3 frame Sqm. 2,717.81 3,125.48

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.700 Nos. 900.00 630.00
Labour
Unskilled 0.600 Nos. 600.00 360.00
MS plate 4.5*20 mm 28.240 Kg. 143.17 4,043.12
Material Square rod 12 mm solid core 215.000 Kg. 103.00 22,145.00
Total 27,178.12
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,076.71
Grand Total 31,254.83

Fabricating, supplying & fixing of different size M.S. angle


13.04 M4 Kg. 175.96 202.36

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.687 Nos. 900.00 618.30
Labours
Unskilled 0.781 Nos. 600.00 468.60
MS angle different size 18.940 Kg. 113.30 2,145.90
Material
Primer etc L.S. 100.00
Total 3,332.80
Rate analysis for :18.94 Kg. 15 % Contractor overhead 499.92
Grand Total 3,832.72

13.05 M5 Spiral stair case 3.00 mtr height 90 cm. width Rmtr. 10,304.12 11,849.73

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 900.00 -
Labour
Unskilled - Nos. 600.00 -
MS Spiral Staircase Readymade 1.00 Rmtr. 10,304.12 10,304.12

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 43 of 276

Total 10,304.12
Rate analysis for : 1.00 Rmtr. 15 % Contractor overhead 1,545.61
Grand Total 11,849.73

Providing & fixing MS folded sheet rolling shutters with


13.06 M6(24-2) iron clamps, spring and axle of good quality finish with one coat Sqm. 4,017.00 4,619.55
red- oxide paint on shutter and oiling on spring and axle.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled - Nos. 900.00 -
Labour
Unskilled - Nos. 600.00 -
Rolling Shutter 1.00 Nos. 4,017.00 4,017.00
Total 4,017.00
Rate analysis for : 1.00Sqm 15 % Contractor overhead 602.55
Grand Total 4,619.55

Collapsible shutter including manufacturing, welding, supply


13.07 M7(24-4) of material, painting and fixing Sqm. 8,652.00 9,949.80
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled - Nos. 900.00 -
Material Collapisible gate (60 kg/sqm.) 10.00 Sqm. 8,652.00 86,520.00
Total 86,520.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 12,978.00
Grand Total 99,498.00

Providing and fixing MS gate as per drawing with 50 mm X


50 mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe,
16 gauge MS flat sheet, 12 mm X 3 mm MS flat , ready
13.08 M8(24-3) Sqm. 4,516.90 5,194.43
made pivot hing welded to 175 mm long angle hold fast
embedded in concrete and iron locking arrangement over one
coat primer .
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Fixing charge L.S. 5,000.00
Material MS grill gate 5*20 mm(35 kg/sqm) 10.00 Sqm. 4,016.90 40,169.00
Total 45,169.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 6,775.35
Grand Total 51,944.35

Providing and fixing MS gate as per drawing with 50 mm X


50 mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe,
13.09 M8(24-3) ready made pivot hing welded to 175 mm long angle hold fast Sqm. 6,226.80 7,160.82
embedded in concrete and iron locking arrangement over one
coat primer.

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Fixing charge L.S. 5,000.00

Material MS grill gate 5*25 mm(40 kg/sqm) M.


sheet 10.00 Sqm. 5,726.80 57,268.00
Total 62,268.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 9,340.20
Grand Total 71,608.20

Supplying and fixing of Barbed wire 14 gauge including


13.10 M9(24-6) hooks, nails etc Rmtr. 67.01 77.06
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.076 Nos. 900.00 968.40
Labours
Unskilled 5.380 Nos. 600.00 3,228.00
Barbed wire 14 gauge 110.00 Rmtr. 22.32 2,454.83
Material
U-nail, killa etc L. S. 50.00
Total 6,701.23
Rate analysis for :100.00 Rmtr. 15 % Contractor overhead 1,005.18
Grand Total 7,706.41

Supplying and fixing of Barbed wire 12 gauge including


13.11 M10(24-7)
hooks, nails etc 5 H+2D with 75x100 mm sal wood 2100 mm Rmtr. 4,065.96 4,675.85
long .
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 900.00 900.00
Labours
Unskilled 2.000 Nos. 600.00 1,200.00
Wood Sal 0.190 Cum. 257,500.00 48,925.00
Material Barbed wire 12 gauge 250.000 Rmtr. 283.25 70,812.50
U-nail 77.000 Nos. 1.84 141.35
Total 121,978.85
Rate analysis for :30.00 Rmtr. 15 % Contractor overhead 18,296.82
Grand Total 140,275.67

Fabricating, supplying & fixing of different size M.S. black


13.12 M11 pipe Truss with metal primer Kg. 170.81 196.43

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.687 Nos. 900.00 618.30
Labours
Unskilled 0.781 Nos. 600.00 468.60

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 44 of 276

MS black pipe 18.940 Kg. 108.15 2,048.36


Material
Primer etc L.S. 100.00
Total 3,235.26
Rate analysis for : 18.94 Kg. 15 % Contractor overhead 485.28
Grand Total 3,720.54

Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0


mtr with 10 S.W.G.G. I. Chain Link 2"x2" mesh size fixing
13.13 M12 in 4x20x20 mm & 4x25x25 mm ms angle frame & top 3x20 Sqm. 3,047.03 3,504.08
mm MS grill 15 cm height with primer coat..

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 900.00 6,300.00
Labours 9,300.00
Unskilled 5.000 Nos. 600.00 3,000.00
MS Black pipe 35.510 Kg. 108.15 3,840.40
Angle 4x25x25 32.060 Kg. 113.30 3,632.39
Material Angle 4x20x20 25.190 Kg. 113.30 2,854.02 18,408.97
Grill 3x20 14.760 Kg. 133.90 1,976.36
Chain Link 2"x2" mesh (10 SWG G. I.) 10.000 Kg. 610.58 6,105.80
Fabrication charge 15% of materials 2,761.35
Total 30,470.32
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 4,570.54
Grand Total 35,040.86

Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0


mtr with 7 mm Ø TMT bar mesh 62x62 mm size 4x25x25
13.14 M13 mm ms angle frame & top 3x20 mm MS grill 15 cm height Sqm. 2,725.46 3,134.28
with primer coat..

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 900.00 6,300.00
Labours 9,300.00
Unskilled 5.000 Nos. 600.00 3,000.00
MS Black pipe 35.510 Kg. 108.15 3,840.40
Angle 32.060 Kg. 113.30 3,632.39
Material 15,612.77
MS grill 14.760 Kg. 133.90 1,976.36
TMT reinforcement bar 7 mm Ø 66.490 Kg. 92.70 6,163.62
Fabrication charge 15% of materials 2,341.91
Total 27,254.68
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 4,088.20
Grand Total 31,342.88

13.15 M14 900 mm height stainless steel staircase railing work Sqm. 4,224.28 4,857.92
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled Nos. 900.00 -
Labours -
Unskilled Nos. 600.00 -

Stainless Steel 50mm dia Handrail in


Material 2.00m.distance with 50mm dia.vertical post 4,224.28
& 3 layer Horizontal 25mm dia.stainless
steel member ,2.5' to 3' height Railing with
Painting & fixing. 1.000 Rmtr. 4,224.28 4,224.28
Total 4,224.28
Rate analysis for : 1.00Rm 15 % Contractor overhead 633.64
Grand Total 4,857.92

Supplying & fixing work of 38 mm Ø stainless steel pipe


post @ 2.0 mtr , 8 mm Ø stainless steel pipe hand rail with
13.16 M15 two rows 25 mm Ø stainless steel pipe in between ground Sqm. 3,212.21 3,694.04
& hand rail.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.780 Nos. 900.00 7,002.00
Labours 13,812.00
Unskilled 11.350 Nos. 600.00 6,810.00
Stainless steel pipe 38 mm Ø 15.490 Rmtr. 387.28 5,998.96
Material 11,004.76
Stainless steel pipe 25 mm Ø 20.000 Rmtr. 250.29 5,005.80
Gas welding charge 9.150 LS 500.00 4,575.00
Total 29,391.76
Rate analysis for : 9.15 Sqm. 15 % Contractor overhead 4,408.76
Grand Total 33,800.52

Supplying & fixing work of 150x150 mm size sisham wood


13.17 M16 ornamental post , 75x75 mm size bluster with 75x100 mm Sqm. - -
hand rail.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.720 Nos. 900.00 5,148.00
Labours 5,460.00
Unskilled 0.520 Nos. 600.00 312.00
Material Wood Sisham 0.329 Cum. 154,500.00 50,830.50 50,830.50
Ornamental work 9.000 Sqm. -
Total
Rate analysis for : 9.00 Sqm.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 45 of 276

Rate analysis for : 9.00 Sqm. 15 % Contractor overhead


Grand Total

Hand rail 3"x4" size sisham wood supplying & fixing work
13.18 M17 Rmtr. 1,355.10 1,558.36

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.100 Nos. 900.00 90.00 LS
Labours
Unskilled 0.100 Nos. 600.00 60.00 LS
Material Wood sisham 0.0078 Cum. 154,500.00 1,205.10
Total 1,355.10
Rate analysis for : 1.00 Rmtr 15 % Contractor overhead 203.26
Grand Total 1,558.36

Supplying & fixing work of 20x20 mm square pipe railing


13.19 M18 two nos. every trade 900 to 1000 mm height with 3"x4" Rmtr. 2,674.36 3,075.51
sisham wood hand rail
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.200 Nos. 900.00 180.00
Labours
Unskilled 0.200 Nos. 600.00 120.00
Material Wood sisham 0.024 Cum. 154,500.00 3,769.80
Square pipe1"x1" 16.200 Rmtr 103.00 1,668.60
MS plate 4x20 2.650 kgs 143.17 379.40
MS Black pipe 40mm dia. 6.500 kgs 108.15 702.97
Welding charge ls 400.00
Total 7,220.77
Rate analysis for : 2.70 Rmtr 15 % Contractor overhead 1,083.11
Grand Total 8,303.88

Supplying & fixing work of 20x20 mm square pipe railing


13.20 M19 two nos. every trade 900 to 1000 mm height with 40 mm Rmtr. 1,830.19 2,104.71
MS black pipe hand rail
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.000 Nos. 900.00 -
Labours -
Unskilled 0.000 Nos. 600.00 -
Material Square pipe1"x1" 18.200 Kg. 103.00 1,874.60
MS plate 4x20 4.600 kgs 143.17 658.58
MS Black pipe 40mm dia. 18.570 kgs 108.15 2,008.34
Welding charge ls 400.00
Total 4,941.52
Rate analysis for : 2.70 Rmtr 15 % Contractor overhead 741.22
Grand Total 5,682.74

O - ROAD WORK
Subgrade prepairing work with simple mud cutting 10 mtr.
15.01 O1 lead Sqm. 92.70 106.60

Resources Level/Type Quantity Unit Rate Amount Remarks


Labours Unskilled 0.150 Nos. 600.00 90.00
Material T&P 3 % of labour 2.70
Total 92.70
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 13.90
Grand Total 106.60

15.02 O2 Rolling work Sqm. 7.94 9.13


Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Unskilled 0.500 Nos. 600.00 300.00
Equipment Road roller 8-10 M.T. 1.600 Hours 309.00 494.40
Total 794.40
Rate analysis for : 100.00 Cum. 15 % Contractor overhead 119.16
Grand Total 913.56

10 cm. compact sub base laying work with sand mixed


15.03 O3(15-9A) gravel, load unload & proper levelling. Sqm. 189.02 217.37

Resources Level/Type Quantity Unit Rate Amount Remarks


Labours Unskilled 0.150 Nos. 600.00 90.00
Material Sand mixed gravel 0.128 Cum. 751.90 96.24
Equipment Road roller 8-10 M.T. 0.009 Hours 309.00 2.78
Total 189.02
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 28.35
Grand Total 217.37

15 cm. compact sub base laying work with sand mixed


15.04 O3(15-9C) gravel, load unload & proper levelling. Sqm. 262.37 301.72

Resources Level/Type Quantity Unit Rate Amount Remarks


Labours Unskilled 0.190 Nos. 600.00 114.00
Material Sand mixed gravel 0.192 Cum. 751.90 144.36

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 46 of 276

Equipment Road roller 8-10 M.T. 0.013 Hours 309.00 4.01


Total 262.37
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 39.35
Grand Total 301.72

20 cm. compact sub base laying work with sand mixed


15.05 O3(15-9D) gravel, load unload & proper levelling. Sqm. 324.04 372.64

Resources Level/Type Quantity Unit Rate Amount Remarks


Labours Unskilled 0.210 Nos. 600.00 126.00
Material Sand mixed gravel 0.256 Cum. 751.90 192.48
Equipment Road roller 8-10 M.T. 0.018 Hours 309.00 5.56
Total 324.04
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 48.60
Grand Total 372.64

25 Misclenious WORK

Alluminium fixed panel window With ventilation but


25.01 without fly mesh shutter from section( 88mmx38.1mm Sqm. 6,386.00 7,343.90
x1.3mm , Glass 5mm)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium fixed panel window With
ventilation but without fly mesh shutter
Materials 1.00 Sqm. 6,386.00 6,386.00
from section( 88mmx38.1mm x1.3mm ,
Glass 5mm)
Total 6,386.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 957.90
Grand Total 7,343.90

Alluminium fixed panel window With Ventilation with fly


25.02 mesh shutter from section(88mmx38.1mm x1.3mm , Glass Sqm. 7,107.00 8,173.05
5mm )
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium fixed panel window With
Ventilation with fly mesh shutter from
Materials 1.00 Sqm. 7,107.00 7,107.00
section(88mmx38.1mm x1.3mm , Glass
5mm )
Total 7,107.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,066.05
Grand Total 8,173.05

Alluminium framed Sliding window Without ventilator


25.03 ( Aluminium :- Natural anodised 101.6mmx45mm Sqm. 8,446.00 9,712.90
x1.50mm , Glass 5mm clear)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed Sliding window
Without ventilator ( Aluminium :-
Materials Natural anodised 101.6mmx45mm 1.00 Sqm. 8,446.00 8,446.00
x1.50mm , Glass 5mm clear)
Total 8,446.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,266.90
Grand Total 9,712.90

Alluminium framed Sliding window With ventilator and


25.04 Mosquito Net ( Aluminium :- Natural anodised Sqm. 8,446.00 9,712.90
101mmx45mm x1.5mm , Glass 5mm clear)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed Sliding window
With ventilator and Mosquito Net
Materials ( Aluminium :- Natural anodised 1.00 Sqm. 8,446.00 8,446.00
101mmx45mm x1.5mm , Glass 5mm
clear)

Total 8,446.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,266.90
Grand Total 9,712.90

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 47 of 276

Alluminium framed Casement window With ventilator


25.05 ( Aluminium :- Natural anodised 38mmx34mm x1.5mm , Sqm. 5,381.75 6,189.01
Glass 5mm clear)

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed Casement window
With ventilator ( Aluminium :- Natural
Materials anodised 38mmx34mm x1.5mm , 1.00 Sqm. 5,381.75 5,381.75
Glass 5mm clear)
Total 5,381.75
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 807.26
Grand Total 6,189.01

Alluminium framed Sliding Door ( Aluminium :- Natural


25.06 anodised 101mmx45mm x1.5mm , Glass 5mm clear , board Sqm. 7,926.88 9,115.91
: 9mm Laminated
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed Sliding Door
( Aluminium :- Natural anodised
Materials 101mmx45mm x1.5mm , Glass 5mm 1.00 Sqm. 7,926.88 7,926.88
clear , board : 9mm Laminated
Total 7,926.88
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,189.03
Grand Total 9,115.91

Alluminium framed Casement Door (One -Way Openable )


25.07 ( Aluminium :- Natural anodised 101.6mmx45mm x1.5mm , Sqm. 9,064.00 10,423.60
Glass 5mm clear , board : 9mm Laminated

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed Casement Door
(One -Way Openable ) ( Aluminium :-
Materials Natural anodised 101.6mmx45mm 1.00 Sqm. 9,064.00 9,064.00
x1.5mm , Glass 5mm clear , board :
9mm Laminated

Total 9,064.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,359.60
Grand Total 10,423.60

Alluminium framed Swing Door (Two -Way Openable )


25.08 ( Aluminium :- Natural anodised 101.6mmx45mm x1.5mm , Sqm. 9,527.50 10,956.62
Glass 5mm clear , board : 9mm Laminated
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed Swing Door (Two
-Way Openable ) ( Aluminium :-
Materials Natural anodised 101.6mmx45mm 1.00 Sqm. 9,527.50 9,527.50
x1.5mm , Glass 5mm clear , board :
9mm Laminated

Total 9,527.50
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,429.12
Grand Total 10,956.62

Alluminium framed fixed partition ( Aluminium :- Natural


25.09 anodised 101mmx45mm x1.5mm , Glass 5mm clear or Sqm. 6,643.50 7,640.02
board : 9mm Laminated
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed fixed partition
( Aluminium :- Natural anodised
Materials 101mmx45mm x1.5mm , Glass 5mm 1.00 Sqm. 6,643.50 6,643.50
clear or board : 9mm Laminated
Total 6,643.50
Rate analysis for : 1.00 Sqm.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 48 of 276

Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 996.52


Grand Total 7,640.02

Alluminium fixed panel window With ventilation but


25.10 without fly mesh shutter from section( 78mmx38.1mm Sqm. 4,156.05 4,779.45
x1.1mm , Glass 4.75 -5mm
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium fixed panel window With
ventilation but without fly mesh shutter
Materials 1.00 Sqm. 4,156.05 4,156.05
from section( 78mmx38.1mm x1.1mm ,
Glass 4.75 -5mm
Total 4,156.05
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 623.40
Grand Total 4,779.45

Alluminium framed Sliding window With ventilator and with


25.11 Mosquito Net ( Aluminium :- Natural anodised Sqm. - -
78mmx35mm x1.2mm , Glass 5mm clear)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
Alluminium framed Sliding window
With ventilator and with Mosquito Net (
Materials Aluminium :- Natural anodised 1.00 Sqm. - -
78mmx35mm x1.2mm , Glass 5mm
clear)

Total -
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead -
Grand Total -

25.12 False ceiling by Gypsum ,Gypsum Board : 12.5mm Sqm. 133.90 153.98

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 900.00 -
Labour
Unskilled 0.00 Nos. 600.00 -
False ceiling by Gypsum ,Gypsum
Materials 1.00 Sqm. 133.90 133.90
Board : 12.5mm
Total 133.90
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 20.08
Grand Total 153.98

11.09 K6(18-13B) ASO Joint Tape laying Work. Rm - -


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.100 Nos. 900.00 90.00
Labour
Unskilled 0.000 Nos. 600.00 -
ASO Joint Tape laying Work. 1.100 Rm 741.60 815.76 rm=720.00
Materials Two coat elastocret cementious
elastomeric water proofing work 0.100 sqm - -
Total -
Rate analysis for :1.00 Rm. 15 % Contractor overhead -
Grand Total -

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Measurement Book (MB-1st & Final)
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi F.Y. 2078/079

S.N. Description of Work No. Length Breadth Height Qty. Unit Rate Amount Remark
A. Civil Work
CONSTRUCTION OF GHAT
Pond Length: 59 m (N), 75 m (S), 55 m (E), 82 m (W)
1 Cutting and clearing all rubbish, bushes, top
soil,
West Side 1.00 28.000 7.000 196.000
Total 196.000 Sqm 6.00 1,176.00
2 Dewatering of pond all complete as per
instruction of site Incharge
Water area 1.00 67.000 68.500 1.800 8,261.100
Total 2,753.700 Hr 34.32 94,506.98
3 Earthfill with transported earth

Inside pond ( west- 61 m, south- 56 m, East-42


m, North- 46.50 m) 0.50 205.500 4.000 0.900 369.900
West Side Filling 1.00 36.200 6.000 1.400 304.080
Ghat walkway 1.00 34.850 1.480 1.100 56.736
step 1 1.00 33.100 0.700 0.500 11.585
Step 2 1.00 31.800 0.750 0.500 11.925
Step 3 1.00 30.450 0.370 0.500 5.633
Step 4 1.00 29.570 0.370 0.500 5.470
Step 5 1.00 28.410 0.370 0.500 5.256
Total 770.585 Cum. 540.00 416,116.09
4 flat brick soling
Ghat walkway 1.00 34.850 1.480 51.578
Ghat walkway Side wall 1 1.00 19.700 0.230 4.531
Ghat walkway Side wall 2 1.00 33.500 0.230 7.705
Side wall 1 1.00 32.700 0.230 7.521
Side wall 2 1.00 30.900 0.230 7.107
Side wall 3 1.00 30.000 0.230 6.900
Side wall 4 1.00 29.140 0.230 6.702
Side wall 5 Rest on Stone Masonary Wall
Step 1 1.00 33.100 0.700 23.170
Step 2 1.00 31.800 0.750 23.850
Step 3 1.00 30.450 0.370 11.267
Step 4 1.00 29.570 0.370 10.941
Step 5 1.00 28.410 0.370 10.512
Solar Light 25.00 0.600 0.600 9.000
approach staircase for walkway 1.00 4.00 0.900 3.600
2.00 1.000 0.900 1.800
Total 186.183 Sqm. 576.83 107,396.11
5 Plain cement Concrete (PCC) in 1:2:4 ratio
for foundations, flooring and walls.
Bottom of Stone Masonary wall 1.00 28.000 2.000 0.127 7.112
Top of Stone Masonary wall 1.00 28.000 0.800 0.100 2.240
Ghat walkway side wall -1 1.00 19.700 0.230 0.075 0.340
Ghat walkway side wall -2 1.00 33.500 0.230 0.075 0.578
Side wall -1 1.00 32.700 0.230 0.075 0.564
Side wall -2 1.00 30.900 0.230 0.075 0.533
Side wall -3 1.00 30.000 0.230 0.075 0.518
Side wall -4 1.00 29.140 0.230 0.075 0.503
Side wall -5 1.00 27.680 0.230 0.075 0.477
Ghat walkway 1.00 34.850 1.940 0.075 5.071
Step -1 (1.00 m) 1.00 33.100 0.700 0.075 1.738
Step -2 (1.00 m) 1.00 31.800 0.750 0.075 1.789
Step -3 (0.6 m) 1.00 30.450 0.370 0.075 0.845
Step -4 (0.6 m) 1.00 29.570 0.370 0.075 0.821
Step -5 (0.6 m) 1.00 28.410 0.370 0.075 0.788
Solar Light 25.00 0.600 0.600 1.300 11.700
approach staircase for walkway 1.00 4.00 0.900 0.075 0.270
2.00 1.000 0.900 0.075 0.135
PCC for Fencing Poles 44.00 0.300 0.300 0.680 2.693
Total 38.713 Cum. 10,693.80 413,992.85
6 Good quality local chimney made flat / edge
Brickwork in 1:4 C/S mortar
Ghat walkway side wall 1 1.00 19.700 0.230 1.100 4.984
1.00 16.500 0.230 0.700 2.657 above PCC road
Ghat walkway side wall 2 1.00 33.500 0.230 1.100 8.476
Side wall -1 1.00 32.700 0.230 0.650 4.889
Side wall -2 1.00 30.900 0.230 0.650 4.620
Side wall -3 1.00 30.000 0.230 0.600 4.140
GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Measurement Book (MB-1st & Final)
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi F.Y. 2078/079

S.N. Description of Work No. Length Breadth Height Qty. Unit Rate Amount Remark
Side wall -4 1.00 29.140 0.230 0.600 4.021
Side wall -5 (on stone masonary wall) 1.00 27.680 0.230 0.740 4.711
Step - 1 1.00 32.100 0.700 0.140 3.146
Step - 2 1.00 30.800 0.750 0.140 3.234
Step - 3 1.00 29.450 0.370 0.140 1.526
Step - 4 1.00 28.570 0.370 0.140 1.480
Step - 5 1.00 27.410 0.370 0.140 1.420
Step - 6 (on stone masonary wall) 1.00 26.560 0.800 0.140 2.975
Buttress wall on Step 1 2.00 0.900 0.500 0.360 0.324
Buttress wall on Step 2 2.00 0.975 0.500 0.690 0.673
Buttress wall on Step 3 2.00 0.600 0.500 0.990 0.594
Buttress wall on Step 4 2.00 0.600 0.500 0.390 0.234
Buttress wall on Step 5 2.00 0.600 0.500 0.690 0.414
Buttress wall on Stone Masonary wall 2.00 0.850 0.500 1.040 0.884
approach staircase for walkway 2.00 0.300 4.000 0.900 2.160
2.00 0.300 1.000 0.650 0.390
2.00 0.300 1.000 0.250 0.150
4.00 0.300 1.000 0.900 1.080
4.00 0.300 1.000 0.650 0.780
4.00 0.300 1.000 0.250 0.300
Total 60.259 Cum. 10,488.00 631,999.54
7 Gravel packing
for Stone Masonary 1.00 28.000 2.000 0.150 8.400
Total 8.400 Cum. 1,666.92 14,002.13
8 Stone soling
for Stone Masonary 1.00 28.000 2.000 0.150 8.400
Total 8.400 Cum. 3,420.00 28,728.00
9 Earthwork in exavation in ordinary soil
Excavation for Stone Masonary 1.00 28.000 2.000 1.500 84.000
Ghat walkway side wall 1 1.00 19.700 0.400 0.500 3.940
Ghat walkway side wall 2 1.00 33.500 0.400 0.500 6.700
Side wall -1 1.00 32.700 0.400 0.200 2.616
Side wall -2 1.00 30.900 0.400 0.200 2.472
Side wall -3 1.00 30.000 0.400 0.200 2.400
Side wall -4 1.00 29.140 0.400 0.200 2.331
Solar Light 25.00 0.600 0.600 1.000 9.000
Excavation for Fencing Poles 44.00 0.450 0.450 0.750 6.683
Total 120.142 Cum. 432.60 51,973.30
10 Back fill
1.00 72.085 0.600 43.251
Total 43.251 Cum. 300.00 12,975.30
11 Stone Masonary Wall in 1:4 C/S mortar up
for Retaining Wall
0.50 28.000 0.300 1.700 7.140
0.50 28.000 0.300 1.700 7.140
1.00 28.000 1.200 1.700 57.120
1.00 28.000 0.800 0.300 6.720
Total 78.120 Cum. 9,811.00 766,435.32
12 Formwork, shuttering, centering with
approved materials.
Bottom of stone masonry wall 2.00 28.000 0.127 7.112
Top of stone masonry wall 2.00 28.000 0.100 5.600
Ghat Walkway 2.00 34.850 0.075 5.228
Walkway side wall 1 2.00 19.700 0.075 2.955
Walkway side wall 2 2.00 33.500 0.075 5.025
Side Wall 1 2.00 32.700 0.075 4.905
Side Wall 2 2.00 30.900 0.075 4.635
Side Wall 3 2.00 30.000 0.075 4.500
Side Wall 4 2.00 29.140 0.075 4.371
Side Wall 5 (Rest on Stone Masonry wall) 1.00 27.410 0.075 2.056
Total 46.386 Sqm. 542.95 25,185.41
13
Supply & fixing work of 50mm Ф MS black
pipe @ 2.0 mtr with 10 S.W.G.G.I. Chain Link
2"x2" mesh size fixing in 4x20x20 mm &
4x25x25 mm MS angle frame & top 3x20 mm
MS grill 15 cm height with primer coat

86.000 1.500 129.000


Total 129.000 Sqm. 2,985.37 385,112.73
GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Measurement Book (MB-1st & Final)
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi F.Y. 2078/079

S.N. Description of Work No. Length Breadth Height Qty. Unit Rate Amount Remark
14 Fabricating, supplying & fixing of different
size IS or BS Mild steel Sections including
one coat of Primer Paint as per direction,
instruction all complete
MS Pipe 50mm dia 44.00 1.500 4.080 269.28
Total 269.280 Kg 175.96 47,382.51
15 Installation of Solar Light
15.1 Supply of 200wattPV (solar panel) 13.00 13.000 set 18540.00 241,020.00
Supply of Solar Lithium Ion Battery 80
15.2 Ah@c20, 12V
13.00 13.000 set 33,578.00 436,514.00
15.3 Supply of Charger Controller 15 Amp 13.00 13.000 set 5,047.00 65,611.00
15.4 40W LED Light 13.00 13.000 set 15,553.00 202,189.00
15.4 150 Watt Led COV Light 12.00 12.000 set 20,000.00 240,000.00
15.5 Light Arm 25.00 25.000 set 2,266.00 56,650.00
15.6 UV Cable and installation materials 250.00 250.000 m 150.00 37,500.00
9Mtrs Long Hot Deep Galvanized Iron Pole
(5"dia.5m GI Pipe heavy class + 4" dia. 2M
long GI Pipe heavy class + 3" dia. 2M long GI
15.7 Pipe heavy class , light stand battery box , 25.00 25.000 set 27,707.00 692,675.00
panel base etc as per specification direction ,
Instruction of site Incharge

Supply ,Delivary and insttalation of Battery


box,battery stand & light stand ,nut bolt etc. as
15.8 per specification direction , Instruction of site 13.00 13.000 set 9,270.00 120,510.00
Incharge.
15.9 Installation Charge 25.00 25.000 LS 10,000.00 250,000.00
16 HDPE Pipe 200 mm (6Kg/sqcm)
For Pond outlet 1.00 4.250 4.250
Total 4.250 m 1,860.00 7,905.00
12.5 mm. thick cement sand plaster work
17 1:4 on wall.
Pond walkway outer wall 1.00 20.000 0.640 12.800
1.00 20.000 0.630 12.600
1.00 20.000 0.603 12.050
1.00 20.000 0.670 13.400
1.00 20.000 0.614 12.280
1.00 20.000 0.510 10.200
1.00 20.000 0.596 11.920
1.00 20.000 0.738 14.760
1.00 20.000 0.686 13.720
1.00 20.000 0.664 13.280
1.00 3.200 0.717 2.293
1.00 20.000 0.866 17.320
1.00 8.130 1.140 9.268
1.00 4.400 1.150 5.060
1.00 6.750 1.064 7.182
1.00 2.000 0.900 1.800
Total 169.934 Sq.m 308.80 52,475.48
5,400,031.75
Grand Total 5,400,031.75
Budget Allocation 4,500,000.00
4% Contingencies 180,000.00
Net payable amount 4,320,000.00
User-committee contribution 1,080,031.75
User-committee contribution % 20.00%
Grand Total 5,400,031.75
52of276
GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Abstract of Cost
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi F.Y. 2078/079
S.N. Description of Work Unit Qty. Rate Amount Remark

A Civil Work

1 Cutting and clearing all rubbish, Sqm 196.00 6.00 1,176.00


bushes, top soil,
2 Dewatering of pond all complete as Cum 5,507.40 34.32 189,013.97
per instruction of site Incharge

Earth filling (Earth transported from 5


3 Km. surronding) work in every 15-15 Cum. 770.59 540.00 416,116.09
cm. layer with proper manual
compaction.
4 Dry flat Brick paving work Sqm. 186.18 576.83 107,396.11

Providing and laying of


5 Plain/Reinforced Cement Concrete in Cum. 38.71 10,693.80 413,992.85
Foundation complete as per Drawing
and Technical Specifications, PCC
Grade M 15

6 First class chimney brick masonry work Cum. 60.26 10,488.00 631,999.54
in (1:4) cement sand mortar in G. F.
7 Gravel packing Cum. 8.40 1,666.92 14,002.13
8 Stone soling Cum. 8.40 3,420.00 28,728.00
Earth work excavation in foundation in
9 clay & silty soft soil lead upto 10 mtr. & Cum. 120.14 432.60 51,973.30
lift 1.5 mtr.
10 Back fill Cum. 43.25 300.00 12,975.30
Stone Masonary Wall in 1:4 C/S mortar
11 up for Retaining Wall Cum. 78.12 9,811.00 766,435.32

12 Formwork, shuttering, centering with Sqm. 46.39 542.95 25,185.41


approved materials.

Supply & fixing work of 50mm Ф MS


black pipe @ 2.0 mtr with 10
13 S.W.G.G.I. Chain Link 2"x2" mesh size Sqm. 129.00 2,985.37 385,112.73
fixing in 4x20x20 mm & 4x25x25 mm
MS angle frame & top 3x20 mm MS
grill 15 cm height with primer coat

Fabricating, supplying & fixing of


14 different size IS or BS Mild steel Kg. 269.28 175.96 47,382.51
Sections including one coat of Primer
Paint as per direction, instruction all
complete
15 Installation of Solar Light
15.1 Supply of 200wattPV (solar panel) set 13.00 18,540.00 241,020.00 KTM
15.2 Supply of Solar Lithium Ion Battery 80 set 13.00 33,578.00 436,514.00
Ah@c20, 12V Dhanusha

15.3 set 13.00 5,047.00 65,611.00


Supply of Charger Controller 15 Amp Dhanusha
15.4 40W LED Light set 13.00 15,553.00 202,189.00 Dhanusha
15.5 Solar Light Arm Set 25.00 2,266.00 56,650.00 KTM
15.6 UV Cable and installation materials m 250.00 150.00 37,500.00

9Mtrs Long Hot Deep Galvanized Iron


Pole (5"dia.5m GI Pipe heavy class + 4"
15.7 dia. 2M long GI Pipe heavy class + 3" set 25.00 27,707.00 692,675.00
dia. 2M long GI Pipe heavy class , light
stand battery box , panel base etc as
per specification direction , Instruction
of site Incharge KTM
Prepared By: Checked By: Approved By:
53of276
GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Abstract of Cost
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi F.Y. 2078/079
S.N. Description of Work Unit Qty. Rate Amount Remark

15.8 Supply ,Delivary and insttalation of set 13.00 9,270.00 120,510.00


Battery box,battery stand & light stand
,nut bolt etc. as per specification
direction , Instruction of site Incharge. KTM
15.9 Installation Charge Ps 25.00 10,000.00 250,000.00
16 HDPE Pipe 200 mm (6Kg/sqcm) Mtr. 4.25 1,860.00 7,905.00
17 12.5 mm. thick cement sand plaster Sqm. 169.93 308.80 52,475.48
work 1:4 on wall.
Total 5,254,538.74
B. Provisional Sum
Carrying out diferrent laboratory tests PS 1.00 15,000.00 15,000.00
from site engineer.
Total 15,000.00
Grand Total 5,269,538.74
Budget Allocation 4,500,000.00
4% Contingencies 180,000.00
Net payable amount 4,320,000.00
User-committee contribution 949,538.74
User-committee contribution % 18.02%
Grand Total 5,269,538.74

Prepared By: Checked By: Approved By:


54 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

A - SITE PREPARATION WORK

Cutting of tree, branch & log etc. (12-30 cm. girth above 1.00
1.01 A1 (1-1A) Nos. 78.00 89.70
mtr. From G.L.) with lead upto 15 mtr.
Cutting of tree, branch & log etc. (31-60 cm. girth above 1.00
1.02 A1 (1-1B) Nos. 234.00 269.10
mtr. From G.L.) with lead upto 15 mtr.
Cutting of tree, branch & log etc. (61-120 cm. girth above 1.00
1.03 A1 (1-1C) Nos. 588.00 676.20
mtr. From G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
1.04 A2 (1-2A) Nos. 240.00 276.00
G.L.) with lead upto 15 mtr.
Removing of tree root (31-60 cm. girth above 1.00 mtr. From
1.05 A2 (1-2B) Nos. 318.00 365.70
G.L.) with lead upto 15 mtr.
Removing of tree root (61-120 cm. girth above 1.00 mtr. From
1.06 A2 (1-2C) Nos. 1,512.00 1,738.80
G.L.) with lead upto 15 mtr.
Cutting of grass, taking of root & brocken of uplecutting of
1.07 A3 Sqm. 13.80 15.87
raised soil & site leveling with all complete
Surface dressing work with cutting of raised soil & filling the
1.08 A4 sqm. 6.00 6.90
ditches.

B - EARTH & SAND WORK


Earth work excavation in foundation in clay & silty soft soil lead
2.01 B1 (2-1) Cum. 432.60 497.49
upto 10 mtr. & lift 1.5 mtr.
Earth work excavation in foundation in clay & soft murram
2.02 B1 (2-2) Cum. 494.40 568.56
stone (30 cm.) hard soil lead upto 10 mtr. & lift 1.5 mtr.
Earth filling work in every 15-15 cm. layer with watering & lead
2.03 B2 (2-25A) Cum. 300.00 345.00
upto 1o.00 mtr. & proper manual compaction.
Earth filling (Earth transported from 5 Km. surronding) work in
2.04 B2 (2-25A) every 15-15 cm. layer with watering & proper manual Cum. 765.55 880.38
compaction.
Earth filling work in every 15-15 cm. layer without watering &
2.05 B2 (2-25B) Cum. 150.00 172.50
proper manual compaction.
Earth filling (Earth transported from 5 Km. surronding) work in
2.06 B2 (2-25B) every 15-15 cm. layer without watering & proper manual Cum. 551.70 634.45
compaction.

2.07 B3 (2-42A) Sand filling work with watering & proper manual compaction. Cum. 1,343.02 1,544.47

Gravel Sand mixed (agg-50% + sand 50%) filling work with


2.08 B3 (2-42B) Cum. 2,158.56 2,482.34
proper manual compaction.
2.09 B4 (2-34) Pumping of water from foundation or trench Hrs 35.34 40.65

2.11 B5 Compaction of filled earth by 8-10 M.T. roller in 20/20 cm layer Cum. 15.48 17.80

Compaction of filled earth by 1.00 M.T. Hand roller in 20/20 cm


2.12 B5 Cum. 5.16 5.93
layer
Earth work excavation in foundation in SOFT SOIL(USED 0.80
2.13 B7 Cum. 48.79 56.10
CUM. CAPACITY HYDROLIC EXCAVATOR)
Earth work excavation in foundation in HARD SOIL USED
2.14 B7 Cum. 58.64 67.43
0.80 CUM. CAPACITY HYDROLIC EXCAVATOR)
Earth work excavation in foundation in HARD Rock Used 0.80
2.15 B7 Cum. 80.70 92.80
Cum capecity Hydraulic excavator
Earth work excavation in foundation in SOFT SOILUsed
2.16 B7 Cum. 139.11 159.97
1.32Cum capecity hydrolic excavator
Earth work excavation in foundation in HARD SOIL Used
2.17 B7 Cum. 169.36 194.76
1.32Cum capecity Hydraulic excavator

Prepared by Checked by Approved by


55 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

C - MASONRY WORK
C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement sand
3.01 Cum. 11,283.04 12,975.49
5-2A) mortar in G. F.
C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement sand
3.02 Cum. 11,592.04 13,330.84
5-2B) mortar in F. F.
C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement sand
3.03 Cum. 12,024.64 13,828.33
5-2B) mortar in S. F.
C2( 5-1-B2 & First class chimney brick masonry work in (1:4) cement sand
3.04 Cum. 10,742.47 12,353.84
5-2A) mortar in G. F.
C25-1-B2 & First class chimney brick masonry work in (1:4) cement sand
3.05 Cum. 11,051.47 12,709.19
5-2B) mortar in F. F.
C2(5-1-B2 First class chimney brick masonry work in (1:4) cement sand
3.06 Cum. 11,484.07 13,206.68
& 5-2B) mortar in S. F.
C2(5-1-B3 First class chimney brick masonry work in (1:6) cement sand
3.07 Cum. 10,206.16 11,737.08
& 5-2A) mortar in G. F.
C2(5-1-B3 & First class chimney brick masonry work in (1:6) cement sand
3.08 Cum. 10,515.16 12,092.43
5-2B) mortar in F. F.
C2( 5-1-B3 & First class chimney brick masonry work in (1:6) cement sand
3.09 Cum. 10,947.76 12,589.92
5-2B) mortar in S F.
C2(5-1-B6 &
3.1 First class chimney brick masonry work in mud mortar in G. F. Cum. 8,073.02 9,283.97
5-2A)
C2( 5-1-B6 &
3.11 First class chimney brick masonry work in mud mortar in F. F. Cum. 8,382.02 9,639.32
5-2B)
C2(5-1-B6 &
3.12 First class chimney brick masonry work in mud mortar in S. F. Cum. 8,814.62 10,136.81
5-2B)
3.13 C6( 6-1-1A) R.R. stone masonry work in cement sand (1:3) mortar Cum. 10,626.99 12,221.03
3.14 C6( 6-1-1B) R.R. stone masonry work in cement sand (1:4) mortar Cum. 10,013.03 11,514.98
Aslar (Crused stone) stone masonry work in cement sand (1:4)
3.14a C6( 6-1-1B) Cum. 10,013.03 11,514.98
mortar
3.15 C6( 6-1-1C) R.R. stone masonry work in cement sand (1:6) mortar Cum. 9,062.15 10,421.47
Aslar (Crused stone)stone masonry work in cement sand (1:6)
3.15a C6( 6-1-1C) Cum. 9,062.15 10,421.47
mortar
3.16 C6( 6-2-1) R.R. stone masonry work for dry wall Cum. 4,479.30 5,151.19
3.17 C6( 6-2-2) R.R. stone masonry work in mud mortar Cum. 4,759.08 5,472.94
3.18 C10( 6-5) Stone filling in trench with proper leveling Cum. 3,495.60 4,019.94

D - CEMENT CONCRETE WORK

4.01 D1(7-2B) P.C.C. (1:4:8) work in foundation, wall (River bed) Cum. 7,807.48 8,978.60
4.02 D1(7-2C) P.C.C. (1:3:6) work in foundation, wall (River bed) Cum. 8,716.93 10,024.46
4.03 D1(7-2D) P.C.C. (1:2:4) work in foundation, wall (River bed) Cum. 10,487.55 12,060.68
4.04 D2(7-4A) P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (River bed) Cum. 12,107.55 13,923.68

4.05 D2(7-4B) P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (River bed) Cum. 13,640.64 15,686.73

4.06 D2(7-4C) P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (River bed) Cum. 17,446.76 20,063.77
P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall
4.07 D3(A) Cum. 8,656.16 9,954.58
(River bed)

Prepared by Checked by Approved by


56 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall
4.08 D3(B) Cum. 10,453.45 12,021.46
(River bed)
P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,
4.09 D4(A) Cum. 12,005.74 13,806.60
beam etc (River bed)
P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam
4.10 D4(B) Cum. 15,811.86 18,183.63
etc (River bed)
P.C.C. (1:1:2) for R.C.C. work in slab (River bed) with micro
4.11 D(5) Cum. 27,414.68 31,526.88
silica & super plasticiser
P.C.C. (1:4:8) work in foundation, wall (crushed or stone
4.12 D1(7-2B) Cum. 8,406.75 9,667.76
ballast)
P.C.C. (1:3:6) work in foundation, wall (crushed or stone
4.13 D1(7-2C) Cum. 9,316.20 10,713.63
ballast)
P.C.C. (1:2:4) work in foundation, wall (crushed or stone
4.14 D1(7-2D) Cum. 11,048.57 12,705.85
ballast)
P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (crushed or
4.15 D2(7-4A) Cum. 12,668.57 14,568.85
stone ballast)
P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (crushed or
4.16 D2(7-4B) Cum. 14,159.08 16,282.94
stone ballast)
P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (crushed or
4.17 D2(7-4C) Cum. 17,961.08 20,655.24
stone ballast)
P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall
4.18 D3(A) Cum. 9,255.43 10,643.74
(crushed or stone ballast)
P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall
4.19 D3(B) Cum. 11,017.22 12,669.80
(crushed or stone ballast)
P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,
4.20 D4(A) Cum. 12,524.18 14,402.80
beam etc (crushed or stone ballast)
P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam
4.21 D4(B) Cum. 16,326.18 18,775.10
etc (crushed or stone ballast)
P.C.C. (1:1:2) for R.C.C. work in slab (crushed or stone
4.22 D(5) Cum. 27,918.96 32,106.80
ballast) with micro silica & super plasticiser
Torsteel reinforcement bar for R.C.C. work with cutting,
4.23 D9(7-5) Kg. 116.77 134.29
bending, binding & laying with all complete.

E - FORM & PROPS WORK


Form work shuttering & centering (COLUMN) with (USED
5.01 E1(8-3A) Sqm. 1,139.42 1,310.34
LOCAL WOOD) all complete.
Form work shuttering & centering (COLUMN) with (USED PLY
5.02 E2(51B) Sqm. 612.11 703.93
WOOD) all complete.
Form work shuttering & centering (BEAM-0.30 Mtr) with
5.03 E3(8-4A) Sqm. 1,184.78 1,362.50
(USED LOCAL WOOD) all complete.
Form work shuttering & centering (BEAM-0.30-0.80 Mtr) with
5.04 E4(8-4B) Sqm. 945.08 1,086.85
(USED LOCAL WOOD) all complete.
Form work shuttering & centering (COLUMN) with (USED PLY
5.05 E5(51A) Sqm. 1,287.21 1,480.29
WOOD) all complete.
Form work shuttering & centering with MS pipe (prop),
5.06 E6(8-4A) Sqm. 1,044.44 1,201.11
plyboard for slab etc
Form work shuttering & centering with Bamboo, plyboard for
5.06(A) E6(8-4A) Sqm. 554.52 637.70
slab etc
5.07 E12(8-13A) Trench work open type form work (up to 1.50 Mtr.) Sqm. 225.45 259.27
5.08 E12(8-13B) Trench work open type form work ( 1.50 to 3.00 Mtr.) Sqm. 232.20 267.03
5.09 E13(8-13C) Trench work open type form work (above 3.00 Mtr.) Sqm. 241.20 277.38

F - ROOFING WORK

Prepared by Checked by Approved by


57 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
26 (H) 0.41 mm thick colored C.G.I. sheet roofing work
6.01 F1( 9-1) Sqm. 1,688.56 1,941.85
(65kg/bandal)
26 (H) 0.41mm thick plane C.G.I. sheet roofing work
6.02 F1( 9-1) Sqm. 1,446.52 1,663.50
(62kg/bandal)
26 (L) 0.35mm thick plane C.G.I. sheet roofing work
6.03 F1( 9-1) Sqm. 1,276.56 1,468.05
(55kg/bandal)
26 (H) 0.41 mm thick colour C.G.I. sheet roofing work
6.04 F3( 9-1) Sqm. 1,688.56 1,941.85
(65kg/bandal)
26 (L) 0.35mm thick colour C.G.I. sheet roofing work
6.05 F3( 9-1) Sqm. 1,474.84 1,696.06
(62kg/bandal)
6.08 F2( 9-2) 28 (H) G.I. plane ridge cover Rmtr. 608.24 699.47
6.09 F4( 9-2) 26 (L) C.G.I. colour ridge cover Rmtr. 770.40 885.96
6.11 F5 28 (H) 0.31 mm thick plane G.I. sheet roofing work Rmtr. 1,190.31 1,368.85
6.12 F5 26 (L) 0.35 mm thick plane G.I. sheet roofing work Rmtr. 1,277.85 1,469.53
6.13 F6 26 (H) 0.41 mm thick Colour G.I. sheet roofing work Rmtr. 1,729.40 1,988.81
6.14 F6 26 (M) 0.38 mm thick Colour G.I. sheet roofing work Rmtr. 1,603.33 1,843.83
150 mm breadth upto 450 mm G. I. plane sheet Gutter fixing
6.16 F7 Rmtr. 1,133.10 1,303.06
work with 3x40 mm M.S. bracke,t nut bolt & washer .
150 mm breadth upto 450 mm G. I. colour sheet Gutter fixing
6.17 F7 Rmtr. 1,189.20 1,367.59
work with 3x40 mm M.S. bracke,t nut bolt & washer .
6.18 F10( 9-6) Clay tile roofing work Rmtr. 576.75 663.26
6.19 F11( 9-7) Clay tile ridge cover Rmtr. 366.36 421.31
6.2 F12( 9-8) 100 mm lime concrete (1:1:3) work Sqm. 1,198.94 1,378.79
6.21 F13( 9-9A) 80 mm thick khar roof with bamboo frame Sqm. 2,513.66 2,890.70
6.22 F13( 9-9B) 150 mm thick khar roof with bamboo frame Sqm. 3,891.80 4,475.57
6.23 F14 1.20 mm thick fiber glass corgated sheet roofing work Sqm. 1,576.71 1,813.22
6.24 F15 1.20 mm thick fiber glass ridge cover Rmtr. 1,130.57 1,300.15
Readymade colour concrete tile laying work on cement sand
6.25 F18 Sqm. 715.12 822.39
(1:4) screeding
6.26 F19( 10-17) Making and fixing of Sal wood beam, lintel, etc Cum. 287,416.00 330,528.40
6.27 F20(10-19) Making and fixing of 25 mm sal wood eaves board Sqm. 7,228.53 8,312.80
6.28 F22 2 mm thick UPVC roofing sheet roofing work Sqm. - -
6.29 F23 3 mm thick UPVC roofing sheet roofing work Sqm. 2,164.55 2,489.23

G - DOOR & WINDOW WORK


7.01 G1(10-1) Sal wood works for chaukhats with all complete. Cum. 320,911.36 369,048.06
7.02 G1(10-1) Local wood works for chaukhats with all complete. Cum. 105,641.36 121,487.56
38 mm thick sal wood fully paneled shutter fixing work with all
7.03 G2(10-2) Sqm. 16,031.36 18,436.06
complete. Size of shutter 1.07 x 1.982 =2.114 Sqm.
38 x 75 mm thick sal wood frame with 4 mm thick fully glazed
7.04 G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 10,392.49 11,951.37
1.22 =2.23 Sqm.
38 x 75 mm thick sal wood frame with 3 mm thick fully glazed
7.04a G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 10,342.38 11,893.73
1.22 =2.23 Sqm.

Prepared by Checked by Approved by


58 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
38 x 75 mm thick Gamhair wood frame with 4 mm thick fully
7.05 G3(10-4) glazed shutter fixing work with all complete. Size of shutter Sqm. 6,028.99 6,933.33
1.829 x 1.22 =2.23 Sqm.
38 mm thick sal wood frame with 4 mm thick commercial
7.06 G4(10-7) plywood (bothside) flush shutter fixing with all comolete. Size Sqm. 8,376.67 9,633.17
of shutter 1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 3 mm thick TEAK plywood
7.07 G4(10-8) (Both side ) flush shutter fixing with all comolete. Size of Sqm. 8,174.00 9,400.10
shutter 1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 26 Bwg G.I. plane sheet
7.08 G4(10-9) (bothside) shutter fixing with all comolete. Size of shutter Sqm. 8,546.66 9,828.66
1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 24 Bwg G.I. mosquito proof &
7.09 G4(10-10) Expanded metal net net shutter fixing with all comolete. Size of Sqm. 7,075.02 8,136.27
shutter 1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 24 Bwg G.I. mosquito proof
7.10 G4(10-10) net shutter fixing with all comolete. Size of shutter 1.092 x Sqm. 6,902.25 7,937.59
2.058 =2.245 Sqm.
7.11 G5(10-11B) 4 mm thick plane glass fixing work with wooden listies. Sqm. 990.24 1,138.77

7.12 G5(10-11B) 26 Bwg plane sheet fixing work with wooden listies. Sqm. 745.49 857.31

7.13 G6(10-12) 4 mm thick ply wood fixing work with wooden listies. Sqm. 541.07 622.23

7.14 G5(10-11B) Mosquito proof net fixing work with wooden listies. Sqm. 1,522.29 1,750.63
Mosquito proof & Expanded metal net fixing work with
7.15 G5(10-11B) Sqm. 1,713.52 1,970.54
wooden listies.
False ceiling of 6 mm thick commerical plywood with 50 mm x
7.16 10-16-A 75 mm size local wood frame of box size 0.600 x 0.900 m and Sqm. 3,811.20 4,382.88
fixing of wooden listy in joints
Torsteel reinforcement bar fixing work in window frame with all
7.17 G7(10-21) Kg. 127.33 146.43
complete,
38 x100mm thick sal wood frame with 12 mm thick commercial
G8(10-3 & plywood paneled & one side 4 mm thick Teak plywood
7.18 Sqm. 8,701.12 10,006.28
10-7) paneled shutter fixing with all comolete. Size of shutter 1.092
x 2.058 =2.245 Sqm.
38 x100mm thick sal wood frame with 12 mm thick commercial
G9(10-3 & plywood paneled & both side 4 mm thick Teak plywood
7.19 Sqm. 9,228.96 10,613.30
10-7) paneled shutter fixing with all comolete. Size of shutter 1.092
x 2.058 =2.245 Sqm.

38 x100mm thick sal wood frame with 12 mm thick water proof


G10(10-3 & plywood paneled & one side 4 mm thick Teak plywood
7.20 Sqm. 8,701.12 10,006.28
10-7) paneled shutter fixing with all comolete. Size of shutter 1.092
x 2.058 =2.245 Sqm.

H - FLOORING WORK
25 mm or 1" thick P.C.C. (1:2:4) work in floor with all complete.
8.01 H1(11-1A) Sqm. 389.18 447.56

38 mm or 1½" thick P.C.C. (1:2:4) work in floor with all


8.02 H1(11-1B) Sqm. 525.59 604.42
complete.
50 mm or 2" thick P.C.C. (1:2:4) work in floor with all complete.
8.03 H1(11-1C) Sqm. 644.01 740.61

8.04 H1(11-1D) 75 mm or 3" thick P.C.C. (1:2:4) work in floor with all complete. Sqm. 872.15 1,002.97

Prepared by Checked by Approved by


59 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
25 mm thick mosaic flooring with 20 mm thick P.C.C. (1:2:4) &
8.05 H2(11-2) 5 mm thick white cement marble chips1:1 rubbing & polishing Sqm. 1,737.75 1,998.41
work with all complete.
25 mm thick mosaic flooring with 19 mm thick cement sand
8.06 H3(11-3) plaster 1:2 & 6 mm thick white cement marble chips1:1 rubbing Sqm. 3,110.57 3,577.15
& polishing work with all complete.
20 mm thick mosaic flooring with 12.5mm thick cement sand
8.07 H4(11-4) plaster 1:2 & 6 mm thick white cement marble chips1:1 rubbing Sqm. 3,133.42 3,603.44
& polishing work with all complete.
20 mm thick Terrazo tile paving with 20 mm thick cement sand
8.08 H5(11-5) Sqm. 2,924.22 3,362.86
mortar 1:4 rubbing & polishing work with all complete.
15 mm thick marble tile 600x600 mm paving with 20 mm thick
8.09 11-6 cement sand mortar 1:2 rubbing & polishing work with all Sqm. 3,871.85 4,452.63
complete.
Porcelain glazed /non glazed tile paving work in cement sand
8.10 H6(11-7) Sqm. 3,205.82 3,686.69
(1:4) mortar
Spartik Non-glazed tile paving work in cement sand (1:4)
8.11 H6(11-7) Sqm. 2,717.72 3,125.38
mortar

8.12 H12(11-12) Flat Brick paving in 1:6 & cement sand pointing in1:2 in joints Sqm. 989.86 1,138.34

8.13 H13(11-13) Edge Brick paving in 1:6 & cement sand pointing in1:2 in joints Sqm. 1,178.06 1,354.77

H15(11-
8.14 Dry flat Brick paving work Sqm. 597.04 686.60
15A)
H15(11-
8.15 Dry flat Brick (Brick Bat ) paving work Sqm. 380.74 437.85
15A)
H15(11-
8.16 Dry edge Brickpaving work Sqm. 1,061.32 1,220.52
15B)
H15(11-
8.17 Dry edge Brick (Brick Bat ) paving work Sqm. 702.88 808.31
15B)
8.18 H16( 11-16) Stone filling in floor with sand lead up to 30 mtr. Cum. 5,757.44 6,621.05
Edge brick paving with sand packing in voids & cement sand
8.19 H17( 11-17) Sqm. 1,144.22 1,315.85
(1:3) flush pointing in top surface.
H19( 11-
8.20 Sand filling work Cum. 1,505.97 1,731.87
19A)
H19( 11-
8.21 15-15 cm. Brick bat filling work. Cum. 913.59 1,050.63
19B)
8.22 H20( 11-20) 3 mm thick neat cement punning work. Sqm. 245.89 282.77
25 mm thick Sal wood planking work with 50x75 mm sal wood
8.23 H21(11-21) Sqm. 11,484.75 13,207.46
frame in 600x600 mm
8.24 H24( 11-20) 3 mm thick neat Plaster of Paris punning work. Sqm. 269.64 310.09
Clay tile(Machine Made) paving work in cement sand (1:4)
8.25 H25(11-7) Sqm. 1,592.54 1,831.42
mortar
Granite 16mm thick paving with 20 mm thick cement sand
8.26 H26(11-6) Sqm. 6,197.35 7,126.95
mortar 1:2 rubbing & polishing work with all complete.
I - PLASTER & POINTING WORK
9.01 I1(12-1B) 12.5 mm. thick cement sand plaster work 1:3 on wall. Sqm. 327.37 376.47
9.02 I1(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on wall. Sqm. 313.19 360.17
9.03 I1(12-1D) 12.5 mm. thick cement sand plaster work 1:6 on wall. Sqm. 286.00 328.90
9.04 I4(12-4A) 20 mm. thick cement sand plaster work 1:3 on wall etc. Sqm. 429.36 493.77
9.05 I4(12-4B) 20 mm. thick cement sand plaster work 1:4 on wall etc. Sqm. 404.42 465.08

Prepared by Checked by Approved by


60 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
9.06 I4(12-4C) 20 mm. thick cement sand plaster work1:6 on wall etc. Sqm. 362.41 416.78
9.07 I5(12-5) 25 mm. thick mud plaster on wall etc. Sqm. 343.28 394.78
9.08 I5(12-6) 12.5 mm. thick mud plaster on wall etc. Sqm. 268.59 308.88
9.09 I7(12-1B) 12.5 mm. thick cement sand plaster work (1:3 ) on ceilling Sqm. 378.37 435.12
9.10 I7(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on ceilling Sqm. 364.19 418.82
Flush pointing works in 1:1 Cement sand mortar on Brick
9.11 I8(14-1A) Sqm. 225.30 259.09
masonry wall
Flush pointing works in 1:2 Cement sand mortar on Brick
9.12 I8(14-1B) Sqm. 206.78 237.79
masonry work
Flush pointing works in 1:3 Cement sand mortar on Brick
9.13 I8(14-1C) Sqm. 197.11 226.68
masonry wall
Rulled pointing works in 1:1 Cement sand mortar on Brick
9.14 I8(14-1A) Sqm. 308.55 354.83
masonry wall
Ruled pointing works in 1:2 Cement sand mortar on Brick
9.15 I8(14-1B) Sqm. 290.03 333.53
masonry work
Ruled pointing works in 1:3 Cement sand mortar on Brick
9.16 I8(14-1C) Sqm. 280.36 322.42
masonry wall
Flush/Rulled pointing works in 1:1 Cement sand mortar on
9.17 I9(14-2A) Sqm. 287.91 331.10
Stone masonry wall
Flush/Rulled pointing works in 1:2 Cement sand mortar on
9.18 I9(14-2B) Sqm. 252.31 290.16
Stone masonry work
Flush/Rulled pointing works in 1:3 Cement sand mortar on
9.19 (14-2C) Sqm. 234.43 269.59
Stone masonry work
Flush/Rulled pointing works in 1:3 Cement sand mortar on
9.20 I10(14-3) Sqm. 153.50 176.52
Aslar Stone masonry work
1:3 Cement sand pointing on 450 mm x 450 mm flat stone
9.21 I11(14-4) Sqm. 82.82 95.24
paving joints.
9.22 I12(14-5) 1:1 Cement sand pointing on Teliya brick paving joints. Sqm. 177.87 204.55
9.23 (14-6) 3 mm thick Cement sand 1:1 flushing plaster Sqm. 212.48 244.36
9.24 I13(14-7) 3 mm thick lime flushing plaster Sqm. 150.03 172.54
9.25 I14(14-8) 3 mm thick Cement flushing plaster Sqm. 243.36 279.87
9.26 I15 20 mm thick Jhalar/pani patti making over cement plaster Sqm. 168.31 193.55

9.27 I16 25 mm thick roofing tile butta plaster in cement sand (1:4) work Sqm. 641.69 737.94

9.28 I17 2 mm thick plane white putting plaster work in wall &ceilling Sqm. 221.23 254.41

13. PAINTING WORK


10.01 J1(13-1B) Two coat white washing work on wall. Sqm. 27.54 31.68
10.02 J1(13-1B) Two coat white washing work on ceilling. Sqm. 32.57 37.46
10.03 J1(13-1C) Three coat white washing work on wall. Sqm. 54.03 62.14
10.04 J1(13-1C) Three coat white washing work on ceilling. Sqm. 64.83 74.56
10.05 J2(13-2) white washing work in old surface. Sqm. 14.78 17.00
10.06 J3(13-3AB) One coat distemper painting work over primer coat. Sqm. 103.10 118.57

10.07 J3(13-3ABC) Two coat distemper painting work over primer coat. Sqm. 142.98 164.42

10.08 J3(13-3B) One coat distemper painting work without primer coat. Sqm. 46.73 53.74
10.09 J3(13-3BC) Two coat distemper painting work without primer coat. Sqm. 86.61 99.60
10.10 J3(13-3AB) One coat weather proof painting work over primer coat. Sqm. 174.87 201.10

Prepared by Checked by Approved by


61 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

10.11 J3(13-3ABC) Two coat weather proof painting work over primer coat. Sqm. 268.04 308.25

10.12 J3(13-3B) One coat weather proof painting work without primer coat. Sqm. 116.03 133.43
10.13 J3(13-3BC) Two coat weather proof painting work without primer coat. Sqm. 209.20 240.58

10.14 J4(13-4A) One coat water proof cement paint painting work in old surface Sqm. 56.40 64.86

10.15 J4(13-4B) Two coat water proof cement paint painting work in old surface Sqm. 124.95 143.69

10.16 J4(13-4A) One coat white cement paint painting work . Sqm. 34.15 39.27
10.17 J4(13-4B) Two coat white cement paint painting work . Sqm. 88.98 102.33
One coat enamel painting work over primer coat in wooden
10.18 J5(13-5AB) Sqm. 197.09 226.65
surface.
Two coat enamel painting work over primer coat in wooden
10.19 J5(13-5ABC) Sqm. 302.93 348.37
surface.
10.20 J5(13-5AB) One coat plastic emulsion painting work over primer coat. Sqm. 243.44 279.95
10.21 J5(13-5AB) Two coat plastic emulsion painting work over primer coat. Sqm. 412.85 474.78
Two coat aluminium painting work over primer coat in metal
10.22 J6(13-6) Sqm. 266.32 306.26
surface.
10.23 J7(13-8AB) Two coat double boiled Linseed oil painting work . Sqm. 76.99 88.54
10.24 J8(13-9A) One coat varnish painting work . Sqm. 69.90 80.38
10.25 J7(13-8A) One coat double boiled Linseed oil painting work . Sqm. 39.27 45.16
10.25(A) J8(13-9AB) Two coat varnish painting work . Sqm. 134.65 154.84
10.26 J9(13-10A) One coat Bitumen painting work . Sqm. 43.29 49.78
10.27 J9(13-10B) Two coat Bitumen painting work . Sqm. 75.28 86.58
10.28 J10(13-11) Three coat chapra painting work . Sqm. 165.17 189.94
10.29 J11(13-4C) One coat RED OXIDE painting work . Sqm. 146.01 167.91
10.30 J11(13-4C) Two coat RED OXIDE painting work . Sqm. 247.32 284.42
One coat water proof cement paint painting work in plastered
10.31 J12(13-12A) Sqm. 83.40 95.91
surface
J12(13- Two coat water proof cement paint painting work in plastered
10.32 Sqm. 149.00 171.35
12AB) surface

10.33 J15(5-5) ENAMEL paint painting work over linceed oil in face brick wall Sqm. 205.38 236.18

One coat enamel painting work without primer coat in wooden


10.34 J16(13-5B) Sqm. 121.89 140.17
surface.
Two coat enamel painting work without primer coat in wooden
10.35 J17(13-5BC) Sqm. 226.36 260.31
surface.
10.36 J18(13-5B) One coat plastic emulsion painting work without primer coat. Sqm. 168.24 193.47
10.37 J19(13-5BC) Two coat plastic emulsion painting work without primer coat. Sqm. 308.76 355.07
One coat aluminium painting work without primer coat in metal
10.38 J20(13-6) Sqm. 92.63 106.53
surface.
Two coat aluminium painting work without primer coat in metal
10.39 J21(13-6) Sqm. 188.78 217.09
surface.
10.40 J22(13-7) One coat RED OXIDE painting work without primer coat Sqm. 93.09 107.06
10.41 J23(13-7) Two coat RED OXIDE painting work without primer coat Sqm. 186.28 214.22

10.44 J26 Two coat washable distemper painting work over primer coat. Sqm. 154.56 177.75

K - Damp proofing work

Prepared by Checked by Approved by


62 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
20 mm thick D.P.C. work in cement sand mortar in 1:2 with
11.01 K1(18-7) Sqm. 401.71 461.97
W.P.Compound.
25 mm thick D.P.C. work in cement concrete in 1:1½:3
11.02 K2(18-8) Sqm. 433.25 498.24
withwith W.P.Compound.
38 mm thick D.P.C. work in cement concrete in 1:2:4 with with
11.03 18-9 Sqm. 514.86 592.09
W.P.Compound.
11.05 K4(18-11) 500 gauge polythine sheet laying work Sqm. 148.91 171.25

11.06 K5(18-12A) One layer tarfelt laying work. Sqm. 779.91 896.90

11.07 K5(18-12B) Two layer tarfelt laying work. Sqm. 1,264.97 1,454.72

11.08 K6(18-13A) One layer damp proof grade tarfelt laying work. Sqm. 1,016.25 1,168.68

11.09 K6(18-13B) Two layer damp proof grade tarfelt laying work. Sqm. 1,885.80 2,168.67
Two coat elastocret cementious elastomeric water proofing
11.10 K7 Sqm. 531.97 611.76
work
One coat rain Crystallization seal paint or equivalent paint
11.11 K8(18-14) Sqm. 139.15 160.02
work.
Expansion Joint Works: - Chipping and laying thermocol in
the hole, masking tape on the thermocol and plaster with
11.12 0 Sqm. 7,139.54 8,210.47
mixing Perma Bond SBR or eqv. modified mortar up to 40
mm wide and levelling all complete.

L - MAINTAINANCE & DISMANTLING WORK

Dismantling work of mud masonry wall & removing of material


12.01 L1(19-1) Cum. 636.00 731.40
upto 10 mtr lead.
Dismantling work of cement masonry wall & removing of
12.02 L2(19-2) Cum. 1,272.00 1,462.80
material upto 10 mtr lead.
Dismantling work of R.C.C. / R.B.C. & removing of material
12.03 L3(19-3) Cum. 6,600.00 7,590.00
upto 10 mtr lead.
Dismantling work of P.C.C. / L.C.C. & removing of material
12.04 L4(19-4) Cum. 2,400.00 2,760.00
upto 10 mtr lead.
Dismantling work of cement sand / lime surkhee plaster &
12.05 L5(19-5) Sqm. 64.80 74.52
removing of material upto 10 mtr lead.
Dismantling work of tile roof & removing of all material wood,
12.06 L6(19-6) Sqm. 97.20 111.78
tile upto 10 mtr lead.
12.07 L7 Wood preservative paint painting work Sqm. 409.41 470.82
Clearance work of old existing marble floor with Oxalic acid &
12.08 L11 Sqm.. 255.51 293.84
carborendum stone
12.09 L12 Clearance work of old existing parket & polishing work Sqm.. 202.50 232.87
Clearance work of old existing mosaic floor with Oxalic acid ,
12.10 L13 Sqm.. 280.45 322.52
main polish , terpantain oil & carborendum stone
Clearance work of brick from mud masonry wall & stacking of
12.11 L14(A) Nos. 2.61 3.00
brick for re-used
Clearance work of brick from cement masonry wall & stacking
12.12 L14(C) Nos. 4.38 5.04
of brick for re-used
Clearance work of stone from cement masonry wall &
12.13 L15(B) Cum. 932.40 1,072.26
stacking of stone for re-used
Clearance work of stone from mud masonry wall & stacking of
12.13a Cum. 757.52 871.14
stone for re-used
Dismantling work of R. C. C. barbed wire fencing work with
12.14 L19(A) Sqm. 270.00 310.50
earthwork excavation filling & leveling

Prepared by Checked by Approved by


63 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
Dismantling work of IRON. barbed wire fencing work with
12.15 L19(B) Sqm. 252.00 289.80
earthwork excavation filling & leveling
Dismantling work of WOODEN. barbed wire fencing work with
12.16 L19(C) Sqm. 240.00 276.00
earthwork excavation filling & leveling
Dismantling work of M.S. bar from R.C.C./R.B.C.& stacking
12.17 L19(C) Sqm. 810.00 931.50
upto 10 mtr.
12.18 L21 Dismantling work of Gavian work Sqm. 906.00 1,041.90
Dismantling work of cgi sheet roof & removing of all material
12.19 L22 Sqm. 48.30 55.54
wood, cgi sheet upto 10 mtr lead.

24 IRON WORK
3 x 20mm Metal Grill including manufacturing, fitting, painting
13.01 M1(24-1A) Sqm. 2,008.50 2,309.77
with Aluminium paint, sand papering all complete
4 x 20mm Metal Grill including manufacturing, fitting, painting
13.02 M2(24-1B) Sqm. 2,878.85 3,310.67
with Aluminium paint, sand papering all complete
12x12 mm solid core square rod M. S. grill with 4 x 20mm
13.03 M3 Sqm. 2,717.81 3,125.48
Metal frame
13.04 M4 Fabricating, supplying & fixing of different size M.S. angle Kg. 175.96 202.36

13.05 M5 Spiral stair case 3.00 mtr height 90 cm. width Rmtr. 10,304.12 11,849.73

Providing & fixing MS folded sheet rolling shutters with iron


13.06 M6(24-2) clamps, spring and axle of good quality finish with one coat Sqm. 4,017.00 4,619.55
red- oxide paint on shutter and oiling on spring and axle.
Collapsible shutter including manufacturing, welding, supply
13.07 M7(24-4) Sqm. 8,652.00 9,949.80
of material, painting and fixing

Providing and fixing MS gate as per drawing with 50 mm X 50


mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe, 16
13.08 M8(24-3) gauge MS flat sheet, 12 mm X 3 mm MS flat , ready made Sqm. 4,516.90 5,194.43
pivot hing welded to 175 mm long angle hold fast embedded in
concrete and iron locking arrangement over one coat primer .

Providing and fixing MS gate as per drawing with 50 mm X 50


mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe,
13.09 M8(24-3) ready made pivot hing welded to 175 mm long angle hold fast Sqm. 6,226.80 7,160.82
embedded in concrete and iron locking arrangement over one
coat primer.
Supplying and fixing of Barbed wire 14 gauge including hooks,
13.10 M9(24-6) Rmtr. 67.01 77.06
nails etc

Supplying and fixing of Barbed wire 12 gauge including hooks,


13.11 M10(24-7) Rmtr. 4,065.96 4,675.85
nails etc 5 H+2D with 75x100 mm sal wood 2100 mm long .

Fabricating, supplying & fixing of different size M.S. black pipe


13.12 M11 Kg. 170.81 196.43
Truss with metal primer
Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0 mtr
with 10 S.W.G.G. I. Chain Link 2"x2" mesh size fixing in
13.13 M12 Sqm. 3,047.03 3,504.08
4x20x20 mm & 4x25x25 mm ms angle frame & top 3x20 mm
MS grill 15 cm height with primer coat..
Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0 mtr
with 7 mm Ø TMT bar mesh 62x62 mm size 4x25x25 mm ms
13.14 M13 Sqm. 2,725.46 3,134.28
angle frame & top 3x20 mm MS grill 15 cm height with primer
coat..
13.15 M14 900 mm height stainless steel staircase railing work Sqm. 4,224.28 4,857.92

Prepared by Checked by Approved by


64 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
Supplying & fixing work of 38 mm Ø stainless steel pipe post
@ 2.0 mtr , 8 mm Ø stainless steel pipe hand rail with two
13.16 M15 Sqm. 3,212.21 3,694.04
rows 25 mm Ø stainless steel pipe in between ground & hand
rail.
Supplying & fixing work of 150x150 mm size sisham wood
13.17 M16 ornamental post , 75x75 mm size bluster with 75x100 mm Sqm. - -
hand rail.
13.18 M17 Hand rail 3"x4" size sisham wood supplying & fixing work Rmtr. 1,355.10 1,558.36
Supplying & fixing work of 20x20 mm square pipe railing two
13.19 M18 nos. every trade 900 to 1000 mm height with 3"x4" sisham Rmtr. 2,674.36 3,075.51
wood hand rail
Supplying & fixing work of 20x20 mm square pipe railing two
13.20 M19 nos. every trade 900 to 1000 mm height with 40 mm MS black Rmtr. 1,830.19 2,104.71
pipe hand rail

25 ROAD WORK

Subgrade prepairing work with simple mud cutting 10 mtr.


15.01 O1 Sqm. 92.70 106.60
lead
15.02 O2 Rolling work Sqm. 7.94 9.13
10 cm. compact sub base laying work with sand mixed gravel,
15.03 O3(15-9A) Sqm. 189.02 217.37
load unload & proper levelling.
15 cm. compact sub base laying work with sand mixed gravel,
15.04 O3(15-9C) Sqm. 262.37 301.72
load unload & proper levelling.

20 cm. compact sub base laying work with sand mixed gravel,
15.05 O3(15-9D) Sqm. 324.04 372.64
load unload & proper levelling.

26 Misclenious WORK

Alluminium fixed panel window With ventilation but without fly


25.01 #N/A mesh shutter from section( 88mmx38.1mm x1.3mm , Glass Sqm. 6,386.00 7,343.90
5mm)
Alluminium fixed panel window With Ventilation with fly mesh
25.02 #N/A Sqm. 7,107.00 8,173.05
shutter from section(88mmx38.1mm x1.3mm , Glass 5mm )
Alluminium framed Sliding window Without ventilator without
25.03 #N/A fly mesh ( Aluminium :- Natural anodised 101.6mmx45mm Sqm. 8,446.00 9,712.90
x1.50mm , Glass 5mm clear)
Alluminium framed Sliding window With ventilator and
25.04 #N/A Mosquito Net ( Aluminium :- Natural anodised 101mmx45mm Sqm. 8,446.00 9,712.90
x1.5mm , Glass 5mm clear)
Alluminium framed Casement window With ventilator
25.05 #N/A ( Aluminium :- Natural anodised 38mmx34mm x1.5mm , Glass Sqm. 5,381.75 6,189.01
5mm clear)
Alluminium framed Sliding Door ( Aluminium :- Natural
25.06 #N/A anodised 101mmx45mm x1.5mm , Glass 5mm clear , board : Sqm. 7,926.88 9,115.91
9mm Laminated
Alluminium framed Casement Door (One -Way Openable )
25.07 #N/A ( Aluminium :- Natural anodised 101.6mmx45mm x1.5mm , Sqm. 9,064.00 10,423.60
Glass 5mm clear , board : 9mm Laminated

Prepared by Checked by Approved by


65 of 276
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :SARLAHI 2078/2079


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

Alluminium framed Swing Door (Two -Way Openable )


25.08 #N/A ( Aluminium :- Natural anodised 101.6mmx45mm x1.5mm , Sqm. 9,527.50 10,956.62
Glass 5mm clear , board : 9mm Laminated
Alluminium framed fixed partition ( Aluminium :- Natural
25.09 #N/A anodised 101mmx45mm x1.5mm , Glass 5mm clear or board : Sqm. 6,643.50 7,640.02
9mm Laminated
Alluminium fixed panel window With ventilation but without fly
25.10 #N/A mesh shutter from section( 78mmx38.1mm x1.1mm , Glass Sqm. 4,156.05 4,779.45
4.75 -5mm
Aluminum framed Sliding window With ventilator and with
25.11 0 Mosquito Net ( Aluminium :- Natural anodised 78mmx35mm Sqm. - -
x1.2mm , Glass 5mm clear)

25.12 0 False ceiling by Gypsum ,Gypsum Board : 12mm Sqm. 133.90 153.98
11.09 0 ASO Joint Tape laying Work. Rm - -

Prepared by Checked by Approved by


66of276
GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Detail Estimate
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi

S.N. Description of Work No. Length Breadth Height Qty. Unit Rate
A. Civil Work
CONSTRUCTION OF GHAT
Pond Length: 59 m (N), 75 m (S), 55 m (E), 82 m (W)
1 Cutting and clearing all rubbish, bushes, top
soil,
West Side 1.00 30.000 7.000 210.000
Total 210.000 Sqm 6.00
2 Dewatering of pond all complete as per
instruction of site Incharge
Water area 1.00 67.000 68.500 1.200 5,507.400
Total 5,507.400 Cum 34.32
3 Earthfill with transported earth
West Side Filling 1.00 35.000 6.000 1.400 294.000
Ghat walkway 1.00 35.000 1.500 1.100 57.750
Outer Side of walkway 1.00 35.000 1.000 0.500 17.500
step 1 1.00 33.500 0.770 0.500 12.898
Step 2 1.00 32.500 0.770 0.500 12.513
Step 3 1.00 31.750 0.370 0.500 5.874
Step 4 1.00 31.250 0.370 0.500 5.781
Step 5 1.00 31.000 0.370 0.500 5.735
Total 412.050 Cum. 540.00
4 flat brick soling
Ghat walkway 1.00 35.000 1.540 53.900
Ghat walkway Side wall 1 1.00 36.000 0.230 8.280
Ghat walkway Side wall 2 1.00 34.000 0.230 7.820
Side wall 1 1.00 33.000 0.230 7.590
Side wall 2 1.00 32.000 0.230 7.360
Side wall 3 1.00 31.500 0.230 7.245
Side wall 4 1.00 31.000 0.230 7.130
Side wall 5 Rest on Stone Masonary Wall
Step 1 1.00 33.500 0.770 25.795
Step 2 1.00 32.500 0.770 25.025
Step 3 1.00 31.750 0.370 11.748
Step 4 1.00 31.250 0.370 11.563
Step 5 1.00 31.000 0.370 11.470
Solar Light 6.00 0.600 0.600 2.160
Total 187.085 Sqm. 576.83
5 Plain cement Concrete (PCC) in 1:2:4 ratio for
foundations, flooring and walls.
Bottom of Stone Masonary wall 1.00 30.000 2.000 0.127 7.620
Top of Stone Masonary wall 1.00 30.000 0.800 0.100 2.400
Ghat walkway side wall -1 1.00 36.000 0.230 0.075 0.621
Ghat walkway side wall -2 1.00 34.000 0.230 0.075 0.587
Side wall -1 1.00 33.000 0.230 0.075 0.569
Side wall -2 1.00 32.000 0.230 0.075 0.552
Side wall -3 1.00 31.500 0.230 0.075 0.543
Side wall -4 1.00 31.250 0.230 0.075 0.539
Side wall -5 1.00 31.000 0.230 0.075 0.535
Ghat walkway 1.00 35.000 2.000 0.100 7.000
Step -1 (1.00 m) 1.00 33.500 0.770 0.075 1.935
Step -2 (1.00 m) 1.00 32.500 0.770 0.075 1.877
Step -3 (0.6 m) 1.00 31.750 0.370 0.075 0.881
Step -4 (0.6 m) 1.00 31.250 0.370 0.075 0.867
Step -5 (0.6 m) 1.00 31.000 0.370 0.075 0.860
Solar Light 6.00 0.600 0.600 1.300 2.808
Total 30.194 Cum. 10,693.80
6 Good quality local chimney made flat / edge
Brickwork in 1:4 C/S mortar
Ghat walkway side wall 1 1.00 36.000 0.230 1.100 9.108
Ghat walkway side wall 2 1.00 34.000 0.230 1.100 8.602
Side wall -1 1.00 33.000 0.230 0.675 5.123
Side wall -2 1.00 32.000 0.230 0.675 4.968
Side wall -3 1.00 31.500 0.230 0.675 4.890
Side wall -4 1.00 31.250 0.230 0.675 4.852
Side wall -5 (on stone masonary wall) 1.00 31.000 0.230 0.675 4.813
Step - 1 1.00 32.500 0.770 0.140 3.504
Step - 2 1.00 31.500 0.770 0.140 3.396
Step - 3 1.00 30.750 0.370 0.140 1.593
Step - 4 1.00 30.250 0.370 0.140 1.567

Prepared By: Checked By: Approved By:


67of276
GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Detail Estimate
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi

S.N. Description of Work No. Length Breadth Height Qty. Unit Rate
Step - 5 1.00 30.000 0.370 0.140 1.554
Step - 6 (on stone masonary wall) 1.00 29.750 0.800 0.140 3.332
Buttress wall on Step 1 2.00 1.000 0.500 0.440 0.440
Buttress wall on Step 2 2.00 1.000 0.500 0.740 0.740
Buttress wall on Step 3 2.00 0.600 0.500 1.040 0.624
Buttress wall on Step 4 2.00 0.600 0.500 0.440 0.264
Buttress wall on Step 5 2.00 0.600 0.500 0.740 0.444
Buttress wall on Stone Masonary wall 2.00 0.800 0.500 1.040 0.832
Total 60.645 Cum. 10,488.00
7 Gravel packing
for Stone Masonary 1.00 30.000 2.000 0.150 9.000
Total 9.000 Cum. 1,666.92
8 Stone soling
for Stone Masonary 1.00 30.000 2.000 0.150 9.000
Total 9.000 Cum. 3,420.00
9 Earthwork in exavation in ordinary soil
Excavation for Stone Masonary 1.00 30.000 2.000 1.500 90.000
Ghat walkway side wall 1 1.00 36.000 0.400 0.500 7.200
Ghat walkway side wall 2 1.00 34.000 0.400 0.500 6.800
Side wall -1 1.00 33.000 0.400 0.200 2.640
Side wall -2 1.00 32.000 0.400 0.200 2.560
Side wall -3 1.00 31.500 0.400 0.200 2.520
Side wall -4 1.00 31.250 0.400 0.200 2.500
Solar Light 2.00 0.600 0.600 1.000 0.720
Total 114.940 Cum. 432.60
10 Back fill
1.00 68.964 0.600 41.378
Total 41.378 Cum. 300.00
11 Stone Masonary Wall in 1:4 C/S mortar up for
Retaining Wall
0.50 30.000 0.300 1.700 7.650
0.50 30.000 0.300 1.700 7.650
1.00 30.000 1.200 1.700 61.200
1.00 30.000 0.800 0.300 7.200
Total 83.700 Cum. 9,811.00
12 Formwork, shuttering, centering with approved
materials.
Bottom of stone masonry wall 2.00 30.000 0.127 7.620
Top of stone masonry wall 2.00 30.000 0.127 7.620
Ghat Walkway 2.00 35.000 0.100 7.000
Walkway side wall 1 2.00 36.000 0.075 5.400
Walkway side wall 2 2.00 34.000 0.075 5.100
Side Wall 1 2.00 33.000 0.075 4.950
Side Wall 2 2.00 32.000 0.075 4.800
Side Wall 3 2.00 31.500 0.075 4.725
Side Wall 4 2.00 31.250 0.075 4.688
Side Wall 5 (Rest on Stone Masonry wall) 1.00 30.000 0.075 2.250
Total 54.153 Sqm. 542.95
13
Supply & fixing work of 50mm Ф MS black pipe
@ 2.0 mtr with 10 S.W.G.G.I. Chain Link 2"x2"
mesh size fixing in 4x20x20 mm & 4x25x25 mm
MS angle frame & top 3x20 mm MS grill 15 cm
height with primer coat
1.00 64.000 1.500 96.000
Total 96.000 Sqm. 2,985.37
14 Installation of Solar Light
14.1 Supply of 200wattPV (solar panel) 6.00 6.000 set 18540
14.2 Supply of 100A 12Volt Solar Gel Battery 6.00 6.000 set 41,241.20
14.3 Supply of Charger Controller 20 Amp 6.00 6.000 set 4,927.52
14.4 40W LED Light 6.00 6.000 set 19,710.08
14.5 Solar Light Arm 6.00 6.000 Set 2,266.00
14.6 UV Cable and installation materials 60.00 60.000 m 150.00
9Mtrs Long Hot Deep Galvanized Iron Pole
(5"dia.5m GI Pipe heavy class + 4" dia. 2M long
GI Pipe heavy class + 3" dia. 2M long GI Pipe
14.7 heavy class , light stand battery box , panel base etc 6.000 set 27,707.00
as per specification direction , Instruction of site
Incharge 6.00

Prepared By: Checked By: Approved By:


68of276
GOVERNMENT OF NEPAL
MINISTRY OF URBAN DEVELOPMENT
DEPARTMENT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION
FEDERAL PROJECT IMPLEMENTATION UNIT, DHANUSHA
Detail Estimate
Project : Construction of Ghat and Beautification of Khutauna Pond
Site : Malangwa-6, Khutauna, Sarlahi

S.N. Description of Work No. Length Breadth Height Qty. Unit Rate

Supply ,Delivary and insttalation of Battery


14.8 box,battery stand & light stand ,nut bolt etc. as per 6.000 set 9,270.00
specification direction , Instruction of site Incharge.
6.00
14.9 Installation Charge 1.00 1.000 LS 50,000.00
Supplying & Fixing Checker Tiles with Level as
15 per Site Instruction
Ghat Walkway 1.00 243.000 2.000 486.000
1St Step 1.00 234.000 1.000 234.000
2nd Step 1.00 196.000 1.000 196.000
916.000 Sqm 2,031.50
B. Provisional Sum
Carrying out diferrent laboratory tests from site
engineer. 15,000.00
1 1.00 PS

Prepared By: Checked By: Approved By:


69of276

F.Y. 2078/079

Amount Remark

1,260.00

189,013.97

222,507.00

107,916.24

322,887.93

Prepared By: Checked By: Approved By:


70of276

F.Y. 2078/079

Amount Remark

636,044.10

15,002.28

30,780.00

49,723.04

12,413.52

821,180.70

29,402.10

286,595.52

111,240.00
247,447.20
29,565.12
118,260.48
13,596.00
9,000.00

166,242.00

Prepared By: Checked By: Approved By:


71of276

F.Y. 2078/079

Amount Remark

55,620.00
50,000.00

1,860,854.00

15,000.00

Prepared By: Checked By: Approved By:


Summary of Rates Page 1 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Operation and maintenance of Temporary diversion of road/ bridge to keep the road
1 1.1 104 serviceable through out the contract period as per specification and instruction of km-month/LS 0
engineer
Carry out maintenance of the existing road to keep the road serviceable through out
2 1.2 109 Km-month 0
the contract period as per specification and instruction of the Engineer
Providing and installation of project signboards with size of 1.8 x 1.2 m as per
3 1.3 110 nos 7923.5
specification and instruction of engineer.
Providing and establishing camp with mobilization and demobilization for contractor's
4 1.4 111 Labour and staff and demolishing after completion of works as per the specifications job 0
and instruction of the Engineer.
Relocation of services / minor infrastructures, as per specifications and instruction of
5 1.5 111 job 0
the Engineer.
6 1.6 116 Supply of Project Record as per specifications and instruction of the Engineer. set 0
7 1.7 111 Reinstatement of quarry sites at the completion of works as instructed by the engineers. 0

Engineer's Facilities: Establishment and maintenance of office and site camp etc, and
8 PS 0
providing furniture and other facilities as directed by the Engineer.
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
9 20.4.B 2000 cum 12665.9
per drawing and Technical Specifications, PCC Grade M20, Height upto 5 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
10 20.4.C.p 2000 cum 14160.28
per drawing and Technical Specifications, PCC Grade M 25, Height upto 5 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


11 20.4.C.q 2000 cum 14675.2
per drawing and Technical Specifications, PCC Grade M 25, Height above 5 m to 10 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


12 20.4.C.r 2000 cum 15318.85
per drawing and Technical Specifications, PCC Grade M 25, Height above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
13 20.4.D.p 2000 cum 16604.26
per drawing and Technical Specifications, PCC Grade M 30, Height upto 5 m

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
1 2.1.I.i.A 201 sqm 13.8
stacking of serviceable Material to be used or auctioned, up to a lead of 30 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Manual Means:-, In area of light jungle (less than 15 number per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
2 2.1.I.i.B 201 sqm 20.7
stacking of serviceable Material to be used or auctioned, up to a lead of 30 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Manual Means:-, In area of thorny jungle ( more than 15 numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
3 2.1.I.ii.A 201 sqm 8.54
stacking of serviceable Material to be used or auctioned, up to a lead of 30 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Mechanical Means, In area of light jungle (less than 15 number per 100 sqm )

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
4 2.1.I.i.C 201 stacking of serviceable Material to be used or auctioned, up to a lead of 30 meters cum 1380
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Manual Means:-, Felling and uprooting of bamboo clearing the area, stacking of
bamboo and disposing of wastes

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
5 2.1.I.ii.B 201 sqm 8.75
stacking of serviceable Material to be used or auctioned, up to a lead of 30 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Mechanical Means, In area of thorny jungle ( more than 15 numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
6 2.1.I.ii.C 201 stacking of serviceable Material to be used or auctioned, up to a lead of 30 meters cum 544.48
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Mechanical Means, Felling and uprooting of bamboo clearing the area, stacking of
bamboo and disposing of wastes

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
7 2.1.II.i.A 201 sqm 17.06
stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Manual Means:-, In area of light jungle (less than 15 number per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
8 2.1.II.i.B 201 sqm 23.96
stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
In area of thorny jungle ( more than 15 numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
9 2.1.II.i.C 201 stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters cum 1705.68
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
Felling and uprooting of bamboo clearing the area, stacking of bamboo and disposing
of wastes

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 2 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
2.1.II.ii. mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
10 201 sqm 10.21
A stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Mechanical Means, In area of light jungle (less than 15 number per 100 sqm )

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
2.1.II.ii. mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
11 201 sqm 10.49
B stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Mechanical Means, In area of thorny jungle ( more than 15 numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and
2.1.II.ii.
12 201 stacking of serviceable Material to be used or auctioned, up to a lead of 1000 meters cum 1069.64
C
including removal and disposal of top organic soil not exceeding 150 mm in thickness.,
By Mechanical Means, Felling and uprooting of bamboo clearing the area, stacking of
bamboo and disposing of wastes

Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees,
including cutting of trunks, branches and removal of stumps, roots, stacking of
13 2.2.i 201 number 830.3
serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
depression/pit., Girth from 300 mm to 600 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees,
including cutting of trunks, branches and removal of stumps, roots, stacking of
14 2.2.ii 201 number 2490.9
serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
depression/pit., Girth from 600 mm to 900 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees,
including cutting of trunks, branches and removal of stumps, roots, stacking of
15 2.2.iii 201 number 6361.8
serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
depression/pit., Girth from 900 mm to 1800 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees,
including cutting of trunks, branches and removal of stumps, roots, stacking of
16 2.2.iv 201 number 14869.5
serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
depression/pit., Girth from 1800 - 2500 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees,
including cutting of trunks, branches and removal of stumps, roots, stacking of
17 2.2.v 201 number 49818
serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
depression/pit., Girth above 2500 mm
Clearing Grass and Removal of Rubbish and Dressing and levelling the construction
surface Clearing grass/ top soil and removal up to a distance of 50 meters outside the
18 2.3 201 sqm 6
periphery of the area , including cutting and filling of small undulation., By Manual
Means

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
19 2.4.i.I.A 202 cum 1262.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Lime /Cement Concrete, By Manual Means, Lime Concrete, cement
concrete grade M-10 and below

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
20 2.4.i.I.B 202 cum 1469.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Lime /Cement Concrete, By Manual Means, Cement Concrete Grade M-
15 & M-20

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
21 2.4.i.I.C 202 cum 3249.9
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Lime /Cement Concrete, By Manual Means, Pre-stressed / Reinforced
cement concrete grade M-20 & above

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
22 2.4.i.II.A 202 cum 2482.62
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Lime /Cement Concrete, By Mechanical Means, Cement Concrete Grade
M-15 & M-20

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
23 2.4.i.II.B 202 cum 2862.12
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Lime /Cement Concrete, By Mechanical Means, Prestressed / reinforced
cement concrete grade M-20 & above

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
24 2.4.ii.A 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 848.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Brick / Tile work, In lime mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
25 2.4.ii.B 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 1559.4
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Brick / Tile work, In cement mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
26 2.4.ii.C 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 779.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Brick / Tile work, In mud mortar

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 3 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
27 2.4.ii.D 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 848.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Brick / Tile work, Dry brick pitching or brick soling

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
28 2.4.iii.A 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 952.2
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Stone Masonry, Rubble stone masonry in lime mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
29 2.4.iii.B 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 1559.4
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Stone Masonry, Rubble stone masonry in cement mortar.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
30 2.4.iii.C 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 848.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Stone Masonry, Rubble Stone Masonry in mud mortar.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
31 2.4.iii.D 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 779.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Stone Masonry, Dry rubble masonry

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
32 2.4.iii.E 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 710.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Stone Masonry, Dismantling stone pitching/ dry stone spalls.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
33 2.4.iii.F 202 cum 952.2
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Dismantling Stone Masonry, Dismantling boulders laid in wire crates
including opening of crates and stacking dismantled Material.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
34 2.4.iv 202 cum 1559.4
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Wood Work wrought framed and fixed in frames of trusses upto a height
of 5 m above plinth level

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
35 2.4.v.A 202 tonne 5421.68
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Steel Work in all types of sections upto a height of 5 m above plinth level
excluding cutting of rivet., Including dismembering

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
36 2.4.v.B 202 tonne 4643.7
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Steel Work in all types of sections upto a height of 5 m above plinth level
excluding cutting of rivet., Excluding dismembering.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
37 2.4.v.C 202 number 34.5
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Steel Work in all types of sections upto a height of 5 m above plinth level
excluding cutting of rivet., Extra over item No( v ) A and( v ) B for cutting rivets.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
38 2.4.vi.A 202 number 32.78
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Scraping of Bricks Dismantled from Brick Work including Stacking., In
lime/Cement mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
39 2.4.vi.B 202 number 22.43
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Scraping of Bricks Dismantled from Brick Work including Stacking., In
mud mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
40 2.4.vii.A 202 cum 1069.5
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Scraping of Stone from Dismantled Stone Masonry, In cement and lime
mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
41 2.4.vii.B 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of cum 448.5
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Scraping of Stone from Dismantled Stone Masonry, In Mud mortar

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 4 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
42 2.4.viii 202 scaffolding wherever necessary, sorting the dismantled Material, disposal of sqm 77.97
unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
2.4.v.ix. scaffolding wherever necessary, sorting the dismantled Material, disposal of
43 202 meter 448.5
A unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Removing all type of Hume Pipes and Stacking within a lead of 50 metres
including Earthwork and Dismantling of Masonry Works., Up to 600 mm dia

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
scaffolding wherever necessary, sorting the dismantled Material, disposal of
44 2.4.v.ix.B 202 unserviceable Material and stacking the serviceable Material with all lifts and lead of meter 655.5
1000 meters, Removing all type of Hume Pipes and Stacking within a lead of 50 metres
including Earthwork and Dismantling of Masonry Works., Above 600 mm to 900 mm
dia

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
2.4.v.ix. scaffolding wherever necessary, sorting the dismantled Material, disposal of
45 202 meter 931.5
C unserviceable Material and stacking the serviceable Material with all lifts and lead of
1000 meters, Removing all type of Hume Pipes and Stacking within a lead of 50 metres
including Earthwork and Dismantling of Masonry Works., Above 900 mm
Dismantling of Flexible Pavements, Dismantling of flexible pavements and disposal of
46 2.5.I.A 202 dismantled Material up to a lead of 1000 metres, stacking serviceable and unserviceable cum 1904.4
Material separately, By Manual Means, Bituminous courses
Dismantling of Flexible Pavements, Dismantling of flexible pavements and disposal of
47 2.5.I.B 202 dismantled Material up to a lead of 1000 metres, stacking serviceable and unserviceable cum 1697.4
Material separately, By Manual Means, Granular courses
Dismantling of Flexible Pavements, Dismantling of flexible pavements and disposal of
48 2.5.II.A 202 dismantled Material up to a lead of 1000 metres, stacking serviceable and unserviceable cum 1139.19
Material separately, By Mechanical Means, Bituminous course
Dismantling of cement concrete pavement by mechanical means using pneumatic tools,
breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated
49 2.6 202 cum 4112.63
locations and disposal of dismantled Material up to a lead of 1000 metres, stacking
serviceable and unserviceable Material separately
Dismantling guard rails by manual means and disposal of dismantled Material with all
50 2.7 202 lifts and up to a lead of 1000 metres, stacking serviceable Material and unserviceable meter 224.94
Material separately.
Dismantling Kerb stone by manual means and disposal of dismantled Material with all
51 2.8 202 meter 107.64
lifts and up to a lead of 1000 meter
Dismantling Kerb stone channel by manual means and disposal of dismantled Material
52 2.9 202 meter 121.44
with all lifts and up to a lead of 1000 meter
Dismantling of kilometer stone including cutting of earth, foundation and disposal of
53 2.10.A 202 dismantled Material with all lifts and lead upto 1000 m and back filling of pit., Five number 222.18
KM stone
Dismantling of kilometer stone including cutting of earth, foundation and disposal of
54 2.10.B 202 dismantled Material with all lifts and lead upto 1000 m and back filling of pit., One KM number 131.79
Stone
Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation
concrete, back filling of pit by manual means including disposal of dismantled Material
55 2.11 202 meter 180.09
with all lifts and up to a lead of 1000 metres, stacking serviceable Material and
unserviceable Material separately.
Dismantling of CI water pipe line upto 600 mm dia including disposal with all lifts and
56 2.12 202 lead upto 1000 metres and stacking of serviceable Material and unserviceable Material meter 545.74
separately .

Removal of cement concrete pipe of sewer gutter 1500 mm dia including disposal with
57 2.13 202 all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable meter 560
Material separately but excluding earth excavation and dismantling of masonry works.

Removal of telephone / Electric poles including excavation and dismantling of


foundation concrete and lines under the supervision of concerned department, disposal
58 2.14 202 nos 683.68
with all lifts and up to a lead of 1000 metres and stacking the serviceable and
unserviceable Material separately
Providing, jointing and laying HDPE pipes with or without collar etc. complete in place
1 7.1.A 701 meter 874.86
as per Drawing and Technical Specifications., a) 110 mm/125 mm outer dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts
2 7.2.A 701 including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., meter 3973.06
300 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts
3 7.2.B 701 including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., meter 5032.46
450 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts
4 7.2.C 701 including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., meter 7530.75
600 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts
5 7.2.D 701 including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., meter 13090.09
900 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts
6 7.2.E 701 including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., meter 14579.49
1000 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts
7 7.2.F 701 including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., meter 2734.83
1200 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts
8 7.3.A 701 including fixing collar with cement mortar 1:2 as per Drawing and Technical meter 3973.06
Specifications., 300 mm internal dia.

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 5 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts
9 7.3.C 701 including fixing collar with cement mortar 1:2 as per Drawing and Technical meter 7530.75
Specifications., 600 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts
10 7.3.B 701 including fixing collar with cement mortar 1:2 as per Drawing and Technical meter 5787.32
Specifications., 450 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts
11 7.3.D 701 including fixing collar with cement mortar 1:2 as per Drawing and Technical meter 13090.09
Specifications., 900 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts
12 7.3.E 701 including fixing collar with cement mortar 1:2 as per Drawing and Technical meter 14579.49
Specifications., 1000 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts
13 7.3.F 701 including fixing collar with cement mortar 1:2 as per Drawing and Technical meter 2734.83
Specifications., 1200 mm internal dia.
Providing and laying concrete channeling as per Drawing and Technical
14 7.4.A 702 0
Specifications., Cast in situ
Providing and laying concrete channeling as per Drawing and Technical
15 7.4.B 702 0
Specifications., Pre cast
16 7.4.C 702 Laying (Joining) of Precast concrete panel meter 275.2
Earthwork Excavation in Cutting., Roadway Excavation in all types of Soil by Manual
Means ., Roadway Excavation in all types of soil as per drawing and technical
1 9.1.I.A 905 cum 562.64
specification, including removal of stumps and other deleterious matter, with all lifts
and lead as per Drawing and instruction of the Engineer.
Earthwork Excavation in Cutting., Roadway Excavation in all types of Soil by
Mechanical Means ., Road way Excavation in all types of soil as per Drawing and
2 9.1.I.B 905 cum 77.05
technical specifications including removal of stumps and other deleterious matter, all
lifts and lead as per Drawing and instruction of the Engineer.
Earthwork Excavation in Cutting., Roadway Excavation in ordinary rock by Manual
Means ., Roadway Excavation in ordinary rock as per Drawing and Technical
3 9.1.II.A 905 cum 645.55
specification, including all lift and lead as per Drawing and instruction of the
Engineer.
Earthwork Excavation in Cutting., Roadway Excavation in ordinary rock by
Mechanical Means ., Roadway Excavation in ordinary rock as per Drawing and
4 9.1.II.B 905 cum 231.15
Technical specification, including all lift and lead as per Drawing and instruction of
the Engineer.
Earthwork Excavation in Cutting., Roadway Excavation in Hard Rock, mechanical
Drilling, Roadway Excavation in hard rock with mechanical drilling, including
5 9.1.III.A 905 cum 1118.75
blasting and breaking, and disposal of cut road within all lifts and leads as per
Drawing and instruction of the Engineer.
Earthwork Excavation in Cutting., Excavation in Hard Rock, manual Drilling,
6 9.1.III.B 905 Roadway excavation in hard rock with manual drilling, blasting, breaking, lifts and cum 1234.51
leads all complete as per Drawing and instruction of the Engineer.
Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting prohibited),
Roadway Excavation in hard rock with rock breakers, including breaking rock,
7 9.1.IV.A 905 cum 2035.5
lifts and lead for disposal as per Drawing and Technical Specifications, Mechanical
method, lead upto 30 m
Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting prohibited),
8 9.1.IV.B 905 Roadway Excavation in hard rock manually chiseling including breaking rock, lifts cum 2790.98
and lead for disposal as per Drawing and Technical Specifications ,

Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting prohibited),


9 9.1.IV.C 905 Roadway Excavation in hard rock manually with use of chemical, including breaking cum 843.96
rock, disposal within all lifts and lead as per Drawing and Technical Specifications

Earthwork Excavation in Cutting., Excavation in Marshy Soil, Roadway Excavation in


10 9.1.V 905 cum 195.09
marshy soil as per Drawing and Technical Specifications
Removal of Unserviceable Soil with Disposal upto 1000 meters, Removal of
11 9.2 900 cum 162.57
unserviceable soil including excavation, loading and disposal upto 1000 meters lead

Trimming/ Rock Excavation Slopes, Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of explosives and blasting accessories
12 9.3 907 sqm 268.36
in properly aligned and spaced drill holes, collection of the excavated rock by machine,
with all lifts and lead as per Drawing and instruction of the Engineer.

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
13 9.4.I.A.i 907 cum 655.5
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Ordinary soil by Manual Means, Depth upto 3 m
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
14 9.4.I.A.ii 907 cum 931.5
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Ordinary soil by Manual Means, Depth 3 m to 6 m
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
15 9.4.I.A.iii 907 cum 1449
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Ordinary soil by Manual Means, Depth above 6 m
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
16 9.4.I.B.i 907 cum 115.58
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Ordinary soil by Mechanical Means, Depth upto 3 m
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
17 9.4.I.B.ii 907 cum 132.09
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Ordinary soil by Mechanical Means, Depth 3 m to 6 m
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
18 9.4.I.B.iii 907 cum 163.68
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Ordinary soil by Mechanical Means, Depth above 6 m

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 6 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
19 9.4.II.A.i 907 other deleterious matter and backfilling with approved Material as per Drawing and cum 793.5
Technical Specifications., Ordinary Rock (not requiring blasting) by Manual Means,
Depth upto 3 m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
20 9.4.II.B 907 other deleterious matter and backfilling with approved Material as per Drawing and cum 308.2
Technical Specifications., Ordinary Rock (not requiring blasting) by Mechanical
Means, Depth upto 3 m
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
21 9.4.III.A 907 cum 1394.26
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Hard Rock ( requiring blasting ) by Manual Means
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
22 9.4.IV.A 907 cum 1496.96
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Hard Rock ( blasting prohibited ) by Mechanical Means
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
23 9.4.V.A 907 cum 1904.4
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Marshy Soil by Manual Means, Depth upto 3 m
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
24 9.4.V.B 907 cum 574.66
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Marshy Soil by Mechanical Means
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
25 9.4.VI 907 cum 943
other deleterious matter and backfilling with approved Material as per Drawing and
Technical Specifications., Back Filling in Marshy Foundation Pits
Stripping and Storing Top Soil, Stripping, storing of top soil by road side at 15 m
internal and re-application on embankment slopes, cut slopes and other areas in
26 9.5 905 cum 165.39
localities where the available embankment Material is not conducive to plant growth
as per Drawing and Technical Specifications.
Stripping, Storing and Re-laying Top Soil from Borrow Areas in Agriculture Fields.,
Stripping of top soil from borrow areas located in agriculture fields, storing at a
27 9.6 909 suitable place, spreading and re-laying after taking the borrow earth to maintain cum 353.79
fertility of the agricultural field, finishing it to the required levels to the satisfaction of
the farmer as per Drawing and Technical Specifications.
Preparation and Surface Treatment of Formation., Preparation and surface treatment
of Formation by removing mud and slurry, watering to the extent needed to maintain
28 9.7 909910 sqm 11.36
desired moisture content , compacting all complete as per Drawing and Technical
Specifications.
Construction of Embankment with Material obtained from Borrow pits, Providing,
29 9.8 909910 laying, spreading and compacting embankment with borrow material as per Drawing cum 834.9
and Technical Specifications.
Construction of Embankment with Material Deposited from Roadway Cutting,
Providing, laying, spreading and compacting embankment with roadway cutting
30 9.9.A 909910 cum 600.71
material and compact to the required density as per Drawing and Technical
Specifications.( Manually)
Construction of Embankment with Material Deposited from Roadway Cutting,
Providing, laying, spreading and compacting embankment with roadway cutting
31 9.9.B 909910 cum 480.17
material and compact to the required density as per Drawing and Technical
Specifications. (With machine)
Construction of Rock fill Embankment, Providing and laying of rock fill embankment
with broken hard rock fragments of size not exceeding 300 mm laid in layers not
32 9.10' 909910 exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top cum 526.84
layer with granular Material, rolled to required density all complete as per Drawing
and Technical Specifications.
Providing suitable material and Back filling behind abutment, wing wall and return
33 9.11.A 908 cum 1949.54
wall complete as per Drawing and Technical Specifications., Granular Material
Providing suitable material and Back filling behind abutment, wing wall and return
34 9.11.B 908 cum 1502.19
wall complete as per Drawing and Technical Specifications., Sandy Material
Providing suitable material and Back filling behind abutment, wing wall and return
35 9.11.C 908 wall complete as per Drawing and Technical Specifications., Locally available Material cum 974.67
including compaction by tamping rod ( without watering)
Providing suitable material and Back filling behind abutment, wing wall and return
36 9.11.D 908 wall complete as per Drawing and Technical Specifications., Locally available Material, cum 857.6
with out watering and compaction by tamping rod
Providing and laying of Filter media with granular Material/stone crushed aggregates
to a thickness of not less than 600 mm with smaller size towards the soil and bigger size
37 9.12 909910 towards the wall and provided over the entire surface behind abutment, wing wall and cum 2564.5
return wall to the full height compacted to a firm condition complete as per drawing
and Technical Specification.
Providing and filling sand in Foundation Trenches as per Drawing & Technical
38 9.13 909910 cum 1224.75
Specification
Scarifying Existing road Surface to a Depth of 50 mm by
Manual Means, Scarifying the existing road surface to a depth of 50 mm and disposal
1 10.1.A 1003 sqm 31.74
of scarified Material with all lifts and leads as per Drawing and Technical
Specifications.
Scarifying Existing road Surface to a Depth of 50 mm by
Manual Means, Scarifying the existing granular road surface to a depth of 50mm and
2 10.1.B 1003 sqm 15.53
disposal of scarified Material with all lifts and leads within Right of way as per
Drawing and Technical Specifications.
Scarifying Existing road Surface to a depth of 50 mm by Mechanical Means, Scarifying
3 10.2.A 1003 the existing road surface to a depth of 50 mm and disposal of scarified Material with in sqm 21.76
all lifts and lead as per Drawing and Technical Specifications.

Scarifying Existing road Surface to a depth of 50 mm by Mechanical Means, Scarifying


4 10.2.B 1003 the existing bituminous road surface to a depth of 50 mm and disposal of scarified sqm 14.5
Material with in all lifts and lead as per Drawing and Technical Specifications.

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 7 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Construction of Subgrade and Earthen Shoulders with approved Material ( capping
layer), Providing and laying sub-grade and earthen shoulders with approved Material
5 10.3.A 1004 sqm 133.18
obtained from borrow pits with all lifts & leads as per Drawing and Technical
Specifications.
Compacting Original Ground, Compacting original ground supporting sub-grade,
6 10.4.I_a 1003, 1005 Loosening of the ground upto a level of 500 mm below the sub-grade level, watered, cum 149.25
graded and compacted in layers as per Drawing and Technical Specifications.
Compacting Original Ground, Compacting original ground supporting embankment,
Loosening, leveling and Compacting original ground supporting embankment to
7 10.4.II_a 1003, 1005 facilitate placement of first layer of embankment, scarified to a depth of 150 mm, sqm 93.36
mixed with water at OMC and then compacted by rolling so as to achieve dry density
as per Drawing and Technical Specifications.
Providing and laying granular sub-base on prepared surface, mixing at OMC, and
1 12.1.A compacting to achieve the desired density, complete as per Drawing and Technical cum 1666.92
Specifications., By Mechanical means
Providing and laying granular sub-base on prepared surface, mixing at OMC, and
2 12.1.B compacting to achieve the desired density, complete as per Drawing and Technical cum 2046.3
Specifications., By manual Means
Providing, laying and spreading soil on a prepared sub grade, pulverizing, adding the
designed quantity of cement to the spread soil, mixing in place , grading and
3 12.2 compacting at OMC to achieve the desired unconfined compressive strength and to cum 2425.74
form a layer of sub-base/base as per Drawing and Technical Specifications., For 4 per
cent quantity of cement by weight of soil
Providing, laying, spreading and compacting screening / coarse sand of specified grade
4 12.5 in uniform layer on a prepared surface and compacting to form a inverted Choke as cum 1188.88
per Drawing and Technical Specifications.
Providing, laying, spreading and compacting Water bound macadam including
brooming requisite type of screening/ binding Materials to fill up the interstices of
5 12.6.A_a coarse aggregate, watering and compacting to the required density as per Drawing and cum 2941.62
Technical Specifications., By Manual Means, By using stone screening 13.2mm and
Vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices of
6 12.6.A_b coarse aggregate, watering and compacting to the required density as per Drawing and cum 2910.77
Technical Specifications., By Manual Means, By using stone screening 13.2mm and
Smooth 3 wheeled steel roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices of
7 12.6.A_c coarse aggregate, watering and compacting to the required density as per Drawing and cum 3121.02
Technical Specifications., By Manual Means, By using stone screening 11.2 mm for
grading-II and Vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices of
8 12.6.A_d coarse aggregate, watering and compacting to the required density as per Drawing and cum 3090.17
Technical Specifications., By Manual Means, By using stone screening 11.2 mm for
grading-II and Smooth 3 wheeled

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices of
9 12.6.B_a coarse aggregate, watering and compacting to the required density as per Drawing and cum 2254.59
Technical Specifications., By Mechanical Means:, By using stone screening 13.2 mm for
grading-II and vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices of
10 12.6.B_b coarse aggregate, watering and compacting to the required density as per Drawing and cum 2269.99
Technical Specifications., By Mechanical Means:, By using stone screening 13.2 mm for
grading-II and Smooth 3 wheeled steel roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices of
11 12.6.B_c coarse aggregate, watering and compacting to the required density as per Drawing and cum 2433.99
Technical Specifications., By Mechanical Means:, By using stone screening 11.2 mm for
grading-II and Smooth 3 vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices of
12 12.6.B_d coarse aggregate, watering and compacting to the required density as per Drawing and cum 2449.39
Technical Specifications., By Mechanical Means:, By using stone screening 11.2 mm for
grading-II and Smooth 3 wheeled steel roller
Providing and laying Crusher Run Macadam on a prepared surface, spreading and
13 12.7_a mixing , watering and compacting to form a layer of sub-base/Base course as per cum 2450.72
Drawing and Technical Specifications., By Mix in Place Method
Providing and laying Crusher Run Macadam on a prepared surface, spreading and
14 12.7_b mixing , watering and compacting to form a layer of sub-base/Base course as per cum 2864.82
Drawing and Technical Specifications., By Mix in Place Method
Providing and laying Median and Island above road level with approved Material
15 12.8 deposited including compacted as per Drawing and Specifications. ( using material cum 618.86
from Roadway excavation).
Providing and laying Median and Island above road level with approved Material
16 12.9 deposited including compacted as per Drawing and Specifications. ( using material cum 1111.72
from borrow area).
Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC laying in
17 12.14.A uniform layers in sub- base / base course on well prepared surface and compacting to cum 2530.31
achieve required density as per Drawing and Technical Specifications., Base course
with B1 material, Vibratory Road Roller

Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC laying in
18 12.14.B uniform layers in sub- base / base course on well prepared surface and compacting to cum 2530.31
achieve required density as per Drawing and Technical Specifications., Base course
with B2 material, Vibratory Road Roller

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 8 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC laying in
19 12.14.C uniform layers in sub- base / base course on well prepared surface and compacting to cum 2545.64
achieve required density as per Drawing and Technical Specifications., Sub Base
course with S1 material, Vibratory Road Roller

Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC laying in
20 12.14.D uniform layers in sub- base / base course on well prepared surface and compacting to cum 2545.64
achieve required density as per Drawing and Technical Specifications., Sub Base
course with S2 material, Vibratory Road Roller
Prime Coat, Prime Coat, with MC 30 / 70 by Mechanical Means, Providing and
applying prime coat with Hot Bitumen ( including cutter) on prepared surface of
1 13.1.A 1302 lit 119.14
granular base including cleaning of road surface and spraying by mechanical means as
per Technical Specification ., Bitumen ( cutback) MC 30 ( for WBM)
Prime Coat, Prime Coat, with MC 30 / 70 by Mechanical Means, Providing and
applying prime coat with Hot Bitumen ( including cutter) on prepared surface of
2 13.1.A_b 1302 granular base including cleaning of road surface and spraying by mechanical means as lit 119.14
per Technical Specification ., Bitumen ( cutback) MC 30 ( for stabilized soil base/
crusher run macadam)

, Prime Coat, with MC 30 / 70 by Bitumen , by manual means, Providing and applying


prime coat with Hot Bitumen(including cutter) on prepared surface of granular base
3 13.1.B 1302 lit 208.99
including cleaning of road surface and spraying at specified rate by manual means as
per Technical Specification . , Bitumen ( cutback) MC 30 ( for WBM)

, Prime Coat, with MC 30 / 70 by Bitumen , by manual means, Providing and applying


prime coat with Hot Bitumen(including cutter) on prepared surface of granular base
4 13.1.B_b 1302 including cleaning of road surface and spraying at specified rate by manual means as lit 208.99
per Technical Specification . , Bitumen (cut back )MC 70 ( for stabilized soil base/
crusher run macadam)
, Prime Coat, with Emulsion by Mechanical Means, Providing and applying primer
coat with Bitumen emulsion on prepared surface of granular base including cleaning
5 13.1.C 1302 lit 92.63
of road surface and spraying primer at specified rate using mechanical means as per
Technical Specification .
, Prime Coat with emulsion, for manual works, Providing and applying primer coat
6 13.1.D 1302 with Bitumen emulsion on prepared surface of granular base including cleaning of lit 157.1
road surface and spraying primer at specified rate as per Technical Specification.
Tack Coat, Tack coat with Bitumen By Mechanical Means, Providing and applying
7 13.2.A 1302 tack coat with hot Bitumen at specified rate on the prepared non-bituminous surfaces lit 108.1
including cleaning as per Technical Speciation .
, Tack coat with Bitumen by Manual Means, Providing and applying tack coat with hot
8 13.2.B 1302 Bitumen at the specified rate the prepared surfaces including cleaning as per Technical lit 162.36
Speciation .
, Tack coat with Emulsion By Mechanical Means, Providing and applying tack coat
9 13.2.C 1302 with Bitumen emulsion at specified rate on the prepared non-bituminous surfaces lit 86.05
including cleaning as per Technical Speciation .
, Tack coat with Emulsion By Manual Means, Providing and applying tack coat with
10 13.2.D 1302 Bitumen emulsion at the specified rate the prepared surfaces including cleaning as lit 102.7
per Technical Speciation .
Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant
using crushed aggregates of grading as per specification premixed with bituminous
11 13.3 1307 cum 14584.24
binder, laid over a previously prepared surface as per Drawing and Technical
Specifications. , Grading I ( 40 mm nominal size )
Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant
using crushed aggregates of grading as per specification premixed with bituminous
12 13.3_i 1307 binder, laid over a previously prepared surface as per Drawing and Technical cum 14752.09
Specifications. , Grading I ( 40 mm nominal size ), In case BM is laid over freshly laid
tack coat
Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant
using crushed aggregates of grading as per specification premixed with bituminous
13 13.3_a 1307 cum 14614.36
binder, laid over a previously prepared surface as per Drawing and Technical
Specifications. , Grading II(19 mm nominal size)
Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant
using crushed aggregates of grading as per specification premixed with bituminous
14 13.3_a_i 1307 binder, laid over a previously prepared surface as per Drawing and Technical cum 14782.21
Specifications. , Grading II(19 mm nominal size), In case BM is laid over freshly laid
tack coat
Bituminous Penetration Macadam, Providing and laying penetration macadam over
prepared Base by providing a layer of compacted crushed coarse aggregate with
15 13.4.A 1304 sqm 469.77
applications of bituminous binder and key aggregates as per Drawing and Technical
Specifications., 50 mm thick
Bituminous Penetration Macadam, Providing and laying penetration macadam over
prepared Base by providing a layer of compacted crushed coarse aggregate with
16 13.4.B 1304 sqm 628.35
applications of bituminous binder and key aggregates as per Drawing and Technical
Specifications., 75 mm thick
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with bituminous
17 13.5 1308 cum 17426.09
binder and filler as per Drawing and Technical Specifications., Grading - I 40 mm
(Nominal Size)
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with bituminous
18 13.5_i 1308 cum 17602.54
binder and filler as per Drawing and Technical Specifications., Grading - I 40 mm
(Nominal Size), In case DBM is laid over freshly laid tack coat
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with bituminous
19 13.5_a 1308 cum 17441.55
binder and filler as per Drawing and Technical Specifications., Grading - II 19 mm
(Nominal Size)
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with bituminous
20 13.5_a_i 1308 cum 17618
binder and filler as per Drawing and Technical Specifications., Grading - II 19 mm
(Nominal Size), In case DBM is laid over freshly laid tack coat

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 9 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/
Asphalt concrete using crushed aggregates of specified grading, premixed with
21 13.6 1309 cum 20835.18
bituminous binder and filler as per Drawing and Technical Specifications, Grading -
I-19 mm (Nominal Size)
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/
Asphalt concrete using crushed aggregates of specified grading, premixed with
22 13.6_i 1309 cum 21015.33
bituminous binder and filler as per Drawing and Technical Specifications, Grading -
I-19 mm (Nominal Size), In case BC is laid over freshly laid tack coat
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/
Asphalt concrete using crushed aggregates of specified grading, premixed with
23 13.6_a 1309 cum 21416.25
bituminous binder and filler as per Drawing and Technical Specifications, Grading -
II-13 mm (Nominal Size)
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/
Asphalt concrete using crushed aggregates of specified grading, premixed with
24 13.6_a_i 1309 cum 21021.5
bituminous binder and filler as per Drawing and Technical Specifications, Grading -
II-13 mm (Nominal Size), In case BC is laid over freshly laid tack coat
Surface Dressing, Providing and laying surface dressing as wearing course in single
coat using gravel of specified size on a recently applied layer of bituminous binder on
25 13.7.A.I 1303 sqm 43.48
prepared surface as per Drawing and Technical Specifications., MECHANICAL
MEANS, 19 mm nominal chipping size
Surface Dressing, Providing and laying surface dressing as wearing course in single
coat using gravel of specified size on a recently applied layer of bituminous binder on
26 13.7.A.II 1303 sqm 31.39
prepared surface as per Drawing and Technical Specifications., MECHANICAL
MEANS, 13 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in single
13.7.A.II coat using gravel of specified size on a recently applied layer of bituminous binder on
27 1303 sqm 24.9
I prepared surface as per Drawing and Technical Specifications., MECHANICAL
MEANS, 10 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in single
13.7.A.I coat using gravel of specified size on a recently applied layer of bituminous binder on
28 1303 sqm 18.85
V prepared surface as per Drawing and Technical Specifications., MECHANICAL
MEANS, 6.0 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in single
coat using gravel of specified size on a recently applied layer of bituminous binder on
29 13.7.B.I 1303 sqm 86.07
prepared surface as per Drawing and Technical Specifications., MANUAL MEANS,
19 mm nominal size chipping 1:02:04
Surface Dressing, Providing and laying surface dressing as wearing course in single
coat using gravel of specified size on a recently applied layer of bituminous binder on
30 13.7.B.II 1303 sqm 41.86
prepared surface as per Drawing and Technical Specifications., MANUAL MEANS,
13 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in single
13.7.B.II coat using gravel of specified size on a recently applied layer of bituminous binder on
31 1303 sqm 35.13
I prepared surface as per Drawing and Technical Specifications., MANUAL MEANS,
10 mm nominal size chipping

Pre-coating Chips, Pre-coating of chips with 1 per cent of paving bitumen by weight of
32 13.8 N/A cum 2370.38
chips in a suitable mixer duly heated to 160 degree C as per Technical Specification

40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen /


Modified bitumen) Binder, Providing and laying open-graded premix carpet of 20 mm
33 13.9.A 1311 sqm 1030.46
thickness composed of 13.2 mm to 5.6 mm aggregates as wearing course on a previously
prepared base as per drawing and Technical Specifications ., By Manual Means

40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen /


Modified bitumen) Binder, By Mechanical Means, Providing and laying open-graded
34 13.9.B.i 1311 premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates as sqm 12541
wearing course on a previously prepared base as per drawing and Technical
Specifications ., Mechanical method using Hot Mix Plant

40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen /


Modified bitumen) Binder, By Mechanical Means, Providing and laying open-graded
35 13.9.B.ii 1311 premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates as sqm 454.79
wearing course on a previously prepared base as per drawing and Technical
Specifications ., Open-Graded Premix Surfacing using cationic Bitumen Emulsion

Close Graded Premix Surfacing/Mixed Seal Surfacing , Mechanical means using HMP
of appropriate capacity ,, Providing and laying close-graded premix surfacing material
36 13.10_a 1310 of 20 mm thickness composed of 11.2 mm to 0.09 mm or 13.2 mm to 0.09 mm sqm 304.32
aggregates using bitumen as wearing course on a previously prepared base, including
mixing in a suitable plant as per Drawing and Technical Specifications., Type - A

Close Graded Premix Surfacing/Mixed Seal Surfacing , Mechanical means using HMP
of appropriate capacity ,, Providing and laying close-graded premix surfacing material
37 13.10_b 1310 of 20 mm thickness composed of 11.2 mm to 0.09 mm or 13.2 mm to 0.09 mm sqm 275.7
aggregates using bitumen as wearing course on a previously prepared base, including
mixing in a suitable plant as per Drawing and Technical Specifications., Type - B

Seal Surfacing, Providing and laying seal coat sealing the voids in a bituminous surface
38 13.11 1310 sqm 101.01
as per Drawing and Technical Specifications.
Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine aggregates,
Portland cement filler, bituminous emulsion and water on a road surface including
39 13.12.i 1310 cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and sqm 98.71
compacting to provide even riding surface as per Drawing and Technical
Specifications., 5 mm thickness

Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine aggregates,
Portland cement filler, bituminous emulsion and water on a road surface including
40 13.12.ii 1310 cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and sqm 68.56
compacting to provide even riding surface as per Drawing and Technical
Specifications., 3 mm thickness

Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine aggregates,
Portland cement filler, bituminous emulsion and water on a road surface including
41 13.12.iii 1310 cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and sqm 42.31
compacting to provide even riding surface as per Drawing and Technical
Specifications., 1.5 mm thickness

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 10 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Fog Spray, Providing and applying low viscosity bitumen emulsion for sealing cracks
42 13.13 1310 less than 3 mm wide or incipient fretting or disintegration in an existing bituminous sqm 58.67
surfacing as per Drawing and Technical Specifications.
Fog Spray, Providing and applying low viscosity bitumen emulsion for sealing cracks
43 13.13_a 1310 less than 3 mm wide or incipient fretting or disintegration in an existing bituminous sqm 66.76
surfacing as per Drawing and Technical Specifications., Blind the fog spray
Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of
bituminous cold mix on prepared base consisting of a mixture of unheated mineral
44 13.14.i 1313 aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable cum 17596.99
type as per Drawing and Technical Specifications., Using bitumen emulsion and 9.5
mm or 13.2 mm size aggregate

Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of
bituminous cold mix on prepared base consisting of a mixture of unheated mineral
45 13.14.ii 1313 aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable cum 17517.05
type as per Drawing and Technical Specifications., Using bitumen emulsion and 19 mm
or 26.5 mm nominal size aggregate

Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of
bituminous cold mix on prepared base consisting of a mixture of unheated mineral
46 13.14.iii 1313 aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable cum 14701.51
type as per Drawing and Technical Specifications., Using cutback bitumen and 9.5 mm
or 13.2 mm nominal size aggregate

Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of
bituminous cold mix on prepared base consisting of a mixture of unheated mineral
47 13.14.iv 1313 aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable cum 14621.57
type as per Drawing and Technical Specifications., Using cutback bitumen and 19 mm
or 26.5 mm nominal size aggregate
Sand Asphalt Base Course, Providing, laying and rolling sand-asphalt base course
48 13.15. 1312 composed of sand, mineral filler and bituminous binder on a prepared sub-grade or cum 15154.06
sub-base as per Drawing and Technical Specifications.
Anti- Stripping agent, Providing and mixing of Anti stripping agent as per Design/
49 13.16 1300 kg 390.01
direction of Engineer
Bitumen Cutter, Providing and mixing of Bitumen cutter as per design / direction of
50 13.17 1300 lit 126.17
Engineer
Modified Binder, Supply of modified binder (produced by mixing bitumen with
51 13.18 1300 modifier such as natural rubber or crumb rubber or any other polymer found tonne 89240
compatible with bitumen) as per Specifications and direction of the Engineer.
Otta seal, Providing and laying Otta seal surface as wearing course in single coat using
52 13.19 1315 river bed shingles /aggregates of specified size ( 0- 16 mm) laid on prepared surface as sqm 183.93
per Drawing and Technical Specifications.
Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface,
53 13.20.i 1313 cum 10591.6
by paver finisher, rolled with a pneumatic tired roller initially and finished with a
smooth steel wheel roller, all as per specifications., 75 mm thickness
Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface,
54 13.20.ii 1313 cum 14550.27
by paver finisher, rolled with a pneumatic tired roller initially and finished with a
smooth steel wheel roller, all as per specifications., 40 mm thickness
Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface,
55 13.20.iii 1313 cum 16907.63
by paver finisher, rolled with a pneumatic tired roller initially and finished with a
smooth steel wheel roller, all as per specifications., 25 mm thickness
Mastic Asphalt, Providing and laying 25 mm thick mastic asphalt wearing course
excluding prime coat with paving grade bitumen including providing antiskid surface
56 13.21 1300 with bitumen pre-coated fine grained hard stone chipping at an spacing of 10 cm sqm 1402.29
center to center in both directions all complete as per Drawing and Technical
specifications.

Precast Cement Concrete M 20 Kerb , Providing and laying of /20 precast cement
concrete Kerb 38 cm * 20 cm * 25 cm ( H*B*L) with 12 mm thick 1:3 cement sand
1 14.1 1401 mortar bedding and joints including foundation excavation levelling but excluding meter 1388.57
foundation concrete for foundation or sand gravel material, all complete as per
Drawing and Technical Specifications.
Cast in Situ Cement Concrete or natural stone block for footpath, Providing and
laying of precast / cast in situ 50 mm thick cement concrete slab footpath on 12 mm
2 14.2.A 1401 sqm 1741.88
thick 1: 3 cement sand mortar over the prepared base, all complete as per Drawing and
Technical Specifications.
, Providing and laying 25 mm thick Natural stone slab footpath on 12 mm thick 1: 3
3 14.2.B 1401 sqm 566.71
cement sand mortar over the prepared base, all complete as per specification.
Cast in Situ Cement Concrete Kerb , Providing and laying cement concrete Kerb with
top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC
4 14.3 1401 on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond meter 785.22
Kerb stone, Kerb stone laid with Kerb laying machine, foundation concrete laid
manually, all complete as per Drawing and Technical Specifications.

Cast in Situ Cement Concrete M 20 Kerb with Channel, Providing and laying cement
concrete Kerb with channel with top and bottom width 115 and 165 mm respectively,
250 mm high in M 20 grade PCC on grade foundation 150 mm thick, Kerb channel
5 14.4 1401 meter 1545.4
300 mm wide, 50 mm thick in PCC grade, sloped towards the Kerb, Kerb stone with
channel laid with Kerb laying machine, foundation concrete laid manually, all complete
as specification.
Brick work for footpath, Providing and laying brick on edge over 60 mm thick sand
6 14.5.A 1403 bed in footpath including excavation sand bedding all complete as per Drawing and sqm 1369.77
Technical Specifications.
Brick work for footpath, Providing and laying flat brick over 60 mm thick sand bed
7 14.5.B 1403 sqm 791.89
in footpath including excavation sand bedding all complete as per specification.
Non Reflective Traffic Signs, Providing and fixing of Non reflective warning,
mandatory and informatory sign board of 2 mm thick MS Sheet with back support
frame fixed on heavy 50 mm tube or Channel section of 75 mm X 40 mm firmly fixed to
1 15.1 1501 the ground by means of properly designed foundation with M 10/40 grade cement no 1912.78
concrete 300 mm x 300 mm x 300 mm, l as per drawings and Technical Specification/
DOR Publication., Heavy Duty Steel Tube internal 50 mm dia., MS Sheet 60 cm height
equilateral triangle

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 11 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.

Retro-Reflectorized Traffic Signs, Providing and fixing of retro- reflectorized warning,


Regulatory and informatory sign as per specification clause 1501 made of high intensity
grade sheeting , fixed over aluminum sheeting, 1.5 mm thick supported on a 50 mm
internal dia steel tube or mild steel angle iron post 75 mm x 40 mm x 6 mm firmly fixed
2 15.2 1501 no 905.35
to the ground by means of properly designed foundation with M 10/40 grade cement
concrete 30 cm x 30 cm , 30 cm below ground level or as per Drawing and Technical
Specifications., MS Sheet 60 cm height equilateral triangle, Heavy Duty Steel Tube
internal 50 mm dia.

Overhead Signs, Providing and erecting overhead signs with a corrosion resistant 2
mm thick aluminum alloy sheet reflectorized with micro prismatic retro-reflective type
with vertical and lateral clearance as per drawing and installed as per Specification
3 15.3.A 1502 tonne 40705.4
over a designed support system of aluminum alloy or galvanized steel trusses of
sections and type as per structural design requirements , Drawing and Technical
Specifications., Truss and Vertical Support

Overhead Signs, Providing and erecting overhead signs with a corrosion resistant 2
mm thick aluminum alloy sheet reflectorized with micro prismatic retro-reflective type
with vertical and lateral clearance as per drawing and installed as per Specification
4 15.3.B 1502 sqm 464.6
over a designed support system of aluminum alloy or galvanized steel trusses of
sections and type as per structural design requirements , Drawing and Technical
Specifications., Aluminum Alloy Plate for Over Head Sign
Painting Two Coats on Concrete Surfaces, Providing and Painting two coats after
5 15.4 1501 filling the surface with synthetic enamel paint in all shades on concrete / plaster sqm 912.43
surfaces as per Drawing and Technical Specifications.
Painting Two Coats on Steel Surfaces, Providing and applying two coats of ready mix
6 15.5 1501 paint of approved brand on steel surface after through cleaning of surface to give an sqm 182.48
even shade as per Drawing and Technical Specifications.
`, Providing and applying two coats of ready mix paint of approved brand on wood
7 15.6 1509 surface after thorough cleaning of surface to give an even shade as per Drawing and sqm 231.05
Technical Specifications.
Painting Lines, Dashes, Arrows etc. on Roads in Two Coats, Providing required
material and Painting lines, dashes, arrows etc. on roads in two coats on new work with
ready mixed road marking paint conforming to NS 408/ IS 164 on bituminous surface,
8 15.7.i 1503 sqm 344.16
including cleaning the surface of all dirt, dust and other foreign matter, demarcation at
site and traffic control as per Drawing and Technical Specifications., Over 10 cm in
width

Painting Lines, Dashes, Arrows etc. on Roads in Two Coats, Providing required
material and Painting lines, dashes, arrows etc. on roads in two coats on new work with
ready mixed road marking paint conforming to NS 408/ IS 164 on bituminous surface,
9 15.7.ii 1503 sqm 344.16
including cleaning the surface of all dirt, dust and other foreign matter, demarcation at
site and traffic control as per Drawing and Technical Specifications., Up to 10 cm in
width

Painting Lines, Dashes, Arrows etc. on Roads in Two Coats on Old Work, Providing
required materials and Painting lines, dashes, arrows etc. on roads in two coats on old
work with ready mixed road marking paint conforming to NS 408/ IS: 164 on
10 15.8.i 1503 sqm 303.93
bituminous surface, including cleaning the surface of all dirt, dust and other foreign
matter, demarcation at site and traffic control as per Drawing and Technical
Specifications., over 10 cm in width

Painting Lines, Dashes, Arrows etc. on Roads in Two Coats on Old Work, Providing
required materials and Painting lines, dashes, arrows etc. on roads in two coats on old
work with ready mixed road marking paint conforming to NS 408/ IS: 164 on
11 15.8.ii 1503 sqm 303.93
bituminous surface, including cleaning the surface of all dirt, dust and other foreign
matter, demarcation at site and traffic control as per Drawing and Technical
Specifications., Up to 10 cm in width

Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass
Beads on Bituminous Surface, On smooth surface (similar to Asphalt concrete and
rigid pavement), Providing and laying of hot applied thermoplastic compound at least 2
12 15.9.i 1504 sqm 1762.42
mm thick including reflectorizing glass beads as per DOR Traffic sign manual/
Specifications .The finished surface to be level, uniform and free from streaks and
holes.
Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass
Beads on Bituminous Surface, On rough surface ( similar to surface dressing),
Providing and laying of hot applied thermoplastic compound at least 2 mm thick
13 15.9.ii 1504 sqm 3025.38
including reflectorizing glass beads as per DOR Traffic sign manual/
Specifications .The finished surface to be level, uniform and free from streaks and
holes.
Providing and fixing of road stud 100x 100 mm, die-cast in aluminum, resistant to
corrosive effect of salt and grit, fitted with lenses reflectors, installed in concrete or
asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per Specification clause 1505.,
14 15.10' 1505 Providing and fixing of road stud 100 x 100 mm, die-cast in aluminum, resistant to no 48.3
corrosive effect of salt and grit, fitted with lenses reflectors, installed in concrete or
asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per Drawing and Technical
Specifications., Cats Eye

Kilometer Stone, Providing and Fixing Reinforced cement concrete M 15 grade


15 15.11.i 1506 kilometer Post including painting and printing as per Standard Drawing-2070 and no 4280.08
Technical Specifications. position, Five kilometer Post (precast)
Kilometer Stone, Providing and Fixing Reinforced cement concrete M 15 grade
16 15.11.ii 1506 kilometer Post including painting and printing as per Standard Drawing-2070 and no 2266.11
Technical Specifications. position, One kilometer post (precast)
Road Delineators Post, Providing and installation of 150 mm * 150 mm 1. 5 m long
delineators (road way indicators, hazard markers, object markers), 80-100 cm high
17 15.12 1507 no 1160.55
above ground level, painted black and white in 20 cm wide strips, buried or pressed
into the ground and conforming to the drawings and Technical Specifications.

Reinforced Cement Concrete Crash Barrier, Providing and Fixing Reinforced cement
concrete crash barrier at the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD reinforcement and dowel
18 15.13.i 1508 meter 3199.88
bars 25 mm dia, 450 mm long at expansion joints filled with pre-molded asphalt filler
board, keyed to the structure on which it is built and installed as per design, Drawing
and Technical Specifications.

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 12 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.

Metal Beam Crash Barrier, Type - A, "W" : Metal Beam Crash Barrier, Providing and
erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet
metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical
19 15.14.A 1509 meter 316.09
post, 150 x 75 x 5 mm spaced 2 m center to center, 1.8 m high, 1.1 m below ground/road
level metal beam rail to be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per Drawing and Technical Specifications.

Metal Beam Crash Barrier, Type - B, "THRIE" : Metal Beam Crash Barrier,
Providing and erecting a "Thrie" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series
20 15.14.B 1509 channel vertical post, 150 x 75 x 5 mm spaced 2 m center to center, 2.1 m high with 1.3 meter 352.88
m below ground level, metal beam rail to be fixed on the vertical post with a space of
channel section 150 x 75 x 5 mm, 546 mm long complete as per Drawing and Technical
specifications.

Metal Beam Crash Barrier, Flexible Crash Barrier, Wire Rope Safety Barrier,
Providing and erecting a wire rope safety barrier with vertical posts of medium weight
RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above
ground and 0.65 m below ground level, split at the bottom for better grip, embedded in
M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center to center and with 4
21 15.14.C 1509 meter 4098.17
horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15 grade cement concrete foundation 2400 x 450 x
900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450
inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation
concrete as per design , Drawing and Technical Specifications.

Anti-Glare Devices in Median, Plantation, Providing and Plantation of shrubs and


22 15.15.A 2800/1500 plants of approved species in the median. apart from cutting off glare from vehicle 0
coming from opposite direction,

Anti-Glare Devices in Median, Anti-glare screen with 25 mm steel pipe framework


fixed with circular and rectangular vans, Providing and erecting an anti - glare screen
with 25 mm dia vertical pipes fabricated and framed in the form of panels of one meter
length and 1.75 meter height fixed with circular vane 250 mm dia at top and
23 15.15.B 2800/1500 meter 6484.01
rectangular vane 600 x 300 mm at the middle, made out of steel sheet of 3 mm
thickness, end vertical pipes of the panel made larger for embedding in foundation
concrete, applying 2 coats of paint on all exposed surfaces, all as per design , drawings
and Technical Specifications.

Anti-Glare Devices in Median, Anti-glare screen with rectangular vane of MS sheet,


Providing and erecting anti - glare screen with rectangular vanes of size 750 x 500 mm
made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
24 15.15.C 2800/1500 450 to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 meter 2837.09
m above ground level, vertical post firmly embedded in M-15 cement concrete
foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, all
complete as per design , Drawing and Technical Specifications.

Street Lighting, Providing and erecting street light mounted on a steel circular hollow
pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m
25 15.16 missing overhang on both sides if fixed in the median and on one side if fixed on the footpath, no 3417.84
fitted with sodium vapor lamp and fixed firmly in concrete foundation as per design ,
Drawing and Technical Specifications..

Rumble Strips, Providing and making of Rumble strips with premix bituminous
carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at
approved locations to control speed, marked with white strips of road marking paint.,
26 15.17 1300 sqm 0
Provision of 15 Nos rumble strips covered with premix bituminous carpet, 15-20 mm
high at center, 250 mm wide placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking paint.
Lettering new Letter and Figures of any Shade, Providing and lettering new letter and
27 15.18.i 1506 figures of any shade with synthetic enamel paint black or any other approved color to cm-letter 3.75
give an even shade, Nepali
Lettering new Letter and Figures of any Shade, Providing and lettering new letter and
28 15.18.ii 1506 figures of any shade with synthetic enamel paint black or any other approved color to cm-letter 2.37
give an even shade, English and Roman
Providing , Preparing and Installing form work including necessary supports and
1 18.1.a 1804, 1805 removing after completion for foundation and footings., (Class F1 Finish), Using timber sqm 532.59
(soft wood )

Providing , Preparing and Installing form work including necessary supports and
2 18.1.b 1804, 1805 sqm 2528.36
removing after completion for foundation and footings., (Class F1 Finish), Using steel

Providing , Preparing and Installing form work including necessary supports and
3 18.2.A.i 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 1810.72
timber (soft wood ), Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
4 18.2.A.ii 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 2241.76
timber (soft wood ), Height above 3 m to 6 m
Providing , Preparing and Installing form work including necessary supports and
5 18.2.A.iii 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 2734.9
timber (soft wood ), Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
6 18.2.A.iv 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 0
timber (soft wood ), Height above 9 m
Providing , Preparing and Installing form work including necessary supports and
7 18.2.B.i 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 2529.55
steel, Height upto
Providing , Preparing and Installing form work including necessary supports and
8 18.2.B.ii 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 2608.11
steel, Height above 3 m to 6 m
Providing , Preparing and Installing form work including necessary supports and
9 18.2.B.iii 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 2740.51
steel, Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
10 18.2.B.iv 1804, 1805 removing after completion for walls., (Class F2 Finish), vertical plain surface, Using sqm 0
steel, Height above 9 m

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 13 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing , Preparing and Installing form work including necessary supports and
11 18.3.A.i 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 13569.96
timber, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
12 18.3.A.ii 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 16272.64
timber, Height above 3m to 6 m
Providing , Preparing and Installing form work including necessary supports and
13 18.3.A.iii 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 20352.86
timber, Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
14 18.3.A.iv 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 0
timber, Height above 9 m
Providing , Preparing and Installing form work including necessary supports and
15 18.3.B.i 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 2638.08
steel, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
16 18.3.B.ii 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 2741.83
steel, Height above 3 m to 6 m
Providing , Preparing and Installing form work including necessary supports and
17 18.3.B.iii 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 2925.88
steel, Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
18 18.3.B.iv 1804, 1805 removing after completion for walls., (Class F2 Finish), Vertical curve surface, using sqm 0
steel, Height more than above 9 m
Providing , Preparing and Installing form work including necessary supports and
19 18.4.A.i 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 11366.37
surface, Using timber, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
20 18.4.A.ii 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 13633.45
surface, Using timber, Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
21 18.4.A.iii 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 17040.42
surface, Using timber, Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
22 18.4.A.iv 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0
surface, Using timber, Above 9 m
Providing , Preparing and Installing form work including necessary supports and
23 18.4.B.i 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 2913.13
surface, Using steel, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
24 18.4.B.ii 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 2998.88
surface, Using steel, Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
25 18.4.B.iii 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 3160.79
surface, Using steel, Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
26 18.4.B.iv 1804, 1805 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0
surface, Using steel, Above 9 m
Providing , Preparing and Installing form work including necessary supports and
27 18.5.A.i 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using sqm 16923.12
timber, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
28 18.5.A.ii 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using sqm 22447.42
timber, Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
29 18.5.A.iii 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using sqm 26992.24
timber, Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
30 18.5.A.iv 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using sqm 0
timber, Above 9 m
Providing , Preparing and Installing form work including necessary supports and
31 18.5.B.i 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, sqm 3032.46
Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
32 18.5.B.ii 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, sqm 3155.85
Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
33 18.5.B.iii 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, sqm 3154.02
Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
34 18.5.B.iv 1804, 1805 removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, sqm 0
Above 9 m
Providing , Preparing and Installing form work including necessary supports and
35 18.6.A 1804, 1805 removing after completion for slab structure., Class F2 Finish, False work not included, sqm 693.27
Using timber
Providing , Preparing and Installing form work including necessary supports and
36 18.6.B 1804, 1805 removing after completion for slab structure., Class F2 Finish, False work not included, sqm 2853.26
Using steel
Providing , Preparing and Installing form work including necessary supports and
37 18.6.C 1804, 1805 removing after completion for slab structure., Class F2 Finish, False work not included, sqm 474.24
Using shuttering Ply
Providing , Preparing and Installing form work including necessary supports and
38 18.7.A 1804, 1805 removing after completion for slab & beam structure., Class F2 Finish, False work not sqm 1028.08
included, Using timber
Providing , Preparing and Installing form work including necessary supports and
39 18.7.B 1804, 1805 removing after completion for slab & beam structure., Class F2 Finish, False work not sqm 3371.6
included, Using steel
Providing , Preparing and Installing form work including necessary supports and
40 18.7.C 1804, 1805 removing after completion for slab & beam structure., Class F2 Finish, False work not sqm 625.39
included, Using shuttering Ply

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 14 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing , Preparing and Installing form work including necessary supports and
41 18.8.A 1804, 1805 removing after completion for arch structure., Class F2 Finish, False work not sqm 742.05
included, Using timber
Providing , Preparing and Installing form work including necessary supports and
42 18.8.B 1804, 1805 removing after completion for arch structure., Class F2 Finish, False work not sqm 3423.35
included, Using steel
Providing , Preparing and Installing form work including necessary supports and
43 18.9.I.a 1804, 1805 removing after completion for precast element., Class F3 Finish, Square / Rectangular sqm 4843.31
section, Using timber
Providing , Preparing and Installing form work including necessary supports and
44 18.9.I.b 1804, 1805 removing after completion for precast element., Class F3 Finish, Square / Rectangular sqm 3302.6
section, Using steel
Providing , Preparing and Installing form work including necessary supports and
45 18.9.II.a 1804, 1805 removing after completion for precast element., Class F3 Finish, Circular section, sqm 4942.72
Using timber
Providing , Preparing and Installing form work including necessary supports and
46 18.9.II.b 1804, 1805 removing after completion for precast element., Class F3 Finish, Circular section, sqm 3359.5
Using steel
Providing and assembling in position falsework for the construction of RCC
47 18.10.A.i 1803 superstructure and removing after completion including design & drawings as per sqm 3565.03
specification For Slab and Box culverts, Using timber, Height upto 2 m
Providing and assembling in position falsework for the construction of RCC
18.10.A.i
48 1803 superstructure and removing after completion including design & drawings as per sqm 6716.88
i
specification For Slab and Box culverts, Using timber, Height above 2 m to 4 m
Providing and assembling in position falsework for the construction of RCC
18.10.A.i
49 1803 superstructure and removing after completion including design & drawings as per sqm 9599.7
ii
specification For Slab and Box culverts, Using timber, Height above 4 m to 6 m
Providing and assembling in position falsework for the construction of RCC
18.10.A.i
50 1803 superstructure and removing after completion including design & drawings as per 0
v
specification For Slab and Box culverts, Using timber, For Height above 6 m
Providing and assembling in position falsework for the construction of RCC
51 18.10.B.i 1803 superstructure and removing after completion including design & drawings as per sqm 82830.64
specification For Slab and Box culverts, Using steel, Height upto 2 m
Providing and assembling in position falsework for the construction of RCC
18.10.B.i
52 1803 superstructure and removing after completion including design & drawings as per sqm 83695.47
i
specification For Slab and Box culverts, Using steel, Height above 2 m to 4 m
Providing and assembling in position falsework for the construction of RCC
18.10.B.i
53 1803 superstructure and removing after completion including design & drawings as per sqm 84793.22
ii
specification For Slab and Box culverts, Using steel, Height above 4 m to 6 m
Providing and assembling in position falsework for the construction of RCC
18.10.B.i
54 1803 superstructure and removing after completion including design & drawings as per sqm 0
v
specification For Slab and Box culverts, Using steel, Height above 6 m
Providing and assembling in position falsework for the construction of RCC
55 18.11.a.i 1803 superstructure and removing after completion including design & drawings as per sqm 7874.3
specification, for RCC Beam Bridge, Using timber, Height upto 3 m
Providing and assembling in position falsework for the construction of RCC
56 18.11.a.ii 1803 superstructure and removing after completion including design & drawings as per sqm 16024.59
specification, for RCC Beam Bridge, Using timber, Height above 3 m to 6 m
Providing and assembling in position falsework for the construction of RCC
18.11.a.ii
57 1803 superstructure and removing after completion including design & drawings as per sqm 26697.54
i
specification, for RCC Beam Bridge, Using timber, Height above 6 m to 9 m
18.11.a.i , Height above 9 m Increase the rate by 10% for every additional meter height to the
58 0
v rate for the previous height or Design as a special case and derive Norms
Providing and assembling in position falsework for the construction of RCC
59 18.11.b.i 1803 superstructure and removing after completion including design & drawings as per sqm 83516.77
specification, for RCC Beam Bridge, Using steel, Height upto 3 m
Providing and assembling in position falsework for the construction of RCC
60 18.11.b.ii 1803 superstructure and removing after completion including design & drawings as per sqm 85360.54
specification, for RCC Beam Bridge, Using steel, Height above 3 m to 6m
Providing and assembling in position falsework for the construction of RCC
18.11.b.ii
61 1803 superstructure and removing after completion including design & drawings as per sqm 87210.87
i
specification, for RCC Beam Bridge, Using steel, Height above 3 m to 6m
18.11.b.i , Height above 9 m Increase the rate by 10% for every additional meter height to the
62 0
v rate for the previous height or Design as a special case and derive Norms
Providing and assembling in position falsework for the construction of RCC
63 18.12.A.i 1803 superstructure and removing after completion including design & drawings as per sqm 6241.26
specification, for RCC Arch Bridge, Using timber, Height upto 3 m
Providing and assembling in position falsework for the construction of RCC
18.12.A.i
64 superstructure and removing after completion including design & drawings as per sqm 12758.53
i
specification, for RCC Arch Bridge, Using timber, Height above 3m to 6 m
Providing and assembling in position falsework for the construction of RCC
18.12.A.i
65 superstructure and removing after completion including design & drawings as per sqm 20564.63
ii
specification, for RCC Arch Bridge, Using timber, Height above 6 m to 9 m
Providing and assembling in position falsework for the construction of RCC
18.12.A.i
66 superstructure and removing after completion including design & drawings as per 0
v
specification, for RCC Arch Bridge, Using timber, Height above 9 m
Providing and assembling in position falsework for the construction of RCC
67 18.12.B.i superstructure and removing after completion including design & drawings as per sqm 83719.9
specification, for RCC Arch Bridge, Using steel, Height upto 3 m
Providing and assembling in position falsework for the construction of RCC
18.12.B.i
68 superstructure and removing after completion including design & drawings as per sqm 85628.79
i
specification, for RCC Arch Bridge, Using steel, Height above 3 m to 6 m
Providing and assembling in position falsework for the construction of RCC
18.12.B.i
69 superstructure and removing after completion including design & drawings as per sqm 88244.54
ii
specification, for RCC Arch Bridge, Using steel, Height above 6 m to 9 m
Providing and assembling in position falsework for the construction of RCC
18.12.B.i
70 superstructure and removing after completion including design & drawings as per 0
v
specification, for RCC Arch Bridge, Using steel, Height above 9 m
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in
1 20.1 2000 cum 8736.82
Foundation complete as per Drawing and Technical Specifications.

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 15 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in
2 20.1.b 2000 cum 8552.36
Foundation complete as per Drawing and Technical Specifications., Manual Mixing

Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as


3 20.2.A 2000 cum 10104.26
per Drawing and Technical Specifications, PCC Grade M 15

Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as


4 20.2.A_a 2000 cum 10138.3
per Drawing and Technical Specifications, PCC Grade M 15, Manual Mixing

Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as


5 20.2.B 2000 cum 11514.45
per Drawing and Technical Specifications, PCC Grade M 20

Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as


6 20.2.C 2000 cum 11607.41
per Drawing and Technical Specifications., RCC Grade M 20

Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as


7 20.2.D 2000 cum 12872.99
per Drawing and Technical Specifications., PCC Grade M 25
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as
8 20.2.E 2000 cum 12981.66
per Drawing and Technical Specifications., RCC Grade M 25
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as
9 20.2.F 2000 cum 15094.79
per Drawing and Technical Specifications., PCC Grade M 30
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as
10 20.2.G 2000 cum 13050.66
per Drawing and Technical Specifications., RCC Grade M30
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as
11 20.2.H 2000 cum 13368.06
per Drawing and Technical Specifications., RCC Grade M 35
Providing and laying , fitting and placing un-coated Mild steel / HYSD reinforcement
12 20.3 2014 tonne 126408
complete in foundation as per drawing and technical specification
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
13 20.4.A 2000 cum 10104.26
per drawing and Technical Specifications, PCC Grade M 15, Height upto 5 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


14 20.4.D.q 2000 cum 15094.79
per drawing and Technical Specifications, PCC Grade M 30, Height above 5 m to 10 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


15 20.4.D.r 2000 cum 15094.79
per drawing and Technical Specifications, PCC Grade M 30, Height above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
16 20.4.E.p 2000 cum 11607.41
per drawing and Technical Specifications, RCC Grade M 20, Height upto 5 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


17 20.4.E.q 2000 cum 11607.41
per drawing and Technical Specifications, RCC Grade M 20, Height above 5 m to 10 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


18 20.4.E.r 2000 cum 11607.41
per drawing and Technical Specifications, RCC Grade M 20, Height above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
19 20.4.F.p 2000 cum 12981.66
per drawing and Technical Specifications, RCC Grade M 25, Height upto 5 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


20 20.4.F.q 2000 cum 12981.66
per drawing and Technical Specifications, RCC Grade M 25, Height above 5 m to 10 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


21 20.4.F.r 2000 cum 12981.66
per drawing and Technical Specifications, RCC Grade M 25, Height above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
22 20.4.G.p 2000 cum 13050.66
per drawing and Technical Specifications, RCC Grade M 30, Height upto 5 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


23 20.4.G.q 2000 cum 13050.66
per drawing and Technical Specifications, RCC Grade M 30, Height above 5 m to 10 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


24 20.4.G.r 2000 cum 13050.66
per drawing and Technical Specifications, RCC Grade M 30, Height above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as
25 20.4.H.p 2000 cum 13368.06
per drawing and Technical Specifications, RCC Grade M 35, Height upto 5 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


26 20.4.H.q 2000 cum 13368.06
per drawing and Technical Specifications, RCC Grade M 35, Height above 5 m to 10 m

Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as


27 20.4.H.r 2000 cum 13368.06
per drawing and Technical Specifications, RCC Grade M 35, Height above 10 m
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure
28 20.5 2014 tonne 126408
complete as per Drawing and Technical Specifications
Providing and laying ,fitting and placing Mild steel reinforcement complete in sub-
29 20.6 2014 tonne 132434
structure as per drawing and Technical Specification
Providing and laying weep holes in Brick dry/Plain/ Reinforced concrete abutment,
wing wall/ return wall with 110 mm dia HDPE pipe, extending through the full width of
30 20.7 3109 meter 750.11
the structure with slope of 1V :20H towards drawing face Complete as per Drawing
and Technical Specifications.
31 20.7_a 3109 pcc meter 1182.21
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as
32 20.8.A 2000 meter 5751
per drawing and Technical Specification, RCC Grade M 20
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.A.i.
33 2000 structure as per drawing and Technical Specification, RCC Grade M 20, Height upto 5 meter 5751
p
m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.A.i.
34 2000 structure as per drawing and Technical Specification, RCC Grade M 20, Height above meter 5751
q
5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
35 20.8.A.i.r 2000 structure as per drawing and Technical Specification, RCC Grade M 20, Height above meter 5751
10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.A.ii.
36 2000 super-structure as per drawing and Technical Specification, RCC Grade M 20, Height meter 5751
p
upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.A.ii.
37 2000 super-structure as per drawing and Technical Specification, RCC Grade M 20, Height meter 5751
q
above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.A.ii.
38 2000 super-structure as per drawing and Technical Specification, RCC Grade M 20, Height meter 5751
r
above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as
39 20.8.B 2000 cum 12898.86
per drawing and Technical Specification, RCC Grade M 25
Prepared By:________________ Checked By:________________ Approved By:________________
Summary of Rates Page 16 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.B.i.
40 2000 structure as per drawing and Technical Specification, RCC Grade M 25, Height upto 5 cum 12898.86
p
m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.B.i.
41 2000 structure as per drawing and Technical Specification, RCC Grade M 25, Height above cum 12898.86
q
5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
42 20.8.B.i.r 2000 structure as per drawing and Technical Specification, RCC Grade M 25, Height above cum 16768.52
10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.B.ii.
43 2000 super-structure as per drawing and Technical Specification, RCC Grade M 25, Height cum 16123.58
p
upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.B.ii.
44 2000 super-structure as per drawing and Technical Specification, RCC Grade M 25, Height cum 12898.86
q
above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.B.ii.
45 2000 super-structure as per drawing and Technical Specification, RCC Grade M 25, Height cum 12898.86
r
above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as
46 20.8.C 2000 cum 13142.66
per drawing and Technical Specification, RCC Grade M 30
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.C.i.
47 2000 structure as per drawing and Technical Specification, RCC Grade M 30, Height upto 5 cum 13142.66
p
m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.C.i.
48 2000 structure as per drawing and Technical Specification, RCC Grade M 30, Height above cum 13142.66
q
5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
49 20.8.C.i.r 2000 structure as per drawing and Technical Specification, RCC Grade M 30, Height above cum 13142.66
10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.C.ii.
50 2000 super-structure as per drawing and Technical Specification, RCC Grade M 30, Height cum 13142.66
p
upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.C.ii.
51 2000 super-structure as per drawing and Technical Specification, RCC Grade M 30, Height cum 13142.66
q
above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.C.ii.
52 2000 super-structure as per drawing and Technical Specification, RCC Grade M 30, Height cum 13142.66
r
above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as
53 20.8.D 2000 cum 13460.06
per drawing and Technical Specification, RCC/PSC Grade M 35
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.D.i.
54 2000 structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height cum 13460.06
p
upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
20.8.D.i.
55 2000 structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height cum 13460.06
q
above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-
56 20.8.D.i.r 2000 structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height cum 13460.06
above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.D.ii.
57 2000 super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, cum 13460.06
p
Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.D.ii.
58 2000 super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, cum 13460.06
q
Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.D.ii.
59 2000 super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, cum 13460.06
r
Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder and
20.8.D.iii
60 2000 balanced cantilever super-structure as per drawing and Technical Specification, cum 13460.06
.p
RCC/PSC Grade M 35, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder and
20.8.D.iii
61 2000 balanced cantilever super-structure as per drawing and Technical Specification, cum 13460.06
.q
RCC/PSC Grade M 35, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder and
20.8.D.iii
62 2000 balanced cantilever super-structure as per drawing and Technical Specification, cum 13460.06
.r
RCC/PSC Grade M 35, Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as
63 20.8.E 2000 cum 13740.66
per drawing and Technical Specification, PSC Grade M-40
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab super-
20.8.E.i.
64 2000 structure as per drawing and Technical Specification, PSC Grade M-40, Height upto 5 cum 13740.66
p
m
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab super-
20.8.E.i.
65 2000 structure as per drawing and Technical Specification, PSC Grade M-40, Height above cum 13740.66
q
5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab super-
66 20.8.E.i.r 2000 structure as per drawing and Technical Specification, PSC Grade M-40, Height above cum 13740.66
10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.E.ii.
67 2000 super-structure as per drawing and Technical Specification, PSC Grade M-40, Height cum 13740.66
p
upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.E.ii.
68 2000 super-structure as per drawing and Technical Specification, PSC Grade M-40, Height cum 13740.66
q
above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab
20.8.E.ii.
69 2000 super-structure as per drawing and Technical Specification, PSC Grade M-40, Height cum 13740.66
r
above 10 m
Providing and laying , fitting and placing HYSD bar reinforcement in super-structure
70 20.9 2014 tonne 128478
complete as per drawing and technical specifications
Providing and laying of PCC M 15 Grade leveling course below approach slab
71 "20.10" no number cum 10104.26
complete as per drawing and Technical specification

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 17 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing and laying of Reinforced cement concrete approach slab including
72 20.11 2014 cum 18031.31
reinforcement and formwork complete as per drawing and Technical specification
Providing and laying Cement concrete wearing coat M-30 grade including
73 20.12 2000 cum 26778.9
reinforcement complete as per drawing and Technical Specifications
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
1 25.1.C 2500 structure complete excluding Pointing and Plastering, as per Drawing and Technical cum 12793.87
Specifications., Cement sand mortar (1:4)
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
2 25.1.C_a 2500 structure complete excluding Pointing and Plastering, as per Drawing and Technical cum 12442.31
Specifications., Cement sand mortar (1:4), Using Concrete Mixer
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
3 25.1.D 2500 structure complete excluding Pointing and Plastering, as per Drawing and Technical cum 12287.41
Specifications., Cement sand mortar (1:6)
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
4 25.1.D_a 2500 structure complete excluding Pointing and Plastering, as per Drawing and Technical cum 11935.85
Specifications., Cement sand mortar (1:6), Using Concrete Mixer
Providing and laying Brick masonry work in superstructure/ sub-structure complete
5 25.2.C 2500 excluding pointing and plastering, as per drawing and Technical Specifications, cum 13940.71
Cement Mortar 1:4 (1 cement : 4 sand)
Providing and laying Brick masonry work in superstructure/ sub-structure complete
6 25.2.C_a 2500 excluding pointing and plastering, as per drawing and Technical Specifications, cum 13568.45
Cement Mortar 1:4 (1 cement : 4 sand), Using Concrete Mixer
Providing and laying Brick masonry work in superstructure/ sub-structure complete
7 25.2.D 2500 excluding pointing and plastering, as per drawing and Technical Specifications, cum 13408.93
Cement Mortar 1:6 (1 cement : 6 sand)
Providing and laying Brick masonry work in superstructure/ sub-structure complete
8 25.2.D_a 2500 excluding pointing and plastering, as per drawing and Technical Specifications, cum 13036.67
Cement Mortar 1:6 (1 cement : 6 sand), Using Concrete Mixer
Providing, and applying Pointing with cement mortar (1:3 ) on brick work in structure
9 25.3 2500 sqm 223.77
as per Technical Specifications .
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work
10 25.4.A 2500 sqm 3924.65
structure as per Technical Specifications , Cement Mortar 1:2 (1 cement : 2 sand)
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work
11 25.4.A_a 2500 structure as per Technical Specifications , Cement Mortar 1:2 (1 cement : 2 sand), sqm 3817.87
Using Concrete Mixer
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work
12 25.4.B 2500 sqm 3447.13
structure as per Technical Specifications , Cement Mortar 1:3 (1 cement : 3 sand)
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work
13 25.4.B_a 2500 structure as per Technical Specifications , Cement Mortar 1:3 (1 cement : 3 sand), sqm 334.03
Using Concrete Mixer
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work
14 25.4.C 2500 sqm 317.24
structure as per Technical Specifications , Cement Mortar 1:4 (1 cement : 4 sand)
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work
15 25.4.C_a 2500 structure as per Technical Specifications , Cement Mortar 1:4 (1 cement : 4 sand), sqm 306.56
Using Concrete Mixer
Providing and laying weep holes in Brick works / Masonry/ Plain/ Reinforced concrete
16 25.5 2500 abutment, wing wall/ return wall with 100 mm dia HDPE pipe as per Drawing and meter 132.4
Technical Specifications.

2602, 2603, Providing and laying of dry Stone Masonry Work as per Drawing and Technical
1 26.1 cum 6333.28
2608 Specifications

2602, 2603, Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement
2 26.3.B cum 10830.98
2607 Mortar 1:4 in Foundation complete as per Drawing and Technical Specifications.

Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement
2602, 2603,
3 26.3.B_a Mortar 1:4 in Foundation complete as per Drawing and Technical Specifications., cum 10034.37
2607
Using Concrete Mixer

2602, 2603, Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement
4 26.3.C cum 10034.76
2607 Mortar 1:6 in Foundation complete as per Drawing and Technical Specifications.

Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement
2602, 2603,
5 26.3.C_a Mortar 1:6 in Foundation complete as per Drawing and Technical Specifications., cum 9407.21
2607
Using Concrete Mixer
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete
6 26.5.A 2607 cum 12252.86
as per Drawing and Technical, Random Rubble Masonry

Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete
7 26.5.A_a 2607 cum 11590.81
as per Drawing and Technical, Random Rubble Masonry, Using Concrete Mixer

Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete
8 26.5.B 2606 cum 12476.47
as per Drawing and Technical, Coursed rubble Masonry (first sort )
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete
9 26.5.B_a 2606 as per Drawing and Technical, Coursed rubble Masonry (first sort ), Using Concrete cum 11814.41
Mixer
Providing and laying Stone Masonry work in cement mortar 1:6 in structure complete
10 26.6.A 2607 as per Drawing and Technical Specifications, Random Rubble Masonry cum 11515.06
(coursed/uncoursed)

Providing and laying Stone Masonry work in cement mortar 1:6 in structure complete
11 26.6.A_a 2607 cum 10853
as per Drawing and Technical, Random Rubble Masonry, Using Concrete Mixer

Providing and laying Stone Masonry work in cement mortar 1:6 in structure complete
12 26.6.B 2606 cum 11821.43
as per Drawing and Technical Specifications, Coursed rubble Masonry (first sort )

Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete
13 26.6.B_a 2606 as per Drawing and Technical, Coursed rubble Masonry (first sort ), Using Concrete cum 11159.37
Mixer
Providing and Pointing with cement mortar on masonry work in structure as per
14 26.7.A 2600 sqm 223.16
Technical Specifications, cement mortar (1:3 )
Providing and Pointing with cement mortar on masonry work in structure as per
15 26.7.A_a 2600 sqm 219.38
Technical Specifications, cement mortar (1:3 ), Using Concrete Mixer
Providing and Pointing with cement mortar on masonry work in structure as per
16 26.7.B 2600 sqm 240.77
Technical Specifications, cement mortar (1:2 )

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 18 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing and Pointing with cement mortar on masonry work in structure as per
17 26.7.B_a 2600 sqm 237
Technical Specifications, cement mortar (1:2 ), Using Concrete Mixer
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
1 24.1.A.i 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 7320.19
mm X 120 mm,, Box size 3 X 1 X 1 m ( 16 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
2 24.1.A.ii 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 7397.56
mm X 120 mm,, Box size 2 X 1 X 1 m ( 11 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
3 24.1.A.iii 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 7722.86
mm X 120 mm,, Box size 1.5 X 1 X 1 m ( 9 sqm )
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
4 24.1.A.iv 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 7734.57
mm X 120 mm,, Box size 1.0 X 1 X 1 m ( 6 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
5 24.1.A.v 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 7626.66
mm X 120 mm,, Box size 3.0 X 1 X 0 .75 m ( 13.5 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
6 24.1.A.vi 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 7762.71
mm X 120 mm,, Box size 2.0 X 1 X 0 .75 m ( 9. 25 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.A.vi
7 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 8009.32
i
mm X 120 mm,, Box size 1.0 X 1 X 0 .75 m ( 5 sqm m)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.A.vi
8 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 8147.24
ii
mm X 120 mm,, Box size 3.0 X 1 X 0 .5 m ( 11 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
9 24.1.A.ix 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 8345.48
mm X 120 mm,, Box size 2.0 X 1 X 0 .5 m ( 7.5 sqm m)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
10 24.1.A.x 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 8781.91
mm X 120 mm,, Box size 1 X 1 X 0 .5 m (4 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
11 24.1.A.xi 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 9381.12
mm X 120 mm,, Box size 3 X 1 X 0 .3 m ( 9 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.A.xi
12 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 9285.98
i
mm X 120 mm,, Box size 2 X 1 X 0 .3 m ( 6.1 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.A.xi
13 2401 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 cum 8621
ii
mm X 120 mm,, Box size 1 X 1 X 0 .3 m ( 2.2 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
14 24.1.B.i 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 7720.5
mm,, Box size 3 X 1 X 1 m ( 16 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
15 24.1.B.ii 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 7804.81
mm,, Box size 2 X 1 X 1 m ( 11 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
16 24.1.B.iii 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 8047.12
mm,, Box size 1.5 X 1 X 1 m ( 9 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
17 24.1.B.iv 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 8059.01
mm,, Box size 1 X 1 X 1 m (6 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
18 24.1.B.v 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 8485.58
mm,, Box size 3.0 X 1 X 0 .75 m (13.5 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
19 24.1.B.vi 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 8095.63
mm,, Box size 2.0 X 1 X 0 .75 m ( 9.25 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.B.vi
20 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 8476.73
i
mm,, Box size 1.0 X 1 X 0 .75 m ( 5 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.B.vi
21 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 8653.05
ii
mm,, Box size 3.0 X 1 X 0 .5 m ( 11 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
22 24.1.B.ix 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 8762.56
mm,, Box size 2.0 X 1 X 0 .5 m ( 7.5 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
23 24.1.B.x 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 55001.35
mm,, Box size 1 X 1 X 0 .5 m ( 4 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24 24.1.B.xi 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 10038.04
mm,, Box size 3 X 1 X 0 .3 m ( 9 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.B.xi
25 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 10241.33
i
mm,, Box size 2 X 1 X 0 .3 m ( 6.1 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire
24.1.B.xi
26 2401 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 cum 9272.05
ii
mm,, Box size 1 X 1 X 0 .3 m ( 2.2 sqm)
Providing mechanically woven double twisted crates / mattress including rolling,
cutting and with lacing wire and binding wire as per specification.
27 24.2.A 2402 , sqm 198.38
Hexagonal mesh type 100 mm x 120 mm, mesh wire 3 mm, selvage wire 3.9 mm, lacing
wire 2.4 mm

Providing mechanically woven double twisted crates / mattress including rolling,


cutting and with lacing wire and binding wire as per specification.
28 24.2.B 2402 , sqm 264.5
Hexagonal mesh type 100 mm x 120 mm, mesh wire 2.7 mm, selvage wire 3.4 mm,
lacing wire 2.2 mm

Prepared By:________________ Checked By:________________ Approved By:________________


Summary of Rates Page 19 of 276
Summary of Rates

Specificati
Norms
S.N. on Clause Description Unit Rate (NRs)
No
No.
Providing mechanically woven double twisted crates / mattress including rolling,
cutting and with lacing wire and binding wire as per specification.
29 24.2.C 2402 , sqm 0
Hexagonal mesh type 80 mm x 100 mm, mesh wire 3 mm, selvage wire 3.9 mm, lacing
wire 2.4 mm

Providing mechanically woven double twisted crates / mattress including rolling,


cutting and with lacing wire and binding wire as per specification.
30 24.2.D 2402 , sqm 264.5
Hexagonal mesh type 80 mm x 100 mm, mesh wire 2.7 mm, selvage wire 3.4 mm, lacing
wire 2.2 mm

Providing mechanically woven double twisted crates / mattress including rolling,


cutting and with lacing wire and binding wire as per specification.
31 24.2.E 2402 , sqm 0
Hexagonal mesh type 60 mm x 80 mm, mesh wire 2.7 mm, selvage wire 3.4 mm, lacing
wire 2.2 mm

Providing mechanically woven double twisted crates / mattress including rolling,


cutting and with lacing wire and binding wire as per specification.
, Zinc +
32 24.2.F 2402 sqm 264.5
PVC coated Hexagonal mesh type 100 mm x 120 mm, mesh wire 2.7 mm/3.7 mm,
selvage wire 3.4 mm/4.4 mm, lacing wire 2.2 mm/3.2 mm with Pac coating thickness
nominal 0.5 mm ( minimum 0.38 mm)

Providing mechanically woven double twisted crates / mattress including rolling,


cutting and with lacing wire and binding wire as per specification.
, Zinc +
33 24.2.G 2402 sqm 264.5
PVC coated Hexagonal mesh type 80 mm x 100 mm, mesh wire 2.2 mm/3.2 mm, selvage
wire 2.7 mm/3.7 mm, lacing wire 2.2 mm/3.2 mm with Pac coating thickness nominal
0.5 mm ( minimum 0.38 mm)

Assembling mechanical woven Gabion boxes /mattresses, placing in position including


stretching; forming compartments; tying the sides and diaphragms with binding wire
34 24.3 2402 sqm 56.06
in each mesh; tying with bracing wires and tie wires; and tying down the lid complete
as per specification (stone filling not included
Providing and filling stone/boulder in gabion boxes/mattress etc.. Including dressing,
35 24.4 2402 cum 4968.92
bedding, bonding all complete as per Drawing and Technical Specifications.
Laying and fixing of Geo-Textile all complete as per specification., Providing and
36 24.5 2404 laying of a geotextile filter between pitching and embankment slopes as per Drawing sqm #VALUE!
and Technical Specifications.
Laying and fixing of Geo-Textile all complete as per specification., Providing and
37 24.06 2404 sqm #VALUE!
laying and fixing of Geo-membrane all complete as per specification.
GEOSYNTHETIC AND REINFORCED EARTH, Sub-Surface Drain with Geotextiles,
Providing and laying sub surface drain 200 mm dia using geotextiles treated with
38 24.7 2404 carbon black to a stable network and a planar geo-composite structure, joints meter #VALUE!
wrapped with geotextile to prevent ingress of soil, including excavation and backfilling
as per Drawing and Technical Specifications.
Narrow Filter Sub-Surface Drain, Providing and making narrow filter sub- surface
drain consisting of porous or perforated pipe laid in narrow trench surrounded by a
39 24.8 2404 meter #VALUE!
geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed
including excavation and backfilling
Laying Paving Fabric Beneath a Pavement Overlay, Providing and laying paving fabric
over a tack coat of paving grade Bitumen, laid at the rate of 1 kg per sqm over
40 24.9 2410 sqm 115.97
thoroughly cleaned and repaired surface to provide a water resistant membrane and
crack retarding layer as per Drawing and Technical Specifications.
Laying Boulder Apron in Crates of Synthetic Geogrids, Providing and laying of
41 24.10' 2400 Geogrids crated apron 1 m x 5 m, 600 mm thick with baffles at 1 meter interval, made cum #VALUE!
with Geogrids as per Design, Drawing and Technical specifications. design.
Providing and laying HDPE pipes with perforations including joining, series II, HDPE
42 24.20.A 2414 meter 2358.66
pipe 200 mm dia
Providing and laying HDPE pipes with perforations including joining, series II, HDPE
43 24.20.B 2414 meter 1349.21
pipe 160 mm dia

Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and
44 24.21.A.I 2421 cum 9120.33
Specifications, 60% M 15 concrete and 40% boulders/stones, using Mechanical Aids

24.21.A.I Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and
45 2421 cum 10519.84
I Specifications, 60% M 15 concrete and 40% boulders/stones, Manual means
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and
46 24.21.B.I 2421 cum 9515.43
Specifications, 70% M 15 concrete and 30% boulders/stones, Using Mechanical Aids
24.21.B.I Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and
47 2421 cum 1095.93
I Specifications, 70% M 15 concrete and 30% boulders/stones, Manual means
Sub-Surface Drains with Perforated Pipe, Providing and laying subsurface drain with
perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement
48 24.22 2414 concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending meter #NAME?
upon size of material surrounding the pipe, with 150 mm bedding below the pipe and
300 mm cushion above the pipe,. as per Drawing and Specifications.
Aggregate Sub-Surface Drains, Providing and laying aggregate sub surface drain 300
49 24.23 2414 mm x 450 mm with aggregates conforming to table 300-4, excavated material to be meter #NAME?
utilized in roadway.
Underground Drain at Edge of Pavement, Providing and laying an underground drain
50 24.24 2414 1 m x 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab meter 17970.74
10 cm in thickness on urban roads.

Prepared By:________________ Checked By:________________ Approved By:________________


Page 20 of 276

Transportation Analysis for SUNSARI 2077/78


SAND
crushor Sand from gachiya average
distance 20km Pakki+5 Km Gravel
+1.5km kachhi ) Vol. of
Material as
1 per norms Km Rate rate per cum
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 5.38 20 4167 774.54
Transportation cost for additional 5km
gravel road (6 Metric Ton Truck
Capacity) 5.38 0 416.58 0.00
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
5.38 0 486.18 0.00
Total Transportation cost from gachiya
to MORANG 774.54
cost of sand at gachiya 730.00
final rate of sand with transportation 1504.54

river screening Sand from gachiya


average distance 20km Pakki+5 Km
Gravel +1.5km kachhi ) Vol. of
Material as
2 per norms Km Rate
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 5.38 20 4167 774.54
Transportation cost for additional 5km
(6 Metric Ton Truck Capacity) 5.38 0 416.58 0.00
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
5.38 0 486.18 0
Total Transportation cost from gachiya
to MORANG 774.54
cost of sand at gachiya 1050.00
final rate of sand with transportation 1824.54
AGRREEGATE
Coarse Aggregate from gachiya
average distance 20km Pakki+5 Km
Gravel +1.5km kachhi ) for 10mm to Vol. of
20mm down Material as
3 per norms Km Rate
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 4.87 20 4167 855.65
Transportation cost for additional 5km
(6 Metric Ton Truck Capacity) 4.87 0 416.58 0.00
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
4.87 0 486.18 0.00
Total Transportation cost from gachiya
to MORANG 855.65
cost of coarse aggregate at gachiya 2000.00
final rate of coarse aggregate with
transportation 2855.65

stone dust from gachiya average


distance 20km Pakki+5 Km Gravel
+1.5km kachhi) Vol. of
Material as
4 per norms Km Rate

prepared By :- Checked BY:- Approved BY:-


Page 21 of 276

Transportation Analysis for SUNSARI 2077/78


Transportation cost for 20km (6 Metric
Ton Truck Capacity) 4.87 20 4167 855.65
Transportation cost for additional 5km
(6 Metric Ton Truck Capacity) 4.87 0 416.58 0.00
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
4.87 0 486.18 0.00
Total Transportation cost from gachiya
to MORANG 855.65
cost of stone dust at gachiya 1850.00
final rate of Stone dust with
transportation 2705.65

Bolder/ stone from


yangshila/jateko/letang average
distance 35 km Pakki+5km Gravel Vol. of
+1.5km kachhi ) Material as
5 per norms Km Rate
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 4.87 20 4167 855.65
Transportation cost for additional 5km
(6 Metric Ton Truck Capacity) 4.87 0 416.58 0.00
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
4.87 0 486.18 0.00
Total Transportation cost from gachiya
to MORANG 855.65
cost of boulder/stone at
yangshila/jateko/letang 2000.00
final rate of Boulder with transportation
2855.65

natural subbase gravel from gachiya


average distance 20km Pakki+5 km
Gravel +1.5km kachhi ) Vol. of
Material as
6 per norms Km Rate
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 4.87 20 4167 855.65
Transportation cost for additional 5km
(6 Metric Ton Truck Capacity) 4.87 0 416.58 0.00
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
4.87 0 486.18 0.00
Total Transportation cost from gachiya
to MORANG 4.87 855.65
cost of natural crushorrun subbase
gravel at gachiya 1425.00
final rate of Subd base with
transportation 2280.65

20to40mm th. Aggregate


Coarse Aggregate from gachiya
average distance 20km Pakki 5 km
Gravel +1.5km kachhi ) Vol. of
Material as
7 per norms Km Rate
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 4.87 20 4167 855.65

prepared By :- Checked BY:- Approved BY:-


Page 22 of 276

Transportation Analysis for SUNSARI 2077/78


Transportation cost for additional 5km
(6Metric Ton Truck Capacity) 4.87 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity) 4.87 0 486.18 0.000
Total Transportation cost from gachiya
to biratnagar 855.65
cost of coarse aggregate at gachiya 1600.00
final rate of coarse aggregate with
transportation 2455.65

Soil cost with 4.5km Gravel + 0.5 km


Kacchi transportation
Vol. of
Material as
8 per norms Km Rate
Transportation cost for 4.5 km (5.38
Metric Ton Truck Capacity) 5.38 5 416.58 0.00
Transportation cost for .5km (5.38
Metric Ton Truck Capacity) 5.38 0.5 486.18 0.00
Upto10 k.m transportation of soil 292.88
cost of soil 385.00
final rate of soil with transportation 677.88

Clay sand from around average


distance 7 km Gravel +1.5 km kachhi )
Vol. of
Material as
9 per norms Km Rate
Transportation cost for 0 km 5.38Metric
Ton Truck Capacity) 5.38 20 4167 0.00
Transportation cost for additional 7km
(5.38Metric Ton Truck Capacity) 5.38 7 416.58 0.00
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
5.38 1.5 486.18 0.00
Total Transportation cost o filling Sand
upto 10 km 292.88
cost of Clay sand at gachiya 450.00
final rate of sand with transportation 742.88

Transportation cost for 20km


1st class brick biratnagar
10 peripheri
5.38 20 4167 0.77
cost of brick no-1 17.50
final rate of Brick No-1 with
transportation 18.27

11 5to10mm th. Aggregate


Transportation cost for (20km Pakki+5
Km Gravel+1.5 km. Kachhi) 6 Ton
Truck Capacity) 5.38 20 4167 774.54
Transportation cost for additional 5km
(4.87Metric Ton Truck Capacity) 5.38 0 416.58 0.00

prepared By :- Checked BY:- Approved BY:-


Page 23 of 276

Transportation Analysis for SUNSARI 2077/78


Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
5.38 0 486.18 0.00
Total Transportation cost from gachiya
to MORANG 774.54
cost of coarse aggregate at gachiya 2075.00
cost of silcon(micro aggregate) at
gachiya 2849.54
N.P^3 HUME PIPE
R.C.C. Hume Pipe 30 cm Dia from
gachiya average distance 20km Pakki+
+5 km Gravel ) Vol. of
Material as
12 per norms Km Rate
Transportation cost for 20km 6 Metric
Ton Truck Capacity) on Mettaled Road
17.5 20 4167 238.11
Transportation cost for additional 5km
(6Metric Ton Truck Capacity) Gravel
Road 12.5 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity)
Kachi Road 12.5 0 486.18 486.18
Total Transportation cost from gachiya
to MORANG 724.29
Cost of R.C.C. hume pipe 30 cm Dia 8500
Net Cost of R.C.C. Hume Pipe 30 cm. dia. 9224.29

R.C.C. Hume Pipe 45 cm Dia from


gachiya average distance 20km Pakki+
+5 km Gravel ) Vol. of
Material as
13 per norms Km Rate
Transportation cost for 20km 6 Metric
Ton Truck Capacity) on Mettaled Road
17.5 20 4167 238.11
Transportation cost for additional 5km
(6Metric Ton Truck Capacity) Gravel
Road 12.5 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity)
Kachi Road 12.5 0 486.18 486.18
Total Transportation cost from gachiya
to MORANG 724.29
Cost of R.C.C. hume pipe 45 cm Dia 10500
Net Cost of R.C.C. Hume Pipe 45 cm. dia. 11224.29

R.C.C. Hume Pipe 60 cm Dia from


gachiya average distance 20km Pakki+
+5 km Gravel ) Vol. of
Material as
13 per norms Km Rate
Transportation cost for 20km 6 Metric
Ton Truck Capacity) on Mettaled Road
17.5 20 4167 238.11

prepared By :- Checked BY:- Approved BY:-


Page 24 of 276

Transportation Analysis for SUNSARI 2077/78


Transportation cost for additional 5km
(6Metric Ton Truck Capacity) Gravel
Road 12.5 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity)
Kachi Road 12.5 0 486.18 486.18
Total Transportation cost from gachiya
to MORANG 724.29
Cost of R.C.C. hume pipe 60 cm Dia 14000
Net Cost of R.C.C. Hume Pipe 60 cm. dia. 14724.29

R.C.C. Hume Pipe75cm Dia from


gachiya average distance 20km Pakki+
+5 km Gravel ) Vol. of
Material as
13 per norms Km Rate
Transportation cost for 20km 6 Metric
Ton Truck Capacity) on Mettaled Road
17.5 20 4167 238.11
Transportation cost for additional 5km
(6Metric Ton Truck Capacity) Gravel
Road 12.5 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity)
Kachi Road 12.5 0 486.18 486.18
Total Transportation cost from gachiya
to MORANG 724.29
Cost of R.C.C. hume pipe 75 cm Dia 18000
Net Cost of R.C.C. Hume Pipe75 cm. dia. 18724.29

R.C.C. Hume Pipe 90 cm Dia from


gachiya average distance 20km Pakki+
+5 km Gravel ) Vol. of
Material as
12 per norms Km Rate
Transportation cost for 20km 6 Metric
Ton Truck Capacity) on Mettaled Road
17.5 20 4167 238.11
Transportation cost for additional 5km
(6Metric Ton Truck Capacity) Gravel
Road 12.5 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity)
Kachi Road 12.5 0 486.18 486.18
Total Transportation cost from gachiya
to MORANG 724.29
Cost of R.C.C. hume pipe 90 cm Dia 22000
Net Cost of R.C.C. Hume Pipe 90 cm. dia. 22724.29

R.C.C. Hume Pipe 120 cm Dia from


gachiya average distance 20km Pakki+
+5 km Gravel) Vol. of
Material as
13 per norms Km Rate

prepared By :- Checked BY:- Approved BY:-


Page 25 of 276

Transportation Analysis for SUNSARI 2077/78


Transportation cost for 20km 6 Metric
Ton Truck Capacity) on Mettaled Road
17.5 20 4167 238.11
Transportation cost for additional 5km
(6Metric Ton Truck Capacity) Gravel
Road 17.5 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity)
Kachi Road 17.5 0 486.18 486.18
Total Transportation cost from gachiya
to MORANG 724.29
Cost of R.C.C. hume pipe 120 cm Dia 39000
Net Cost of R.C.C. Hume Pipe120 cm. dia. 39724.29

R.C.C. Hume Pipe 150 cm Dia from


gachiya average distance 20km Pakki+
+5 km Gravel) Vol. of
Material as
per norms Km Rate
Transportation cost for 20km 6 Metric
Ton Truck Capacity) on Mettaled Road
17.5 20 4167 238.11
Transportation cost for additional 5km
(6Metric Ton Truck Capacity) Gravel
Road 17.5 0 416.58 0.00
Transportation cost for additional 1km
kachhi (6 Metric Ton Truck Capacity)
Kachi Road 17.5 0 486.18 486.18
Total Transportation cost from gachiya
to MORANG 724.29
Cost of R.C.C. hume pipe 150 cm Dia 63050
Net Cost of R.C.C. Hume Pipe150 cm. dia. 63774.29
Transportation cost for 560 km
1st classMechin made brick at Vol. of
biratnagar peripheri Material as
14 per norms Km Rate
Transportation cost for distance 560km
Pakki 6 Metric Ton Truck Capacity) on
Mettaled Road 4.87 20 4167 855.65
Transportation cost for after 20 km 6
Metric Ton Truck Capacity) on Mettaled
Road 4.87 540 416.58 416.58
cost of Mechin made brick no1 1272.23
Net Cost of Mechine Made Brick 1.02
17.50
18.52

Debries transportation average


distance 3km mettaled =1km Gravel
+1km kachhi ) Vol. of
Material as
15 per norms Km Rate
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 4.87 20 4167.00 855.65
Transportation cost for additional 5km
(6 Metric Ton Truck Capacity) 4.87 1 416.58 85.54

prepared By :- Checked BY:- Approved BY:-


Page 26 of 276

Transportation Analysis for SUNSARI 2077/78


Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
4.87 1 486.18 99.83
Cost of Debries
Total Transportation cost from site to
biratnagar arournd 5 km 1041.02

Transportation cost for 20km


2nd class brick biratnagar
16 peripheri
4.87 20 4167 0.42
cost of brick no-2 16.6
final rate of Brick No-1 with
transportation 17.016

Bitummen 80/100 Grade


Bitumeen Grade 80/100 average
distance260 km Pakki Road )
Vol. of
Material as
17 per norms Km Rate
Transportation cost for 20km (6 Metric
Ton Truck Capacity) 6 20 4167 694.50
Transportation cost for additional 5km
(6.0 Metric Ton Truck Capacity) 6 5 416.58 347.15
Transportation cost for additional =260-
20-5 kmPakki Road (6 Metric Ton
Truck Capacity) 6 235 486.18 19042.05
Total Transportation cost from gachiya
to MORANG 20083.70
cost of Bitumeen Grade 80/100 at
Factory 33600.00
final rate of coarse aggregate with
transportation 53683.70
204 523.34 1216 105076.02 127451.10

Slate stonetrtransportation average


distance 3km mettaled =1km Gravel
+1km kachhi ) Vol. of
Material as
1 per norms Km Rate
4.87 500 4167.00 855.65
Transportation cost for additional 5km
(6 Metric Ton Truck Capacity) 4.87 1 416.58 85.54
Transportation cost for additional 1.5km
kachhi (6 Metric Ton Truck Capacity)
4.87 1 486.18 99.83
Cost of slate
Total Transportation cost from site to
biratnagar arournd 5 km 1041.02

prepared By :- Checked BY:- Approved BY:-


Page 27 of 276

per cum

per cum

per cum

per cum
per cum
per cum

per cum

per cum

per cum

per cum
per cum
per cum

per cum

per cum

per cum

per cum
per cum

per cum

prepared By :- Checked BY:- Approved BY:-


Page 28 of 276

per cum

per cum

per cum

per cum
per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

per cum

prepared By :- Checked BY:- Approved BY:-


Page 29 of 276

per cum

per cum

per cum
per cum

per cum

per cum

per cum
per cum

per cum

per cum

per cum

per cum
per cum
per cum

0.77

per cum

per cum

prepared By :- Checked BY:- Approved BY:-


Page 30 of 276

per cum

per cum
per cum

per cum

per Rm

per Rm

per Rm

per Rm
per Rm
per Rm

per Rm

per Rm

per Rm

per Rm
per Rm
per Rm

per Rm

prepared By :- Checked BY:- Approved BY:-


Page 31 of 276

per Rm

per Rm

per Rm
per Rm
per Rm

per Rm

per Rm

per Rm

per Rm
per Rm
per Rm

per Rm

per Rm

per Rm

per Rm
per Rm
per Rm

prepared By :- Checked BY:- Approved BY:-


Page 32 of 276

per Rm

per Rm

per Rm

per Rm
per Rm
per Rm

per Rm

per Rm

per Rm

per Rm
per Rm
per Rm

per cum

per cum

prepared By :- Checked BY:- Approved BY:-


Page 33 of 276

per cum

per cum

per Mt.

per Mt.

per Mt.

per Mt.

per Mt.

per Mt.
0.7745353

per cum

per cum

per cum

per cum

prepared By :- Checked BY:- Approved BY:-


Abstract of Cost Page 1 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
1 General
Operation and maintenance of Temporary diversion of road/ bridge to keep the km-
1.1 road serviceable through out the contract period as per specification and month/ 0 0 0
instruction of engineer LS

Carry out maintenance of the existing road to keep the road serviceable through Km-
1.2 0 0 0
out the contract period as per specification and instruction of the Engineer month

Providing and installation of project signboards with size of 1.8 x 1.2 m as per
1.3 nos 0 7923.5 0
specification and instruction of engineer.
Providing and establishing camp with mobilization and demobilization for
1.4 contractor's Labour and staff and demolishing after completion of works as per job 0 0 0
the specifications and instruction of the Engineer.
Relocation of services / minor infrastructures, as per specifications and
1.5 job 0 0 0
instruction of the Engineer.

1.6 Supply of Project Record as per specifications and instruction of the Engineer. set 0 0 0

Reinstatement of quarry sites at the completion of works as instructed by the


1.7 0 0 0
engineers.
Engineer's Facilities: Establishment and maintenance of office and site camp etc,
1.8 PS 0 0 0
and providing furniture and other facilities as directed by the Engineer.
Providing and laying of Plain/Reinforced cement concrete in sub-structure
1.9 complete as per drawing and Technical Specifications, PCC Grade M20, Height cum 0 12665.9 0
upto 5 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
1.10 complete as per drawing and Technical Specifications, PCC Grade M 25, Height cum 0 14160.28 0
upto 5 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
1.11 complete as per drawing and Technical Specifications, PCC Grade M 25, Height cum 0 14675.2 0
above 5 m to 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
1.12 complete as per drawing and Technical Specifications, PCC Grade M 25, Height cum 0 15318.85 0
above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
1.13 complete as per drawing and Technical Specifications, PCC Grade M 30, Height cum 0 16604.26 0
upto 5 m

2 Site clearance
Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.1 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 13.8 0
lead of 30 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Manual Means:-, In area of light jungle
(less than 15 number per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.2 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 20.7 0
lead of 30 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Manual Means:-, In area of thorny jungle
( more than 15 numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.3 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 8.54 0
lead of 30 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Mechanical Means, In area of light jungle
(less than 15 number per 100 sqm )

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.4 materials and stacking of serviceable Material to be used or auctioned, up to a cum 0 1380 0
lead of 30 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Manual Means:-, Felling and uprooting of
bamboo clearing the area, stacking of bamboo and disposing of wastes

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.5 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 8.75 0
lead of 30 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Mechanical Means, In area of thorny jungle
( more than 15 numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.6 materials and stacking of serviceable Material to be used or auctioned, up to a cum 0 544.48 0
lead of 30 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Mechanical Means, Felling and uprooting
of bamboo clearing the area, stacking of bamboo and disposing of wastes

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 2 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.7 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 17.06 0
lead of 1000 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Manual Means:-, In area of light jungle
(less than 15 number per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.8 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 23.96 0
lead of 1000 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., In area of thorny jungle ( more than 15
numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.9 materials and stacking of serviceable Material to be used or auctioned, up to a cum 0 1705.68 0
lead of 1000 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., Felling and uprooting of bamboo clearing the
area, stacking of bamboo and disposing of wastes

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.10 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 10.21 0
lead of 1000 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Mechanical Means, In area of light jungle
(less than 15 number per 100 sqm )

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.11 materials and stacking of serviceable Material to be used or auctioned, up to a sqm 0 10.49 0
lead of 1000 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Mechanical Means, In area of thorny jungle
( more than 15 numbers per 100 sqm)

Clearing and Grubbing Road Land ., Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.12 materials and stacking of serviceable Material to be used or auctioned, up to a cum 0 1069.64 0
lead of 1000 meters including removal and disposal of top organic soil not
exceeding 150 mm in thickness., By Mechanical Means, Felling and uprooting
of bamboo clearing the area, stacking of bamboo and disposing of wastes

Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of


trees, including cutting of trunks, branches and removal of stumps, roots,
2.13 number 0 830.3 0
stacking of serviceable Material with all lifts and up to a lead of 1000 meters and
earth filling in the depression/pit., Girth from 300 mm to 600 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of
trees, including cutting of trunks, branches and removal of stumps, roots,
2.14 number 0 2490.9 0
stacking of serviceable Material with all lifts and up to a lead of 1000 meters and
earth filling in the depression/pit., Girth from 600 mm to 900 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of
trees, including cutting of trunks, branches and removal of stumps, roots,
2.15 number 0 6361.8 0
stacking of serviceable Material with all lifts and up to a lead of 1000 meters and
earth filling in the depression/pit., Girth from 900 mm to 1800 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of
trees, including cutting of trunks, branches and removal of stumps, roots,
2.16 number 0 14869.5 0
stacking of serviceable Material with all lifts and up to a lead of 1000 meters and
earth filling in the depression/pit., Girth from 1800 - 2500 mm
Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of
trees, including cutting of trunks, branches and removal of stumps, roots,
2.17 number 0 49818 0
stacking of serviceable Material with all lifts and up to a lead of 1000 meters and
earth filling in the depression/pit., Girth above 2500 mm
Clearing Grass and Removal of Rubbish and Dressing and levelling the
construction surface Clearing grass/ top soil and removal up to a distance of 50
2.18 sqm 0 6 0
meters outside the periphery of the area , including cutting and filling of small
undulation., By Manual Means

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.19 cum 0 1262.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Lime /Cement Concrete, By Manual Means, Lime
Concrete, cement concrete grade M-10 and below

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.20 cum 0 1469.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Lime /Cement Concrete, By Manual Means,
Cement Concrete Grade M-15 & M-20

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 3 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.21 cum 0 3249.9 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Lime /Cement Concrete, By Manual Means, Pre-
stressed / Reinforced cement concrete grade M-20 & above

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.22 cum 0 2482.62 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Lime /Cement Concrete, By Mechanical Means,
Cement Concrete Grade M-15 & M-20

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.23 cum 0 2862.12 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Lime /Cement Concrete, By Mechanical Means,
Prestressed / reinforced cement concrete grade M-20 & above

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
2.24 including scaffolding wherever necessary, sorting the dismantled Material, cum 0 848.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Brick / Tile work, In lime mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
2.25 including scaffolding wherever necessary, sorting the dismantled Material, cum 0 1559.4 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Brick / Tile work, In cement mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
2.26 including scaffolding wherever necessary, sorting the dismantled Material, cum 0 779.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Brick / Tile work, In mud mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.27 cum 0 848.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Brick / Tile work, Dry brick pitching
or brick soling

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.28 cum 0 952.2 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Stone Masonry, Rubble stone
masonry in lime mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.29 cum 0 1559.4 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Stone Masonry, Rubble stone
masonry in cement mortar.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.30 cum 0 848.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Stone Masonry, Rubble Stone
Masonry in mud mortar.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
2.31 including scaffolding wherever necessary, sorting the dismantled Material, cum 0 779.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Stone Masonry, Dry rubble masonry

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.32 cum 0 710.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Stone Masonry, Dismantling stone
pitching/ dry stone spalls.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.33 cum 0 952.2 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Dismantling Stone Masonry, Dismantling boulders
laid in wire crates including opening of crates and stacking dismantled Material.

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 4 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.34 cum 0 1559.4 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Wood Work wrought framed and fixed in frames
of trusses upto a height of 5 m above plinth level

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.35 tonne 0 5421.68 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Steel Work in all types of sections upto a height of
5 m above plinth level excluding cutting of rivet., Including dismembering

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.36 tonne 0 4643.7 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Steel Work in all types of sections upto a height of
5 m above plinth level excluding cutting of rivet., Excluding dismembering.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.37 disposal of unserviceable Material and stacking the serviceable Material with all number 0 34.5 0
lifts and lead of 1000 meters, Steel Work in all types of sections upto a height of
5 m above plinth level excluding cutting of rivet., Extra over item No( v ) A and(
v ) B for cutting rivets.

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.38 number 0 32.78 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Scraping of Bricks Dismantled from Brick Work
including Stacking., In lime/Cement mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.39 number 0 22.43 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Scraping of Bricks Dismantled from Brick Work
including Stacking., In mud mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.40 cum 0 1069.5 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Scraping of Stone from Dismantled Stone
Masonry, In cement and lime mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.41 cum 0 448.5 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Scraping of Stone from Dismantled Stone
Masonry, In Mud mortar

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.42 sqm 0 77.97 0
disposal of unserviceable Material and stacking the serviceable Material with all
lifts and lead of 1000 meters, Scarping Plaster in Lime or Cement Mortar from
Brick/ Stone Masonry

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.43 disposal of unserviceable Material and stacking the serviceable Material with all meter 0 448.5 0
lifts and lead of 1000 meters, Removing all type of Hume Pipes and Stacking
within a lead of 50 metres including Earthwork and Dismantling of Masonry
Works., Up to 600 mm dia

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.44 disposal of unserviceable Material and stacking the serviceable Material with all meter 0 655.5 0
lifts and lead of 1000 meters, Removing all type of Hume Pipes and Stacking
within a lead of 50 metres including Earthwork and Dismantling of Masonry
Works., Above 600 mm to 900 mm dia

Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work,
including scaffolding wherever necessary, sorting the dismantled Material,
2.45 disposal of unserviceable Material and stacking the serviceable Material with all meter 0 931.5 0
lifts and lead of 1000 meters, Removing all type of Hume Pipes and Stacking
within a lead of 50 metres including Earthwork and Dismantling of Masonry
Works., Above 900 mm

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 5 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)

Dismantling of Flexible Pavements, Dismantling of flexible pavements and


2.46 disposal of dismantled Material up to a lead of 1000 metres, stacking serviceable cum 0 1904.4 0
and unserviceable Material separately, By Manual Means, Bituminous courses

Dismantling of Flexible Pavements, Dismantling of flexible pavements and


2.47 disposal of dismantled Material up to a lead of 1000 metres, stacking serviceable cum 0 1697.4 0
and unserviceable Material separately, By Manual Means, Granular courses

Dismantling of Flexible Pavements, Dismantling of flexible pavements and


disposal of dismantled Material up to a lead of 1000 metres, stacking serviceable
2.48 cum 0 1139.19 0
and unserviceable Material separately, By Mechanical Means, Bituminous
course

Dismantling of cement concrete pavement by mechanical means using pneumatic


tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at
2.49 cum 0 4112.63 0
designated locations and disposal of dismantled Material up to a lead of 1000
metres, stacking serviceable and unserviceable Material separately

Dismantling guard rails by manual means and disposal of dismantled Material


2.50 with all lifts and up to a lead of 1000 metres, stacking serviceable Material and meter 0 224.94 0
unserviceable Material separately.
Dismantling Kerb stone by manual means and disposal of dismantled Material
2.51 meter 0 107.64 0
with all lifts and up to a lead of 1000 meter
Dismantling Kerb stone channel by manual means and disposal of dismantled
2.52 meter 0 121.44 0
Material with all lifts and up to a lead of 1000 meter
Dismantling of kilometer stone including cutting of earth, foundation and
2.53 disposal of dismantled Material with all lifts and lead upto 1000 m and back number 0 222.18 0
filling of pit., Five KM stone
Dismantling of kilometer stone including cutting of earth, foundation and
2.54 disposal of dismantled Material with all lifts and lead upto 1000 m and back number 0 131.79 0
filling of pit., One KM Stone
Dismantling of barbed wire fencing/ wire mesh fencing including posts,
foundation concrete, back filling of pit by manual means including disposal of
2.55 meter 0 180.09 0
dismantled Material with all lifts and up to a lead of 1000 metres, stacking
serviceable Material and unserviceable Material separately.
Dismantling of CI water pipe line upto 600 mm dia including disposal with all
2.56 lifts and lead upto 1000 metres and stacking of serviceable Material and meter 0 545.74 0
unserviceable Material separately .
Removal of cement concrete pipe of sewer gutter 1500 mm dia including
disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable
2.57 meter 0 560 0
and unserviceable Material separately but excluding earth excavation and
dismantling of masonry works.
Removal of telephone / Electric poles including excavation and dismantling of
foundation concrete and lines under the supervision of concerned department,
2.58 nos 0 683.68 0
disposal with all lifts and up to a lead of 1000 metres and stacking the
serviceable and unserviceable Material separately

3 Pipe Drain
Providing, jointing and laying HDPE pipes with or without collar etc. complete
3.1 in place as per Drawing and Technical Specifications., a) 110 mm/125 mm outer meter 0 874.86 0
dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for
3.2 culverts including fixing with cement mortar 1:2 as per Drawing and Technical meter 0 3973.06 0
Specifications., 300 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for
3.3 culverts including fixing with cement mortar 1:2 as per Drawing and Technical meter 0 5032.46 0
Specifications., 450 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for
3.4 culverts including fixing with cement mortar 1:2 as per Drawing and Technical meter 0 7530.75 0
Specifications., 600 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for
3.5 culverts including fixing with cement mortar 1:2 as per Drawing and Technical meter 0 13090.09 0
Specifications., 900 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for
3.6 culverts including fixing with cement mortar 1:2 as per Drawing and Technical meter 0 14579.49 0
Specifications., 1000 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for
3.7 culverts including fixing with cement mortar 1:2 as per Drawing and Technical meter 0 2734.83 0
Specifications., 1200 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for
3.8 culverts including fixing collar with cement mortar 1:2 as per Drawing and meter 0 3973.06 0
Technical Specifications., 300 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for
3.9 culverts including fixing collar with cement mortar 1:2 as per Drawing and meter 0 7530.75 0
Technical Specifications., 600 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for
3.10 culverts including fixing collar with cement mortar 1:2 as per Drawing and meter 0 5787.32 0
Technical Specifications., 450 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for
3.11 culverts including fixing collar with cement mortar 1:2 as per Drawing and meter 0 13090.09 0
Technical Specifications., 900 mm internal dia.

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 6 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for
3.12 culverts including fixing collar with cement mortar 1:2 as per Drawing and meter 0 14579.49 0
Technical Specifications., 1000 mm internal dia.
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for
3.13 culverts including fixing collar with cement mortar 1:2 as per Drawing and meter 0 2734.83 0
Technical Specifications., 1200 mm internal dia.
Providing and laying concrete channeling as per Drawing and Technical
3.14 0 0 0
Specifications., Cast in situ
Providing and laying concrete channeling as per Drawing and Technical
3.15 0 0 0
Specifications., Pre cast
3.16 Laying (Joining) of Precast concrete panel meter 0 275.2 0

4 Earthwork

Earthwork Excavation in Cutting., Roadway Excavation in all types of Soil by


Manual Means ., Roadway Excavation in all types of soil as per drawing and
4.1 cum 0 562.64 0
technical specification, including removal of stumps and other deleterious matter,
with all lifts and lead as per Drawing and instruction of the Engineer.

Earthwork Excavation in Cutting., Roadway Excavation in all types of Soil by


Mechanical Means ., Road way Excavation in all types of soil as per Drawing
4.2 cum 0 77.05 0
and technical specifications including removal of stumps and other deleterious
matter, all lifts and lead as per Drawing and instruction of the Engineer.

Earthwork Excavation in Cutting., Roadway Excavation in ordinary rock by


Manual Means ., Roadway Excavation in ordinary rock as per Drawing and
4.3 cum 0 645.55 0
Technical specification, including all lift and lead as per Drawing and
instruction of the Engineer.
Earthwork Excavation in Cutting., Roadway Excavation in ordinary rock by
Mechanical Means ., Roadway Excavation in ordinary rock as per Drawing and
4.4 cum 0 231.15 0
Technical specification, including all lift and lead as per Drawing and
instruction of the Engineer.
Earthwork Excavation in Cutting., Roadway Excavation in Hard Rock,
mechanical Drilling, Roadway Excavation in hard rock with mechanical drilling,
4.5 cum 0 1118.75 0
including blasting and breaking, and disposal of cut road within all lifts and
leads as per Drawing and instruction of the Engineer.
Earthwork Excavation in Cutting., Excavation in Hard Rock, manual Drilling,
4.6 Roadway excavation in hard rock with manual drilling, blasting, breaking, lifts cum 0 1234.51 0
and leads all complete as per Drawing and instruction of the Engineer.
Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting
prohibited), Roadway Excavation in hard rock with rock breakers, including
4.7 cum 0 2035.5 0
breaking rock, lifts and lead for disposal as per Drawing and Technical
Specifications, Mechanical method, lead upto 30 m
Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting
prohibited), Roadway Excavation in hard rock manually chiseling including
4.8 cum 0 2790.98 0
breaking rock, lifts and lead for disposal as per Drawing and Technical
Specifications ,
Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting
prohibited), Roadway Excavation in hard rock manually with use of chemical,
4.9 cum 0 843.96 0
including breaking rock, disposal within all lifts and lead as per Drawing and
Technical Specifications
Earthwork Excavation in Cutting., Excavation in Marshy Soil, Roadway
4.10 cum 0 195.09 0
Excavation in marshy soil as per Drawing and Technical Specifications
Removal of Unserviceable Soil with Disposal upto 1000 meters, Removal of
4.11 unserviceable soil including excavation, loading and disposal upto 1000 meters cum 0 162.57 0
lead
Trimming/ Rock Excavation Slopes, Carrying out excavation in hard rock to
achieve a specified slope of the rock face by controlled use of explosives and
4.12 blasting accessories in properly aligned and spaced drill holes, collection of the sqm 0 268.36 0
excavated rock by machine, with all lifts and lead as per Drawing and
instruction of the Engineer.

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.13 cum 0 655.5 0
other deleterious matter and backfilling with approved Material as per Drawing
and Technical Specifications., Ordinary soil by Manual Means, Depth upto 3 m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.14 other deleterious matter and backfilling with approved Material as per Drawing cum 0 931.5 0
and Technical Specifications., Ordinary soil by Manual Means, Depth 3 m to 6
m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.15 cum 0 1449 0
other deleterious matter and backfilling with approved Material as per Drawing
and Technical Specifications., Ordinary soil by Manual Means, Depth above 6 m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.16 other deleterious matter and backfilling with approved Material as per Drawing cum 0 115.58 0
and Technical Specifications., Ordinary soil by Mechanical Means, Depth upto 3
m

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 7 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Excavation for Structures Foundation, Earth work in excavation of foundation of
structures, including construction of shoring and bracing, removal of stumps and
4.17 other deleterious matter and backfilling with approved Material as per Drawing cum 0 132.09 0
and Technical Specifications., Ordinary soil by Mechanical Means, Depth 3 m to
6m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.18 other deleterious matter and backfilling with approved Material as per Drawing cum 0 163.68 0
and Technical Specifications., Ordinary soil by Mechanical Means, Depth above
6m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.19 other deleterious matter and backfilling with approved Material as per Drawing cum 0 793.5 0
and Technical Specifications., Ordinary Rock (not requiring blasting) by Manual
Means, Depth upto 3 m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.20 other deleterious matter and backfilling with approved Material as per Drawing cum 0 308.2 0
and Technical Specifications., Ordinary Rock (not requiring blasting) by
Mechanical Means, Depth upto 3 m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.21 other deleterious matter and backfilling with approved Material as per Drawing cum 0 1394.26 0
and Technical Specifications., Hard Rock ( requiring blasting ) by Manual
Means

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.22 other deleterious matter and backfilling with approved Material as per Drawing cum 0 1496.96 0
and Technical Specifications., Hard Rock ( blasting prohibited ) by Mechanical
Means

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.23 cum 0 1904.4 0
other deleterious matter and backfilling with approved Material as per Drawing
and Technical Specifications., Marshy Soil by Manual Means, Depth upto 3 m

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.24 cum 0 574.66 0
other deleterious matter and backfilling with approved Material as per Drawing
and Technical Specifications., Marshy Soil by Mechanical Means

Excavation for Structures Foundation, Earth work in excavation of foundation of


structures, including construction of shoring and bracing, removal of stumps and
4.25 cum 0 943 0
other deleterious matter and backfilling with approved Material as per Drawing
and Technical Specifications., Back Filling in Marshy Foundation Pits

Stripping and Storing Top Soil, Stripping, storing of top soil by road side at 15 m
internal and re-application on embankment slopes, cut slopes and other areas in
4.26 cum 0 165.39 0
localities where the available embankment Material is not conducive to plant
growth as per Drawing and Technical Specifications.

Stripping, Storing and Re-laying Top Soil from Borrow Areas in Agriculture
Fields., Stripping of top soil from borrow areas located in agriculture fields,
4.27 storing at a suitable place, spreading and re-laying after taking the borrow earth cum 0 353.79 0
to maintain fertility of the agricultural field, finishing it to the required levels to
the satisfaction of the farmer as per Drawing and Technical Specifications.

Preparation and Surface Treatment of Formation., Preparation and surface


treatment of Formation by removing mud and slurry, watering to the extent
4.28 sqm 0 11.36 0
needed to maintain desired moisture content , compacting all complete as per
Drawing and Technical Specifications.
Construction of Embankment with Material obtained from Borrow pits,
4.29 Providing, laying, spreading and compacting embankment with borrow material cum 0 834.93 0
as per Drawing and Technical Specifications.
Construction of Embankment with Material Deposited from Roadway Cutting,
Providing, laying, spreading and compacting embankment with roadway cutting
4.30 cum 0 600.71 0
material and compact to the required density as per Drawing and Technical
Specifications.( Manually)
Construction of Embankment with Material Deposited from Roadway Cutting,
Providing, laying, spreading and compacting embankment with roadway cutting
4.31 cum 0 480.17 0
material and compact to the required density as per Drawing and Technical
Specifications. (With machine)
Construction of Rock fill Embankment, Providing and laying of rock fill
embankment with broken hard rock fragments of size not exceeding 300 mm laid
4.32 in layers not exceeding 500 mm thick including filling of surface voids with cum 0 526.84 0
stone spalls, blinding top layer with granular Material, rolled to required density
all complete as per Drawing and Technical Specifications.
Providing suitable material and Back filling behind abutment, wing wall and
4.33 return wall complete as per Drawing and Technical Specifications., Granular cum 0 1949.54 0
Material
Providing suitable material and Back filling behind abutment, wing wall and
4.34 return wall complete as per Drawing and Technical Specifications., Sandy cum 0 1502.19 0
Material
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
Abstract of Cost Page 8 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing suitable material and Back filling behind abutment, wing wall and
4.35 return wall complete as per Drawing and Technical Specifications., Locally cum 0 974.67 0
available Material including compaction by tamping rod ( without watering)
Providing suitable material and Back filling behind abutment, wing wall and
4.36 return wall complete as per Drawing and Technical Specifications., Locally cum 0 857.6 0
available Material, with out watering and compaction by tamping rod
Providing and laying of Filter media with granular Material/stone crushed
aggregates to a thickness of not less than 600 mm with smaller size towards the
4.37 soil and bigger size towards the wall and provided over the entire surface behind cum 0 2564.5 0
abutment, wing wall and return wall to the full height compacted to a firm
condition complete as per drawing and Technical Specification.
Providing and filling sand in Foundation Trenches as per Drawing & Technical
4.38 cum 0 1224.75 0
Specification

5 Subgrade
Scarifying Existing road Surface to a Depth of 50 mm by
Manual Means, Scarifying the existing road surface to a depth of 50 mm and
5.1 sqm 0 31.74 0
disposal of scarified Material with all lifts and leads as per Drawing and
Technical Specifications.
Scarifying Existing road Surface to a Depth of 50 mm by
Manual Means, Scarifying the existing granular road surface to a depth of 50mm
5.2 sqm 0 15.53 0
and disposal of scarified Material with all lifts and leads within Right of way as
per Drawing and Technical Specifications.

Scarifying Existing road Surface to a depth of 50 mm by Mechanical Means,


5.3 Scarifying the existing road surface to a depth of 50 mm and disposal of scarified sqm 0 21.76 0
Material with in all lifts and lead as per Drawing and Technical Specifications.

Scarifying Existing road Surface to a depth of 50 mm by Mechanical Means,


Scarifying the existing bituminous road surface to a depth of 50 mm and disposal
5.4 sqm 0 14.5 0
of scarified Material with in all lifts and lead as per Drawing and Technical
Specifications.
Construction of Subgrade and Earthen Shoulders with approved Material
( capping layer), Providing and laying sub-grade and earthen shoulders with
5.5 sqm 0 133.18 0
approved Material obtained from borrow pits with all lifts & leads as per
Drawing and Technical Specifications.
Compacting Original Ground, Compacting original ground supporting sub-grade,
Loosening of the ground upto a level of 500 mm below the sub-grade level,
5.6 sqm 0 149.25 0
watered, graded and compacted in layers as per Drawing and Technical
Specifications.
Compacting Original Ground, Compacting original ground supporting
embankment, Loosening, leveling and Compacting original ground supporting
5.7 embankment to facilitate placement of first layer of embankment, scarified to a sqm 0 93.36 0
depth of 150 mm, mixed with water at OMC and then compacted by rolling so as
to achieve dry density as per Drawing and Technical Specifications.

6 Sub base and Base


Providing and laying granular sub-base on prepared surface, mixing at OMC,
6.1 and compacting to achieve the desired density, complete as per Drawing and cum 0 1666.92 0
Technical Specifications., By Mechanical means
Providing and laying granular sub-base on prepared surface, mixing at OMC,
6.2 and compacting to achieve the desired density, complete as per Drawing and cum 0 2046.3 0
Technical Specifications., By manual Means

Providing, laying and spreading soil on a prepared sub grade, pulverizing, adding
the designed quantity of cement to the spread soil, mixing in place , grading and
6.3 compacting at OMC to achieve the desired unconfined compressive strength and cum 0 2425.74 0
to form a layer of sub-base/base as per Drawing and Technical Specifications.,
For 4 per cent quantity of cement by weight of soil

Providing, laying, spreading and compacting screening / coarse sand of specified


6.4 grade in uniform layer on a prepared surface and compacting to form a inverted cum 0 1188.88 0
Choke as per Drawing and Technical Specifications.
Providing, laying, spreading and compacting Water bound macadam including
brooming requisite type of screening/ binding Materials to fill up the interstices
6.5 of coarse aggregate, watering and compacting to the required density as per cum 0 2941.62 0
Drawing and Technical Specifications., By Manual Means, By using stone
screening 13.2mm and Vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices
6.6 of coarse aggregate, watering and compacting to the required density as per cum 0 2910.77 0
Drawing and Technical Specifications., By Manual Means, By using stone
screening 13.2mm and Smooth 3 wheeled steel roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices
6.7 of coarse aggregate, watering and compacting to the required density as per cum 0 3121.02 0
Drawing and Technical Specifications., By Manual Means, By using stone
screening 11.2 mm for grading-II and Vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices
6.8 of coarse aggregate, watering and compacting to the required density as per cum 0 3090.17 0
Drawing and Technical Specifications., By Manual Means, By using stone
screening 11.2 mm for grading-II and Smooth 3 wheeled
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
Abstract of Cost Page 9 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing, laying, spreading and compacting Water bound macadam including
brooming requisite type of screening/ binding Materials to fill up the interstices
6.9 of coarse aggregate, watering and compacting to the required density as per cum 0 2254.59 0
Drawing and Technical Specifications., By Mechanical Means:, By using stone
screening 13.2 mm for grading-II and vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices
6.10 of coarse aggregate, watering and compacting to the required density as per cum 0 2269.99 0
Drawing and Technical Specifications., By Mechanical Means:, By using stone
screening 13.2 mm for grading-II and Smooth 3 wheeled steel roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices
6.11 of coarse aggregate, watering and compacting to the required density as per cum 0 2433.99 0
Drawing and Technical Specifications., By Mechanical Means:, By using stone
screening 11.2 mm for grading-II and Smooth 3 vibratory roller

Providing, laying, spreading and compacting Water bound macadam including


brooming requisite type of screening/ binding Materials to fill up the interstices
6.12 of coarse aggregate, watering and compacting to the required density as per cum 0 2449.39 0
Drawing and Technical Specifications., By Mechanical Means:, By using stone
screening 11.2 mm for grading-II and Smooth 3 wheeled steel roller

Providing and laying Crusher Run Macadam on a prepared surface, spreading


6.13 and mixing , watering and compacting to form a layer of sub-base/Base course cum 0 2450.72 0
as per Drawing and Technical Specifications., By Mix in Place Method

Providing and laying Crusher Run Macadam on a prepared surface, spreading


6.14 and mixing , watering and compacting to form a layer of sub-base/Base course cum 0 2864.82 0
as per Drawing and Technical Specifications., By Mix in Place Method

Providing and laying Median and Island above road level with approved
6.15 Material deposited including compacted as per Drawing and Specifications. cum 0 618.86 0
( using material from Roadway excavation).
Providing and laying Median and Island above road level with approved
6.16 Material deposited including compacted as per Drawing and Specifications. cum 0 1111.72 0
( using material from borrow area).

Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC
6.17 laying in uniform layers in sub- base / base course on well prepared surface and cum 0 2530.31 0
compacting to achieve required density as per Drawing and Technical
Specifications., Base course with B1 material, Vibratory Road Roller

Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC
6.18 laying in uniform layers in sub- base / base course on well prepared surface and cum 0 2530.31 0
compacting to achieve required density as per Drawing and Technical
Specifications., Base course with B2 material, Vibratory Road Roller

Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC
6.19 laying in uniform layers in sub- base / base course on well prepared surface and cum 0 2545.64 0
compacting to achieve required density as per Drawing and Technical
Specifications., Sub Base course with S1 material, Vibratory Road Roller

Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at OMC
6.20 laying in uniform layers in sub- base / base course on well prepared surface and cum 0 2545.64 0
compacting to achieve required density as per Drawing and Technical
Specifications., Sub Base course with S2 material, Vibratory Road Roller

7 Bituminous

Prime Coat, Prime Coat, with MC 30 / 70 by Mechanical Means, Providing and


applying prime coat with Hot Bitumen ( including cutter) on prepared surface of
7.1 lit 0 119.14 0
granular base including cleaning of road surface and spraying by mechanical
means as per Technical Specification ., Bitumen ( cutback) MC 30 ( for WBM)

Prime Coat, Prime Coat, with MC 30 / 70 by Mechanical Means, Providing and


applying prime coat with Hot Bitumen ( including cutter) on prepared surface of
7.2 granular base including cleaning of road surface and spraying by mechanical lit 0 119.14 0
means as per Technical Specification ., Bitumen ( cutback) MC 30 ( for
stabilized soil base/ crusher run macadam)

, Prime Coat, with MC 30 / 70 by Bitumen , by manual means, Providing and


applying prime coat with Hot Bitumen(including cutter) on prepared surface of
7.3 granular base including cleaning of road surface and spraying at specified rate lit 0 208.99 0
by manual means as per Technical Specification . , Bitumen ( cutback) MC 30
( for WBM)

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 10 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
, Prime Coat, with MC 30 / 70 by Bitumen , by manual means, Providing and
applying prime coat with Hot Bitumen(including cutter) on prepared surface of
7.4 granular base including cleaning of road surface and spraying at specified rate lit 0 208.99 0
by manual means as per Technical Specification . , Bitumen (cut back )MC 70
( for stabilized soil base/ crusher run macadam)
, Prime Coat, with Emulsion by Mechanical Means, Providing and applying
primer coat with Bitumen emulsion on prepared surface of granular base
7.5 lit 0 92.63 0
including cleaning of road surface and spraying primer at specified rate using
mechanical means as per Technical Specification .
, Prime Coat with emulsion, for manual works, Providing and applying primer
coat with Bitumen emulsion on prepared surface of granular base including
7.6 lit 0 157.1 0
cleaning of road surface and spraying primer at specified rate as per Technical
Specification.
Tack Coat, Tack coat with Bitumen By Mechanical Means, Providing and
7.7 applying tack coat with hot Bitumen at specified rate on the prepared non- lit 0 108.1 0
bituminous surfaces including cleaning as per Technical Speciation .
, Tack coat with Bitumen by Manual Means, Providing and applying tack coat
7.8 with hot Bitumen at the specified rate the prepared surfaces including cleaning as lit 0 162.36 0
per Technical Speciation .
, Tack coat with Emulsion By Mechanical Means, Providing and applying tack
7.9 coat with Bitumen emulsion at specified rate on the prepared non-bituminous lit 0 86.05 0
surfaces including cleaning as per Technical Speciation .
, Tack coat with Emulsion By Manual Means, Providing and applying tack coat
7.10 with Bitumen emulsion at the specified rate the prepared surfaces including lit 0 102.7 0
cleaning as per Technical Speciation .
Bituminous Macadam, Providing and laying bituminous macadam with hot mix
plant using crushed aggregates of grading as per specification premixed with
7.11 cum 0 14584.24 0
bituminous binder, laid over a previously prepared surface as per Drawing and
Technical Specifications. , Grading I ( 40 mm nominal size )
Bituminous Macadam, Providing and laying bituminous macadam with hot mix
plant using crushed aggregates of grading as per specification premixed with
7.12 bituminous binder, laid over a previously prepared surface as per Drawing and cum 0 14752.09 0
Technical Specifications. , Grading I ( 40 mm nominal size ), In case BM is laid
over freshly laid tack coat
Bituminous Macadam, Providing and laying bituminous macadam with hot mix
plant using crushed aggregates of grading as per specification premixed with
7.13 cum 0 14614.36 0
bituminous binder, laid over a previously prepared surface as per Drawing and
Technical Specifications. , Grading II(19 mm nominal size)
Bituminous Macadam, Providing and laying bituminous macadam with hot mix
plant using crushed aggregates of grading as per specification premixed with
7.14 bituminous binder, laid over a previously prepared surface as per Drawing and cum 0 14782.21 0
Technical Specifications. , Grading II(19 mm nominal size), In case BM is laid
over freshly laid tack coat
Bituminous Penetration Macadam, Providing and laying penetration macadam
over prepared Base by providing a layer of compacted crushed coarse aggregate
7.15 sqm 0 469.77 0
with applications of bituminous binder and key aggregates as per Drawing and
Technical Specifications., 50 mm thick
Bituminous Penetration Macadam, Providing and laying penetration macadam
over prepared Base by providing a layer of compacted crushed coarse aggregate
7.16 sqm 0 628.35 0
with applications of bituminous binder and key aggregates as per Drawing and
Technical Specifications., 75 mm thick
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with
7.17 cum 0 17426.09 0
bituminous binder and filler as per Drawing and Technical Specifications.,
Grading - I 40 mm (Nominal Size)
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with
7.18 bituminous binder and filler as per Drawing and Technical Specifications., cum 0 17602.54 0
Grading - I 40 mm (Nominal Size), In case DBM is laid over freshly laid tack
coat
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with
7.19 cum 0 17441.55 0
bituminous binder and filler as per Drawing and Technical Specifications.,
Grading - II 19 mm (Nominal Size)
Dense Graded Bituminous Macadam, Providing and laying dense bituminous
macadam using crushed aggregates of specified grading, premixed with
7.20 bituminous binder and filler as per Drawing and Technical Specifications., cum 0 17618 0
Grading - II 19 mm (Nominal Size), In case DBM is laid over freshly laid tack
coat
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous
concrete/ Asphalt concrete using crushed aggregates of specified grading,
7.21 cum 0 20835.18 0
premixed with bituminous binder and filler as per Drawing and Technical
Specifications, Grading - I-19 mm (Nominal Size)
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous
concrete/ Asphalt concrete using crushed aggregates of specified grading,
7.22 premixed with bituminous binder and filler as per Drawing and Technical cum 0 21015.33 0
Specifications, Grading - I-19 mm (Nominal Size), In case BC is laid over
freshly laid tack coat

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 11 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous
concrete/ Asphalt concrete using crushed aggregates of specified grading,
7.23 cum 0 21416.25 0
premixed with bituminous binder and filler as per Drawing and Technical
Specifications, Grading - II-13 mm (Nominal Size)
Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous
concrete/ Asphalt concrete using crushed aggregates of specified grading,
7.24 premixed with bituminous binder and filler as per Drawing and Technical cum 0 21021.5 0
Specifications, Grading - II-13 mm (Nominal Size), In case BC is laid over
freshly laid tack coat
Surface Dressing, Providing and laying surface dressing as wearing course in
single coat using gravel of specified size on a recently applied layer of
7.25 sqm 0 43.48 0
bituminous binder on prepared surface as per Drawing and Technical
Specifications., MECHANICAL MEANS, 19 mm nominal chipping size
Surface Dressing, Providing and laying surface dressing as wearing course in
single coat using gravel of specified size on a recently applied layer of
7.26 sqm 0 31.39 0
bituminous binder on prepared surface as per Drawing and Technical
Specifications., MECHANICAL MEANS, 13 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in
single coat using gravel of specified size on a recently applied layer of
7.27 sqm 0 24.9 0
bituminous binder on prepared surface as per Drawing and Technical
Specifications., MECHANICAL MEANS, 10 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in
single coat using gravel of specified size on a recently applied layer of
7.28 sqm 0 18.85 0
bituminous binder on prepared surface as per Drawing and Technical
Specifications., MECHANICAL MEANS, 6.0 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in
single coat using gravel of specified size on a recently applied layer of
7.29 sqm 0 86.07 0
bituminous binder on prepared surface as per Drawing and Technical
Specifications., MANUAL MEANS, 19 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in
single coat using gravel of specified size on a recently applied layer of
7.30 sqm 0 41.86 0
bituminous binder on prepared surface as per Drawing and Technical
Specifications., MANUAL MEANS, 13 mm nominal size chipping
Surface Dressing, Providing and laying surface dressing as wearing course in
single coat using gravel of specified size on a recently applied layer of
7.31 sqm 0 35.13 0
bituminous binder on prepared surface as per Drawing and Technical
Specifications., MANUAL MEANS, 10 mm nominal size chipping
Pre-coating Chips, Pre-coating of chips with 1 per cent of paving bitumen by
7.32 weight of chips in a suitable mixer duly heated to 160 degree C as per Technical cum 0 2370.38 0
Specification
40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen /
Modified bitumen) Binder, Providing and laying open-graded premix carpet of
7.33 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates as wearing course sqm 0 1030.46 0
on a previously prepared base as per drawing and Technical Specifications ., By
Manual Means

40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen /


Modified bitumen) Binder, By Mechanical Means, Providing and laying open-
7.34 graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm sqm 0 12541 0
aggregates as wearing course on a previously prepared base as per drawing and
Technical Specifications ., Mechanical method using Hot Mix Plant

40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen /


Modified bitumen) Binder, By Mechanical Means, Providing and laying open-
graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm
7.35 sqm 0 454.79 0
aggregates as wearing course on a previously prepared base as per drawing and
Technical Specifications ., Open-Graded Premix Surfacing using cationic
Bitumen Emulsion

Close Graded Premix Surfacing/Mixed Seal Surfacing , Mechanical means using


HMP of appropriate capacity ,, Providing and laying close-graded premix
surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm or 13.2
7.36 sqm 0 304.32 0
mm to 0.09 mm aggregates using bitumen as wearing course on a previously
prepared base, including mixing in a suitable plant as per Drawing and Technical
Specifications., Type - A

Close Graded Premix Surfacing/Mixed Seal Surfacing , Mechanical means using


HMP of appropriate capacity ,, Providing and laying close-graded premix
surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm or 13.2
7.37 sqm 0 275.7 0
mm to 0.09 mm aggregates using bitumen as wearing course on a previously
prepared base, including mixing in a suitable plant as per Drawing and Technical
Specifications., Type - B
Seal Surfacing, Providing and laying seal coat sealing the voids in a bituminous
7.38 sqm 0 101.01 0
surface as per Drawing and Technical Specifications.
Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine
aggregates, Portland cement filler, bituminous emulsion and water on a road
7.39 surface including cleaning of surface, mixing of slurry seal in a suitable mobile sqm 0 98.71 0
plant, laying and compacting to provide even riding surface as per Drawing and
Technical Specifications., 5 mm thickness

Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine
aggregates, Portland cement filler, bituminous emulsion and water on a road
7.40 surface including cleaning of surface, mixing of slurry seal in a suitable mobile sqm 0 68.56 0
plant, laying and compacting to provide even riding surface as per Drawing and
Technical Specifications., 3 mm thickness

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 12 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine
aggregates, Portland cement filler, bituminous emulsion and water on a road
7.41 surface including cleaning of surface, mixing of slurry seal in a suitable mobile sqm 0 42.31 0
plant, laying and compacting to provide even riding surface as per Drawing and
Technical Specifications., 1.5 mm thickness

Fog Spray, Providing and applying low viscosity bitumen emulsion for sealing
7.42 cracks less than 3 mm wide or incipient fretting or disintegration in an existing sqm 0 58.67 0
bituminous surfacing as per Drawing and Technical Specifications.

Fog Spray, Providing and applying low viscosity bitumen emulsion for sealing
cracks less than 3 mm wide or incipient fretting or disintegration in an existing
7.43 sqm 0 66.76 0
bituminous surfacing as per Drawing and Technical Specifications., Blind the
fog spray

Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and


rolling of bituminous cold mix on prepared base consisting of a mixture of
7.44 unheated mineral aggregate and emulsified or cutback bitumen, including mixing cum 0 17596.99 0
in a plant of suitable type as per Drawing and Technical Specifications., Using
bitumen emulsion and 9.5 mm or 13.2 mm size aggregate

Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and


rolling of bituminous cold mix on prepared base consisting of a mixture of
7.45 unheated mineral aggregate and emulsified or cutback bitumen, including mixing cum 0 17517.05 0
in a plant of suitable type as per Drawing and Technical Specifications., Using
bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate

Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and


rolling of bituminous cold mix on prepared base consisting of a mixture of
7.46 unheated mineral aggregate and emulsified or cutback bitumen, including mixing cum 0 14701.51 0
in a plant of suitable type as per Drawing and Technical Specifications., Using
cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate

Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and


rolling of bituminous cold mix on prepared base consisting of a mixture of
7.47 unheated mineral aggregate and emulsified or cutback bitumen, including mixing cum 0 14621.57 0
in a plant of suitable type as per Drawing and Technical Specifications., Using
cutback bitumen and 19 mm or 26.5 mm nominal size aggregate

Sand Asphalt Base Course, Providing, laying and rolling sand-asphalt base
7.48 course composed of sand, mineral filler and bituminous binder on a prepared cum 0 15154.06 0
sub-grade or sub-base as per Drawing and Technical Specifications.
Anti- Stripping agent, Providing and mixing of Anti stripping agent as per
7.49 kg 0 390.01 0
Design/ direction of Engineer
Bitumen Cutter, Providing and mixing of Bitumen cutter as per design /
7.50 lit 0 126.17 0
direction of Engineer

Modified Binder, Supply of modified binder (produced by mixing bitumen with


7.51 modifier such as natural rubber or crumb rubber or any other polymer found tonne 0 89240 0
compatible with bitumen) as per Specifications and direction of the Engineer.

Otta seal, Providing and laying Otta seal surface as wearing course in single coat
7.52 using river bed shingles /aggregates of specified size ( 0- 16 mm) laid on sqm 0 183.93 0
prepared surface as per Drawing and Technical Specifications.
Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared
7.53 surface, by paver finisher, rolled with a pneumatic tired roller initially and cum 0 10591.6 0
finished with a smooth steel wheel roller, all as per specifications., 75 mm
thickness

Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared
7.54 surface, by paver finisher, rolled with a pneumatic tired roller initially and cum 0 14550.27 0
finished with a smooth steel wheel roller, all as per specifications., 40 mm
thickness

Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared
7.55 surface, by paver finisher, rolled with a pneumatic tired roller initially and cum 0 16907.63 0
finished with a smooth steel wheel roller, all as per specifications., 25 mm
thickness

Mastic Asphalt, Providing and laying 25 mm thick mastic asphalt wearing course
excluding prime coat with paving grade bitumen including providing antiskid
7.56 surface with bitumen pre-coated fine grained hard stone chipping at an spacing sqm 0 1402.29 0
of 10 cm center to center in both directions all complete as per Drawing and
Technical specifications.

8 Kerbs and Footpath


Precast Cement Concrete M 20 Kerb , Providing and laying of /20 precast
cement concrete Kerb 38 cm * 20 cm * 25 cm ( H*B*L) with 12 mm thick 1:3
8.1 cement sand mortar bedding and joints including foundation excavation levelling meter 0 1388.57 0
but excluding foundation concrete for foundation or sand gravel material, all
complete as per Drawing and Technical Specifications.

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 13 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Cast in Situ Cement Concrete or natural stone block for footpath, Providing and
laying of precast / cast in situ 50 mm thick cement concrete slab footpath on 12
8.2 sqm 0 1741.88 0
mm thick 1: 3 cement sand mortar over the prepared base, all complete as per
Drawing and Technical Specifications.
, Providing and laying 25 mm thick Natural stone slab footpath on 12 mm
8.3 thick 1: 3 cement sand mortar over the prepared base, all complete as per sqm 0 566.71 0
specification.
Cast in Situ Cement Concrete Kerb , Providing and laying cement concrete Kerb
with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm
8.4 meter 0 785.22 0
projection beyond Kerb stone, Kerb stone laid with Kerb laying machine,
foundation concrete laid manually, all complete as per Drawing and Technical
Specifications.

Cast in Situ Cement Concrete M 20 Kerb with Channel, Providing and laying
cement concrete Kerb with channel with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on grade foundation 150 mm
8.5 meter 0 1545.4 0
thick, Kerb channel 300 mm wide, 50 mm thick in PCC grade, sloped towards
the Kerb, Kerb stone with channel laid with Kerb laying machine, foundation
concrete laid manually, all complete as specification.
Brick work for footpath, Providing and laying brick on edge over 60 mm thick
8.6 sand bed in footpath including excavation sand bedding all complete as per sqm 0 1369.77 0
Drawing and Technical Specifications.
Brick work for footpath, Providing and laying flat brick over 60 mm thick
8.7 sand bed in footpath including excavation sand bedding all complete as per sqm 0 791.89 0
specification.

9 Traffic Signs
Non Reflective Traffic Signs, Providing and fixing of Non reflective warning,
mandatory and informatory sign board of 2 mm thick MS Sheet with back
support frame fixed on heavy 50 mm tube or Channel section of 75 mm X 40
9.1 mm firmly fixed to the ground by means of properly designed foundation with M no 0 1912.78 0
10/40 grade cement concrete 300 mm x 300 mm x 300 mm, l as per drawings
and Technical Specification/ DOR Publication., Heavy Duty Steel Tube internal
50 mm dia., MS Sheet 60 cm height equilateral triangle

Retro-Reflectorized Traffic Signs, Providing and fixing of retro- reflectorized


warning, Regulatory and informatory sign as per specification clause 1501 made
of high intensity grade sheeting , fixed over aluminum sheeting, 1.5 mm thick
supported on a 50 mm internal dia steel tube or mild steel angle iron post 75 mm
9.2 no 0 905.35 0
x 40 mm x 6 mm firmly fixed to the ground by means of properly designed
foundation with M 10/40 grade cement concrete 30 cm x 30 cm , 30 cm below
ground level or as per Drawing and Technical Specifications., MS Sheet 60 cm
height equilateral triangle, Heavy Duty Steel Tube internal 50 mm dia.

Overhead Signs, Providing and erecting overhead signs with a corrosion resistant
2 mm thick aluminum alloy sheet reflectorized with micro prismatic retro-
reflective type with vertical and lateral clearance as per drawing and installed as
9.3 tonne 0 40705.4 0
per Specification over a designed support system of aluminum alloy or
galvanized steel trusses of sections and type as per structural design requirements
, Drawing and Technical Specifications., Truss and Vertical Support

Overhead Signs, Providing and erecting overhead signs with a corrosion resistant
2 mm thick aluminum alloy sheet reflectorized with micro prismatic retro-
reflective type with vertical and lateral clearance as per drawing and installed as
9.4 per Specification over a designed support system of aluminum alloy or sqm 0 464.6 0
galvanized steel trusses of sections and type as per structural design requirements
, Drawing and Technical Specifications., Aluminum Alloy Plate for Over Head
Sign

Painting Two Coats on Concrete Surfaces, Providing and Painting two coats
9.5 after filling the surface with synthetic enamel paint in all shades on concrete / sqm 0 912.43 0
plaster surfaces as per Drawing and Technical Specifications.
Painting Two Coats on Steel Surfaces, Providing and applying two coats of
9.6 ready mix paint of approved brand on steel surface after through cleaning of sqm 0 182.48 0
surface to give an even shade as per Drawing and Technical Specifications.
`, Providing and applying two coats of ready mix paint of approved brand on
9.7 wood surface after thorough cleaning of surface to give an even shade as per sqm 0 231.05 0
Drawing and Technical Specifications.
Painting Lines, Dashes, Arrows etc. on Roads in Two Coats, Providing required
material and Painting lines, dashes, arrows etc. on roads in two coats on new
work with ready mixed road marking paint conforming to NS 408/ IS 164 on
9.8 sqm 0 344.16 0
bituminous surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control as per Drawing and
Technical Specifications., Over 10 cm in width

Painting Lines, Dashes, Arrows etc. on Roads in Two Coats, Providing required
material and Painting lines, dashes, arrows etc. on roads in two coats on new
work with ready mixed road marking paint conforming to NS 408/ IS 164 on
9.9 sqm 0 344.16 0
bituminous surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control as per Drawing and
Technical Specifications., Up to 10 cm in width

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 14 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Painting Lines, Dashes, Arrows etc. on Roads in Two Coats on Old Work,
Providing required materials and Painting lines, dashes, arrows etc. on roads in
two coats on old work with ready mixed road marking paint conforming to NS
9.10 sqm 0 303.93 0
408/ IS: 164 on bituminous surface, including cleaning the surface of all dirt,
dust and other foreign matter, demarcation at site and traffic control as per
Drawing and Technical Specifications., over 10 cm in width

Painting Lines, Dashes, Arrows etc. on Roads in Two Coats on Old Work,
Providing required materials and Painting lines, dashes, arrows etc. on roads in
two coats on old work with ready mixed road marking paint conforming to NS
9.11 sqm 0 303.93 0
408/ IS: 164 on bituminous surface, including cleaning the surface of all dirt,
dust and other foreign matter, demarcation at site and traffic control as per
Drawing and Technical Specifications., Up to 10 cm in width

Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing


Glass Beads on Bituminous Surface, On smooth surface (similar to Asphalt
concrete and rigid pavement), Providing and laying of hot applied thermoplastic
9.12 sqm 0 1762.42 0
compound at least 2 mm thick including reflectorizing glass beads as per DOR
Traffic sign manual/ Specifications .The finished surface to be level, uniform and
free from streaks and holes.

Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing


Glass Beads on Bituminous Surface, On rough surface ( similar to surface
dressing), Providing and laying of hot applied thermoplastic compound at least 2
9.13 sqm 0 3025.38 0
mm thick including reflectorizing glass beads as per DOR Traffic sign manual/
Specifications .The finished surface to be level, uniform and free from streaks
and holes.

Providing and fixing of road stud 100x 100 mm, die-cast in aluminum, resistant
to corrosive effect of salt and grit, fitted with lenses reflectors, installed in
concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as per Specification
9.14 clause 1505., Providing and fixing of road stud 100 x 100 mm, die-cast in no 0 48.3 0
aluminum, resistant to corrosive effect of salt and grit, fitted with lenses
reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a
depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all
as per Drawing and Technical Specifications., Cats Eye

Kilometer Stone, Providing and Fixing Reinforced cement concrete M 15 grade


9.15 kilometer Post including painting and printing as per Standard Drawing-2070 no 0 4280.08 0
and Technical Specifications. position, Five kilometer Post (precast)
Kilometer Stone, Providing and Fixing Reinforced cement concrete M 15 grade
9.16 kilometer Post including painting and printing as per Standard Drawing-2070 no 0 2266.11 0
and Technical Specifications. position, One kilometer post (precast)
Road Delineators Post, Providing and installation of 150 mm * 150 mm 1. 5 m
long delineators (road way indicators, hazard markers, object markers), 80-100
9.17 cm high above ground level, painted black and white in 20 cm wide strips, buried no 0 1160.55 0
or pressed into the ground and conforming to the drawings and Technical
Specifications.

Reinforced Cement Concrete Crash Barrier, Providing and Fixing Reinforced


cement concrete crash barrier at the edges of the road, approaches to bridge
structures and medians, constructed with M-20 grade concrete with HYSD
9.18 meter 0 3199.88 0
reinforcement and dowel bars 25 mm dia, 450 mm long at expansion joints filled
with pre-molded asphalt filler board, keyed to the structure on which it is built
and installed as per design, Drawing and Technical Specifications.

Metal Beam Crash Barrier, Type - A, "W" : Metal Beam Crash Barrier,
Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
9.19 series channel vertical post, 150 x 75 x 5 mm spaced 2 m center to center, 1.8 m meter 0 316.09 0
high, 1.1 m below ground/road level metal beam rail to be fixed on the vertical
post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete
as per Drawing and Technical Specifications.

Metal Beam Crash Barrier, Type - B, "THRIE" : Metal Beam Crash Barrier,
Providing and erecting a "Thrie" metal beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on
9.20 ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m center to center, meter 0 352.88 0
2.1 m high with 1.3 m below ground level, metal beam rail to be fixed on the
vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long
complete as per Drawing and Technical specifications.

Metal Beam Crash Barrier, Flexible Crash Barrier, Wire Rope Safety Barrier,
Providing and erecting a wire rope safety barrier with vertical posts of medium
weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85
m above ground and 0.65 m below ground level, split at the bottom for better
grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m
9.21 center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at meter 0 4098.17 0
terminal posts 15 m apart. Terminal post to be embedded in M 15 grade cement
concrete foundation 2400 x 450 x 900 mm (depth), strengthened by a strut of RS
joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long
at the bottom, all embedded in foundation concrete as per design , Drawing and
Technical Specifications.

Anti-Glare Devices in Median, Plantation, Providing and Plantation of shrubs


9.22 and plants of approved species in the median. apart from cutting off glare from 0 0 0
vehicle coming from opposite direction,

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 15 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)

Anti-Glare Devices in Median, Anti-glare screen with 25 mm steel pipe


framework fixed with circular and rectangular vans, Providing and erecting an
anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the
form of panels of one meter length and 1.75 meter height fixed with circular
9.23 meter 0 6484.01 0
vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made
out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger
for embedding in foundation concrete, applying 2 coats of paint on all exposed
surfaces, all as per design , drawings and Technical Specifications.

Anti-Glare Devices in Median, Anti-glare screen with rectangular vane of MS


sheet, Providing and erecting anti - glare screen with rectangular vanes of size
750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50
x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m center to
9.24 meter 0 2837.09 0
center, top edge of the screen 1.75 m above ground level, vertical post firmly
embedded in M-15 cement concrete foundation 0.60 m below ground level,
applying 2 coats of paint on exposed faces, all complete as per design , Drawing
and Technical Specifications.

Street Lighting, Providing and erecting street light mounted on a steel circular
hollow pole of standard specifications for street lighting, 9 m high spaced 40 m
9.25 apart, 1.8 m overhang on both sides if fixed in the median and on one side if no 0 3417.84 0
fixed on the footpath, fitted with sodium vapor lamp and fixed firmly in concrete
foundation as per design , Drawing and Technical Specifications..

Rumble Strips, Providing and making of Rumble strips with premix bituminous
carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at
approved locations to control speed, marked with white strips of road marking
9.26 paint., Provision of 15 Nos rumble strips covered with premix bituminous carpet, sqm 0 0 0
15-20 mm high at center, 250 mm wide placed at 1 m center to center at
approved locations to control speed, marked with white strips of road marking
paint.

Lettering new Letter and Figures of any Shade, Providing and lettering new letter
9.27 and figures of any shade with synthetic enamel paint black or any other approved cm-letter 0 3.75 0
color to give an even shade, Nepali
Lettering new Letter and Figures of any Shade, Providing and lettering new letter
9.28 and figures of any shade with synthetic enamel paint black or any other approved cm-letter 0 2.37 0
color to give an even shade, English and Roman

10 Falsework formwork
Providing , Preparing and Installing form work including necessary supports and
10.1 removing after completion for foundation and footings., (Class F1 Finish), Using sqm 0 532.59 0
timber (soft wood )
Providing , Preparing and Installing form work including necessary supports and
10.2 removing after completion for foundation and footings., (Class F1 Finish), Using sqm 0 2528.36 0
steel
Providing , Preparing and Installing form work including necessary supports and
10.3 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 1810.72 0
Using timber (soft wood ), Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
10.4 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 2241.76 0
Using timber (soft wood ), Height above 3 m to 6 m
Providing , Preparing and Installing form work including necessary supports and
10.5 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 2734.9 0
Using timber (soft wood ), Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
10.6 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 0 0
Using timber (soft wood ), Height above 9 m
Providing , Preparing and Installing form work including necessary supports and
10.7 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 2529.55 0
Using steel, Height upto
Providing , Preparing and Installing form work including necessary supports and
10.8 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 2608.11 0
Using steel, Height above 3 m to 6 m
Providing , Preparing and Installing form work including necessary supports and
10.9 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 2740.51 0
Using steel, Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
10.10 removing after completion for walls., (Class F2 Finish), vertical plain surface, sqm 0 0 0
Using steel, Height above 9 m
Providing , Preparing and Installing form work including necessary supports and
10.11 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 13569.96 0
using timber, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
10.12 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 16272.64 0
using timber, Height above 3m to 6 m
Providing , Preparing and Installing form work including necessary supports and
10.13 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 20352.86 0
using timber, Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
10.14 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 0 0
using timber, Height above 9 m

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 16 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing , Preparing and Installing form work including necessary supports and
10.15 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 2638.08 0
using steel, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
10.16 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 2741.83 0
using steel, Height above 3 m to 6 m
Providing , Preparing and Installing form work including necessary supports and
10.17 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 2925.88 0
using steel, Height above 6 m to 9 m
Providing , Preparing and Installing form work including necessary supports and
10.18 removing after completion for walls., (Class F2 Finish), Vertical curve surface, sqm 0 0 0
using steel, Height more than above 9 m
Providing , Preparing and Installing form work including necessary supports and
10.19 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 11366.37 0
surface, Using timber, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
10.20 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 13633.45 0
surface, Using timber, Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
10.21 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 17040.42 0
surface, Using timber, Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
10.22 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 0 0
surface, Using timber, Above 9 m
Providing , Preparing and Installing form work including necessary supports and
10.23 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 2913.13 0
surface, Using steel, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
10.24 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 2998.88 0
surface, Using steel, Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
10.25 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 3160.79 0
surface, Using steel, Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
10.26 removing after completion for columns, (Class F3 Finish), Square / Rectangular sqm 0 0 0
surface, Using steel, Above 9 m
Providing , Preparing and Installing form work including necessary supports and
10.27 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 16923.12 0
Using timber, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
10.28 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 22447.42 0
Using timber, Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
10.29 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 26992.24 0
Using timber, Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
10.30 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 0 0
Using timber, Above 9 m
Providing , Preparing and Installing form work including necessary supports and
10.31 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 3032.46 0
Using steel, Height upto 3 m
Providing , Preparing and Installing form work including necessary supports and
10.32 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 3155.85 0
Using steel, Height upto 3 m to 6m
Providing , Preparing and Installing form work including necessary supports and
10.33 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 3154.02 0
Using steel, Height upto 6 m to 9m
Providing , Preparing and Installing form work including necessary supports and
10.34 removing after completion for columns, (Class F3 Finish), Circular surface, sqm 0 0 0
Using steel, Above 9 m
Providing , Preparing and Installing form work including necessary supports and
10.35 removing after completion for slab structure., Class F2 Finish, False work not sqm 0 693.27 0
included, Using timber
Providing , Preparing and Installing form work including necessary supports and
10.36 removing after completion for slab structure., Class F2 Finish, False work not sqm 0 2853.26 0
included, Using steel
Providing , Preparing and Installing form work including necessary supports and
10.37 removing after completion for slab structure., Class F2 Finish, False work not sqm 0 474.24 0
included, Using shuttering Ply
Providing , Preparing and Installing form work including necessary supports and
10.38 removing after completion for slab & beam structure., Class F2 Finish, False sqm 0 1028.08 0
work not included, Using timber
Providing , Preparing and Installing form work including necessary supports and
10.39 removing after completion for slab & beam structure., Class F2 Finish, False sqm 0 3371.6 0
work not included, Using steel
Providing , Preparing and Installing form work including necessary supports and
10.40 removing after completion for slab & beam structure., Class F2 Finish, False sqm 0 625.39 0
work not included, Using shuttering Ply
Providing , Preparing and Installing form work including necessary supports and
10.41 removing after completion for arch structure., Class F2 Finish, False work not sqm 0 742.05 0
included, Using timber
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
Abstract of Cost Page 17 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing , Preparing and Installing form work including necessary supports and
10.42 removing after completion for arch structure., Class F2 Finish, False work not sqm 0 3423.35 0
included, Using steel
Providing , Preparing and Installing form work including necessary supports and
10.43 removing after completion for precast element., Class F3 Finish, Square / sqm 0 4843.31 0
Rectangular section, Using timber
Providing , Preparing and Installing form work including necessary supports and
10.44 removing after completion for precast element., Class F3 Finish, Square / sqm 0 3302.6 0
Rectangular section, Using steel
Providing , Preparing and Installing form work including necessary supports and
10.45 removing after completion for precast element., Class F3 Finish, Circular sqm 0 4942.72 0
section, Using timber
Providing , Preparing and Installing form work including necessary supports and
10.46 removing after completion for precast element., Class F3 Finish, Circular sqm 0 3359.5 0
section, Using steel
Providing and assembling in position falsework for the construction of RCC
10.47 superstructure and removing after completion including design & drawings as sqm 0 3565.03 0
per specification For Slab and Box culverts, Using timber, Height upto 2 m
Providing and assembling in position falsework for the construction of RCC
superstructure and removing after completion including design & drawings as
10.48 sqm 0 6716.88 0
per specification For Slab and Box culverts, Using timber, Height above 2 m to 4
m
Providing and assembling in position falsework for the construction of RCC
superstructure and removing after completion including design & drawings as
10.49 sqm 0 9599.7 0
per specification For Slab and Box culverts, Using timber, Height above 4 m to 6
m

Providing and assembling in position falsework for the construction of RCC


10.50 superstructure and removing after completion including design & drawings as 0 0 0
per specification For Slab and Box culverts, Using timber, For Height above 6 m

Providing and assembling in position falsework for the construction of RCC


10.51 superstructure and removing after completion including design & drawings as sqm 0 82830.64 0
per specification For Slab and Box culverts, Using steel, Height upto 2 m
Providing and assembling in position falsework for the construction of RCC
superstructure and removing after completion including design & drawings as
10.52 sqm 0 83695.47 0
per specification For Slab and Box culverts, Using steel, Height above 2 m to 4
m
Providing and assembling in position falsework for the construction of RCC
superstructure and removing after completion including design & drawings as
10.53 sqm 0 84793.22 0
per specification For Slab and Box culverts, Using steel, Height above 4 m to 6
m
Providing and assembling in position falsework for the construction of RCC
10.54 superstructure and removing after completion including design & drawings as sqm 0 0 0
per specification For Slab and Box culverts, Using steel, Height above 6 m
Providing and assembling in position falsework for the construction of RCC
10.55 superstructure and removing after completion including design & drawings as sqm 0 7874.3 0
per specification, for RCC Beam Bridge, Using timber, Height upto 3 m

Providing and assembling in position falsework for the construction of RCC


10.56 superstructure and removing after completion including design & drawings as sqm 0 16024.59 0
per specification, for RCC Beam Bridge, Using timber, Height above 3 m to 6 m

Providing and assembling in position falsework for the construction of RCC


10.57 superstructure and removing after completion including design & drawings as sqm 0 26697.54 0
per specification, for RCC Beam Bridge, Using timber, Height above 6 m to 9 m

, Height above 9 m Increase the rate by 10% for every additional meter height to
10.58 0 0 0
the rate for the previous height or Design as a special case and derive Norms

Providing and assembling in position falsework for the construction of RCC


10.59 superstructure and removing after completion including design & drawings as sqm 0 83516.77 0
per specification, for RCC Beam Bridge, Using steel, Height upto 3 m

Providing and assembling in position falsework for the construction of RCC


10.60 superstructure and removing after completion including design & drawings as sqm 0 85360.54 0
per specification, for RCC Beam Bridge, Using steel, Height above 3 m to 6m

Providing and assembling in position falsework for the construction of RCC


10.61 superstructure and removing after completion including design & drawings as sqm 0 87210.87 0
per specification, for RCC Beam Bridge, Using steel, Height above 3 m to 6m

, Height above 9 m Increase the rate by 10% for every additional meter height to
10.62 0 0 0
the rate for the previous height or Design as a special case and derive Norms

Providing and assembling in position falsework for the construction of RCC


10.63 superstructure and removing after completion including design & drawings as sqm 0 6241.26 0
per specification, for RCC Arch Bridge, Using timber, Height upto 3 m

Providing and assembling in position falsework for the construction of RCC


10.64 superstructure and removing after completion including design & drawings as sqm 0 12758.53 0
per specification, for RCC Arch Bridge, Using timber, Height above 3m to 6 m

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 18 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)

Providing and assembling in position falsework for the construction of RCC


10.65 superstructure and removing after completion including design & drawings as sqm 0 20564.63 0
per specification, for RCC Arch Bridge, Using timber, Height above 6 m to 9 m

Providing and assembling in position falsework for the construction of RCC


10.66 superstructure and removing after completion including design & drawings as 0 0 0
per specification, for RCC Arch Bridge, Using timber, Height above 9 m
Providing and assembling in position falsework for the construction of RCC
10.67 superstructure and removing after completion including design & drawings as sqm 0 83719.9 0
per specification, for RCC Arch Bridge, Using steel, Height upto 3 m

Providing and assembling in position falsework for the construction of RCC


10.68 superstructure and removing after completion including design & drawings as sqm 0 85628.79 0
per specification, for RCC Arch Bridge, Using steel, Height above 3 m to 6 m

Providing and assembling in position falsework for the construction of RCC


10.69 superstructure and removing after completion including design & drawings as sqm 0 88244.54 0
per specification, for RCC Arch Bridge, Using steel, Height above 6 m to 9 m

Providing and assembling in position falsework for the construction of RCC


10.70 superstructure and removing after completion including design & drawings as 0 0 0
per specification, for RCC Arch Bridge, Using steel, Height above 9 m

11 Concrete
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix)
11.1 cum 0 8736.82 0
in Foundation complete as per Drawing and Technical Specifications.
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix)
11.2 in Foundation complete as per Drawing and Technical Specifications., Manual cum 0 8552.36 0
Mixing
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.3 cum 0 10104.26 0
complete as per Drawing and Technical Specifications, PCC Grade M 15
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.4 complete as per Drawing and Technical Specifications, PCC Grade M 15, cum 0 10138.3 0
Manual Mixing
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.5 cum 0 11514.45 0
complete as per Drawing and Technical Specifications, PCC Grade M 20
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.6 cum 0 11607.41 0
complete as per Drawing and Technical Specifications., RCC Grade M 20
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.7 cum 0 12872.99 0
complete as per Drawing and Technical Specifications., PCC Grade M 25
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.8 cum 0 12981.66 0
complete as per Drawing and Technical Specifications., RCC Grade M 25
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.9 cum 0 15094.79 0
complete as per Drawing and Technical Specifications., PCC Grade M 30
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.10 cum 0 13050.66 0
complete as per Drawing and Technical Specifications., RCC Grade M30
Providing and laying of Plain/Reinforced Cement Concrete in Foundation
11.11 cum 0 13368.06 0
complete as per Drawing and Technical Specifications., RCC Grade M 35

Providing and laying , fitting and placing un-coated Mild steel / HYSD
11.12 tonne 0 126408 0
reinforcement complete in foundation as per drawing and technical specification

Providing and laying of Plain/Reinforced cement concrete in sub-structure


11.13 complete as per drawing and Technical Specifications, PCC Grade M 15, Height cum 0 10104.26 0
upto 5 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.14 complete as per drawing and Technical Specifications, PCC Grade M 30, Height cum 0 15094.79 0
above 5 m to 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.15 complete as per drawing and Technical Specifications, PCC Grade M 30, Height cum 0 15094.79 0
above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.16 complete as per drawing and Technical Specifications, RCC Grade M 20, Height cum 0 11607.41 0
upto 5 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.17 complete as per drawing and Technical Specifications, RCC Grade M 20, Height cum 0 11607.41 0
above 5 m to 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.18 complete as per drawing and Technical Specifications, RCC Grade M 20, Height cum 0 11607.41 0
above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.19 complete as per drawing and Technical Specifications, RCC Grade M 25, Height cum 0 12981.66 0
upto 5 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.20 complete as per drawing and Technical Specifications, RCC Grade M 25, Height cum 0 12981.66 0
above 5 m to 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.21 complete as per drawing and Technical Specifications, RCC Grade M 25, Height cum 0 12981.66 0
above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.22 complete as per drawing and Technical Specifications, RCC Grade M 30, Height cum 0 13050.66 0
upto 5 m

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 19 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.23 complete as per drawing and Technical Specifications, RCC Grade M 30, Height cum 0 13050.66 0
above 5 m to 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.24 complete as per drawing and Technical Specifications, RCC Grade M 30, Height cum 0 13050.66 0
above 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.25 complete as per drawing and Technical Specifications, RCC Grade M 35, Height cum 0 13368.06 0
upto 5 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.26 complete as per drawing and Technical Specifications, RCC Grade M 35, Height cum 0 13368.06 0
above 5 m to 10 m
Providing and laying of Plain/Reinforced cement concrete in sub-structure
11.27 complete as per drawing and Technical Specifications, RCC Grade M 35, Height cum 0 13368.06 0
above 10 m
Providing and laying , fitting and placing HYSD bar reinforcement in sub-
11.28 tonne 0 126408 0
structure complete as per Drawing and Technical Specifications
Providing and laying ,fitting and placing Mild steel reinforcement complete in
11.29 tonne 0 132434 0
sub-structure as per drawing and Technical Specification
Providing and laying weep holes in Brick dry/Plain/ Reinforced concrete
abutment, wing wall/ return wall with 110 mm dia HDPE pipe, extending
11.30 meter 0 750.11 0
through the full width of the structure with slope of 1V :20H towards drawing
face Complete as per Drawing and Technical Specifications.

Providing and laying weep holes in Stone Masonry/Plain/ Reinforced concrete


abutment, wing wall/ return wall with 150mm dia HDPE pipe, extending through
11.31 meter 0 1182.21 0
the full width of the structure with slope of 1V :20H towards drawing face
Complete as per Drawing and Technical Specifications.

Providing and laying of Reinforced/ Pre-stressed cement concrete in super-


11.32 meter 0 5751 0
structure as per drawing and Technical Specification, RCC Grade M 20
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.33 super-structure as per drawing and Technical Specification, RCC Grade M 20, meter 0 5751 0
Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.34 super-structure as per drawing and Technical Specification, RCC Grade M 20, meter 0 5751 0
Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.35 super-structure as per drawing and Technical Specification, RCC Grade M 20, meter 0 5751 0
Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.36 slab super-structure as per drawing and Technical Specification, RCC Grade M meter 0 5751 0
20, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.37 slab super-structure as per drawing and Technical Specification, RCC Grade M meter 0 5751 0
20, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.38 slab super-structure as per drawing and Technical Specification, RCC Grade M meter 0 5751 0
20, Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-
11.39 cum 0 12898.86 0
structure as per drawing and Technical Specification, RCC Grade M 25
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.40 super-structure as per drawing and Technical Specification, RCC Grade M 25, cum 0 12898.86 0
Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.41 super-structure as per drawing and Technical Specification, RCC Grade M 25, cum 0 12898.86 0
Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.42 super-structure as per drawing and Technical Specification, RCC Grade M 25, cum 0 16768.52 0
Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.43 slab super-structure as per drawing and Technical Specification, RCC Grade M cum 0 16123.58 0
25, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.44 slab super-structure as per drawing and Technical Specification, RCC Grade M cum 0 12898.86 0
25, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.45 slab super-structure as per drawing and Technical Specification, RCC Grade M cum 0 12898.86 0
25, Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-
11.46 cum 0 13142.66 0
structure as per drawing and Technical Specification, RCC Grade M 30
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.47 super-structure as per drawing and Technical Specification, RCC Grade M 30, cum 0 13142.66 0
Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.48 super-structure as per drawing and Technical Specification, RCC Grade M 30, cum 0 13142.66 0
Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.49 super-structure as per drawing and Technical Specification, RCC Grade M 30, cum 0 13142.66 0
Height above 10 m

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 20 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.50 slab super-structure as per drawing and Technical Specification, RCC Grade M cum 0 13142.66 0
30, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.51 slab super-structure as per drawing and Technical Specification, RCC Grade M cum 0 13142.66 0
30, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.52 slab super-structure as per drawing and Technical Specification, RCC Grade M cum 0 13142.66 0
30, Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-
11.53 cum 0 13460.06 0
structure as per drawing and Technical Specification, RCC/PSC Grade M 35
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.54 super-structure as per drawing and Technical Specification, RCC/PSC Grade M cum 0 13460.06 0
35, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.55 super-structure as per drawing and Technical Specification, RCC/PSC Grade M cum 0 13460.06 0
35, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab
11.56 super-structure as per drawing and Technical Specification, RCC/PSC Grade M cum 0 13460.06 0
35, Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.57 slab super-structure as per drawing and Technical Specification, RCC/PSC cum 0 13460.06 0
Grade M 35, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.58 slab super-structure as per drawing and Technical Specification, RCC/PSC cum 0 13460.06 0
Grade M 35, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.59 slab super-structure as per drawing and Technical Specification, RCC/PSC cum 0 13460.06 0
Grade M 35, Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder
11.60 and balanced cantilever super-structure as per drawing and Technical cum 0 13460.06 0
Specification, RCC/PSC Grade M 35, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder
11.61 and balanced cantilever super-structure as per drawing and Technical cum 0 13460.06 0
Specification, RCC/PSC Grade M 35, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder
11.62 and balanced cantilever super-structure as per drawing and Technical cum 0 13460.06 0
Specification, RCC/PSC Grade M 35, Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-
11.63 cum 0 13740.66 0
structure as per drawing and Technical Specification, PSC Grade M-40
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab
11.64 super-structure as per drawing and Technical Specification, PSC Grade M-40, cum 0 13740.66 0
Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab
11.65 super-structure as per drawing and Technical Specification, PSC Grade M-40, cum 0 13740.66 0
Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab
11.66 super-structure as per drawing and Technical Specification, PSC Grade M-40, cum 0 13740.66 0
Height above 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.67 slab super-structure as per drawing and Technical Specification, PSC Grade M- cum 0 13740.66 0
40, Height upto 5 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.68 slab super-structure as per drawing and Technical Specification, PSC Grade M- cum 0 13740.66 0
40, Height above 5 m to 10 m
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and
11.69 slab super-structure as per drawing and Technical Specification, PSC Grade M- cum 0 13740.66 0
40, Height above 10 m
Providing and laying , fitting and placing HYSD bar reinforcement in super-
11.70 tonne 0 128478 0
structure complete as per drawing and technical specifications
Providing and laying of PCC M 15 Grade leveling course below approach slab
11.71 cum 0 10104.26 0
complete as per drawing and Technical specification
Providing and laying of Reinforced cement concrete approach slab including
11.72 reinforcement and formwork complete as per drawing and Technical cum 0 18031.31 0
specification
Providing and laying Cement concrete wearing coat M-30 grade including
11.73 cum 0 26778.9 0
reinforcement complete as per drawing and Technical Specifications

12 Brickwork
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
12.1 structure complete excluding Pointing and Plastering, as per Drawing and cum 0 12793.87 0
Technical Specifications., Cement sand mortar (1:4)
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
12.2 structure complete excluding Pointing and Plastering, as per Drawing and cum 0 12442.31 0
Technical Specifications., Cement sand mortar (1:4), Using Concrete Mixer
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
12.3 structure complete excluding Pointing and Plastering, as per Drawing and cum 0 12287.41 0
Technical Specifications., Cement sand mortar (1:6)
Providing and laying Brick Masonry Work in Cement mortar in Foundation /
12.4 structure complete excluding Pointing and Plastering, as per Drawing and cum 0 11935.85 0
Technical Specifications., Cement sand mortar (1:6), Using Concrete Mixer
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
Abstract of Cost Page 21 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing and laying Brick masonry work in superstructure/ sub-structure
12.5 complete excluding pointing and plastering, as per drawing and Technical cum 0 13940.71 0
Specifications, Cement Mortar 1:4 (1 cement : 4 sand)

Providing and laying Brick masonry work in superstructure/ sub-structure


12.6 complete excluding pointing and plastering, as per drawing and Technical cum 0 13568.45 0
Specifications, Cement Mortar 1:4 (1 cement : 4 sand), Using Concrete Mixer

Providing and laying Brick masonry work in superstructure/ sub-structure


12.7 complete excluding pointing and plastering, as per drawing and Technical cum 0 13408.93 0
Specifications, Cement Mortar 1:6 (1 cement : 6 sand)

Providing and laying Brick masonry work in superstructure/ sub-structure


12.8 complete excluding pointing and plastering, as per drawing and Technical cum 0 13036.67 0
Specifications, Cement Mortar 1:6 (1 cement : 6 sand), Using Concrete Mixer

Providing, and applying Pointing with cement mortar (1:3 ) on brick work in
12.9 sqm 0 223.77 0
structure as per Technical Specifications .
Providing and applying 12.5 mm thick Plaster with cement mortar on brick
12.10 work structure as per Technical Specifications , Cement Mortar 1:2 (1 cement : 2 sqm 0 3924.65 0
sand)
Providing and applying 12.5 mm thick Plaster with cement mortar on brick
12.11 work structure as per Technical Specifications , Cement Mortar 1:2 (1 cement : 2 sqm 0 3817.87 0
sand), Using Concrete Mixer
Providing and applying 12.5 mm thick Plaster with cement mortar on brick
12.12 work structure as per Technical Specifications , Cement Mortar 1:3 (1 cement : 3 sqm 0 3447.13 0
sand)
Providing and applying 12.5 mm thick Plaster with cement mortar on brick
12.13 work structure as per Technical Specifications , Cement Mortar 1:3 (1 cement : 3 sqm 0 334.03 0
sand), Using Concrete Mixer
Providing and applying 12.5 mm thick Plaster with cement mortar on brick
12.14 work structure as per Technical Specifications , Cement Mortar 1:4 (1 cement : 4 sqm 0 317.24 0
sand)
Providing and applying 12.5 mm thick Plaster with cement mortar on brick
12.15 work structure as per Technical Specifications , Cement Mortar 1:4 (1 cement : 4 sqm 0 306.56 0
sand), Using Concrete Mixer
Providing and laying weep holes in Brick works / Masonry/ Plain/ Reinforced
12.16 concrete abutment, wing wall/ return wall with 100 mm dia HDPE pipe as per meter 0 132.4 0
Drawing and Technical Specifications.

13 Masonary
Providing and laying of dry Stone Masonry Work as per Drawing and Technical
13.1 cum 0 6333.28 0
Specifications
Random Rubble Masonry, Providing and laying of Stone Masonry Work in
13.2 Cement Mortar 1:4 in Foundation complete as per Drawing and Technical cum 0 10830.98 0
Specifications.
Random Rubble Masonry, Providing and laying of Stone Masonry Work in
13.3 Cement Mortar 1:4 in Foundation complete as per Drawing and Technical cum 0 10034.37 0
Specifications., Using Concrete Mixer
Random Rubble Masonry, Providing and laying of Stone Masonry Work in
13.4 Cement Mortar 1:6 in Foundation complete as per Drawing and Technical cum 0 10034.76 0
Specifications.
Random Rubble Masonry, Providing and laying of Stone Masonry Work in
13.5 Cement Mortar 1:6 in Foundation complete as per Drawing and Technical cum 0 9407.21 0
Specifications., Using Concrete Mixer
Providing and laying Stone Masonry work in cement mortar 1:4 in structure
13.6 cum 0 12252.86 0
complete as per Drawing and Technical, Random Rubble Masonry
Providing and laying Stone Masonry work in cement mortar 1:4 in structure
13.7 complete as per Drawing and Technical, Random Rubble Masonry, Using cum 0 11590.81 0
Concrete Mixer
Providing and laying Stone Masonry work in cement mortar 1:4 in structure
13.8 cum 0 12476.47 0
complete as per Drawing and Technical, Coursed rubble Masonry (first sort )
Providing and laying Stone Masonry work in cement mortar 1:4 in structure
13.9 complete as per Drawing and Technical, Coursed rubble Masonry (first sort ), cum 0 11814.41 0
Using Concrete Mixer
Providing and laying Stone Masonry work in cement mortar 1:6 in structure
13.10 complete as per Drawing and Technical Specifications, Random Rubble cum 0 11515.06 0
Masonry (coursed/uncoursed)
Providing and laying Stone Masonry work in cement mortar 1:6 in structure
13.11 complete as per Drawing and Technical, Random Rubble Masonry, Using cum 0 10853 0
Concrete Mixer
Providing and laying Stone Masonry work in cement mortar 1:6 in structure
13.12 complete as per Drawing and Technical Specifications, Coursed rubble Masonry cum 0 11821.43 0
(first sort )
Providing and laying Stone Masonry work in cement mortar 1:4 in structure
13.13 complete as per Drawing and Technical, Coursed rubble Masonry (first sort ), cum 0 11159.37 0
Using Concrete Mixer
Providing and Pointing with cement mortar on masonry work in structure as per
13.14 sqm 0 223.16 0
Technical Specifications, cement mortar (1:3 )
Providing and Pointing with cement mortar on masonry work in structure as per
13.15 sqm 0 219.38 0
Technical Specifications, cement mortar (1:3 ), Using Concrete Mixer
Providing and Pointing with cement mortar on masonry work in structure as per
13.16 sqm 0 240.77 0
Technical Specifications, cement mortar (1:2 )
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
Abstract of Cost Page 22 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing and Pointing with cement mortar on masonry work in structure as per
13.17 sqm 0 237 0
Technical Specifications, cement mortar (1:2 ), Using Concrete Mixer

14 River Training
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.1 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 7320.19 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 3 X 1 X 1 m ( 16 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.2 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 7397.56 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 2 X 1 X 1 m ( 11 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.3 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 7722.86 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 1.5 X 1 X 1 m ( 9 sqm )
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.4 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 7734.57 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 1.0 X 1 X 1 m ( 6 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m)
14.5 cum 0 7626.66 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 3.0 X 1 X 0 .75 m ( 13.5
sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m)
14.6 cum 0 7762.71 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 2.0 X 1 X 0 .75 m ( 9. 25
sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m)
14.7 cum 0 8009.32 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 1.0 X 1 X 0 .75 m ( 5 sqm
m)

Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),


14.8 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 8147.24 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 3.0 X 1 X 0 .5 m ( 11 sqm)

Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),


Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m)
14.9 cum 0 8345.48 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 2.0 X 1 X 0 .5 m ( 7.5 sqm
m)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.10 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 8781.91 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 1 X 1 X 0 .5 m (4 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.11 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 9381.12 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 3 X 1 X 0 .3 m ( 9 sqm)

Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),


14.12 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 9285.98 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 2 X 1 X 0 .3 m ( 6.1 sqm)

Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),


14.13 Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) cum 0 8621 0
Hexagonal mesh Type 100 mm X 120 mm,, Box size 1 X 1 X 0 .3 m ( 2.2 sqm)

Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),


14.14 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 7720.5 0
mesh Type 80 mm X 100 mm,, Box size 3 X 1 X 1 m ( 16 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.15 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 7804.81 0
mesh Type 80 mm X 100 mm,, Box size 2 X 1 X 1 m ( 11 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.16 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 8047.12 0
mesh Type 80 mm X 100 mm,, Box size 1.5 X 1 X 1 m ( 9 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.17 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 8059.01 0
mesh Type 80 mm X 100 mm,, Box size 1 X 1 X 1 m (6 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.18 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 8485.58 0
mesh Type 80 mm X 100 mm,, Box size 3.0 X 1 X 0 .75 m (13.5 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.19 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 8095.63 0
mesh Type 80 mm X 100 mm,, Box size 2.0 X 1 X 0 .75 m ( 9.25 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.20 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 8476.73 0
mesh Type 80 mm X 100 mm,, Box size 1.0 X 1 X 0 .75 m ( 5 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.21 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 8653.05 0
mesh Type 80 mm X 100 mm,, Box size 3.0 X 1 X 0 .5 m ( 11 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.22 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 8762.56 0
mesh Type 80 mm X 100 mm,, Box size 2.0 X 1 X 0 .5 m ( 7.5 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.23 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 55001.35 0
mesh Type 80 mm X 100 mm,, Box size 1 X 1 X 0 .5 m ( 4 sqm)

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 23 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.24 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 10038.04 0
mesh Type 80 mm X 100 mm,, Box size 3 X 1 X 0 .3 m ( 9 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.25 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 10241.33 0
mesh Type 80 mm X 100 mm,, Box size 2 X 1 X 0 .3 m ( 6.1 sqm)
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m),
14.26 Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal cum 0 9272.05 0
mesh Type 80 mm X 100 mm,, Box size 1 X 1 X 0 .3 m ( 2.2 sqm)
Providing mechanically woven double twisted crates / mattress including
rolling, cutting and with lacing wire and binding wire as per specification.
14.27 sqm 0 198.38 0
, Hexagonal mesh type 100 mm x 120 mm, mesh wire 3 mm, selvage wire 3.9
mm, lacing wire 2.4 mm
Providing mechanically woven double twisted crates / mattress including
rolling, cutting and with lacing wire and binding wire as per specification.
14.28 sqm 0 264.5 0
, Hexagonal mesh type 100 mm x 120 mm, mesh wire 2.7 mm, selvage wire
3.4 mm, lacing wire 2.2 mm
Providing mechanically woven double twisted crates / mattress including
rolling, cutting and with lacing wire and binding wire as per specification.
14.29 sqm 0 0 0
, Hexagonal mesh type 80 mm x 100 mm, mesh wire 3 mm, selvage wire 3.9
mm, lacing wire 2.4 mm
Providing mechanically woven double twisted crates / mattress including
rolling, cutting and with lacing wire and binding wire as per specification.
14.30 sqm 0 264.5 0
, Hexagonal mesh type 80 mm x 100 mm, mesh wire 2.7 mm, selvage wire 3.4
mm, lacing wire 2.2 mm
Providing mechanically woven double twisted crates / mattress including
rolling, cutting and with lacing wire and binding wire as per specification.
14.31 sqm 0 0 0
, Hexagonal mesh type 60 mm x 80 mm, mesh wire 2.7 mm, selvage wire 3.4
mm, lacing wire 2.2 mm
Providing mechanically woven double twisted crates / mattress including
rolling, cutting and with lacing wire and binding wire as per specification.

14.32 sqm 0 264.5 0


, Zinc + PVC coated Hexagonal mesh type 100 mm x 120 mm, mesh wire 2.7
mm/3.7 mm, selvage wire 3.4 mm/4.4 mm, lacing wire 2.2 mm/3.2 mm with Pac
coating thickness nominal 0.5 mm ( minimum 0.38 mm)
Providing mechanically woven double twisted crates / mattress including
rolling, cutting and with lacing wire and binding wire as per specification.

14.33 sqm 0 264.5 0


, Zinc + PVC coated Hexagonal mesh type 80 mm x 100 mm, mesh wire 2.2
mm/3.2 mm, selvage wire 2.7 mm/3.7 mm, lacing wire 2.2 mm/3.2 mm with Pac
coating thickness nominal 0.5 mm ( minimum 0.38 mm)
Assembling mechanical woven Gabion boxes /mattresses, placing in position
including stretching; forming compartments; tying the sides and diaphragms with
14.34 sqm 0 56.06 0
binding wire in each mesh; tying with bracing wires and tie wires; and tying
down the lid complete as per specification (stone filling not included
Providing and filling stone/boulder in gabion boxes/mattress etc.. Including
14.35 dressing, bedding, bonding all complete as per Drawing and Technical cum 0 4968.92 0
Specifications.
Laying and fixing of Geo-Textile all complete as per specification., Providing
14.36 and laying of a geotextile filter between pitching and embankment slopes as per sqm 0 #VALUE! #VALUE!
Drawing and Technical Specifications.

Laying and fixing of Geo-Textile all complete as per specification., Providing


14.37 sqm 0 #VALUE! #VALUE!
and laying and fixing of Geo-membrane all complete as per specification.

GEOSYNTHETIC AND REINFORCED EARTH, Sub-Surface Drain with


Geotextiles, Providing and laying sub surface drain 200 mm dia using geotextiles
14.38 treated with carbon black to a stable network and a planar geo-composite meter 0 #VALUE! #VALUE!
structure, joints wrapped with geotextile to prevent ingress of soil, including
excavation and backfilling as per Drawing and Technical Specifications.

Narrow Filter Sub-Surface Drain, Providing and making narrow filter sub-
surface drain consisting of porous or perforated pipe laid in narrow trench
14.39 meter 0 #VALUE! #VALUE!
surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of
fabric and installed including excavation and backfilling
Laying Paving Fabric Beneath a Pavement Overlay, Providing and laying paving
fabric over a tack coat of paving grade Bitumen, laid at the rate of 1 kg per sqm
14.40 over thoroughly cleaned and repaired surface to provide a water resistant sqm 0 115.97 0
membrane and crack retarding layer as per Drawing and Technical
Specifications.
Laying Boulder Apron in Crates of Synthetic Geogrids, Providing and laying of
Geogrids crated apron 1 m x 5 m, 600 mm thick with baffles at 1 meter interval,
14.41 cum 0 #VALUE! #VALUE!
made with Geogrids as per Design, Drawing and Technical specifications.
design.
Providing and laying HDPE pipes with perforations including joining, series II,
14.42 meter 0 2358.66 0
HDPE pipe 200 mm dia

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Abstract of Cost Page 24 of 276
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
[Branch/Directorate/FHSMO]
[Division/Project Office]

Abstract Of Cost
Contract Identification No :
BH No :
Nature of the work :
Name of Road :
Rate Amount
S.N. Description of Works Unit Quantity Remarks
(NRs) (NRs)
Providing and laying HDPE pipes with perforations including joining, series II,
14.43 meter 0 1349.21 0
HDPE pipe 160 mm dia
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing
14.44 and Specifications, 60% M 15 concrete and 40% boulders/stones, using cum 0 9120.33 0
Mechanical Aids

Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing
14.45 cum 0 10519.84 0
and Specifications, 60% M 15 concrete and 40% boulders/stones, Manual means

Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing
14.46 and Specifications, 70% M 15 concrete and 30% boulders/stones, Using cum 0 9515.43 0
Mechanical Aids

Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing
14.47 cum 0 1095.93 0
and Specifications, 70% M 15 concrete and 30% boulders/stones, Manual means

Sub-Surface Drains with Perforated Pipe, Providing and laying subsurface drain
with perforated pipe of 100 mm internal diameter of metal/ asbestos cement/
cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm
14.48 meter 0 #NAME? #NAME?
depending upon size of material surrounding the pipe, with 150 mm bedding
below the pipe and 300 mm cushion above the pipe,. as per Drawing and
Specifications.
Aggregate Sub-Surface Drains, Providing and laying aggregate sub surface drain
14.49 300 mm x 450 mm with aggregates conforming to table 300-4, excavated meter 0 #NAME? #NAME?
material to be utilized in roadway.
Underground Drain at Edge of Pavement, Providing and laying an underground
14.50 drain 1 m x 1 m (inside dimensions) lined with RCC-20 cm thick and covered meter 0 17970.74 0
with RCC slab 10 cm in thickness on urban roads.

Total (Excl. VAT & Contin.) #VALUE!


Provisional Sum 0
VAT (13%) #VALUE!
Contingency (5%) #VALUE!
Provision for Price Escalation (10%) #VALUE!
Physical Contingency (10%) #VALUE!
GRAND TOTAL #VALUE!

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District Rates Page 1 of 276
1) District rates MAHOTTARI 2078/79: Materials
District
District Rate
S.N. Description Unit Transportation Adopted Rate Remarks Page No:
(D)
(Dt)

1 ac_pipe_100_mm_dia meter 0.000 0 0.00


2 ac_pipe_collar nos 0.000 0 0.00
3 admixture kg 125.000 0 125.00 8
4 aggregate_10_20_mm cum 1725.000 0.00 1725.00
5 aggregate_10_mm cum 1800.000 0.00 1800.00
6 aggregate_13.2_mm cum 1725.000 0.00 1725.00
7 aggregate_20_40_mm cum 1700.000 0.00 1700.00
8 aggregate_20_mm cum 1725.000 0.00 1725.00
9 aggregate_40_70_mm cum 1150.000 0.00 1150.00
10 aggregate_40_75_mm cum 1150.000 0.00 1150.00
11 aggregate_10_mm cum 1800.000 0.00 1800.00
aluminum_alloy_plate
12 sqm 0.000 0 0.00
_2_mm
13 anti_stripping_agent kg 320.000 0 320.00
14 binding_wire kg 140.000 0 140.00 sarlahi 18

15 bitumen tonne 77600.000 77600.00 ktm rate

borrow_pit_material
16 cum 400.000 400.00
soil
17 bricks nos 12.000 0 12.00
18 bricks_1st_class nos 12.000 12.00
19 capping_layer cum 550.800 0 0.00 ktm rate
20 cats_eye nos. 1025.000 0 0.00
21 cement tonne 17500.000 17500.00
22 clamps nos. 46.800 0 46.80 hold fast
concrete_block_footpa
23 sqm 915.353 0 915.35
th 40 mm
concrete M20
ktm rate page
24 _block_kerb stone - nos 279.467 0 279.47
30
380*200*250
25 concrete_channel nos. 0.000 0 0.00
26 cutback_bitumen tonne 78100.000 78100.00 ktm rate
27 diesel litre 101.500 0 101.50 net
28 electric_detonator nos 0.000 0 0.00
29 electricity kWh 8.140 0 8.14 net
30 emulsion tonne 63600.000 63600.00
31 filter_material cum 1250.000 0 1250.00
32 fuse_wire_blasting m 0.000 0 0.00
Gabion_100x120_MW
33 2.7_3.7_SW3.4_4.4_L sqm 230.000 0 230.00
W2.2_3.2
Gabion_100x120_MW
34 sqm 230.000 0 230.00
3_SW3.9_LW2.64
Gabion_50x80_MW2. 75 % of
35 sqm 172.500 0 172.50
7_SW3.4_LW2.2 above rate
Gabion_100x120_MW
36 sqm 230.000 0 230.00
2.7_SW3.4_LW2.2
Prepared By:________________ Checked By:________________ Approved By:________________
District Rates Page 2 of 276
37 gabion_mesh_wire kg 114.400 0 114.40
38 Galvanized_Angle sqm 0.000 0 0.00
galvanized_channel_p
39 kg 0.000 0.00
ost
galvanized_corrugated
40 kg 0.000 0.00
_thrie_beam
galvanized_corrugated
41 kg 0.000 0.00
_w_beam_sheet
galvanized_spacer_cha
42 kg 0.000 0.00
nnel
43 galvanized_steel tonne 0.000 0 0.00
44 gelatin Kg 0.000 0 0.00
45 geogrid sqm 0 #VALUE!
46 geogrid_connectors nos. 0.000 0 0.00
47 geotextile 150 GSM sqm 0 #VALUE!
48 gi_wire 8-12 Gauge Kg 101.000 0 101.00 11
49 glass_beads kg 267.000 0 267.00
50 gravel cum 1150.000 0.00 1150.00 8
51 gravel_20_mm cum 1150.000 0.00 1150.00 8
HDPE_pipe_110_mm
52 meter 508.686 0 508.69 290/kg
4KGF
53 HDPE_pipe_150_mm meter 866.529 0 866.53
54 HDPE_pipe_160_mm meter 1126.995 0 1127.00
55 HDPE_pipe_250_mm meter 2744.157 0 2744.16
HDPE_pipe_200_mm meter 1759.343 0 1759.34
hume_pipe_dia_1000_
56 meter 11924.000 0 11924.00 NP3 10
mm
hume_pipe_dia_100_ 150mm dia.
57 meter 1254.000 0 1254.00 NP3
mm Taken.
hume_pipe_dia_1200_
58 meter 1430.000 0 1430.00 NP3
mm
hume_pipe_dia_300_
59 meter 3044.800 0 3044.80 NP3
mm
hume_pipe_dia_450_
60 meter 4558.400 0 4558.40 NP3
mm
hume_pipe_dia_600_
61 meter 6010.400 0 6010.40 NP3
mm
hume_pipe_dia_900_
62 meter 10780.000 0 10780.00 NP3
mm
63 HYSD_bar tonne 90000.000 0 90000.00
64 kerosene litre 101.500 0 101.50 NOC
65 lime tonne 30000.000 30000.00
66 lpg litre 103.873 0 103.87
67 modified_bitumen tonne 77600.000 0 77600.00
68 ms_bar tonne 90000.000 90000.00
69 ms_clamp nos 52.000 0 52.00
70 ms_pipe_25_mm meter 226.540 0 226.54
71 ms_pipes_dia_40mm m 226.540 0 226.54
72 ms_plate kg 139.100 0 139.10
73 ms_sheet_2_mm sqm 1475.800 0 1475.80
74 nails_spikes kg 114.400 0 114.40
non_explosive_chemic
75 kg 0.000 0 0.00
al
Prepared By:________________ Checked By:________________ Approved By:________________
District Rates Page 3 of 276
76 nuts_bolts tonne 200000.000 0 200000.00 21
thermoplastic
77 paint liter 603.200 0 603.20
paint
78 paving_fabric sqm 0.000 0 0.00

Prepared By:________________ Checked By:________________ Approved By:________________


District Rates Page 4 of 276
79 petrol litre 118.500 0 118.50 NOC
80 planks_38mm_thick cum 29138.000 0 29138.00
commercial
81 ply_wood_12mm_thic sqm 570.000 0 570.00 19
k

commercial
82 sqm 550.000 0 550.00
ply_wood_9mm_thick

83 polymer_braids meter 0.000 0 0.00

pre_coated_stone_chip
84 cum 0.000 0 0.00
s_13mm

pre_moulded_joint_fill
85 sqm 0.000 0 0.00
er
86 project_signboard nos 6500.000 0 6500.00
87 rafter_beam_battens cum 0.000 0 0.00
RCC_collar_dia_1000
88 nos. 0.000 0 0.00
_mm
RCC_collar_dia_1200
89 nos. 0.000 0 0.00
_mm
RCC_collar_dia_300_
90 nos. 0.000 0 0.00
mm
RCC_collar_dia_450_
91 nos. 0.000 0 0.00
mm
RCC_collar_dia_600_
92 nos. 0.000 0 0.00
mm
RCC_collar_dia_900_
93 nos. 0.000 0 0.00
mm
94 RS_joist kg 0.000 0 0.00
95 rubble cum 2000.000 0.00 3328.00
96 sal_wood cum 187143.000 0 187143.00
97 crusher sand cum 730.000 0.00 730.00 8
98 steel_tube_dia_50_mm m 0.000 0 0.00
99 steel_wire_40_mm kg 148.820 0 148.82
100 stone_dust cum 630.000 630.00 8
101 stone_slab_50_mm sqm 0.000 0 0.00
102 stone_spall cum 1588.500 0 1588.50
street_lighting_pole_9
103 nos 0.000 0 0.00
_m
104 struts kg 95.000 0 95.00
105 struts_ballies cum 29138.000 0 29138.00
106 sub_base_material cum 1150.000 0.00 1150.00 8
107 surface_dressing_chips cum 1475.000 0.00 1475.00
108 thermoplastic_paint liter 603.200 0 603.20
109 vapor_lamp nos 0.000 0 0.00
110 ms_angle kg 105.000 0 105.00 18
111 water KL 400.000 0 400.00

Prepared By:________________ Checked By:________________ Approved By:________________


District Rates Page 5 of 276
M-10 grade of
112 cum 12500 12500.00 9
concrete
M-15 grade of rmc rate
113 cum 13000 13000.00 9
concrete
114 M 20 grade concrete cum 14200 14200.00 9

2) District rates: Labours


District Rate
S.N. Description Unit Page No;
(D)
1 blaster day 1100.000 1
2 driller day 1100.000 1
3 foreman day 715.000 1
4 semiskilled day 880.000 1
5 skilled day 900.000 1
6 skilled_blacksmith day 1100.000 1
7 skilled_carpenter day 900.000 1
skilled_electrician_line
8 day 725.000 1
man
9 skilled_mason day 900.000 1
10 skilled_painter day 900.000 1
11 skilled_plumber day 880.000 1
12 technician day 900.000 1
13 unskilled day 600.000 1

Prepared By:________________ Checked By:________________ Approved By:________________


Equipment Rates Page 1 of 276
Usage Rates of Plant and Machinery
The usage rates include: cost of repair and maintenance, running and operation charge which includes crew, fuel & lubricants
Operation Charges (Rs/ hr)
Ownership Fuel oil
Load Time Tyre Fuel Electrictity
SL.no Name Activity Capacity Output of Machine Unit Rate (Rs.) Charge Servicin Maintenan (L/hr) (Units/hr) (Heating-
Factor Factor Fuel Crew replaceme
(Rs/hr) g ce L/hr)
nt cost
P&M-
Air Compressor General Purpose 170/250 cfm 0.8 0.8 hour 1459 349 582 360 159 0 109 5.73
001
P&M-
Bitumen Boiler oil fired Bitumen Spraying 1500 litre 0.7 0.7 hour 858 286 321 120 88 0 99 1.96 2
005
P&M- Applying bitumen tack
Bitumen Pressure Distributor 1750 sqm/hour 0.8 0.8 hour 4377 1843 1344 360 367 63.31 630 10.24 3
004 coat
P&M-
Bitumen / Emulsion sprayer 0.8 0.9 hour 881 358 254 120 69 0 124 2.5
089
P&M-
Hydraulic Chip Spreader Surface Dressing 1500 sqm/hour 0.85 0.8 hour 4444 1877 1380 360 377 42.21 645 13.6
026
P&M-
Batch type cold mixing plant 75 TPH 1 1 hour 2387 592 570 480 277 198 70
059
P&M-
Concrete Mixer Concrete Mixing 0.4 cum 0.8 0.8 hour 362 49 52 240 14 0 16 0.51
009
concrete_needle_vibrator 0 0
P&M-
Crane 5 tonne capacity 0.75 0.75 hour 3102 1276 1005 240 275 42.21 437 9.9
061
P&M- Spreading /Cutting / 200/
Dozer (Track) cum/hour 0.85 0.8 hour 5891 2960 1435 360 392 0 990 14.14
015 Clearing 120/150
P&M-
Percussion drill set 0.9 0.9 hour 279 83 26 144 7 0 24 0.26
094
P&M-
Drum mix plant for cold mixes >75 TPH 0.8 0.8 hour 1718 715 468 240 128 0 248 4.61
068
electric_generator 0 0
P&M-
Electric hand driller 0.8 0.9 hour 20 3 6 5 3 0 0 1
088
P&M-
Electric heating plate 0.8 0.9 hour 25 3 12 5 0 0 0 2
087
emulsion_distributor 1721
Soil Ordinary/Soil
P&M- Hydraulic Excavator of 1 cum
Marshy / Soil 60 cum/hour 0.75 0.8 hour 3570 1716 926 240 253 0 594 9.12
027 bucket
Unsuitable
P&M- Genration of electric
Generator( b) 63 KVA 50 KVA 0.6 0.9 hour 1289 260 745 120 204 0 87 7.34
019 Energy
hand_sprayer 0 0
P&M- DBM/BM/SDC/
Hotmix Plant - 40 TPH capacity 10 cum/hour 0.8 0.9 hour 64921 947 10883 240 3131 0 317 125 100
025 Premix
P&M-
Jack hammer /Rock drill 0.9 0.9 hour 580 349 66 60 18 0 99 0.65
092
P&M- Joint Cutting Machine with 2-3
For rigid pavement 0.8 0.9 hour 1268 572 233 240 64 0 198 2.3
073 blades
P&M-
Kerb Casting Machine Kerb Making 80 Rm/hour 0.9 0.85 hour 1522 710 249 300 68 0 238 2.45
031
P&M- Front End loader 1 cum bucket Soil loading /
60 /25 cum/hour 0.85 0.8 hour 2957 1201 839 360 229 79.14 392 8.27
017 capacity Aggregate loading
P&M-
Mastic Cooker Mastic Wearing coat 1 ton/hr 0.8 0.9 hour 2302 95 1240 180 495 0 32 0 125 5
032

Prepared By:________________ Checked By:________________ Approved By:________________


Equipment Rates Page 2 of 276
Usage Rates of Plant and Machinery
The usage rates include: cost of repair and maintenance, running and operation charge which includes crew, fuel & lubricants
Operation Charges (Rs/ hr)
Ownership Fuel oil
Load Time Tyre Fuel Electrictity
SL.no Name Activity Capacity Output of Machine Unit Rate (Rs.) Charge Servicin Maintenan (L/hr) (Units/hr) (Heating-
Factor Factor Fuel Crew replaceme
(Rs/hr) g ce L/hr)
nt cost
P&M-
Mechanical Broom Hydraulic Surface Cleaning 1250 sqm/hour 0.8 0.8 hour 2020 877 520 240 142 42.21 288 5.12
033
P&M-
Mixture machine 0.9 0.9 hour 765 436 132 60 36 0 124 1.3
090
P&M- Mixing and laying
Mobile slurry seal equipment 2700 sqm/hour 0.85 0.85 hour 2283 877 704 300 192 42.21 288 6.94
035 slurry seal
P&M- Clearing /Spreading 200/200/
Motor Grader cum/hour 0.85 0.85 hour 3618 1604 939 360 257 94.97 525 9.25
034 /GSB /WBM 50/50
P&M- Paver Finisher Mechanical 100 Paving of WMM
40/30 cum/hour 0.85 0.85 hour 4775 2357 1173 300 321 42.21 783 11.56
037 TPH /Paving of DLC
P&M-
Plate compactor 0.9 0.9 hour 289 72 66 120 18 0 25 0.65
076
P&M- Rolling of Asphalt
Pneumatic Road Roller 25 cum/hour 0.8 0.8 hour 3319 1552 831 240 227 84.42 527 8.19
039 Surface
P&M-
Road marking machine Road marking 100 Sqm/hour 0.9 0.9 hour 1004 395 203 360 55 0 25 2
044
road_sweeper 0 0
P&M-
Screw Jack 0.8 0.9 hour 14 9 0 5 0 0 1
086
P&M- Soil Compaction /BM
Smooth Wheeled Roller 8 tonne 70/25 cum/hour 0.7 0.7 hour 1608 437 636 300 174 26.38 143 6.27
045 Compaction
P&M-
Integrated Stone Crusher Crushing of spalls 100 ton/ hr 0.85 0.9 hour 1886 977 311 240 85 0 327 3.06
029
Transportation of soil,
P&M-
Tipper - 5 cum GSB, WMM, Hotmix 5.5 cum/hr 0.65 0.65 hour 1454 300 700 240 191 47.48 95 6.9
047
etc.
P&M-
Tractor Pulling 50 HP 0.75 0.75 hour 1110 248 457 240 125 36.93 81 4.5
050
P&M-
Tractor with Ripper Tractor+ Ripper 0.75 0.75 hour 1142 272 457 240 125 36.93 90 4.5
052
P&M-
Tractor with Rotevator Tractor + Rotevator 0.75 0.75 hour 1133 265 457 240 125 36.93 87 4.5
051
P&M-
Truck 5.5 cum per 10 tonnes Material Transport 4.5 cum 0.7 0.65 hour 2014 496 960 240 263 55.4 165 9.46
054
P&M-
Water Tanker Water transport 6 KL 0.6 0.6 hour 1806 529 731 240 200 0 177 7.2
057
P&M-
Wet Mix Plant 75 TPH 0.8 0.8 hour 1621 644 468 240 128 0 223 4.61
081
Vibratory Roller 2413

Prepared By:________________ Checked By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 1 of 276

DHANUSHA ROAD RATE 2077-78


Description of Work:
Providing and installation of project signboards with size of 1.8 x 1.2 m as per specification and instruction of engineer. 1 nos
Spec. cl. No: 110
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Project signboards with size of 1.8 x 1.2 m having details of


1.3 Skilled day 0.1 900 90.0 nos 1 6500 6500
contract in the format and wording as directed by the Engineer

Unskilled day 0.5 600 300.0


Sub total of A = 390.0 Sub total of B = 6500.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 6890.0 Sub total of A + B + C + D= 6890.0 Contractor's overhead expenses 15% = 1033.5 Norms Rate = 7923.5
Unit Rate = 7923.5

Description of Work:
Providing and establishing camp with mobilization and demobilization for contractor's Labour and staff and demolishing after completion of works as per the specifications and instruction of the Engineer. 1 job
Spec. cl. No: 111
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
1.4 As per site condition
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Relocation of services / minor infrastructures, as per specifications and instruction of the Engineer. 1 job
Spec. cl. No: 111
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
1.5 As per site condition
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Engineer's Facilities: Establishment and maintenance of office and site camp etc, and providing furniture and other facilities as directed by the Engineer. PS
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Providing and installation of project signboards with size of 1.8
nos 0 6890 0.0
x 1.2 m as per specification and instruction of engineer.
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 30 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Manual Means:-, In area of light jungle (less than 15 number per 100 sqm)
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.I.i.A Unskilled day 200 600 120000.0
Sub total of A = 120000.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 120000.0 Sub total of A + B + C + D= 120000.0 Contractor's overhead expenses 15% = 18000.0 Norms Rate = 138000.0
Unit Rate = 13.8

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 30 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Manual Means:-, In area of thorny jungle ( more than 15 numbers per 100 sqm)
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.I.i.B Unskilled day 300 600 180000.0
Sub total of A = 180000.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 180000.0 Sub total of A + B + C + D= 180000.0 Contractor's overhead expenses 15% = 27000.0 Norms Rate = 207000.0
Unit Rate = 20.7

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 30 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Mechanical Means, In area of light jungle (less than 15 number per 100 sqm )
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.I.ii.A Unskilled day 6 600 3600.0 Dozer/Excavator hour 12 5891 70692.0
Sub total of A = 3600.0 Sub total of B = 0.0 Sub total of C = 70692.0 Sub total of D = 0.0
Sub total of A +B + C = 74292.0 Sub total of A + B + C + D= 74292.0 Contractor's overhead expenses 15% = 11143.8 Norms Rate = 85435.8
Unit Rate = 8.54
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 2 of 276

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
serviceable Material to be used or auctioned, up to a lead of 30 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Manual Means:-, Felling and uprooting of bamboo clearing the area, stacking of bamboo and disposing of 100 cum
Spec. cl. No: 201 wastes
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.I.i.C Unskilled day 200 600 120000.0
Sub total of A = 120000.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 120000.0 Sub total of A + B + C + D= 120000.0 Contractor's overhead expenses 15% = 18000.0 Norms Rate = 138000.0
Unit Rate = 1380

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 3 of 276

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 30 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Mechanical Means, In area of thorny jungle ( more than 15 numbers per 100 sqm)
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.I.ii.B Unskilled day 9 600 5400.0 Dozer/Excavator hour 12 5891 70692.0
Sub total of A = 5400.0 Sub total of B = 0.0 Sub total of C = 70692.0 Sub total of D = 0.0
Sub total of A +B + C = 76092.0 Sub total of A + B + C + D= 76092.0 Contractor's overhead expenses 15% = 11413.8 Norms Rate = 87505.8
Unit Rate = 8.75

Description of Work:
Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
serviceable Material to be used or auctioned, up to a lead of 30 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Mechanical Means, Felling and uprooting of bamboo clearing the area, stacking of bamboo and disposing of 100 cum
Spec. cl. No: 201 wastes
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.I.ii.C Unskilled day 20 600 12000.0 Dozer/Excavator hour 6 5891 35346.0
Sub total of A = 12000.0 Sub total of B = 0.0 Sub total of C = 35346.0 Sub total of D = 0.0
Sub total of A +B + C = 47346.0 Sub total of A + B + C + D= 47346.0 Contractor's overhead expenses 15% = 7101.9 Norms Rate = 54447.9
Unit Rate = 544.48

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Manual Means:-, In area of light jungle (less than 15 number per 100 sqm)
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.II.i.A Unskilled day 225 600 135000.0 Tractor - Trolley hour 12 1110 13320.0
Sub total of A = 135000.0 Sub total of B = 0.0 Sub total of C = 13320.0 Sub total of D = 0.0
Sub total of A +B + C = 148320.0 Sub total of A + B + C + D= 148320.0 Contractor's overhead expenses 15% = 22248.0 Norms Rate = 170568.0
Unit Rate = 17.06

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., In area of thorny jungle ( more than 15 numbers per 100 sqm)
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.II.i.B Unskilled day 325 600 195000.0 Tractor - Trolley hour 12 1110 13320.0
Sub total of A = 195000.0 Sub total of B = 0.0 Sub total of C = 13320.0 Sub total of D = 0.0
Sub total of A +B + C = 208320.0 Sub total of A + B + C + D= 208320.0 Contractor's overhead expenses 15% = 31248.0 Norms Rate = 239568.0
Unit Rate = 23.96

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
100 cum
serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., Felling and uprooting of bamboo clearing the area, stacking of bamboo and disposing of wastes
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.II.i.C Unskilled day 225 600 135000.0 Tractor - Trolley hour 12 1110 13320.0
Sub total of A = 135000.0 Sub total of B = 0.0 Sub total of C = 13320.0 Sub total of D = 0.0
Sub total of A +B + C = 148320.0 Sub total of A + B + C + D= 148320.0 Contractor's overhead expenses 15% = 22248.0 Norms Rate = 170568.0
Unit Rate = 1705.68

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Mechanical Means, In area of light jungle (less than 15 number per 100 sqm )
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.II.ii.
Unskilled day 8 600 4800.0 Dozer/Excavator hour 12 5891 70692.0
A
Tractor - Trolley hour 12 1110 13320.0
Sub total of A = 4800.0 Sub total of B = 0.0 Sub total of C = 84012.0 Sub total of D = 0.0
Sub total of A +B + C = 88812.0 Sub total of A + B + C + D= 88812.0 Contractor's overhead expenses 15% = 13321.8 Norms Rate = 102133.8
Unit Rate = 10.21

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
10000 sqm
serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Mechanical Means, In area of thorny jungle ( more than 15 numbers per 100 sqm)
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.II.ii.
Unskilled day 12 600 7200.0 Dozer/Excavator hour 12 5891 70692.0
B
Tractor - Trolley hour 12 1110 13320.0
Sub total of A = 7200.0 Sub total of B = 0.0 Sub total of C = 84012.0 Sub total of D = 0.0
Sub total of A +B + C = 91212.0 Sub total of A + B + C + D= 91212.0 Contractor's overhead expenses 15% = 13681.8 Norms Rate = 104893.8
Unit Rate = 10.49
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 4 of 276

Description of Work: Clearing and Grubbing Road Land ., Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of
serviceable Material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness., By Mechanical Means, Felling and uprooting of bamboo clearing the area, stacking of bamboo and disposing 100 cum
Spec. cl. No: 201 of wastes
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.1.II.ii.
Unskilled day 15 600 9000.0 Dozer/Excavator hour 12 5891 70692.0
C
Tractor - Trolley hour 12 1110 13320.0
Sub total of A = 9000.0 Sub total of B = 0.0 Sub total of C = 84012.0 Sub total of D = 0.0
Sub total of A +B + C = 93012.0 Sub total of A + B + C + D= 93012.0 Contractor's overhead expenses 15% = 13951.8 Norms Rate = 106963.8
Unit Rate = 1069.64

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 5 of 276

Description of Work: Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
30 number
depression/pit., Girth from 300 mm to 600 mm
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.2.i Unskilled day 25 600 15000.0 Tractor - Trolley hour 6 1110 6660.0
Sub total of A = 15000.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 21660.0 Sub total of A + B + C + D= 21660.0 Contractor's overhead expenses 15% = 3249.0 Norms Rate = 24909.0
Unit Rate = 830.3

Description of Work: Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
10 number
depression/pit., Girth from 600 mm to 900 mm
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.2.ii Unskilled day 25 600 15000.0 Tractor - Trolley hour 6 1110 6660.0
Sub total of A = 15000.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 21660.0 Sub total of A + B + C + D= 21660.0 Contractor's overhead expenses 15% = 3249.0 Norms Rate = 24909.0
Unit Rate = 2490.9

Description of Work: Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
5 number
depression/pit., Girth from 900 mm to 1800 mm
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.2.iii Unskilled day 35 600 21000.0 Tractor - Trolley hour 6 1110 6660.0
Sub total of A = 21000.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 27660.0 Sub total of A + B + C + D= 27660.0 Contractor's overhead expenses 15% = 4149.0 Norms Rate = 31809.0
Unit Rate = 6361.8

Description of Work: Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
2 number
depression/pit., Girth from 1800 - 2500 mm
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.2.iv Unskilled day 32 600 19200.0 Tractor - Trolley hour 6 1110 6660.0
Sub total of A = 19200.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 25860.0 Sub total of A + B + C + D= 25860.0 Contractor's overhead expenses 15% = 3879.0 Norms Rate = 29739.0
Unit Rate = 14869.5

Description of Work: Cutting of Trees, including cutting of Trunks, Branches and Removal, Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable Material with all lifts and up to a lead of 1000 meters and earth filling in the
1 number
depression/pit., Girth above 2500 mm
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.2.v Unskilled day 50 600 30000.0 Tractor - Trolley hour 12 1110 13320.0
Sub total of A = 30000.0 Sub total of B = 0.0 Sub total of C = 13320.0 Sub total of D = 0.0
Sub total of A +B + C = 43320.0 Sub total of A + B + C + D= 43320.0 Contractor's overhead expenses 15% = 6498.0 Norms Rate = 49818.0
Unit Rate = 49818

Description of Work:
Clearing Grass and Removal of Rubbish and Dressing and levelling the construction surface Clearing grass/ top soil and removal up to a distance of 50 meters outside the periphery of the area , including cutting and filling of small undulation., By Manual Means 10000 sqm
Spec. cl. No: 201
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.3 Unskilled day 100 600 60000.0
Sub total of A = 60000.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 60000.0 Sub total of A + B + C + D= 60000.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 60000.0
Unit Rate = 6

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Lime /Cement Concrete, By Manual Means, Lime Concrete, cement concrete grade M-10 and below
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.i.I.A Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 24 600 14400.0
Sub total of A = 15300.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 21960.0 Sub total of A + B + C + D= 21960.0 Contractor's overhead expenses 15% = 3294.0 Norms Rate = 25254.0
Unit Rate = 1262.7

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Lime /Cement Concrete, By Manual Means, Cement Concrete Grade M-15 & M-20
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 6 of 276

2.4.i.I.B Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 30 600 18000.0
Sub total of A = 18900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 25560.0 Sub total of A + B + C + D= 25560.0 Contractor's overhead expenses 15% = 3834.0 Norms Rate = 29394.0
Unit Rate = 1469.7

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 7 of 276

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Lime /Cement Concrete, By Manual Means, Pre-stressed / Reinforced cement concrete grade M-20 & above
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.i.I.C Technician day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Skilled day 3 900 2700.0
Unskilled day 30 600 18000.0
Sub total of A = 21600.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 28260.0 Sub total of A + B + C + D= 28260.0 Contractor's overhead expenses 15% = 4239.0 Norms Rate = 32499.0
Unit Rate = 3249.9

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Lime /Cement Concrete, By Mechanical Means, Cement Concrete Grade M-15 & M-20
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.i.II.A Skilled day 1 900 900.0 Air Compressor hour 6 1459 8754.0

Drilling Machine With


Unskilled day 6 600 3600.0 hour 6 279 1674.0
Bit and Accessories

Tractor - Trolley hour 6 1110 6660.0


Sub total of A = 4500.0 Sub total of B = 0.0 Sub total of C = 17088.0 Sub total of D = 0.0
Sub total of A +B + C = 21588.0 Sub total of A + B + C + D= 21588.0 Contractor's overhead expenses 15% = 3238.2 Norms Rate = 24826.2
Unit Rate = 2482.62

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Lime /Cement Concrete, By Mechanical Means, Prestressed / reinforced cement concrete grade M-20 & above
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.i.II.B Skilled day 2 900 1800.0 Air Compressor hour 6 1459 8754.0

Drilling Machine With


Unskilled day 10 600 6000.0 hour 6 279 1674.0
Bit and Accessories

Tractor - Trolley hour 6 1110 6660.0


Sub total of A = 7800.0 Sub total of B = 0.0 Sub total of C = 17088.0 Sub total of D = 0.0
Sub total of A +B + C = 24888.0 Sub total of A + B + C + D= 24888.0 Contractor's overhead expenses 15% = 3733.2 Norms Rate = 28621.2
Unit Rate = 2862.12

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Brick / Tile work, In lime mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.ii.A Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 14760.0 Sub total of A + B + C + D= 14760.0 Contractor's overhead expenses 15% = 2214.0 Norms Rate = 16974.0
Unit Rate = 848.7

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Brick / Tile work, In cement mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.ii.B Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 10 600 6000.0
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 13560.0 Sub total of A + B + C + D= 13560.0 Contractor's overhead expenses 15% = 2034.0 Norms Rate = 15594.0
Unit Rate = 1559.4

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Brick / Tile work, In mud mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.ii.C Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 10 600 6000.0
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 13560.0 Sub total of A + B + C + D= 13560.0 Contractor's overhead expenses 15% = 2034.0 Norms Rate = 15594.0
Unit Rate = 779.7

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
Prepared By:________________ 20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Brick / Checked By:________________
Tile work, Dry brick pitching or brick solingRecommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 8 of 276
Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Brick / Tile work, Dry brick pitching or brick soling
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.ii.D Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 14760.0 Sub total of A + B + C + D= 14760.0 Contractor's overhead expenses 15% = 2214.0 Norms Rate = 16974.0
Unit Rate = 848.7

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 9 of 276

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Stone Masonry, Rubble stone masonry in lime mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.iii.A Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 15 600 9000.0
Sub total of A = 9900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 16560.0 Sub total of A + B + C + D= 16560.0 Contractor's overhead expenses 15% = 2484.0 Norms Rate = 19044.0
Unit Rate = 952.2

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Stone Masonry, Rubble stone masonry in cement mortar.
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.iii.B Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 10 600 6000.0
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 13560.0 Sub total of A + B + C + D= 13560.0 Contractor's overhead expenses 15% = 2034.0 Norms Rate = 15594.0
Unit Rate = 1559.4

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Stone Masonry, Rubble Stone Masonry in mud mortar.
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.iii.C Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 14760.0 Sub total of A + B + C + D= 14760.0 Contractor's overhead expenses 15% = 2214.0 Norms Rate = 16974.0
Unit Rate = 848.7

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Stone Masonry, Dry rubble masonry
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.iii.D Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 10 600 6000.0
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 13560.0 Sub total of A + B + C + D= 13560.0 Contractor's overhead expenses 15% = 2034.0 Norms Rate = 15594.0
Unit Rate = 779.7

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Stone Masonry, Dismantling stone pitching/ dry stone spalls.
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.iii.E Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 8 600 4800.0
Sub total of A = 5700.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 12360.0 Sub total of A + B + C + D= 12360.0 Contractor's overhead expenses 15% = 1854.0 Norms Rate = 14214.0
Unit Rate = 710.7

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
20 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Dismantling Stone Masonry, Dismantling boulders laid in wire crates including opening of crates and stacking dismantled Material.
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.iii.F Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 15 600 9000.0
Sub total of A = 9900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 16560.0 Sub total of A + B + C + D= 16560.0 Contractor's overhead expenses 15% = 2484.0 Norms Rate = 19044.0
Unit Rate = 952.2

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Wood Work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
2.4.iv day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
(Carpenter)
Unskilled day 10 600 6000.0
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 13560.0 Sub total of A + B + C + D= 13560.0 Contractor's overhead expenses 15% = 2034.0 Norms Rate = 15594.0
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 10 of 276

Unit Rate = 1559.4

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 11 of 276

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
5 tonne
and stacking the serviceable Material with all lifts and lead of 1000 meters, Steel Work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet., Including dismembering
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.v.A Skilled day 5 900 4500.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 20 600 12000.0
For gas cutting,
ropes, pulleys 412.5
etc.
Sub total of A = 16912.5 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 23572.5 Sub total of A + B + C + D= 23572.5 Contractor's overhead expenses 15% = 3535.9 Norms Rate = 27108.4
Unit Rate = 5421.68

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
5 tonne
and stacking the serviceable Material with all lifts and lead of 1000 meters, Steel Work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet., Excluding dismembering.
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.v.B Unskilled day 16 600 9600.0 Tractor - Trolley hour 6 1110 6660.0
Skilled day 4 900 3600.0
For gas cutting,
ropes, pulleys 330
etc.
Sub total of A = 13530.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 20190.0 Sub total of A + B + C + D= 20190.0 Contractor's overhead expenses 15% = 3028.5 Norms Rate = 23218.5
Unit Rate = 4643.7

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
50 number
and stacking the serviceable Material with all lifts and lead of 1000 meters, Steel Work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet., Extra over item No( v ) A and( v ) B for cutting rivets.
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.v.C Skilled day 1 900 900.0
Unskilled day 1 600 600.0
Sub total of A = 1500.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 1500.0 Sub total of A + B + C + D= 1500.0 Contractor's overhead expenses 15% = 225.0 Norms Rate = 1725.0
Unit Rate = 34.5

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
200 number
and stacking the serviceable Material with all lifts and lead of 1000 meters, Scraping of Bricks Dismantled from Brick Work including Stacking., In lime/Cement mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.vi.A Skilled day 1 900 900.0
Unskilled day 8 600 4800.0
Sub total of A = 5700.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 5700.0 Sub total of A + B + C + D= 5700.0 Contractor's overhead expenses 15% = 855.0 Norms Rate = 6555.0
Unit Rate = 32.78

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
200 number
and stacking the serviceable Material with all lifts and lead of 1000 meters, Scraping of Bricks Dismantled from Brick Work including Stacking., In mud mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.vi.B Skilled day 1 900 900.0
Unskilled day 5 600 3000.0
Sub total of A = 3900.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 3900.0 Sub total of A + B + C + D= 3900.0 Contractor's overhead expenses 15% = 585.0 Norms Rate = 4485.0
Unit Rate = 22.43

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Scraping of Stone from Dismantled Stone Masonry, In cement and lime mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.vii.A Skilled day 1 900 900.0
Unskilled day 14 600 8400.0
Sub total of A = 9300.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 9300.0 Sub total of A + B + C + D= 9300.0 Contractor's overhead expenses 15% = 1395.0 Norms Rate = 10695.0
Unit Rate = 1069.5

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 cum
and stacking the serviceable Material with all lifts and lead of 1000 meters, Scraping of Stone from Dismantled Stone Masonry, In Mud mortar
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 12 of 276
Norms
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.vii.B Skilled day 1 900 900.0
Unskilled day 5 600 3000.0
Sub total of A = 3900.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 3900.0 Sub total of A + B + C + D= 3900.0 Contractor's overhead expenses 15% = 585.0 Norms Rate = 4485.0
Unit Rate = 448.5

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 13 of 276

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
200 sqm
and stacking the serviceable Material with all lifts and lead of 1000 meters, Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.viii Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 10 600 6000.0
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 13560.0 Sub total of A + B + C + D= 13560.0 Contractor's overhead expenses 15% = 2034.0 Norms Rate = 15594.0
Unit Rate = 77.97

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 meter
and stacking the serviceable Material with all lifts and lead of 1000 meters, Removing all type of Hume Pipes and Stacking within a lead of 50 metres including Earthwork and Dismantling of Masonry Works., Up to 600 mm dia
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.v.ix.
Skilled day 1 900 900.0
A
Unskilled day 5 600 3000.0
Sub total of A = 3900.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 3900.0 Sub total of A + B + C + D= 3900.0 Contractor's overhead expenses 15% = 585.0 Norms Rate = 4485.0
Unit Rate = 448.5

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 meter
and stacking the serviceable Material with all lifts and lead of 1000 meters, Removing all type of Hume Pipes and Stacking within a lead of 50 metres including Earthwork and Dismantling of Masonry Works., Above 600 mm to 900 mm dia
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.v.ix.
Skilled day 1 900 900.0
B
Unskilled day 8 600 4800.0
Sub total of A = 5700.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 5700.0 Sub total of A + B + C + D= 5700.0 Contractor's overhead expenses 15% = 855.0 Norms Rate = 6555.0
Unit Rate = 655.5

Description of Work: Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including scaffolding wherever necessary, sorting the dismantled Material, disposal of unserviceable Material
10 meter
and stacking the serviceable Material with all lifts and lead of 1000 meters, Removing all type of Hume Pipes and Stacking within a lead of 50 metres including Earthwork and Dismantling of Masonry Works., Above 900 mm
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.4.v.ix.
Skilled day 1 900 900.0
C
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 8100.0 Sub total of A + B + C + D= 8100.0 Contractor's overhead expenses 15% = 1215.0 Norms Rate = 9315.0
Unit Rate = 931.5

Description of Work:
Dismantling of Flexible Pavements, Dismantling of flexible pavements and disposal of dismantled Material up to a lead of 1000 metres, stacking serviceable and unserviceable Material separately, By Manual Means, Bituminous courses 10 cum
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.5.I.A Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 15 600 9000.0
Sub total of A = 9900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 16560.0 Sub total of A + B + C + D= 16560.0 Contractor's overhead expenses 15% = 2484.0 Norms Rate = 19044.0
Unit Rate = 1904.4

Description of Work:
Dismantling of Flexible Pavements, Dismantling of flexible pavements and disposal of dismantled Material up to a lead of 1000 metres, stacking serviceable and unserviceable Material separately, By Manual Means, Granular courses 10 cum
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.5.I.B Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 14760.0 Sub total of A + B + C + D= 14760.0 Contractor's overhead expenses 15% = 2214.0 Norms Rate = 16974.0
Unit Rate = 1697.4

Description of Work:
Dismantling of Flexible Pavements, Dismantling of flexible pavements and disposal of dismantled Material up to a lead of 1000 metres, stacking serviceable and unserviceable Material separately, By Mechanical Means, Bituminous course 20 cum
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.5.II.A Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 9 600 5400.0 Tractor with Ripper hour 6 1142 6852.0
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 14 of 276

Sub total of A = 6300.0 Sub total of B = 0.0 Sub total of C = 13512.0 Sub total of D = 0.0
Sub total of A +B + C = 19812.0 Sub total of A + B + C + D= 19812.0 Contractor's overhead expenses 15% = 2971.8 Norms Rate = 22783.8
Unit Rate = 1139.19

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 15 of 276

Description of Work: Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled Material up to a lead of 1000 metres, stacking serviceable and
10 cum
unserviceable Material separately
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.6 Skilled day 1 900 900.0 Air Compressor hour 6 1459 8754.0
Semiskilled day 8 880 7040.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 8 600 4800.0 Joint Cutting Machine hour 6 1268 7608.0
Sub total of A = 12740.0 Sub total of B = 0.0 Sub total of C = 23022.0 Sub total of D = 0.0
Sub total of A +B + C = 35762.0 Sub total of A + B + C + D= 35762.0 Contractor's overhead expenses 15% = 5364.3 Norms Rate = 41126.3
Unit Rate = 4112.63

Description of Work:
Dismantling guard rails by manual means and disposal of dismantled Material with all lifts and up to a lead of 1000 metres, stacking serviceable Material and unserviceable Material separately. 100 meter
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.7 Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 20 600 12000.0
Sub total of A = 12900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 19560.0 Sub total of A + B + C + D= 19560.0 Contractor's overhead expenses 15% = 2934.0 Norms Rate = 22494.0
Unit Rate = 224.94

Description of Work:
Dismantling Kerb stone by manual means and disposal of dismantled Material with all lifts and up to a lead of 1000 meter 100 meter
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.8 Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 3 600 1800.0
Sub total of A = 2700.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 9360.0 Sub total of A + B + C + D= 9360.0 Contractor's overhead expenses 15% = 1404.0 Norms Rate = 10764.0
Unit Rate = 107.64

Description of Work:
Dismantling Kerb stone channel by manual means and disposal of dismantled Material with all lifts and up to a lead of 1000 meter 100 meter
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.9 Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 5 600 3000.0
Sub total of A = 3900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 10560.0 Sub total of A + B + C + D= 10560.0 Contractor's overhead expenses 15% = 1584.0 Norms Rate = 12144.0
Unit Rate = 121.44

Description of Work:
Dismantling of kilometer stone including cutting of earth, foundation and disposal of dismantled Material with all lifts and lead upto 1000 m and back filling of pit., Five KM stone 50 number
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Quantity of concrete =
2.10.A Unskilled day 5 600 3000.0
0.2 cum per post
Tractor - Trolley hour 6 1110 6660.0
Sub total of A = 3000.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 9660.0 Sub total of A + B + C + D= 9660.0 Contractor's overhead expenses 15% = 1449.0 Norms Rate = 11109.0
Unit Rate = 222.18

Description of Work:
Dismantling of kilometer stone including cutting of earth, foundation and disposal of dismantled Material with all lifts and lead upto 1000 m and back filling of pit., One KM Stone 50 number
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Quantity of concrete =
2.10.B Unskilled day 4 600 2400.0
0.1 cum per post
Tractor - Trolley hour 3 1110 3330.0
Sub total of A = 2400.0 Sub total of B = 0.0 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 5730.0 Sub total of A + B + C + D= 5730.0 Contractor's overhead expenses 15% = 859.5 Norms Rate = 6589.5
Unit Rate = 131.79

Description of Work: Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling of pit by manual means including disposal of dismantled Material with all lifts and up to a lead of 1000 metres, stacking serviceable Material and unserviceable
100 meter
Material separately.
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.11 Unskilled day 12 600 7200.0 Tractor - Trolley hour 6 1110 6660.0
Skilled day 2 900 1800.0
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 16 of 276

Sub total of A = 9000.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 15660.0 Sub total of A + B + C + D= 15660.0 Contractor's overhead expenses 15% = 2349.0 Norms Rate = 18009.0
Unit Rate = 180.09

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 17 of 276

Description of Work:
Dismantling of CI water pipe line upto 600 mm dia including disposal with all lifts and lead upto 1000 metres and stacking of serviceable Material and unserviceable Material separately . 100 meter
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.12 Unskilled day 25 600 15000.0 Truck hour 6 2014 12084.0
Skilled
day 2 880 1760.0 Crane hour 6 3102 18612.0
(Plumber)
Sub total of A = 16760.0 Sub total of B = 0.0 Sub total of C = 30696.0 Sub total of D = 0.0
Sub total of A +B + C = 47456.0 Sub total of A + B + C + D= 47456.0 Contractor's overhead expenses 15% = 7118.4 Norms Rate = 54574.4
Unit Rate = 545.74

Description of Work:
Removal of cement concrete pipe of sewer gutter 1500 mm dia including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable Material separately but excluding earth excavation and dismantling of masonry works. 100 meter
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.13 Unskilled day 30 600 18000.0 Crane hour 6 3102 18612.0
Truck Flat Body hour 6 2014 12084.0
Sub total of A = 18000.0 Sub total of B = 0.0 Sub total of C = 30696.0 Sub total of D = 0.0
Sub total of A +B + C = 48696.0 Sub total of A + B + C + D= 48696.0 Contractor's overhead expenses 15% = 7304.4 Norms Rate = 56000.4
Unit Rate = 560

Description of Work: Removal of telephone / Electric poles including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable and unserviceable Material
30 nos
separately
Spec. cl. No: 202
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
2.14 Unskilled day 15 600 9000.0 Tractor - Trolley hour 6 1110 6660.0
Skilled
(Electrician / day 3 725 2175.0
Lineman)
Sub total of A = 11175.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 17835.0 Sub total of A + B + C + D= 17835.0 Contractor's overhead expenses 15% = 2675.3 Norms Rate = 20510.3
Unit Rate = 683.68

Description of Work:
Providing, jointing and laying HDPE pipes with or without collar etc. complete in place as per Drawing and Technical Specifications., a) 110 mm/125 mm outer dia. 50 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
7.1.A Skilled day 3 900 2700.0 HDPE pipe 110 mm dia. meter 50 508.6861 25434.305 Generator hour 6 1289 7734.0
Unskilled day 3 600 1800.0 Screw Jack hour 6 14 84.0
Electric Heating Plate hour 6 25 150.0
other T&P 135.0
Sub total of A = 4500.0 Sub total of B = 25434.3 Sub total of C = 8103.0 Sub total of D = 0.0
Sub total of A +B + C = 38037.3 Sub total of A + B + C + D= 38037.3 Contractor's overhead expenses 15% = 5705.6 Norms Rate = 43742.9
Unit Rate = 874.86

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., 300 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.2.A Skilled day 1 900 900.0 Sand cum 0.08 730 58.4 117.0
bars, chain pulley and
other T&P
Unskilled day 5 600 3000.0 Cement tonne 0.06 17500 1050
NP3 RCC Pipe 300 mm dia meter 12.5 3044.8 38060
Sub total of A = 3900.0 Sub total of B = 39168.4 Sub total of C = 117.0 Sub total of D = 0.0
Sub total of A +B + C = 43185.4 Sub total of A + B + C + D= 43185.4 Contractor's overhead expenses 15% = 6477.8 Norms Rate = 49663.2
Unit Rate = 3973.06

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., 450 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.2.B Skilled day 1 900 900.0 Sand cum 0.09 730 65.7 135.0
bars, chain pulley and
other T&P
Unskilled day 6 600 3600.0 Cement tonne 0.07 17500 1225
NP3 RCC Pipe 450 mm dia meter 12.5 4558.4 56980

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 18 of 276

Sub total of A = 4500.0 Sub total of B = 58270.7 Sub total of C = 135.0 Sub total of D = 0.0
Sub total of A +B + C = 62905.7 Sub total of A + B + C + D= 62905.7 Contractor's overhead expenses 15% = 0.0 Norms Rate = 62905.7
Unit Rate = 5032.46

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 19 of 276

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., 600 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.2.C Skilled day 1 900 900.0 Sand cum 0.1 730 73 153.0
bars, chain pulley and
other T&P
Unskilled day 7 600 4200.0 Cement tonne 0.08 17500 1400
NP3 RCC Pipe 600 mm dia meter 12.5 6010.4 75130
Sub total of A = 5100.0 Sub total of B = 76603.0 Sub total of C = 153.0 Sub total of D = 0.0
Sub total of A +B + C = 81856.0 Sub total of A + B + C + D= 81856.0 Contractor's overhead expenses 15% = 12278.4 Norms Rate = 94134.4
Unit Rate = 7530.75

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., 900 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.2.D Skilled day 1 900 900.0 Sand cum 0.12 730 87.6 171.0
bars, chain pulley and
other T&P
Unskilled day 8 600 4800.0 Cement tonne 0.09 17500 1575
NP3 RCC Pipe 900 mm dia meter 12.5 10780 134750
Sub total of A = 5700.0 Sub total of B = 136412.6 Sub total of C = 171.0 Sub total of D = 0.0
Sub total of A +B + C = 142283.6 Sub total of A + B + C + D= 142283.6 Contractor's overhead expenses 15% = 21342.5 Norms Rate = 163626.1
Unit Rate = 13090.09

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., 1000 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.2.E Skilled day 1.5 900 1350.0 Sand cum 0.14 730 102.2 220.5
bars, chain pulley and
other T&P
Unskilled day 10 600 6000.0 Cement tonne 0.1 17500 1750
NP3 RCC Pipe 1000 mm dia meter 12.5 11924 149050
Sub total of A = 7350.0 Sub total of B = 150902.2 Sub total of C = 220.5 Sub total of D = 0.0
Sub total of A +B + C = 158472.7 Sub total of A + B + C + D= 158472.7 Contractor's overhead expenses 15% = 23770.9 Norms Rate = 182243.6
Unit Rate = 14579.49

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications., 1200 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.2.F Skilled day 2 900 1800.0 Sand cum 0.18 730 131.4 270.0
bars, chain pulley and
other T&P
Unskilled day 12 600 7200.0 Cement tonne 0.14 17500 2450
NP3 RCC Pipe 1200 mm dia meter 12.5 1430 17875
Sub total of A = 9000.0 Sub total of B = 20456.4 Sub total of C = 270.0 Sub total of D = 0.0
Sub total of A +B + C = 29726.4 Sub total of A + B + C + D= 29726.4 Contractor's overhead expenses 15% = 4459.0 Norms Rate = 34185.4
Unit Rate = 2734.83

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 300 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.3.A Skilled day 1 900 900.0 Sand cum 0.08 730 58.4 117.0
bars, chain pulley and
other T&P
Unskilled day 5 600 3000.0 Cement tonne 0.06 17500 1050
NP3 RCC Pipe 300 mm dia meter 12.5 3044.8 38060
NP3 RCC Collar 300 mm dia nos. 4 0 0
Sub total of A = 3900.0 Sub total of B = 39168.4 Sub total of C = 117.0 Sub total of D = 0.0
Sub total of A +B + C = 43185.4 Sub total of A + B + C + D= 43185.4 Contractor's overhead expenses 15% = 6477.8 Norms Rate = 49663.2
Unit Rate = 3973.06

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 20 of 276

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 600 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.3.C Skilled day 1 900 900.0 Sand cum 0.1 730 73 153.0
bars, chain pulley and
other T&P
Unskilled day 7 600 4200.0 Cement tonne 0.08 17500 1400
NP3 RCC Pipe 600 mm dia meter 12.5 6010.4 75130
NP3 RCC Collar 600 mm dia nos. 4 0 0
Sub total of A = 5100.0 Sub total of B = 76603.0 Sub total of C = 153.0 Sub total of D = 0.0
Sub total of A +B + C = 81856.0 Sub total of A + B + C + D= 81856.0 Contractor's overhead expenses 15% = 12278.4 Norms Rate = 94134.4
Unit Rate = 7530.75

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 450 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.3.B Skilled day 1 900 900.0 Sand cum 0.09 730 65.7 135.0
bars, chain pulley and
other T&P
Unskilled day 6 600 3600.0 Cement tonne 0.07 17500 1225
NP3 RCC Pipe 450 mm dia meter 12.5 4558.4 56980
NP3 RCC Collar 450 mm dia nos. 4 0 0
Sub total of A = 4500.0 Sub total of B = 58270.7 Sub total of C = 135.0 Sub total of D = 0.0
Sub total of A +B + C = 62905.7 Sub total of A + B + C + D= 62905.7 Contractor's overhead expenses 15% = 9435.9 Norms Rate = 72341.6
Unit Rate = 5787.32

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 900 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.3.D Skilled day 1 900 900.0 Sand cum 0.12 730 87.6 171.0
bars, chain pulley and
other T&P
Unskilled day 8 600 4800.0 Cement tonne 0.09 17500 1575
NP3 RCC Pipe 900 mm dia meter 12.5 10780 134750
NP3 RCC Collar 900 mm dia nos. 4 0 0
Sub total of A = 5700.0 Sub total of B = 136412.6 Sub total of C = 171.0 Sub total of D = 0.0
Sub total of A +B + C = 142283.6 Sub total of A + B + C + D= 142283.6 Contractor's overhead expenses 15% = 21342.5 Norms Rate = 163626.1
Unit Rate = 13090.09

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 1000 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.3.E Skilled day 1.5 900 1350.0 Sand cum 0.14 730 102.2 220.5
bars, chain pulley and
other T&P
Unskilled day 10 600 6000.0 Cement tonne 0.1 17500 1750
NP3 RCC Pipe 1000 mm dia meter 12.5 11924 149050
NP3 RCC Collar 1000 mm dia nos. 4 0 0
Sub total of A = 7350.0 Sub total of B = 150902.2 Sub total of C = 220.5 Sub total of D = 0.0
Sub total of A +B + C = 158472.7 Sub total of A + B + C + D= 158472.7 Contractor's overhead expenses 15% = 23770.9 Norms Rate = 182243.6
Unit Rate = 14579.49

Description of Work:
Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 1200 mm internal dia. 12.5 meter
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.3.F Skilled day 2 900 1800.0 Sand cum 0.18 730 131.4 270.0
bars, chain pulley and
other T&P
Unskilled day 12 600 7200.0 Cement tonne 0.14 17500 2450
NP3 RCC Pipe 1200 mm dia meter 12.5 1430 17875

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 21 of 276

NP3 RCC Collar 1200 mm dia nos. 4 0 0


Sub total of A = 9000.0 Sub total of B = 20456.4 Sub total of C = 270.0 Sub total of D = 0.0
Sub total of A +B + C = 29726.4 Sub total of A + B + C + D= 29726.4 Contractor's overhead expenses 15% = 4459.0 Norms Rate = 34185.4
Unit Rate = 2734.83

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 22 of 276

Description of Work:
Laying (Joining) of Precast concrete panel 12 meter
Spec. cl. No: 702
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of Labour
cost for bellies, crow
7.4.C Skilled day 0.5 900 450.0 Sand cum 0.04 730 29.2 67.5
bars, chain pulley and
other T&P
Unskilled day 3 600 1800.0 Cement tonne 0.03 17500 525
Concrete Channel nos. 0 0 0
Sub total of A = 2250.0 Sub total of B = 554.2 Sub total of C = 67.5 Sub total of D = 0.0
Sub total of A +B + C = 2871.7 Sub total of A + B + C + D= 2871.7 Contractor's overhead expenses 15% = 430.8 Norms Rate = 3302.5
Unit Rate = 275.2

Description of Work: Earthwork Excavation in Cutting., Roadway Excavation in all types of Soil by Manual Means ., Roadway Excavation in all types of soil as per drawing and technical specification, including removal of stumps and other deleterious matter, with all lifts and lead as per
12 cum
Drawing and instruction of the Engineer.
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.I.A Skilled day 1 900 900.0 Doko , Thunse etc. 171.0
Unskilled day 8 600 4800.0
Sub total of A = 5700.0 Sub total of B = 0.0 Sub total of C = 171.0 Sub total of D = 0.0
Sub total of A +B + C = 5871.0 Sub total of A + B + C + D= 5871.0 Contractor's overhead expenses 15% = 880.7 Norms Rate = 6751.7
Unit Rate = 562.64

Description of Work: Earthwork Excavation in Cutting., Roadway Excavation in all types of Soil by Mechanical Means ., Road way Excavation in all types of soil as per Drawing and technical specifications including removal of stumps and other deleterious matter, all lifts and lead as per
360 cum
Drawing and instruction of the Engineer.
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.I.B Skilled day 1 900 900.0 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 3 600 1800.0
Sub total of A = 2700.0 Sub total of B = 0.0 Sub total of C = 21420.0 Sub total of D = 0.0
Sub total of A +B + C = 24120.0 Sub total of A + B + C + D= 24120.0 Contractor's overhead expenses 15% = 3618.0 Norms Rate = 27738.0
Unit Rate = 77.05

Description of Work:
Earthwork Excavation in Cutting., Roadway Excavation in ordinary rock by Manual Means ., Roadway Excavation in ordinary rock as per Drawing and Technical specification, including all lift and lead as per Drawing and instruction of the Engineer. 60 cum
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.II.A Skilled day 3 900 2700.0 Doko , Thunse etc.t 981.0
Unskilled day 50 600 30000.0
Sub total of A = 32700.0 Sub total of B = 0.0 Sub total of C = 981.0 Sub total of D = 0.0
Sub total of A +B + C = 33681.0 Sub total of A + B + C + D= 33681.0 Contractor's overhead expenses 15% = 5052.2 Norms Rate = 38733.2
Unit Rate = 645.55

Description of Work:
Earthwork Excavation in Cutting., Roadway Excavation in ordinary rock by Mechanical Means ., Roadway Excavation in ordinary rock as per Drawing and Technical specification, including all lift and lead as per Drawing and instruction of the Engineer. 120 cum
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.II.B Skilled day 1 900 900.0 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 3 600 1800.0
Sub total of A = 2700.0 Sub total of B = 0.0 Sub total of C = 21420.0 Sub total of D = 0.0
Sub total of A +B + C = 24120.0 Sub total of A + B + C + D= 24120.0 Contractor's overhead expenses 15% = 3618.0 Norms Rate = 27738.0
Unit Rate = 231.15

Description of Work: Earthwork Excavation in Cutting., Roadway Excavation in Hard Rock, mechanical Drilling, Roadway Excavation in hard rock with mechanical drilling, including blasting and breaking, and disposal of cut road within all lifts and leads as per Drawing and instruction
90 cum
of the Engineer.
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.III.A Skilled day 1 900 900.0 Gelatin kg 32 0 0 Dozer hour 6 5891 35346.0
Jack Hammer/Rock
Unskilled day 20 600 12000.0 Electric Detonator nos. 126 0 0 hour 30 580 17400.0
Drill
Driller day 3 1100 3300.0 Fuse Wire meter 180 0 0 Air Compressor hour 12 1459 17508.0
Credit for excavated rock for use @ 50 per cent of excavated
Blaster day 1 1100 1100.0 cum 0 3328 0
( if available rock is used, quantity = -45)
Sub total of A = 17300.0 Sub total of B = 0.0 Sub total of C = 70254.0 Sub total of D = 0.0
Sub total of A +B + C = 87554.0 Sub total of A + B + C + D= 87554.0 Contractor's overhead expenses 15% = 13133.1 Norms Rate = 100687.1
Unit Rate = 1118.75

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 23 of 276

Description of Work:
Earthwork Excavation in Cutting., Excavation in Hard Rock, manual Drilling, Roadway excavation in hard rock with manual drilling, blasting, breaking, lifts and leads all complete as per Drawing and instruction of the Engineer. 90 cum
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Crow bar and other T
9.1.III.B Skilled day 3 900 2700.0 Gelatin kg 32 0 0 2814.0
&P
Unskilled day 150 600 90000.0 Electric Detonator nos. 126 0 0
Blaster day 1 1100 1100.0 Fuse Wire meter 180 0 0
Credit for excavated rock for use @ 50 per cent of excavated
cum 0 3328 0
( if available rock is used, quantity = -45)
Sub total of A = 93800.0 Sub total of B = 0.0 Sub total of C = 2814.0 Sub total of D = 0.0
Sub total of A +B + C = 96614.0 Sub total of A + B + C + D= 96614.0 Contractor's overhead expenses 15% = 14492.1 Norms Rate = 111106.1
Unit Rate = 1234.51

Description of Work: Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting prohibited), Roadway Excavation in hard rock with rock breakers, including breaking rock, lifts and lead for disposal as per Drawing and Technical Specifications, Mechanical method, lead upto
16 cum
30 m
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.IV.A Skilled day 1 900 900.0 Hydraulic Excavator hour 6 3570 21420.0
Credit for excavated
rock for use @ 50 per
Unskilled day 10 600 6000.0 cent of excavated ( if cum 0 2000 0.0
available rock is used,
quantity = -8)
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 21420.0 Sub total of D = 0.0
Sub total of A +B + C = 28320.0 Sub total of A + B + C + D= 28320.0 Contractor's overhead expenses 15% = 4248.0 Norms Rate = 32568.0
Unit Rate = 2035.5

Description of Work:
Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting prohibited), Roadway Excavation in hard rock manually chiseling including breaking rock, lifts and lead for disposal as per Drawing and Technical Specifications , 16 cum
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Crow bar and other T
9.1.IV.B Skilled day 2 900 1800.0 1131.0
&P@
Credit for excavated
rock for use @ 50 per
Unskilled day 58 600 34800.0 cent of excavated ( if cum 0 2000 0.0
available rock is used,
quantity = -8)
Skilled
day 1 1100 1100.0
(Blacksmith)
Sub total of A = 37700.0 Sub total of B = 0.0 Sub total of C = 1131.0 Sub total of D = 0.0
Sub total of A +B + C = 38831.0 Sub total of A + B + C + D= 38831.0 Contractor's overhead expenses 15% = 5824.7 Norms Rate = 44655.7
Unit Rate = 2790.98

Description of Work:
Earthwork Excavation in Cutting., Excavation in Hard Rock (blasting prohibited), Roadway Excavation in hard rock manually with use of chemical, including breaking rock, disposal within all lifts and lead as per Drawing and Technical Specifications 16 cum
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Crow bar and other T
9.1.IV.C Skilled day 2 900 1800.0 Chemical kg 80 0 0 342.0
&P
Credit for excavated rock for use @ 50 per cent of excavated
Unskilled day 16 600 9600.0 cum 0 3328 0
( if available rock is used, quantity = -8)
Sub total of A = 11400.0 Sub total of B = 0.0 Sub total of C = 342.0 Sub total of D = 0.0
Sub total of A +B + C = 11742.0 Sub total of A + B + C + D= 11742.0 Contractor's overhead expenses 15% = 1761.3 Norms Rate = 13503.3
Unit Rate = 843.96

Description of Work:
Earthwork Excavation in Cutting., Excavation in Marshy Soil, Roadway Excavation in marshy soil as per Drawing and Technical Specifications 300 cum
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.1.V Skilled day 1 900 900.0 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 4 600 2400.0 Tipper hour 18 1454 26172.0
Sub total of A = 3300.0 Sub total of B = 0.0 Sub total of C = 47592.0 Sub total of D = 0.0
Sub total of A +B + C = 50892.0 Sub total of A + B + C + D= 50892.0 Contractor's overhead expenses 15% = 7633.8 Norms Rate = 58525.8
Unit Rate = 195.09

Description of Work:
Removal of Unserviceable Soil with Disposal upto 1000 meters, Removal of unserviceable soil including excavation, loading and disposal upto 1000 meters lead 360 cum

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 24 of 276
Removal of Unserviceable Soil with Disposal upto 1000 meters, Removal of unserviceable soil including excavation, loading and disposal upto 1000 meters lead 360 cum
Spec. cl. No: 900
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.2 Skilled day 1 900 900.0 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 4 600 2400.0 Tipper hour 18 1454 26172.0
Sub total of A = 3300.0 Sub total of B = 0.0 Sub total of C = 47592.0 Sub total of D = 0.0
Sub total of A +B + C = 50892.0 Sub total of A + B + C + D= 50892.0 Contractor's overhead expenses 15% = 7633.8 Norms Rate = 58525.8
Unit Rate = 162.57

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 25 of 276

Description of Work: Trimming/ Rock Excavation Slopes, Carrying out excavation in hard rock to achieve a specified slope of the rock face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock by machine, with all
400 sqm
lifts and lead as per Drawing and instruction of the Engineer.
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.3 Skilled day 1 900 900.0 Gelatin kg 42 0 0 Air Compressor hour 6 1459 8754.0
Jack Hammer/Rock
Unskilled day 22 600 13200.0 Electric Detonator nos. 672 0 0 hour 30 580 17400.0
Drill
Dozer hour 6 5891 35346.0
Loader hour 6 2957 17742.0
Sub total of A = 14100.0 Sub total of B = 0.0 Sub total of C = 79242.0 Sub total of D = 0.0
Sub total of A +B + C = 93342.0 Sub total of A + B + C + D= 93342.0 Contractor's overhead expenses 15% = 14001.3 Norms Rate = 107343.3
Unit Rate = 268.36

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Ordinary soil by Manual Means, Depth upto 3 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.I.A.i Skilled day 1 900 900.0
Unskilled day 8 600 4800.0
Sub total of A = 5700.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 5700.0 Sub total of A + B + C + D= 5700.0 Contractor's overhead expenses 15% = 855.0 Norms Rate = 6555.0
Unit Rate = 655.5

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Ordinary soil by Manual Means, Depth 3 m to 6 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.I.A.ii Skilled day 1 900 900.0
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 8100.0 Sub total of A + B + C + D= 8100.0 Contractor's overhead expenses 15% = 1215.0 Norms Rate = 9315.0
Unit Rate = 931.5

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Ordinary soil by Manual Means, Depth above 6 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.I.A.ii
Skilled day 2 900 1800.0
i
Unskilled day 18 600 10800.0
Sub total of A = 12600.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 12600.0 Sub total of A + B + C + D= 12600.0 Contractor's overhead expenses 15% = 1890.0 Norms Rate = 14490.0
Unit Rate = 1449

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
240 cum
Specifications., Ordinary soil by Mechanical Means, Depth upto 3 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.I.B.i Skilled day 1 900 900.0 0 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 3 600 1800.0
Sub total of A = 2700.0 Sub total of B = 0.0 Sub total of C = 21420.0 Sub total of D = 0.0
Sub total of A +B + C = 24120.0 Sub total of A + B + C + D= 24120.0 Contractor's overhead expenses 15% = 3618.0 Norms Rate = 27738.0
Unit Rate = 115.58

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
210 cum
Specifications., Ordinary soil by Mechanical Means, Depth 3 m to 6 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.I.B.ii Skilled day 1 900 900.0 0 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 3 600 1800.0
Sub total of A = 2700.0 Sub total of B = 0.0 Sub total of C = 21420.0 Sub total of D = 0.0
Sub total of A +B + C = 24120.0 Sub total of A + B + C + D= 24120.0 Contractor's overhead expenses 15% = 3618.0 Norms Rate = 27738.0
Unit Rate = 132.09

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
180 cum
Specifications., Ordinary soil by Mechanical Means, Depth above 6 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 26 of 276

9.4.I.B.ii
Skilled day 2 900 1800.0 0 Hydraulic Excavator hour 6 3570 21420.0
i
Unskilled day 4 600 2400.0
Sub total of A = 4200.0 Sub total of B = 0.0 Sub total of C = 21420.0 Sub total of D = 0.0
Sub total of A +B + C = 25620.0 Sub total of A + B + C + D= 25620.0 Contractor's overhead expenses 15% = 3843.0 Norms Rate = 29463.0
Unit Rate = 163.68

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 27 of 276

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Ordinary Rock (not requiring blasting) by Manual Means, Depth upto 3 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.II.A.i Skilled day 1 900 900.0
Unskilled day 10 600 6000.0
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 6900.0 Sub total of A + B + C + D= 6900.0 Contractor's overhead expenses 15% = 1035.0 Norms Rate = 7935.0
Unit Rate = 793.5

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
90 cum
Specifications., Ordinary Rock (not requiring blasting) by Mechanical Means, Depth upto 3 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.II.B Skilled day 1 900 900.0 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 3 600 1800.0
Sub total of A = 2700.0 Sub total of B = 0.0 Sub total of C = 21420.0 Sub total of D = 0.0
Sub total of A +B + C = 24120.0 Sub total of A + B + C + D= 24120.0 Contractor's overhead expenses 15% = 3618.0 Norms Rate = 27738.0
Unit Rate = 308.2

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Hard Rock ( requiring blasting ) by Manual Means
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.III.A Skilled day 1 900 900.0 Gelatin kg 3.5 0 0 Air Compressor hour 1 1459 1459.0
Jack Hammer/Rock
Driller day 0.5 1100 550.0 Electric Detonator nos 14 0 0 hour 3 580 1740.0
Drill
Blaster day 0.25 1100 275.0 Fuse Wire m 20 0 0
Unskilled day 12 600 7200.0
Sub total of A = 8925.0 Sub total of B = 0.0 Sub total of C = 3199.0 Sub total of D = 0.0
Sub total of A +B + C = 12124.0 Sub total of A + B + C + D= 12124.0 Contractor's overhead expenses 15% = 1818.6 Norms Rate = 13942.6
Unit Rate = 1394.26

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Hard Rock ( blasting prohibited ) by Mechanical Means
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.IV.A Skilled day 1 900 900.0 Air Compressor hour 3 1459 4377.0
Jack Hammer/Rock
Unskilled day 10 600 6000.0 hour 3 580 1740.0
Drill
Sub total of A = 6900.0 Sub total of B = 0.0 Sub total of C = 6117.0 Sub total of D = 0.0
Sub total of A +B + C = 13017.0 Sub total of A + B + C + D= 13017.0 Contractor's overhead expenses 15% = 1952.6 Norms Rate = 14969.6
Unit Rate = 1496.96

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Marshy Soil by Manual Means, Depth upto 3 m
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.V.A Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 15 600 9000.0
Sub total of A = 9900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 16560.0 Sub total of A + B + C + D= 16560.0 Contractor's overhead expenses 15% = 2484.0 Norms Rate = 19044.0
Unit Rate = 1904.4

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
10 cum
Specifications., Marshy Soil by Mechanical Means
Spec. cl. No: 907
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.V.B Skilled day 0.08 900 72.0 Hydraulic Excavator hour 0.3 3570 1071.0
Unskilled day 4 600 2400.0 Tipper hour 1 1454 1454.0
Sub total of A = 2472.0 Sub total of B = 0.0 Sub total of C = 2525.0 Sub total of D = 0.0
Sub total of A +B + C = 4997.0 Sub total of A + B + C + D= 4997.0 Contractor's overhead expenses 15% = 749.6 Norms Rate = 5746.6
Unit Rate = 574.66

Description of Work: Excavation for Structures Foundation, Earth work in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with approved Material as per Drawing and Technical
18 cum
Specifications., Back Filling in Marshy Foundation Pits
Spec. cl. No: 907

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 28 of 276

Norms Labour (A) Material (B) Equipment (C) Formworks (D)


No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.4.VI Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 14760.0 Sub total of A + B + C + D= 14760.0 Contractor's overhead expenses 15% = 2214.0 Norms Rate = 16974.0
Unit Rate = 943

Description of Work: Stripping and Storing Top Soil, Stripping, storing of top soil by road side at 15 m internal and re-application on embankment slopes, cut slopes and other areas in localities where the available embankment Material is not conducive to plant growth as per Drawing and
300 cum
Technical Specifications.

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 29 of 276
Description of Work: Stripping and Storing Top Soil, Stripping, storing of top soil by road side at 15 m internal and re-application on embankment slopes, cut slopes and other areas in localities where the available embankment Material is not conducive to plant growth as per Drawing and
300 cum
Technical Specifications.
Spec. cl. No: 905
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.5 Skilled day 2 900 1800.0 Dozer hour 6 5891 35346.0
Unskilled day 10 600 6000.0
Sub total of A = 7800.0 Sub total of B = 0.0 Sub total of C = 35346.0 Sub total of D = 0.0
Sub total of A +B + C = 43146.0 Sub total of A + B + C + D= 43146.0 Contractor's overhead expenses 15% = 6471.9 Norms Rate = 49617.9
Unit Rate = 165.39

Description of Work: Stripping, Storing and Re-laying Top Soil from Borrow Areas in Agriculture Fields., Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to maintain fertility of the
150 cum
agricultural field, finishing it to the required levels to the satisfaction of the farmer as per Drawing and Technical Specifications.
Spec. cl. No: 909
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.6 Skilled day 2 900 1800.0 Dozer hour 6 5891 35346.0
Unskilled day 15 600 9000.0
Sub total of A = 10800.0 Sub total of B = 0.0 Sub total of C = 35346.0 Sub total of D = 0.0
Sub total of A +B + C = 46146.0 Sub total of A + B + C + D= 46146.0 Contractor's overhead expenses 15% = 6921.9 Norms Rate = 53067.9
Unit Rate = 353.79

Description of Work: Preparation and Surface Treatment of Formation., Preparation and surface treatment of Formation by removing mud and slurry, watering to the extent needed to maintain desired moisture content , compacting all complete as per Drawing and Technical
3500 sqm
Specifications.
Spec. cl. No: 909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.7 Skilled day 1 900 900.0 Water KL 18 400 7200 Roller hour 6 1608 9648.0
Unskilled day 10 600 6000.0 Water Tanker hour 6 1806 10836.0
Sub total of A = 6900.0 Sub total of B = 7200.0 Sub total of C = 20484.0 Sub total of D = 0.0
Sub total of A +B + C = 34584.0 Sub total of A + B + C + D= 34584.0 Contractor's overhead expenses 15% = 5187.6 Norms Rate = 39771.6
Unit Rate = 11.36

Description of Work:
Construction of Embankment with Material obtained from Borrow pits, Providing, laying, spreading and compacting embankment with borrow material as per Drawing and Technical Specifications. 300 cum
Spec. cl. No: 909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.8 Skilled day 1 900 900.0 Water KL 72 400 28800 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 4 600 2400.0 Borrowpit Material cum 360 400 144000 Tractor with Rotavator hour 12 1133 13596.0
Dozer hour 3 5891 17673.0
Mortar Grader hour 3 3618 10854.0
Water Tanker hour 0 1806 0.0
Vibratory Road Roller hour 6 1806 10836.0
Sub total of A = 3300.0 Sub total of B = 172800.0 Sub total of C = 74379.0 Sub total of D = 0.0
Sub total of A +B + C = 250479.0 Sub total of A + B + C + D= 250479.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 250479.0
Unit Rate = 834.93

Description of Work:
Construction of Embankment with Material Deposited from Roadway Cutting, Providing, laying, spreading and compacting embankment with roadway cutting material and compact to the required density as per Drawing and Technical Specifications.( Manually) 100 cum
Spec. cl. No: 909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.9.A Skilled day 2 900 1800.0 Water KL 24 400 9600 Vibratory Road Roller hour 6 1806 10836.0
Unskilled day 50 600 30000.0
Sub total of A = 31800.0 Sub total of B = 9600.0 Sub total of C = 10836.0 Sub total of D = 0.0
Sub total of A +B + C = 52236.0 Sub total of A + B + C + D= 52236.0 Contractor's overhead expenses 15% = 7835.4 Norms Rate = 60071.4
Unit Rate = 600.71

Description of Work:
Construction of Embankment with Material Deposited from Roadway Cutting, Providing, laying, spreading and compacting embankment with roadway cutting material and compact to the required density as per Drawing and Technical Specifications. (With machine) 300 cum
Spec. cl. No: 909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.9.B Skilled day 1 900 900.0 Water KL 72 400 28800 Dozer hour 6 5891 35346.0
Unskilled day 10 600 6000.0 Mortar Grader hour 6 3618 21708.0
Water Tanker hour 12 1806 21672.0
Vibratory Road Roller hour 6 1806 10836.0
Sub total of A = 6900.0 Sub total of B = 28800.0 Sub total of C = 89562.0 Sub total of D = 0.0
Sub total of A +B + C = 125262.0 Sub total of A + B + C + D= 125262.0 Contractor's overhead expenses 15% = 18789.3 Norms Rate = 144051.3
Unit Rate = 480.17

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 30 of 276

Description of Work: Construction of Rock fill Embankment, Providing and laying of rock fill embankment with broken hard rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top layer with
150 cum
granular Material, rolled to required density all complete as per Drawing and Technical Specifications.
Spec. cl. No: 909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.10' Skilled day 1 900 900.0 Water KL 12 400 4800 Dozer hour 6 5891 35346.0
Unskilled day 10 600 6000.0 Vibratory Road Roller hour 6 1806 10836.0
Water Tanker hour 6 1806 10836.0
Sub total of A = 6900.0 Sub total of B = 4800.0 Sub total of C = 57018.0 Sub total of D = 0.0
Sub total of A +B + C = 68718.0 Sub total of A + B + C + D= 68718.0 Contractor's overhead expenses 15% = 10307.7 Norms Rate = 79025.7
Unit Rate = 526.84

Description of Work:
Providing suitable material and Back filling behind abutment, wing wall and return wall complete as per Drawing and Technical Specifications., Granular Material 10 cum
Spec. cl. No: 908
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.11.A Skilled day 0.2 900 180.0 Granular Material cum 11 1150 12650 Plate Compactor hour 2.5 289 722.5
Unskilled day 5 600 3000.0 Water KL 1 400 400
Sub total of A = 3180.0 Sub total of B = 13050.0 Sub total of C = 722.5 Sub total of D = 0.0
Sub total of A +B + C = 16952.5 Sub total of A + B + C + D= 16952.5 Contractor's overhead expenses 15% = 2542.9 Norms Rate = 19495.4
Unit Rate = 1949.54

Description of Work:
Providing suitable material and Back filling behind abutment, wing wall and return wall complete as per Drawing and Technical Specifications., Sandy Material 10 cum
Spec. cl. No: 908
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.11.B Skilled day 0.2 900 180.0 Sand cum 12 730 8760 Plate Compactor hour 2.5 289 722.5
Unskilled day 5 600 3000.0 Water KL 1 400 400
Sub total of A = 3180.0 Sub total of B = 9160.0 Sub total of C = 722.5 Sub total of D = 0.0
Sub total of A +B + C = 13062.5 Sub total of A + B + C + D= 13062.5 Contractor's overhead expenses 15% = 1959.4 Norms Rate = 15021.9
Unit Rate = 1502.19

Description of Work:
Providing suitable material and Back filling behind abutment, wing wall and return wall complete as per Drawing and Technical Specifications., Locally available Material including compaction by tamping rod ( without watering) 10 cum
Spec. cl. No: 908
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.11.C Skilled day 0.2 900 180.0 Compensation for Locally available Material cum 12 400 4800 Tamping 95.4
Unskilled day 5 600 3000.0 Water KL 1 400 400
Sub total of A = 3180.0 Sub total of B = 5200.0 Sub total of C = 95.4 Sub total of D = 0.0
Sub total of A +B + C = 8475.4 Sub total of A + B + C + D= 8475.4 Contractor's overhead expenses 15% = 1271.3 Norms Rate = 9746.7
Unit Rate = 974.67

Description of Work:
Providing suitable material and Back filling behind abutment, wing wall and return wall complete as per Drawing and Technical Specifications., Locally available Material, with out watering and compaction by tamping rod 10 cum
Spec. cl. No: 908
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.11.D Skilled day 0.2 900 180.0 Locally Available Material cum 12 400 4800 Tamping 77.4
Unskilled day 4 600 2400.0
Sub total of A = 2580.0 Sub total of B = 4800.0 Sub total of C = 77.4 Sub total of D = 0.0
Sub total of A +B + C = 7457.4 Sub total of A + B + C + D= 7457.4 Contractor's overhead expenses 15% = 1118.6 Norms Rate = 8576.0
Unit Rate = 857.6

Description of Work: Providing and laying of Filter media with granular Material/stone crushed aggregates to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return
10 cum
wall to the full height compacted to a firm condition complete as per drawing and Technical Specification.
Spec. cl. No: 909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.12 Skilled day 1 900 900.0 Filter Media cum 12 1250 15000
Unskilled day 10 600 6000.0 Water KL 1 400 400
Sub total of A = 6900.0 Sub total of B = 15400.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 22300.0 Sub total of A + B + C + D= 22300.0 Contractor's overhead expenses 15% = 3345.0 Norms Rate = 25645.0
Unit Rate = 2564.5

Description of Work:
Providing and filling sand in Foundation Trenches as per Drawing & Technical Specification 1 cum
Spec. cl. No: 909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
9.13 Skilled day 0.01 900 9.0 Sand cum 1.2 730 876
Unskilled day 0.3 600 180.0
Sub total of A = 189.0 Sub total of B = 876.0 Sub total of C = 0.0 Sub total of D = 0.0
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 31 of 276

Sub total of A +B + C = 1065.0 Sub total of A + B + C + D= 1065.0 Contractor's overhead expenses 15% = 159.8 Norms Rate = 1224.8
Unit Rate = 1224.75

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 32 of 276

Description of Work: Scarifying Existing road Surface to a Depth of 50 mm by


600 sqm
Manual Means, Scarifying the existing road surface to a depth of 50 mm and disposal of scarified Material with all lifts and leads as per Drawing and Technical Specifications.
Spec. cl. No: 1003
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.1.A Skilled day 1 900 900.0 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 15 600 9000.0
Sub total of A = 9900.0 Sub total of B = 0.0 Sub total of C = 6660.0 Sub total of D = 0.0
Sub total of A +B + C = 16560.0 Sub total of A + B + C + D= 16560.0 Contractor's overhead expenses 15% = 2484.0 Norms Rate = 19044.0
Unit Rate = 31.74

Description of Work: Scarifying Existing road Surface to a Depth of 50 mm by


600 sqm
Manual Means, Scarifying the existing granular road surface to a depth of 50mm and disposal of scarified Material with all lifts and leads within Right of way as per Drawing and Technical Specifications.
Spec. cl. No: 1003
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.1.B Skilled day 1 900 900.0
Unskilled day 12 600 7200.0
Sub total of A = 8100.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 8100.0 Sub total of A + B + C + D= 8100.0 Contractor's overhead expenses 15% = 1215.0 Norms Rate = 9315.0
Unit Rate = 15.53

Description of Work:
Scarifying Existing road Surface to a depth of 50 mm by Mechanical Means, Scarifying the existing road surface to a depth of 50 mm and disposal of scarified Material with in all lifts and lead as per Drawing and Technical Specifications. 600 sqm
Spec. cl. No: 1003
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.2.A Skilled day 1 900 900.0 Tractor with Ripper hour 6 1142 6852.0
Unskilled day 6 600 3600.0
Sub total of A = 4500.0 Sub total of B = 0.0 Sub total of C = 6852.0 Sub total of D = 0.0
Sub total of A +B + C = 11352.0 Sub total of A + B + C + D= 11352.0 Contractor's overhead expenses 15% = 1702.8 Norms Rate = 13054.8
Unit Rate = 21.76

Description of Work:
Scarifying Existing road Surface to a depth of 50 mm by Mechanical Means, Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified Material with in all lifts and lead as per Drawing and Technical Specifications. 3000 sqm
Spec. cl. No: 1003
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.2.B Skilled day 1 900 900.0 Tractor with Ripper hour 6 1142 6852.0
Unskilled day 6 600 3600.0 Loader hour 6 2957 17742.0
Tipper hour 6 1454 8724.0
Sub total of A = 4500.0 Sub total of B = 0.0 Sub total of C = 33318.0 Sub total of D = 0.0
Sub total of A +B + C = 37818.0 Sub total of A + B + C + D= 37818.0 Contractor's overhead expenses 15% = 5672.7 Norms Rate = 43490.7
Unit Rate = 14.5

Description of Work:
Construction of Subgrade and Earthen Shoulders with approved Material ( capping layer), Providing and laying sub-grade and earthen shoulders with approved Material obtained from borrow pits with all lifts & leads as per Drawing and Technical Specifications. 600 cum
Spec. cl. No: 1004
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.3.A Skilled day 1 900 900.0 Water KL 72 400 28800 Mortar Grader hour 6 3618 21708.0
Unskilled day 6 600 3600.0 Capping Layer Material cum 750 0 0 Vibratory Road Roller hour 6 2413 14478.0
Sub total of A = 4500.0 Sub total of B = 28800.0 Sub total of C = 36186.0 Sub total of D = 0.0
Sub total of A +B + C = 69486.0 Sub total of A + B + C + D= 69486.0 Contractor's overhead expenses 15% = 10422.9 Norms Rate = 79908.9
Unit Rate = 133.18

Description of Work:
Compacting Original Ground, Compacting original ground supporting sub-grade, Loosening of the ground upto a level of 500 mm below the sub-grade level, watered, graded and compacted in layers as per Drawing and Technical Specifications. 600 Cum
Spec. cl. No: 1003, 1005
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.4.I_a Skilled day 1 900 900.0 Water KL 24 400 9600 Tractor with Ripper hour 12 1142 13704.0
Unskilled day 5 600 3000.0 Mortar Grader hour 6 3618 21708.0
Vibratory Road Roller hour 12 2413 28956.0
Sub total of A = 3900.0 Sub total of B = 9600.0 Sub total of C = 64368.0 Sub total of D = 0.0
Sub total of A +B + C = 77868.0 Sub total of A + B + C + D= 77868.0 Contractor's overhead expenses 15% = 11680.2 Norms Rate = 89548.2
Unit Rate = 149.25

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 33 of 276

Description of Work: Compacting Original Ground, Compacting original ground supporting embankment, Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at
600 Cum
OMC and then compacted by rolling so as to achieve dry density as per Drawing and Technical Specifications.
Spec. cl. No: 1003, 1005
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
10.4.II_a Skilled day 1 900 900.0 Water KL 24 400 9600 Tractor with Ripper hour 6 1142 6852.0

Unskilled day 4 600 2400.0 Vibratory Road Roller hour 12 2413 28956.0
Sub total of A = 3300.0 Sub total of B = 9600.0 Sub total of C = 35808.0 Sub total of D = 0.0
Sub total of A +B + C = 48708.0 Sub total of A + B + C + D= 48708.0 Contractor's overhead expenses 15% = 7306.2 Norms Rate = 56014.2
Unit Rate = 93.36

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 34 of 276

Description of Work:
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density, complete as per Drawing and Technical Specifications., By Mechanical means 300 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.1.A Skilled day 2 900 1800.0 Sub-base Material S1 type or S2 type cum 384 1150 441600 Mortar Grader hour 0 3618 0.0
Unskilled day 12 600 7200.0 Water KL 18 400 7200 Vibratory Road Roller hour 12 2413 28956.0
Tractor / Loader hour 12 1110 13320.0
Sub total of A = 9000.0 Sub total of B = 448800.0 Sub total of C = 42276.0 Sub total of D = 0.0
Sub total of A +B + C = 500076.0 Sub total of A + B + C + D= 500076.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 500076.0
Unit Rate = 1666.92

Description of Work:
Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density, complete as per Drawing and Technical Specifications., By manual Means 200 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.1.B Skilled day 2 900 1800.0 Sub-base Material S1 type or S2 type cum 256 1150 294400 Vibratory Road Roller hour 6 2413 14478.0
Unskilled day 60 600 36000.0 Water KL 23 400 9200
Sub total of A = 37800.0 Sub total of B = 303600.0 Sub total of C = 14478.0 Sub total of D = 0.0
Sub total of A +B + C = 355878.0 Sub total of A + B + C + D= 355878.0 Contractor's overhead expenses 15% = 53381.7 Norms Rate = 409259.7
Unit Rate = 2046.3

Description of Work: Providing, laying and spreading soil on a prepared sub grade, pulverizing, adding the designed quantity of cement to the spread soil, mixing in place , grading and compacting at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-
300 cum
base/base as per Drawing and Technical Specifications., For 4 per cent quantity of cement by weight of soil
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.2 Skilled day 3 900 2700.0 Soil / Borrowpit Material cum 384 400 153600 Hydraulic Excavator hour 6 3570 21420.0
Unskilled day 15 600 9000.0 Cement tonne 21 17500 367500 Mortar Grader hour 6 3618 21708.0
Water KL 72 400 28800 Vibratory Road Roller hour 6 2413 14478.0

Tractor with Rotavator hour 12 1133 13596.0


Sub total of A = 11700.0 Sub total of B = 549900.0 Sub total of C = 71202.0 Sub total of D = 0.0
Sub total of A +B + C = 632802.0 Sub total of A + B + C + D= 632802.0 Contractor's overhead expenses 15% = 94920.3 Norms Rate = 727722.3
Unit Rate = 2425.74

Description of Work:
Providing, laying, spreading and compacting screening / coarse sand of specified grade in uniform layer on a prepared surface and compacting to form a inverted Choke as per Drawing and Technical Specifications. 600 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.5 Skilled day 3 900 2700.0 Screening / Coarse Sand cum 720 730 525600 Mortar Grader hour 6 3618 21708.0
Unskilled day 21 600 12600.0 Water KL 108 400 43200 Vibratory Road Roller hour 6 2413 14478.0
Sub total of A = 15300.0 Sub total of B = 568800.0 Sub total of C = 36186.0 Sub total of D = 0.0
Sub total of A +B + C = 620286.0 Sub total of A + B + C + D= 620286.0 Contractor's overhead expenses 15% = 93042.9 Norms Rate = 713328.9
Unit Rate = 1188.88

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Manual Means, By using stone screening 13.2mm and Vibratory roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.6.A_a Skilled day 10 900 9000.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 Vibratory Road Roller hour 12 2413 28956.0
Unskilled day 375 600 225000.0 Stone Screening for 13.2 mm cum 57.6 1725 99360
Water KL 144 400 57600
Sub total of A = 234000.0 Sub total of B = 657900.0 Sub total of C = 28956.0 Sub total of D = 0.0
Sub total of A +B + C = 920856.0 Sub total of A + B + C + D= 920856.0 Contractor's overhead expenses 15% = 138128.4 Norms Rate = 1058984.4
Unit Rate = 2941.62

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Manual Means, By using stone screening 13.2mm and Smooth 3 wheeled steel roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Smooth Wheeled
12.6.A_b Skilled day 10 900 9000.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 hour 12 1608 19296.0
Roller
Unskilled day 375 600 225000.0 Stone Screening for 13.2 mm cum 57.6 1725 99360
Water KL 144 400 57600
Sub total of A = 234000.0 Sub total of B = 657900.0 Sub total of C = 19296.0 Sub total of D = 0.0

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 35 of 276

Sub total of A +B + C = 911196.0 Sub total of A + B + C + D= 911196.0 Contractor's overhead expenses 15% = 136679.4 Norms Rate = 1047875.4
Unit Rate = 2910.77

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 36 of 276

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Manual Means, By using stone screening 11.2 mm for grading-II and Vibratory roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.6.A_c Skilled day 10 900 9000.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 Vibratory Road Roller hour 12 2413 28956.0
Unskilled day 375 600 225000.0 Stone Screening for 11.2 mm grading-II cum 86.4 1800 155520
Water KL 144 400 57600
Sub total of A = 234000.0 Sub total of B = 714060.0 Sub total of C = 28956.0 Sub total of D = 0.0
Sub total of A +B + C = 977016.0 Sub total of A + B + C + D= 977016.0 Contractor's overhead expenses 15% = 146552.4 Norms Rate = 1123568.4
Unit Rate = 3121.02

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Manual Means, By using stone screening 11.2 mm for grading-II and Smooth 3 wheeled
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Smooth Wheeled
12.6.A_d Skilled day 10 900 9000.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 hour 12 1608 19296.0
Roller
Unskilled day 375 600 225000.0 Stone Screening for 11.2 mm grading-II cum 86.4 1800 155520
Water KL 144 400 57600
Sub total of A = 234000.0 Sub total of B = 714060.0 Sub total of C = 19296.0 Sub total of D = 0.0
Sub total of A +B + C = 967356.0 Sub total of A + B + C + D= 967356.0 Contractor's overhead expenses 15% = 145103.4 Norms Rate = 1112459.4
Unit Rate = 3090.17

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Mechanical Means:, By using stone screening 13.2 mm for grading-II and vibratory roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.6.B_a Skilled day 3 900 2700.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 Mortar Grader hour 6 3618 21708.0

Unskilled day 15 600 9000.0 Stone screening for 13.2 mm grading-I cum 57.6 1725 99360 Vibratory Road Roller hour 6 2413 14478.0
Water KL 144 400 57600
Sub total of A = 11700.0 Sub total of B = 657900.0 Sub total of C = 36186.0 Sub total of D = 0.0
Sub total of A +B + C = 705786.0 Sub total of A + B + C + D= 705786.0 Contractor's overhead expenses 15% = 105867.9 Norms Rate = 811653.9
Unit Rate = 2254.59

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Mechanical Means:, By using stone screening 13.2 mm for grading-II and Smooth 3 wheeled steel roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.6.B_b Skilled day 3 900 2700.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 Mortar Grader hour 6 3618 21708.0

Smooth Wheeled
Unskilled day 15 600 9000.0 Stone screening for 13.2 mm grading-I cum 57.6 1725 99360 hour 12 1608 19296.0
Roller
Water KL 144 400 57600
Sub total of A = 11700.0 Sub total of B = 657900.0 Sub total of C = 41004.0 Sub total of D = 0.0
Sub total of A +B + C = 710604.0 Sub total of A + B + C + D= 710604.0 Contractor's overhead expenses 15% = 106590.6 Norms Rate = 817194.6
Unit Rate = 2269.99

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Mechanical Means:, By using stone screening 11.2 mm for grading-II and Smooth 3 vibratory roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.6.B_c Skilled day 3 900 2700.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 Mortar Grader hour 6 3618 21708.0

Unskilled day 15 600 9000.0 Stone Screening for 11.2 mm grading-II cum 86.4 1800 155520 Vibratory Road Roller hour 6 2413 14478.0
Water KL 144 400 57600
Sub total of A = 11700.0 Sub total of B = 714060.0 Sub total of C = 36186.0 Sub total of D = 0.0
Sub total of A +B + C = 761946.0 Sub total of A + B + C + D= 761946.0 Contractor's overhead expenses 15% = 114291.9 Norms Rate = 876237.9
Unit Rate = 2433.99

Description of Work: Providing, laying, spreading and compacting Water bound macadam including brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Drawing and Technical
360 cum
Specifications., By Mechanical Means:, By using stone screening 11.2 mm for grading-II and Smooth 3 wheeled steel roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.6.B_d Skilled day 3 900 2700.0 Aggregate (Grading as per specification) cum 435.6 1150 500940 Mortar Grader hour 6 3618 21708.0

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 37 of 276

Smooth Wheeled
Unskilled day 15 600 9000.0 Stone Screening for 11.2 mm grading-II cum 86.4 1800 155520 hour 12 1608 19296.0
Roller
Water KL 144 400 57600
Sub total of A = 11700.0 Sub total of B = 714060.0 Sub total of C = 41004.0 Sub total of D = 0.0
Sub total of A +B + C = 766764.0 Sub total of A + B + C + D= 766764.0 Contractor's overhead expenses 15% = 115014.6 Norms Rate = 881778.6
Unit Rate = 2449.39

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 38 of 276

Description of Work:
Providing and laying Crusher Run Macadam on a prepared surface, spreading and mixing , watering and compacting to form a layer of sub-base/Base course as per Drawing and Technical Specifications., By Mix in Place Method(Manual Method) 360 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.7_a Skilled day 3 900 2700.0 Aggregate at site
Unskilled day 14 600 8400.0 For 53 mm maximum size
Macadam Aggregate 63-45 mm cum 157.46 1150 181079
Macadam Aggregate 22.4-5.6 mm cum 151.06 1725 260578.5
Macadam Aggregate 5.6 mm and below cum 166.68 1800 300024
Water KL 36 400 14400
Sub total of A = 11100.0 Sub total of B = 756081.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 767181.5 Sub total of A + B + C + D= 767181.5 Contractor's overhead expenses 15% = 115077.2 Norms Rate = 882258.7
Unit Rate = 2450.72

Description of Work:
Providing and laying Crusher Run Macadam on a prepared surface, spreading and mixing , watering and compacting to form a layer of sub-base/Base course as per Drawing and Technical Specifications., By Mix in Place Method(Mechanical Means) 360 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.7_b Skilled day 3 900 2700.0 Aggregate at site Mortar Grader hour 6 3618 21708.0
Unskilled day 14 600 8400.0 For 45 mm maximum size Vibratory Road Roller hour 6 2413 14478.0
Macadam Aggregate 45-22.5 mm cum 24.12 1700 41004
Macadam Aggregate 22.4-5.6 mm cum 237.6 1725 409860
Macadam Aggregate 5.6 mm and below cum 213.48 1800 384264
Water KL 36 400 14400
Sub total of A = 11100.0 Sub total of B = 849528.0 Sub total of C = 36186.0 Sub total of D = 0.0
Sub total of A +B + C = 896814.0 Sub total of A + B + C + D= 896814.0 Contractor's overhead expenses 15% = 134522.1 Norms Rate = 1031336.1
Unit Rate = 2864.82

Description of Work:
Providing and laying Median and Island above road level with approved Material deposited including compacted as per Drawing and Specifications. ( using material from Roadway excavation). 21 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.8 Skilled day 1 900 900.0 Water KL 6 400 2400 Plate Compactor hour 9 289 2601.0
Unskilled day 9 600 5400.0
Sub total of A = 6300.0 Sub total of B = 2400.0 Sub total of C = 2601.0 Sub total of D = 0.0
Sub total of A +B + C = 11301.0 Sub total of A + B + C + D= 11301.0 Contractor's overhead expenses 15% = 1695.2 Norms Rate = 12996.2
Unit Rate = 618.86

Description of Work:
Providing and laying Median and Island above road level with approved Material deposited including compacted as per Drawing and Specifications. ( using material from borrow area). 21 cum
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.9 Skilled day 1 900 900.0 Soil / Borrowpit Material cum 27 400 10800 Plate Compactor hour 9 289 2601.0
Unskilled day 6 600 3600.0 Water KL 6 400 2400
Sub total of A = 4500.0 Sub total of B = 13200.0 Sub total of C = 2601.0 Sub total of D = 0.0
Sub total of A +B + C = 20301.0 Sub total of A + B + C + D= 20301.0 Contractor's overhead expenses 15% = 3045.2 Norms Rate = 23346.2
Unit Rate = 1111.72

Description of Work: Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub- base / base course on well prepared surface and compacting to achieve
225 cum
required density as per Drawing and Technical Specifications., Base course with B1 material, Vibratory Road Roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.14.A Skilled day 3 900 2700.0 Macadam Aggregate 45-22.4 mm cum 89.1 1700 151470 Wet Mix Plant hour 9 1621 14589.0
Unskilled day 10 600 6000.0 Macadam Aggregate 22.4-2.36 mm cum 118.8 1725 204930 Electric Generator hour 6 0 0.0
Macadam Aggregate 2.36 mm-75 micron cum 89.1 730 65043 Paver Finisher hour 6 4775 28650.0
Water KL 18 400 7200 Vibratory Road Roller hour 6 2413 14478.0
Sub total of A = 8700.0 Sub total of B = 428643.0 Sub total of C = 57717.0 Sub total of D = 0.0
Sub total of A +B + C = 495060.0 Sub total of A + B + C + D= 495060.0 Contractor's overhead expenses 15% = 74259.0 Norms Rate = 569319.0
Unit Rate = 2530.31

Description of Work: Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub- base / base course on well prepared surface and compacting to achieve
225 cum
required density as per Drawing and Technical Specifications., Base course with B2 material, Vibratory Road Roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.14.B Skilled day 3 900 2700.0 Macadam Aggregate 45-22.4 mm cum 89.1 1700 151470 Wet Mix Plant hour 9 1621 14589.0
Unskilled day 10 600 6000.0 Macadam Aggregate 22.4-2.36 mm cum 118.8 1725 204930 Electric Generator hour 6 0 0.0
Macadam Aggregate 2.36 mm-75 micron cum 89.1 730 65043 Paver Finisher hour 6 4775 28650.0

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 39 of 276

Water KL 18 400 7200 Vibratory Road Roller hour 6 2413 14478.0


Sub total of A = 8700.0 Sub total of B = 428643.0 Sub total of C = 57717.0 Sub total of D = 0.0
Sub total of A +B + C = 495060.0 Sub total of A + B + C + D= 495060.0 Contractor's overhead expenses 15% = 74259.0 Norms Rate = 569319.0
Unit Rate = 2530.31

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 40 of 276

Description of Work: Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub- base / base course on well prepared surface and compacting to achieve
225 cum
required density as per Drawing and Technical Specifications., Sub Base course with S1 material, Vibratory Road Roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.14.C Skilled day 3 900 2700.0 Macadam Aggregate 45-22.4 mm cum 89.1 1700 151470 Wet Mix Plant hour 9 1621 14589.0
Unskilled day 15 600 9000.0 Macadam Aggregate 22.4-2.36 mm cum 118.8 1725 204930 Electric Generator hour 6 0 0.0
Macadam Aggregate 2.36 mm-75 micron cum 89.1 730 65043 Paver Finisher hour 6 4775 28650.0
Water KL 18 400 7200 Vibratory Road Roller hour 6 2413 14478.0
Sub total of A = 11700.0 Sub total of B = 428643.0 Sub total of C = 57717.0 Sub total of D = 0.0
Sub total of A +B + C = 498060.0 Sub total of A + B + C + D= 498060.0 Contractor's overhead expenses 15% = 74709.0 Norms Rate = 572769.0
Unit Rate = 2545.64

Description of Work: Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC laying in uniform layers in sub- base / base course on well prepared surface and compacting to achieve
225 cum
required density as per Drawing and Technical Specifications., Sub Base course with S2 material, Vibratory Road Roller
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
12.14.D Skilled day 3 900 2700.0 Macadam Aggregate 45-22.4 mm cum 89.1 1700 151470 Wet Mix Plant hour 9 1621 14589.0
Unskilled day 15 600 9000.0 Macadam Aggregate 22.4-2.36 mm cum 118.8 1725 204930 Electric Generator hour 6 0 0.0
Macadam Aggregate 2.36 mm-75 micron cum 89.1 730 65043 Paver Finisher hour 6 4775 28650.0
Water KL 18 400 7200 Vibratory Road Roller hour 6 2413 14478.0
Sub total of A = 11700.0 Sub total of B = 428643.0 Sub total of C = 57717.0 Sub total of D = 0.0
Sub total of A +B + C = 498060.0 Sub total of A + B + C + D= 498060.0 Contractor's overhead expenses 15% = 74709.0 Norms Rate = 572769.0
Unit Rate = 2545.64

Description of Work: Prime Coat, Prime Coat, with MC 30 / 70 by Mechanical Means, Providing and applying prime coat with Hot Bitumen ( including cutter) on prepared surface of granular base including cleaning of road surface and spraying by mechanical means as per Technical
5000 lit
Specification ., Bitumen ( cutback) MC 30 ( for WBM)
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.1.A Skilled day 3 900 2700.0 Cutback Bitumen MC 30 tonne 5.25 78100 410025 Mechanical Broom hour 8 2020 16160.0
Unskilled day 50 600 30000.0 Water KL 10 400 4000 Air Compressor hour 8 1459 11672.0
Bitumen Distributor hour 6 4377 26262.0
Boiler hour 8 858 6864.0
Generator hour 8 1289 10312.0
Sub total of A = 32700.0 Sub total of B = 414025.0 Sub total of C = 71270.0 Sub total of D = 0.0
Sub total of A +B + C = 517995.0 Sub total of A + B + C + D= 517995.0 Contractor's overhead expenses 15% = 77699.3 Norms Rate = 595694.3
Unit Rate = 119.14

Description of Work: Prime Coat, Prime Coat, with MC 30 / 70 by Mechanical Means, Providing and applying prime coat with Hot Bitumen ( including cutter) on prepared surface of granular base including cleaning of road surface and spraying by mechanical means as per Technical
5000 lit
Specification ., Bitumen ( cutback) MC 30 ( for stabilized soil base/ crusher run macadam)
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.1.A_b Skilled day 3 900 2700.0 Cutback Bitumen MC 70 tonne 5.25 78100 410025 Mechanical Broom hour 8 2020 16160.0
Unskilled day 50 600 30000.0 Water KL 10 400 4000 Air Compressor hour 8 1459 11672.0
Bitumen Distributor hour 6 4377 26262.0
Boiler hour 8 858 6864.0
Generator hour 8 1289 10312.0
Sub total of A = 32700.0 Sub total of B = 414025.0 Sub total of C = 71270.0 Sub total of D = 0.0
Sub total of A +B + C = 517995.0 Sub total of A + B + C + D= 517995.0 Contractor's overhead expenses 15% = 77699.3 Norms Rate = 595694.3
Unit Rate = 119.14

Description of Work: , Prime Coat, with MC 30 / 70 by Bitumen , by manual means, Providing and applying prime coat with Hot Bitumen(including cutter) on prepared surface of granular base including cleaning of road surface and spraying at specified rate by manual means as per
1000 lit
Technical Specification . , Bitumen ( cutback) MC 30 ( for WBM)
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.1.B Skilled day 3 900 2700.0 Cutback Bitumen MC 30 tonne 1.1 78100 85910 Tractor hour 6 1110 6660.0
Unskilled day 100 600 60000.0 Water KL 10 400 4000 Bitumen Sprayer hour 6 881 5286.0
Boiler hour 8 858 6864.0
Generator hour 8 1289 10312.0
Sub total of A = 62700.0 Sub total of B = 89910.0 Sub total of C = 29122.0 Sub total of D = 0.0
Sub total of A +B + C = 181732.0 Sub total of A + B + C + D= 181732.0 Contractor's overhead expenses 15% = 27259.8 Norms Rate = 208991.8
Unit Rate = 208.99

Description of Work: , Prime Coat, with MC 30 / 70 by Bitumen , by manual means, Providing and applying prime coat with Hot Bitumen(including cutter) on prepared surface of granular base including cleaning of road surface and spraying at specified rate by manual means as per
1000 lit
Technical Specification . , Bitumen (cut back )MC 70 ( for stabilized soil base/ crusher run macadam)
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 41 of 276

13.1.B_b Skilled day 3 900 2700.0 Cutback Bitumen MC 70 tonne 1.1 78100 85910 Tractor hour 6 1110 6660.0
Unskilled day 100 600 60000.0 Water KL 10 400 4000 Bitumen Sprayer hour 6 881 5286.0
Boiler hour 8 858 6864.0
Generator hour 8 1289 10312.0
Sub total of A = 62700.0 Sub total of B = 89910.0 Sub total of C = 29122.0 Sub total of D = 0.0
Sub total of A +B + C = 181732.0 Sub total of A + B + C + D= 181732.0 Contractor's overhead expenses 15% = 27259.8 Norms Rate = 208991.8
Unit Rate = 208.99

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 42 of 276

Description of Work: , Prime Coat, with Emulsion by Mechanical Means, Providing and applying primer coat with Bitumen emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at specified rate using mechanical means as per Technical
5000 lit
Specification .
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.1.C Skilled day 3 900 2700.0 Bitumen Emulsion tonne 5.25 63600 333900 Mechanical Broom hour 8 2020 16160.0
Unskilled day 40 600 24000.0 Water KL 10 400 4000 Air Compressor hour 8 1459 11672.0
Bitumen Emulsion
hour 6 1721 10326.0
Pressure Distributor
Sub total of A = 26700.0 Sub total of B = 337900.0 Sub total of C = 38158.0 Sub total of D = 0.0
Sub total of A +B + C = 402758.0 Sub total of A + B + C + D= 402758.0 Contractor's overhead expenses 15% = 60413.7 Norms Rate = 463171.7
Unit Rate = 92.63

Description of Work:
, Prime Coat with emulsion, for manual works, Providing and applying primer coat with Bitumen emulsion on prepared surface of granular base including cleaning of road surface and spraying primer at specified rate as per Technical Specification. 1000 lit
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.1.D Skilled day 3 900 2700.0 Bitumen Emulsion tonne 1.1 63600 69960 Tractor - Trolley hour 6 1110 6660.0
Unskilled day 80 600 48000.0 Water KL 10 400 4000 Emulsion Sprayer hour 6 881 5286.0
Sub total of A = 50700.0 Sub total of B = 73960.0 Sub total of C = 11946.0 Sub total of D = 0.0
Sub total of A +B + C = 136606.0 Sub total of A + B + C + D= 136606.0 Contractor's overhead expenses 15% = 20490.9 Norms Rate = 157096.9
Unit Rate = 157.1

Description of Work:
Tack Coat, Tack coat with Bitumen By Mechanical Means, Providing and applying tack coat with hot Bitumen at specified rate on the prepared non-bituminous surfaces including cleaning as per Technical Speciation . 5000 lit
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.2.A Skilled day 3 900 2700.0 Bitumen tonne 5.25 77600 407400 Air Compressor hour 6 1459 8754.0
Unskilled day 20 600 12000.0 Bitumen Distributor hour 6 4377 26262.0
Boiler hour 6 858 5148.0
Generator hour 6 1289 7734.0
Sub total of A = 14700.0 Sub total of B = 407400.0 Sub total of C = 47898.0 Sub total of D = 0.0
Sub total of A +B + C = 469998.0 Sub total of A + B + C + D= 469998.0 Contractor's overhead expenses 15% = 70499.7 Norms Rate = 540497.7
Unit Rate = 108.1

Description of Work:
, Tack coat with Bitumen by Manual Means, Providing and applying tack coat with hot Bitumen at the specified rate the prepared surfaces including cleaning as per Technical Speciation . 1000 lit
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.2.B Skilled day 3 900 2700.0 Bitumen tonne 1.1 77600 85360 Tractor hour 6 1110 6660.0
Unskilled day 40 600 24000.0 Bitumen Sprayer hour 6 881 5286.0
Boiler hour 8 858 6864.0
Generator hour 8 1289 10312.0
Sub total of A = 26700.0 Sub total of B = 85360.0 Sub total of C = 29122.0 Sub total of D = 0.0
Sub total of A +B + C = 141182.0 Sub total of A + B + C + D= 141182.0 Contractor's overhead expenses 15% = 21177.3 Norms Rate = 162359.3
Unit Rate = 162.36

Description of Work:
, Tack coat with Emulsion By Mechanical Means, Providing and applying tack coat with Bitumen emulsion at specified rate on the prepared non-bituminous surfaces including cleaning as per Technical Speciation . 5000 lit
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.2.C Foreman day 2 715 1430.0 Bitumen Emulsion tonne 5.25 63600 333900 Air Compressor hour 6 1459 8754.0
Bitumen Emulsion
Unskilled day 20 600 12000.0 hour 6 1721 10326.0
Pressure Distributor
Generator hour 6 1289 7734.0
Sub total of A = 13430.0 Sub total of B = 333900.0 Sub total of C = 26814.0 Sub total of D = 0.0
Sub total of A +B + C = 374144.0 Sub total of A + B + C + D= 374144.0 Contractor's overhead expenses 15% = 56121.6 Norms Rate = 430265.6
Unit Rate = 86.05

Description of Work:
, Tack coat with Emulsion By Manual Means, Providing and applying tack coat with Bitumen emulsion at the specified rate the prepared surfaces including cleaning as per Technical Speciation . 1000 lit
Spec. cl. No: 1302
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.2.D Skilled day 2 900 1800.0 Bitumen Emulsion tonne 1.1 63600 69960 Boiler hour 6 858 5148.0
Unskilled day 20 600 12000.0 Water KL 1 400 400 Hand sprayer hour 6 0 0.0
Sub total of A = 13800.0 Sub total of B = 70360.0 Sub total of C = 5148.0 Sub total of D = 0.0
Sub total of A +B + C = 89308.0 Sub total of A + B + C + D= 89308.0 Contractor's overhead expenses 15% = 13396.2 Norms Rate = 102704.2
Unit Rate = 102.7

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 43 of 276

Description of Work: Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per specification premixed with bituminous binder, laid over a previously prepared surface as per Drawing and Technical Specifications. ,
102.5 cum
Grading I ( 40 mm nominal size )
Spec. cl. No: 1307
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.3 Skilled day 7 900 6300.0 Bitumen tonne 7.43 77600 576568 Batch mix HMP hour 6 64921 389526.0
Unskilled day 14 600 8400.0 Grading I ( 40 mm nominal size ) Air Compressor hour 6 1459 8754.0
Aggregate 37.5 - 25 mm cum 21.76 1700 36992 Paver Finisher hour 6 4775 28650.0
Aggregate 25 - 10 mm cum 65.28 1725 112608 Generator hour 6 1289 7734.0
Aggregate 10 - 5 mm cum 36.27 1800 65286 Pneumatic Roller hour 6 3319 19914.0
Aggregate 5 mm and below cum 21.76 1800 39168
Sub total of A = 14700.0 Sub total of B = 830622.0 Sub total of C = 454578.0 Sub total of D = 0.0
Sub total of A +B + C = 1299900.0 Sub total of A + B + C + D= 1299900.0 Contractor's overhead expenses 15% = 194985.0 Norms Rate = 1494885.0
Unit Rate = 14584.24

Description of Work: Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per specification premixed with bituminous binder, laid over a previously prepared surface as per Drawing and Technical Specifications. ,
102.5 cum
Grading I ( 40 mm nominal size ), In case BM is laid over freshly laid tack coat
Spec. cl. No: 1307
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.3_i Skilled day 7 900 6300.0 Bitumen tonne 7.43 77600 576568 Batch mix HMP hour 6 64921 389526.0
Unskilled day 12 600 7200.0 Grading I ( 40 mm nominal size ) Air Compressor hour 6 1459 8754.0
Aggregate 37.5 - 25 mm cum 21.76 1700 36992 Paver Finisher hour 6 4775 28650.0
Aggregate 25 - 10 mm cum 65.28 1725 112608 Generator hour 6 1289 7734.0
Aggregate 10 - 5 mm cum 36.27 1800 65286 Pneumatic Roller hour 6 3319 19914.0
Aggregate 5 mm and below cum 21.76 1800 39168 Mechanical Broom hour 8 2020 16160.0
Sub total of A = 13500.0 Sub total of B = 830622.0 Sub total of C = 470738.0 Sub total of D = 0.0
Sub total of A +B + C = 1314860.0 Sub total of A + B + C + D= 1314860.0 Contractor's overhead expenses 15% = 197229.0 Norms Rate = 1512089.0
Unit Rate = 14752.09

Description of Work: Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per specification premixed with bituminous binder, laid over a previously prepared surface as per Drawing and Technical Specifications. ,
102.5 cum
Grading II(19 mm nominal size)
Spec. cl. No: 1307
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.3_a Skilled day 7 900 6300.0 Bitumen tonne 7.43 77600 576568 Batch mix HMP hour 6 64921 389526.0
Unskilled day 14 600 8400.0 Grading II(19 mm nominal size) Air Compressor hour 6 1459 8754.0
Aggregate 25 - 10 mm cum 58.02 1725 100084.5 Paver Finisher hour 6 4775 28650.0
Aggregate 10 - 5 mm cum 58.02 1800 104436 Generator hour 6 1289 7734.0
Aggregate 5 mm and below cum 29.01 1800 52218 Pneumatic Roller hour 6 3319 19914.0
Sub total of A = 14700.0 Sub total of B = 833306.5 Sub total of C = 454578.0 Sub total of D = 0.0
Sub total of A +B + C = 1302584.5 Sub total of A + B + C + D= 1302584.5 Contractor's overhead expenses 15% = 195387.7 Norms Rate = 1497972.2
Unit Rate = 14614.36

Description of Work: Bituminous Macadam, Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per specification premixed with bituminous binder, laid over a previously prepared surface as per Drawing and Technical Specifications. ,
102.5 cum
Grading II(19 mm nominal size), In case BM is laid over freshly laid tack coat
Spec. cl. No: 1307
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.3_a_i Skilled day 7 900 6300.0 Bitumen tonne 7.43 77600 576568 Batch mix HMP hour 6 64921 389526.0
Unskilled day 12 600 7200.0 Grading II(19 mm nominal size) Air Compressor hour 6 1459 8754.0
Aggregate 25 - 10 mm cum 58.02 1725 100084.5 Paver Finisher hour 6 4775 28650.0
Aggregate 10 - 5 mm cum 58.02 1800 104436 Generator hour 6 1289 7734.0
Aggregate 5 mm and below cum 29.01 1800 52218 Pneumatic Roller hour 6 3319 19914.0
Mechanical Broom hour 8 2020 16160.0
Sub total of A = 13500.0 Sub total of B = 833306.5 Sub total of C = 470738.0 Sub total of D = 0.0
Sub total of A +B + C = 1317544.5 Sub total of A + B + C + D= 1317544.5 Contractor's overhead expenses 15% = 197631.7 Norms Rate = 1515176.2
Unit Rate = 14782.21

Description of Work: Bituminous Penetration Macadam, Providing and laying penetration macadam over prepared Base by providing a layer of compacted crushed coarse aggregate with applications of bituminous binder and key aggregates as per Drawing and Technical Specifications., 50
4500 sqm
mm thick
Spec. cl. No: 1304
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.4.A Unskilled day 9 600 5400.0 Bitumen tonne 15.3 77600 1187280 Chip Spreader hour 6 4444 26664.0
Skilled day 3 900 2700.0 Coarse Aggregate 45-2.8 mm cum 270 1700 459000 Bitumen Distributor hour 6 4377 26262.0
Key Aggregate 22.4-2.8 mm cum 67.5 1725 116437.5 Vibratory Road Roller hour 6 2413 14478.0
Sub total of A = 8100.0 Sub total of B = 1762717.5 Sub total of C = 67404.0 Sub total of D = 0.0
Sub total of A +B + C = 1838221.5 Sub total of A + B + C + D= 1838221.5 Contractor's overhead expenses 15% = 275733.2 Norms Rate = 2113954.7
Unit Rate = 469.77

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 44 of 276

Description of Work: Bituminous Penetration Macadam, Providing and laying penetration macadam over prepared Base by providing a layer of compacted crushed coarse aggregate with applications of bituminous binder and key aggregates as per Drawing and Technical Specifications.,
4500 sqm
75 mm thick
Spec. cl. No: 1304
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.4.B Unskilled day 12 600 7200.0 Bitumen tonne 22.7 77600 1761520 Chip Spreader hour 6 4444 26664.0
Skilled day 3 900 2700.0 Coarse Aggregate 63-2.8 mm cum 405 1150 465750 Bitumen Distributor hour 6 4377 26262.0
Key Aggregate 26.5-2.8 mm cum 81 1725 139725 Vibratory Road Roller hour 12 2413 28956.0
Sub total of A = 9900.0 Sub total of B = 2366995.0 Sub total of C = 81882.0 Sub total of D = 0.0
Sub total of A +B + C = 2458777.0 Sub total of A + B + C + D= 2458777.0 Contractor's overhead expenses 15% = 368816.6 Norms Rate = 2827593.6
Unit Rate = 628.35

Description of Work:
Dense Graded Bituminous Macadam, Providing and laying dense bituminous macadam using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications., Grading - I 40 mm (Nominal Size) 97.5 cum
Spec. cl. No: 1308
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.5 Unskilled day 16 600 9600.0 Bitumen tonne 9.56 77600 741856 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate Paver Finisher hour 6 4775 28650.0
Grading - I 40 mm (Nominal Size) Generator hour 6 1289 7734.0
Aggregate 37.5 - 25 mm cum 31.6 1700 53720 Pneumatic Roller hour 6 3319 19914.0
Aggregate 25 - 10 mm cum 18.67 1725 32205.75 Vibratory Road Roller hour 6 2413 14478.0

Smooth Wheeled
Aggregate 10 - 4.75 mm cum 27.29 1800 49122 hour 6 1608 9648.0
Roller
Aggregate 4.75 mm and below cum 63.2 1800 113760
Filler [stone_dust] tonne 4.31 630 2715.3
Sub total of A = 14100.0 Sub total of B = 993379.1 Sub total of C = 469950.0 Sub total of D = 0.0
Sub total of A +B + C = 1477429.1 Sub total of A + B + C + D= 1477429.1 Contractor's overhead expenses 15% = 221614.4 Norms Rate = 1699043.4
Unit Rate = 17426.09

Description of Work: Dense Graded Bituminous Macadam, Providing and laying dense bituminous macadam using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications., Grading - I 40 mm (Nominal Size), In case
97.5 cum
DBM is laid over freshly laid tack coat
Spec. cl. No: 1308
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.5_i Unskilled day 14 600 8400.0 Bitumen tonne 9.56 77600 741856 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate Paver Finisher hour 6 4775 28650.0
Grading - I 40 mm (Nominal Size) Generator hour 6 1289 7734.0
Aggregate 37.5 - 25 mm cum 31.6 1700 53720 Pneumatic Roller hour 6 3319 19914.0
Aggregate 25 - 10 mm cum 18.67 1725 32205.75 Vibratory Road Roller hour 6 2413 14478.0

Smooth Wheeled
Aggregate 10 - 4.75 mm cum 27.29 1800 49122 hour 6 1608 9648.0
Roller
Aggregate 4.75 mm and below cum 63.2 1800 113760 Mechanical Broom hour 8 2020 16160.0
Filler [stone_dust] tonne 4.31 630 2715.3
Sub total of A = 12900.0 Sub total of B = 993379.1 Sub total of C = 486110.0 Sub total of D = 0.0
Sub total of A +B + C = 1492389.1 Sub total of A + B + C + D= 1492389.1 Contractor's overhead expenses 15% = 223858.4 Norms Rate = 1716247.4
Unit Rate = 17602.54

Description of Work:
Dense Graded Bituminous Macadam, Providing and laying dense bituminous macadam using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications., Grading - II 19 mm (Nominal Size) 97.5 cum
Spec. cl. No: 1308
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.5_a Unskilled day 16 600 9600.0 Bitumen tonne 9.56 77600 741856 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate 0 Paver Finisher hour 6 4775 28650.0
Grading - II 19 mm (Nominal Size) 0 Generator hour 6 1289 7734.0
Aggregate 25 - 10 mm cum 43.08 1725 74313 Pneumatic Roller hour 6 3319 19914.0
Aggregate 10 - 5 mm cum 40.22 1800 72396 Vibratory Road Roller hour 6 2413 14478.0

Smooth Wheeled
Aggregate 5 mm and below cum 57.45 1800 103410 hour 6 1608 9648.0
Roller
Filler [stone_dust] tonne 4.31 630 2715.3
0
Sub total of A = 14100.0 Sub total of B = 994690.3 Sub total of C = 469950.0 Sub total of D = 0.0
Sub total of A +B + C = 1478740.3 Sub total of A + B + C + D= 1478740.3 Contractor's overhead expenses 15% = 221811.0 Norms Rate = 1700551.3
Unit Rate = 17441.55

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 45 of 276

Description of Work: Dense Graded Bituminous Macadam, Providing and laying dense bituminous macadam using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications., Grading - II 19 mm (Nominal Size), In case
97.5 cum
DBM is laid over freshly laid tack coat
Spec. cl. No: 1308
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.5_a_i Unskilled day 14 600 8400.0 Bitumen tonne 9.56 77600 741856 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate 0 Paver Finisher hour 6 4775 28650.0
Grading - II 19 mm (Nominal Size) 0 Generator hour 6 1289 7734.0
Aggregate 25 - 10 mm cum 43.08 1725 74313 Pneumatic Roller hour 6 3319 19914.0
Aggregate 10 - 5 mm cum 40.22 1800 72396 Vibratory Road Roller hour 6 2413 14478.0

Smooth Wheeled
Aggregate 5 mm and below cum 57.45 1800 103410 hour 6 1608 9648.0
Roller
Filler [stone_dust] tonne 4.31 630 2715.3 Mechanical Broom hour 8 2020 16160.0
0
Sub total of A = 12900.0 Sub total of B = 994690.3 Sub total of C = 486110.0 Sub total of D = 0.0
Sub total of A +B + C = 1493700.3 Sub total of A + B + C + D= 1493700.3 Contractor's overhead expenses 15% = 224055.0 Norms Rate = 1717755.3
Unit Rate = 17618

Description of Work: Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/ Asphalt concrete using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications, Grading - I-19 mm
95.5 cum
(Nominal Size)
Spec. cl. No: 1309
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.6 Unskilled day 15 600 9000.0 Bitumen tonne 12.94 77600 1004144 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate Paver Finisher hour 6 4775 28650.0
Grading - I-19 mm (Nominal Size) Generator hour 6 1289 7734.0
Smooth Wheeled
Aggregate 20 - 10 mm cum 49.48 1725 85353 hour 12 1608 19296.0
Roller
Aggregate 10 - 5 mm cum 32.52 1800 58536 Pneumatic Roller hour 6 3319 19914.0
Aggregate 5 mm and below cum 56.55 1800 101790
Filler [stone_dust] tonne 2.83 630 1782.9
Sub total of A = 13500.0 Sub total of B = 1251605.9 Sub total of C = 465120.0 Sub total of D = 0.0
Sub total of A +B + C = 1730225.9 Sub total of A + B + C + D= 1730225.9 Contractor's overhead expenses 15% = 259533.9 Norms Rate = 1989759.8
Unit Rate = 20835.18

Description of Work: Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/ Asphalt concrete using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications, Grading - I-19 mm
95.5 cum
(Nominal Size), In case BC is laid over freshly laid tack coat
Spec. cl. No: 1309
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.6_i Unskilled day 13 600 7800.0 Bitumen tonne 12.94 77600 1004144 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate Paver Finisher hour 6 4775 28650.0
Grading - I-19 mm (Nominal Size) Generator hour 6 1289 7734.0
Smooth Wheeled
Aggregate 20 - 10 mm cum 49.48 1725 85353 hour 12 1608 19296.0
Roller
Aggregate 10 - 5 mm cum 32.52 1800 58536 Pneumatic Roller hour 6 3319 19914.0
Aggregate 5 mm and below cum 56.55 1800 101790 Mechanical Broom hour 8 2020 16160.0
Filler [stone_dust] tonne 2.83 630 1782.9
Sub total of A = 12300.0 Sub total of B = 1251605.9 Sub total of C = 481280.0 Sub total of D = 0.0
Sub total of A +B + C = 1745185.9 Sub total of A + B + C + D= 1745185.9 Contractor's overhead expenses 15% = 261777.9 Norms Rate = 2006963.8
Unit Rate = 21015.33

Description of Work: Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/ Asphalt concrete using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications, Grading - II-13 mm
95.5 cum
(Nominal Size)
Spec. cl. No: 1309
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.6_a Unskilled day 15 600 9000.0 Bitumen tonne 12.94 77600 1004144 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate Paver Finisher hour 6 4775 28650.0
Grading - II-13 mm (Nominal Size) Generator hour 6 1289 7734.0
Smooth Wheeled
Aggregate 13.2 - 10 mm cum 42.41 1725 73157.25 hour 12 1608 19296.0
Roller
Aggregate 10 - 5 mm cum 35.34 1800 63612 Pneumatic Roller hour 6 3319 19914.0
Aggregate 5 mm and below cum 60.79 1800 109422
Filler [cement] tonne 2.83 17500 49525
Sub total of A = 13500.0 Sub total of B = 1299860.3 Sub total of C = 465120.0 Sub total of D = 0.0
Sub total of A +B + C = 1778480.3 Sub total of A + B + C + D= 1778480.3 Contractor's overhead expenses 15% = 266772.0 Norms Rate = 2045252.3
Unit Rate = 21416.25

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 46 of 276

Description of Work: Bituminous Concrete / Asphalt Concrete, Providing and laying Bituminous concrete/ Asphalt concrete using crushed aggregates of specified grading, premixed with bituminous binder and filler as per Drawing and Technical Specifications, Grading - II-13 mm
95.5 cum
(Nominal Size), In case BC is laid over freshly laid tack coat
Spec. cl. No: 1309
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.6_a_i Unskilled day 13 600 7800.0 Bitumen tonne 12.94 77600 1004144 Batch mix HMP hour 6 64921 389526.0
Skilled day 5 900 4500.0 Aggregate Paver Finisher hour 6 4775 28650.0
Grading - II-13 mm (Nominal Size) Generator hour 6 1289 7734.0
Smooth Wheeled
Aggregate 13.2 - 10 mm cum 42.41 1725 73157.25 hour 12 1608 19296.0
Roller
Aggregate 10 - 5 mm cum 35.34 1800 63612 Pneumatic Roller hour 6 3319 19914.0
Aggregate 5 mm and below cum 60.79 1800 109422 Mechanical Broom hour 8 2020 16160.0
Filler [stone_dust] tonne 2.83 630 1782.9
Sub total of A = 12300.0 Sub total of B = 1252118.2 Sub total of C = 481280.0 Sub total of D = 0.0
Sub total of A +B + C = 1745698.2 Sub total of A + B + C + D= 1745698.2 Contractor's overhead expenses 15% = 261854.7 Norms Rate = 2007552.9
Unit Rate = 21021.5

Description of Work: Surface Dressing, Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied layer of bituminous binder on prepared surface as per Drawing and Technical Specifications., MECHANICAL MEANS, 19 mm
6000 sqm
nominal chipping size
Spec. cl. No: 1303
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.7.A.I Unskilled day 12 600 7200.0 Chips 19 mm cum 102 1475 150450 Chip Spreader hour 6 4444 26664.0
Skilled day 3 900 2700.0 Pneumatic Roller hour 12 3319 39828.0
Sub total of A = 9900.0 Sub total of B = 150450.0 Sub total of C = 66492.0 Sub total of D = 0.0
Sub total of A +B + C = 226842.0 Sub total of A + B + C + D= 226842.0 Contractor's overhead expenses 15% = 34026.3 Norms Rate = 260868.3
Unit Rate = 43.48

Description of Work: Surface Dressing, Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied layer of bituminous binder on prepared surface as per Drawing and Technical Specifications., MECHANICAL MEANS, 13 mm
7500 sqm
nominal size chipping
Spec. cl. No: 1303
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.7.A.II Unskilled day 12 600 7200.0 Crushed Stone Chipping 13 mm cum 87 1475 128325 Chip Spreader hour 6 4444 26664.0
Skilled day 3 900 2700.0 Pneumatic Roller hour 12 3319 39828.0
Sub total of A = 9900.0 Sub total of B = 128325.0 Sub total of C = 66492.0 Sub total of D = 0.0
Sub total of A +B + C = 204717.0 Sub total of A + B + C + D= 204717.0 Contractor's overhead expenses 15% = 30707.6 Norms Rate = 235424.6
Unit Rate = 31.39

Description of Work: Surface Dressing, Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied layer of bituminous binder on prepared surface as per Drawing and Technical Specifications., MECHANICAL MEANS, 10 mm
9000 sqm
nominal size chipping
Spec. cl. No: 1303
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.7.A.II
Unskilled day 12 600 7200.0 Crushed Stone Chipping 10 mm cum 80.3 1475 118442.5 Chip Spreader hour 6 4444 26664.0
I
Skilled day 3 900 2700.0 Pneumatic Roller hour 12 3319 39828.0
Sub total of A = 9900.0 Sub total of B = 118442.5 Sub total of C = 66492.0 Sub total of D = 0.0
Sub total of A +B + C = 194834.5 Sub total of A + B + C + D= 194834.5 Contractor's overhead expenses 15% = 29225.2 Norms Rate = 224059.7
Unit Rate = 24.9

Description of Work: Surface Dressing, Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied layer of bituminous binder on prepared surface as per Drawing and Technical Specifications., MECHANICAL MEANS, 6.0 mm
9000 sqm
nominal size chipping
Spec. cl. No: 1303
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.7.A.I
Unskilled day 12 600 7200.0 Crushed Stone Chipping 6 mm cum 48.2 1475 71095 Chip Spreader hour 6 4444 26664.0
V
Skilled day 3 900 2700.0 Pneumatic Roller hour 12 3319 39828.0
Sub total of A = 9900.0 Sub total of B = 71095.0 Sub total of C = 66492.0 Sub total of D = 0.0
Sub total of A +B + C = 147487.0 Sub total of A + B + C + D= 147487.0 Contractor's overhead expenses 15% = 22123.1 Norms Rate = 169610.1
Unit Rate = 18.85

Description of Work: Surface Dressing, Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied layer of bituminous binder on prepared surface as per Drawing and Technical Specifications., MANUAL MEANS, 19 mm
600 sqm
nominal size chipping
Spec. cl. No: 1303
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.7.B.I Unskilled day 12 600 7200.0 Crushed Stone Chipping 19 mm cum 10.2 1475 15045 Pneumatic Roller hour 6 3319 19914.0
Add: 0.5 percent of
Skilled day 3 900 2700.0 49.5
Labour for T&P
Sub total of A = 9900.0 Sub total of B = 15045.0 Sub total of C = 19963.5 Sub total of D = 0.0
Sub total of A +B + C = 44908.5 Sub total of A + B + C + D= 44908.5 Contractor's overhead expenses 15% = 6736.3 Norms Rate = 51644.8
Unit Rate = 86.07

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 47 of 276

Description of Work: Surface Dressing, Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied layer of bituminous binder on prepared surface as per Drawing and Technical Specifications., MANUAL MEANS, 13 mm
900 sqm
nominal size chipping
Spec. cl. No: 1303
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.7.B.II Unskilled day 12 600 7200.0 Crushed Stone Chipping 13 mm cum 10.4 1475 15340 Pneumatic Roller hour 2.25 3319 7467.8

Add: 0.5 per cent of (a)


Skilled day 3 900 2700.0 49.5
Labour for T&P
Sub total of A = 9900.0 Sub total of B = 15340.0 Sub total of C = 7517.3 Sub total of D = 0.0
Sub total of A +B + C = 32757.3 Sub total of A + B + C + D= 32757.3 Contractor's overhead expenses 15% = 4913.6 Norms Rate = 37670.8
Unit Rate = 41.86

Description of Work: Surface Dressing, Providing and laying surface dressing as wearing course in single coat using gravel of specified size on a recently applied layer of bituminous binder on prepared surface as per Drawing and Technical Specifications., MANUAL MEANS, 10 mm
1000 sqm
nominal size chipping
Spec. cl. No: 1303
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.7.B.II
Unskilled day 12 600 7200.0 Crushed Stone Chipping 10 mm cum 8.9 1475 13127.5 Pneumatic Roller hour 2.25 3319 7467.8
I
Add: 0.5 per cent of (a)
Skilled day 3 900 2700.0 49.5
Labour for T&P
Sub total of A = 9900.0 Sub total of B = 13127.5 Sub total of C = 7517.3 Sub total of D = 0.0
Sub total of A +B + C = 30544.8 Sub total of A + B + C + D= 30544.8 Contractor's overhead expenses 15% = 4581.7 Norms Rate = 35126.5
Unit Rate = 35.13

Description of Work:
Pre-coating Chips, Pre-coating of chips with 1 per cent of paving bitumen by weight of chips in a suitable mixer duly heated to 160 degree C as per Technical Specification 30 cum
Spec. cl. No: N/A
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.8 Skilled day 0.5 900 450.0 Bitumen tonne 0.48 77600 37248 Bitumen Boiler hour 6 858 5148.0
Unskilled day 24 600 14400.0 Mixture Machine hour 6 765 4590.0
Sub total of A = 14850.0 Sub total of B = 37248.0 Sub total of C = 9738.0 Sub total of D = 0.0
Sub total of A +B + C = 61836.0 Sub total of A + B + C + D= 61836.0 Contractor's overhead expenses 15% = 9275.4 Norms Rate = 71111.4
Unit Rate = 2370.38

Description of Work: 40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen / Modified bitumen) Binder, Providing and laying open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates as wearing course on a previously prepared
500 sqm
base as per drawing and Technical Specifications ., By Manual Means
Spec. cl. No: 1311
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.9.A Unskilled day 21 600 12600.0 Paving Bitumen or other as per Design tonne 1.46 77600 113296 Mixer hour 4 64921 259684.0
Skilled day 8 900 7200.0 Crushed Stone Chipping 13.2-5.6 mm cum 27 1800 48600 Bitumen Boiler hour 4 858 3432.0
Smooth Wheeled
hour 2 1608 3216.0
Roller
Sub total of A = 19800.0 Sub total of B = 161896.0 Sub total of C = 266332.0 Sub total of D = 0.0
Sub total of A +B + C = 448028.0 Sub total of A + B + C + D= 448028.0 Contractor's overhead expenses 15% = 67204.2 Norms Rate = 515232.2
Unit Rate = 1030.46

Description of Work: 40 mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen / Modified bitumen) Binder, By Mechanical Means, Providing and laying open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates as wearing course on a
4000 sqm
previously prepared base as per drawing and Technical Specifications ., Mechanical method using Hot Mix Plant
Spec. cl. No: 1311
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.9.B.i Unskilled day 16 600 9600.0 Bitumen tonne 11.68 77600 906368 Hot Mix Plant hour 6 64921 389526.0
Skilled day 5 900 4500.0 Crushed Stone Chipping 13.2-5.6 mm cum 216 1800 388800 Generator hour 6 1289 7734.0
Paver Finisher hour 6 4775 28650.0
Smooth Wheeled
hour 6 1608 9648.0
Roller
Sub total of A = 14100.0 Sub total of B = 1295168.0 Sub total of C = 435558.0 Sub total of D = 0.0
Sub total of A +B + C = 1744826.0 Sub total of A + B + C + D= 1744826.0 Contractor's overhead expenses 15% = 261723.9 Norms Rate = 2006549.9
Unit Rate = 12541

Description of Work: 40mm thick Open-Graded Premix Carpet using Bituminous (Paving bitumen / Modified bitumen) Binder, By Mechanical Means, Providing and laying open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates as wearing course on a
900 cum
previously prepared base as per drawing and Technical Specifications ., Open-Graded Premix Surfacing using cationic Bitumen Emulsion
Spec. cl. No: 1311
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.9.B.ii Unskilled day 18 600 10800.0 Bitumen Emulsion tonne 3.88 63600 246768 Concrete Mixer hour 6 362 2172.0
Smooth Wheeled
Skilled day 3 900 2700.0 Crushed Stone Aggregate 13.2-5.6 mm cum 48.6 1725 83835 hour 6 1608 9648.0
Roller
Sub total of A = 13500.0 Sub total of B = 330603.0 Sub total of C = 11820.0 Sub total of D = 0.0
Sub total of A +B + C = 355923.0 Sub total of A + B + C + D= 355923.0 Contractor's overhead expenses 15% = 53388.5 Norms Rate = 409311.5
Unit Rate = 454.79

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 48 of 276

Description of Work: Close Graded Premix Surfacing/Mixed Seal Surfacing , Mechanical means using HMP of appropriate capacity ,, Providing and laying close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm or 13.2 mm to 0.09 mm aggregates using
10250 sqm
bitumen as wearing course on a previously prepared base, including mixing in a suitable plant as per Drawing and Technical Specifications., Type - A
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.10_a Unskilled day 16 600 9600.0 Bitumen tonne 22.5 77600 1746000 HMP hour 6 64921 389526.0
Skilled day 6 900 5400.0 Crushed Stone Aggregate 11.2-0.09 mm cum 276.75 1800 498150 Generator hour 6 1289 7734.0
Loader hour 6 2957 17742.0
Paver Finisher hour 6 4775 28650.0
Smooth Wheeled
hour 6 1608 9648.0
Roller
Sub total of A = 15000.0 Sub total of B = 2244150.0 Sub total of C = 453300.0 Sub total of D = 0.0
Sub total of A +B + C = 2712450.0 Sub total of A + B + C + D= 2712450.0 Contractor's overhead expenses 15% = 406867.5 Norms Rate = 3119317.5
Unit Rate = 304.32

Description of Work: Close Graded Premix Surfacing/Mixed Seal Surfacing , Mechanical means using HMP of appropriate capacity ,, Providing and laying close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm or 13.2 mm to 0.09 mm aggregates using
10250 sqm
bitumen as wearing course on a previously prepared base, including mixing in a suitable plant as per Drawing and Technical Specifications., Type - B
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.10_b Unskilled day 16 600 9600.0 Type - B HMP hour 6 64921 389526.0
Skilled day 6 900 5400.0 Bitumen tonne 19.48 77600 1511648 Generator hour 6 1289 7734.0
Crushed Stone Aggregate 13.2-0.09 mm cum 276.75 1725 477393.75 Loader hour 6 2957 17742.0
Paver Finisher hour 6 4775 28650.0
Smooth Wheeled
hour 6 1608 9648.0
Roller
Sub total of A = 15000.0 Sub total of B = 1989041.8 Sub total of C = 453300.0 Sub total of D = 0.0
Sub total of A +B + C = 2457341.8 Sub total of A + B + C + D= 2457341.8 Contractor's overhead expenses 15% = 368601.3 Norms Rate = 2825943.0
Unit Rate = 275.7

Description of Work:
Seal Surfacing, Providing and laying seal coat sealing the voids in a bituminous surface as per Drawing and Technical Specifications. 7858 sqm
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.11 Skilled day 1 900 900.0 Bitumen tonne 5.34 77600 414384 HMP hour 3 64921 194763.0
Unskilled day 6 600 3600.0 sand cum 47.16 730 34426.8 Generator hour 3 1289 3867.0
Paver Finisher hour 6 4775 28650.0
Roller hour 6 1608 9648.0
Sub total of A = 4500.0 Sub total of B = 448810.8 Sub total of C = 236928.0 Sub total of D = 0.0
Sub total of A +B + C = 690238.8 Sub total of A + B + C + D= 690238.8 Contractor's overhead expenses 15% = 103535.8 Norms Rate = 793774.6
Unit Rate = 101.01

Description of Work: Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine aggregates, Portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to
16000 sqm
provide even riding surface as per Drawing and Technical Specifications., 5 mm thickness
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.12.i Skilled day 1 900 900.0 Binder tonne 19.36 63600 1231296 Mechanical Broom hour 6 2020 12120.0
Unskilled day 8 600 4800.0 Fine Aggregate 4.75 mm cum 102.08 730 74518.4 Air Compressor hour 6 1459 8754.0
Mobile Slurry Seal
Filler tonne 3.52 730 2569.6 hour 6 2283 13698.0
Equipment
Water KL 12 400 4800 Pneumatic Roller hour 6 3319 19914.0
Sub total of A = 5700.0 Sub total of B = 1313184.0 Sub total of C = 54486.0 Sub total of D = 0.0
Sub total of A +B + C = 1373370.0 Sub total of A + B + C + D= 1373370.0 Contractor's overhead expenses 15% = 206005.5 Norms Rate = 1579375.5
Unit Rate = 98.71

Description of Work: Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine aggregates, Portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to
20000 sqm
provide even riding surface as per Drawing and Technical Specifications., 3 mm thickness
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.12.ii Skilled day 1 900 900.0 Binder tonne 17.16 63600 1091376 Mechanical Broom hour 6 2020 12120.0
Unskilled day 7 600 4200.0 Fine Aggregate 3 mm and below cum 74.8 730 54604 Air Compressor hour 6 1459 8754.0
Mobile Slurry Seal
Filler tonne 2.64 730 1927.2 hour 6 2283 13698.0
Equipment
Water KL 12 400 4800
Sub total of A = 5100.0 Sub total of B = 1152707.2 Sub total of C = 34572.0 Sub total of D = 0.0
Sub total of A +B + C = 1192379.2 Sub total of A + B + C + D= 1192379.2 Contractor's overhead expenses 15% = 178856.9 Norms Rate = 1371236.1
Unit Rate = 68.56

Description of Work: Slurry Seal, Providing and laying slurry seal consisting of a mixture of fine aggregates, Portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to
24000 sqm
provide even riding surface as per Drawing and Technical Specifications., 1.5 mm thickness
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 49 of 276
Norms
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.12.iii Skilled day 1 900 900.0 Binder tonne 12.67 63600 805812 Mechanical Broom hour 6 2020 12120.0
Unskilled day 7 600 4200.0 Fine Aggregate 2.36 mm cum 43.3 730 31609 Air Compressor hour 6 1459 8754.0
Mobile Slurry Seal
Filler tonne 1.58 730 1153.4 hour 6 2283 13698.0
Equipment
Water KL 12 400 4800
Sub total of A = 5100.0 Sub total of B = 843374.4 Sub total of C = 34572.0 Sub total of D = 0.0
Sub total of A +B + C = 883046.4 Sub total of A + B + C + D= 883046.4 Contractor's overhead expenses 15% = 132457.0 Norms Rate = 1015503.4
Unit Rate = 42.31

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 50 of 276

Description of Work:
Fog Spray, Providing and applying low viscosity bitumen emulsion for sealing cracks less than 3 mm wide or incipient fretting or disintegration in an existing bituminous surfacing as per Drawing and Technical Specifications. 10500 sqm
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.13 Skilled day 1 900 900.0 Bitumen Emulsion tonne 7.88 63600 501168 Mechanical Broom hour 6 2020 12120.0
Unskilled day 4 600 2400.0 Air Compressor hour 6 1459 8754.0
Bitumen Emulsion
hour 6 1721 10326.0
Pressure Distributor
Sub total of A = 3300.0 Sub total of B = 501168.0 Sub total of C = 31200.0 Sub total of D = 0.0
Sub total of A +B + C = 535668.0 Sub total of A + B + C + D= 535668.0 Contractor's overhead expenses 15% = 80350.2 Norms Rate = 616018.2
Unit Rate = 58.67

Description of Work:
Fog Spray, Providing and applying low viscosity bitumen emulsion for sealing cracks less than 3 mm wide or incipient fretting or disintegration in an existing bituminous surfacing as per Drawing and Technical Specifications., Blind the fog spray 10500 sqm
Spec. cl. No: 1310
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.13_a Skilled day 2 900 1800.0 Crushed Stone Grit 3 mm cum 26.25 730 19162.5 Mechanical Broom hour 6 2020 12120.0
Unskilled day 10 600 6000.0 Bitumen Emulsion tonne 8.67 63600 551412 Air Compressor hour 6 1459 8754.0
Bitumen Emulsion
hour 6 1721 10326.0
Pressure Distributor
Sub total of A = 7800.0 Sub total of B = 570574.5 Sub total of C = 31200.0 Sub total of D = 0.0
Sub total of A +B + C = 609574.5 Sub total of A + B + C + D= 609574.5 Contractor's overhead expenses 15% = 91436.2 Norms Rate = 701010.7
Unit Rate = 66.76

Description of Work: Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of bituminous cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type as per
205 cum
Drawing and Technical Specifications., Using bitumen emulsion and 9.5 mm or 13.2 mm size aggregate
Spec. cl. No: 1313
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.14.i Unskilled day 16 600 9600.0 Bitumen Emulsion tonne 36 63600 2289600 Drum Mix Plant hour 6 1718 10308.0
Skilled day 6 900 5400.0 Filler (Lime) tonne 9 30000 270000 Generator hour 6 1289 7734.0
Aggregate 19-9.5 mm cum 75 1800 135000 Paver Finisher hour 6 4775 28650.0
Aggregate 9.5-6 mm cum 87 1800 156600 Pneumatic Roller hour 6 3319 19914.0
Smooth Wheeled
Aggregate 6-0.075 mm cum 108 1800 194400 hour 6 1608 9648.0
Roller
Sub total of A = 15000.0 Sub total of B = 3045600.0 Sub total of C = 76254.0 Sub total of D = 0.0
Sub total of A +B + C = 3136854.0 Sub total of A + B + C + D= 3136854.0 Contractor's overhead expenses 15% = 470528.1 Norms Rate = 3607382.1
Unit Rate = 17596.99

Description of Work: Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of bituminous cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type as per
205 cum
Drawing and Technical Specifications., Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate
Spec. cl. No: 1313
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.14.ii Unskilled day 16 600 9600.0 Bitumen Emulsion tonne 36 63600 2289600 Drum Mix Plant hour 6 1718 10308.0
Skilled day 6 900 5400.0 Filler (Lime) tonne 9 30000 270000 Generator hour 6 1289 7734.0
Aggregate 37.5-19 mm cum 75 1700 127500 Paver Finisher hour 6 4775 28650.0
Aggregate 19-6 mm cum 90 1725 155250 Pneumatic Roller hour 6 3319 19914.0
Smooth Wheeled
Aggregate 6-0.075 mm cum 105 1800 189000 hour 6 1608 9648.0
Roller
Sub total of A = 15000.0 Sub total of B = 3031350.0 Sub total of C = 76254.0 Sub total of D = 0.0
Sub total of A +B + C = 3122604.0 Sub total of A + B + C + D= 3122604.0 Contractor's overhead expenses 15% = 468390.6 Norms Rate = 3590994.6
Unit Rate = 17517.05

Description of Work: Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of bituminous cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type as per
205 cum
Drawing and Technical Specifications., Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate
Spec. cl. No: 1313
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.14.iii Unskilled day 16 600 9600.0 Cutback Bitumen tonne 22.5 78100 1757250 Drum Mix Plant hour 6 1718 10308.0
Skilled day 6 900 5400.0 Filler (Lime) tonne 9 30000 270000 Generator hour 6 1289 7734.0
Aggregate 19-9.5 mm cum 78 1800 140400 Paver Finisher hour 6 4775 28650.0
Aggregate 9.5-6 mm cum 93 1800 167400 Pneumatic Roller hour 6 3319 19914.0
Smooth Wheeled
Aggregate 6-0.075 mm cum 108 1800 194400 hour 6 1608 9648.0
Roller
Sub total of A = 15000.0 Sub total of B = 2529450.0 Sub total of C = 76254.0 Sub total of D = 0.0
Sub total of A +B + C = 2620704.0 Sub total of A + B + C + D= 2620704.0 Contractor's overhead expenses 15% = 393105.6 Norms Rate = 3013809.6
Unit Rate = 14701.51

Description of Work: Bituminous Cold Mix ( Including Gravel Emulsion), Providing, laying and rolling of bituminous cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type as per
205 cum
Drawing and Technical Specifications., Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate
Spec. cl. No: 1313
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 51 of 276
Norms
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.14.iv Unskilled day 16 600 9600.0 Cutback Bitumen tonne 22.5 78100 1757250 Drum Mix Plant hour 6 1718 10308.0
Skilled day 6 900 5400.0 Filler (Lime) tonne 9 30000 270000 Generator hour 6 1289 7734.0
Aggregate 37.5-19 mm cum 75 1700 127500 Paver Finisher hour 6 4775 28650.0
Aggregate 19-6 mm cum 90 1725 155250 Pneumatic Roller hour 6 3319 19914.0
Smooth Wheeled
Aggregate 6-0.075 mm cum 114 1800 205200 hour 6 1608 9648.0
Roller
Sub total of A = 15000.0 Sub total of B = 2515200.0 Sub total of C = 76254.0 Sub total of D = 0.0
Sub total of A +B + C = 2606454.0 Sub total of A + B + C + D= 2606454.0 Contractor's overhead expenses 15% = 390968.1 Norms Rate = 2997422.1
Unit Rate = 14621.57

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 52 of 276

Description of Work:
Sand Asphalt Base Course, Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base as per Drawing and Technical Specifications. 205 cum
Spec. cl. No: 1312
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.15. Unskilled day 16 600 9600.0 Bitumen tonne 22.5 77600 1746000 Hot Mix Plant hour 6 64921 389526.0
Skilled day 6 900 5400.0 Filler (Lime) tonne 9 30000 270000 Generator hour 6 1289 7734.0
Sand 4.75 - 0.075 mm cum 288.62 730 210692.6 Paver Finisher hour 6 4775 28650.0
Smooth Wheeled
hour 12 1608 19296.0
Roller

Vibratory Road Roller hour 6 2413 14478.0


Sub total of A = 15000.0 Sub total of B = 2226692.6 Sub total of C = 459684.0 Sub total of D = 0.0
Sub total of A +B + C = 2701376.6 Sub total of A + B + C + D= 2701376.6 Contractor's overhead expenses 15% = 405206.5 Norms Rate = 3106583.1
Unit Rate = 15154.06

Description of Work:
Anti- Stripping agent, Providing and mixing of Anti stripping agent as per Design/ direction of Engineer 200 kg
Spec. cl. No: 1300
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 percent of
13.16 Skilled day 0.01 900 9.0 Additive Material kg 210 320 67200 Labour component for 18.3
T&P
Unskilled day 1 600 600.0
Sub total of A = 609.0 Sub total of B = 67200.0 Sub total of C = 18.3 Sub total of D = 0.0
Sub total of A +B + C = 67827.3 Sub total of A + B + C + D= 67827.3 Contractor's overhead expenses 15% = 10174.1 Norms Rate = 78001.4
Unit Rate = 390.01

Description of Work:
Bitumen Cutter, Providing and mixing of Bitumen cutter as per design / direction of Engineer 200 lit
Spec. cl. No: 1300
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 percent of
13.17 Skilled day 0.01 900 9.0 Kerosene / Diesel cutter Lit 210 101.5 21315 Labour component for 18.3
T&P
Unskilled day 1 600 600.0
Sub total of A = 609.0 Sub total of B = 21315.0 Sub total of C = 18.3 Sub total of D = 0.0
Sub total of A +B + C = 21942.3 Sub total of A + B + C + D= 21942.3 Contractor's overhead expenses 15% = 3291.3 Norms Rate = 25233.6
Unit Rate = 126.17

Description of Work:
Modified Binder, Supply of modified binder (produced by mixing bitumen with modifier such as natural rubber or crumb rubber or any other polymer found compatible with bitumen) as per Specifications and direction of the Engineer. 1 tonne
Spec. cl. No: 1300
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.18 Modified Binder tonne 1 77600 77600
Sub total of A = 0.0 Sub total of B = 77600.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 77600.0 Sub total of A + B + C + D= 77600.0 Contractor's overhead expenses 15% = 11640.0 Norms Rate = 89240.0
Unit Rate = 89240

Description of Work:
Otta seal, Providing and laying Otta seal surface as wearing course in single coat using river bed shingles /aggregates of specified size ( 0- 16 mm) laid on prepared surface as per Drawing and Technical Specifications. 4200 sqm
Spec. cl. No: 1315
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.19 Unskilled day 18 600 10800.0 Bitumen tonne 6.43 77600 498968 Bitumen Boiler hour 4.2 858 3603.6
Skilled day 2 900 1800.0 Crushed Stone Chipping 0-16 mm cum 67.2 1150 77280 Air Compressor hour 6 1459 8754.0
Hydraulic Chip
hour 6 4444 26664.0
spreader
Bitumen Sprayer hour 6 881 5286.0
Smooth Wheeled
hour 24 1608 38592.0
Roller
Sub total of A = 12600.0 Sub total of B = 576248.0 Sub total of C = 82899.6 Sub total of D = 0.0
Sub total of A +B + C = 671747.6 Sub total of A + B + C + D= 671747.6 Contractor's overhead expenses 15% = 100762.1 Norms Rate = 772509.7
Unit Rate = 183.93

Description of Work: Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tired roller initially and finished with a smooth steel wheel
205 cum
roller, all as per specifications., 75 mm thickness
Spec. cl. No: 1313
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.20.i Unskilled day 12 600 7200.0 Bitumen Emulsion tonne 20.25 63600 1287900 Cold Mix Plant hour 6 2387 14322.0
Skilled day 6 900 5400.0 Crushed Stone Aggregate 40 mm cum 297 1700 504900 Generator hour 6 1289 7734.0

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 53 of 276

Water KL 6 400 2400 Paver Finisher hour 6 4775 28650.0


Pneumatic Roller hour 6 3319 19914.0
Smooth Wheeled
hour 6 1608 9648.0
Roller
Sub total of A = 12600.0 Sub total of B = 1795200.0 Sub total of C = 80268.0 Sub total of D = 0.0
Sub total of A +B + C = 1888068.0 Sub total of A + B + C + D= 1888068.0 Contractor's overhead expenses 15% = 283210.2 Norms Rate = 2171278.2
Unit Rate = 10591.6

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 54 of 276

Description of Work: Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tired roller initially and finished with a smooth steel wheel
205 cum
roller, all as per specifications., 40 mm thickness
Spec. cl. No: 1313
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.20.ii Unskilled day 12 600 7200.0 Bitumen Emulsion tonne 31.5 63600 2003400 Cold Mix Plant hour 6 2387 14322.0
Skilled day 6 900 5400.0 Crushed Stone Aggregate 14 mm cum 287 1725 495075 Generator hour 6 1289 7734.0
Water KL 6 400 2400 Paver Finisher hour 6 4775 28650.0
Pneumatic Roller hour 6 3319 19914.0
Smooth Wheeled
hour 6 1608 9648.0
Roller
Sub total of A = 12600.0 Sub total of B = 2500875.0 Sub total of C = 80268.0 Sub total of D = 0.0
Sub total of A +B + C = 2593743.0 Sub total of A + B + C + D= 2593743.0 Contractor's overhead expenses 15% = 389061.5 Norms Rate = 2982804.5
Unit Rate = 14550.27

Description of Work: Recipe Cold Mix, Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tired roller initially and finished with a smooth steel wheel
205 cum
roller, all as per specifications., 25 mm thickness
Spec. cl. No: 1313
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.20.iii Unskilled day 12 600 7200.0 Bitumen Emulsion tonne 38.25 63600 2432700 Cold Mix Plant hour 6 2387 14322.0
Skilled day 6 900 5400.0 Crushed Stone Aggregate 10 mm cum 270 1800 486000 Generator hour 6 1289 7734.0
Water KL 6 400 2400 Paver Finisher hour 6 4775 28650.0
Pneumatic Roller hour 6 3319 19914.0
Smooth Wheeled
hour 6 1608 9648.0
Roller
Sub total of A = 12600.0 Sub total of B = 2921100.0 Sub total of C = 80268.0 Sub total of D = 0.0
Sub total of A +B + C = 3013968.0 Sub total of A + B + C + D= 3013968.0 Contractor's overhead expenses 15% = 452095.2 Norms Rate = 3466063.2
Unit Rate = 16907.63

Description of Work: Mastic Asphalt, Providing and laying 25 mm thick mastic asphalt wearing course excluding prime coat with paving grade bitumen including providing antiskid surface with bitumen pre-coated fine grained hard stone chipping at an spacing of 10 cm center to center in
140 sqm
both directions all complete as per Drawing and Technical specifications.
Spec. cl. No: 1300
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
13.21 Unskilled day 40 600 24000.0 Base mastic (without coarse aggregates) = 60 per cent Mechanical Broom hour 1 2020 2020.0
Skilled day 4 900 3600.0 Coarse aggregate(3.35 mm to 9.5 mm size) = 40 per cent . Air Compressor hour 1 1459 1459.0
Proportion of Material required for mastic asphalt with coarse
Mastic Cooker hour 6 2302 13812.0
aggregates
Bitumen tonne 0.86 77600 66736 Bitumen Boiler hour 6 858 5148.0
Crusher Stone Dust cum 1.72 630 1083.6 Tractor hour 1 1110 1110.0
Lime Stone Dust tonne 1.58 30000 47400
Coarse Aggregate 6.3-13.2 mm cum 2.42 1725 4174.5
Pre-coated Stone Chips 13 mm @ 0.005 cum per 10 sqm cum 0.08 0 0
Bitumen tonne 0.0022 77600 170.72
Sub total of A = 27600.0 Sub total of B = 119564.8 Sub total of C = 23549.0 Sub total of D = 0.0
Sub total of A +B + C = 170713.8 Sub total of A + B + C + D= 170713.8 Contractor's overhead expenses 15% = 25607.1 Norms Rate = 196320.9
Unit Rate = 1402.29

Description of Work: Precast Cement Concrete M 20 Kerb , Providing and laying of /20 precast cement concrete Kerb 38 cm * 20 cm * 25 cm ( H*B*L) with 12 mm thick 1:3 cement sand mortar bedding and joints including foundation excavation levelling but excluding foundation
400 meter
concrete for foundation or sand gravel material, all complete as per Drawing and Technical Specifications.
Spec. cl. No: 1401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Precast / cast in situ concrete block of /20 Concrete (0.38 m *
14.1 Skilled day 3 900 2700.0 nos 1600 279.4673775 447147.804 Kerb Casting Machine hour 6.00 1522 9132.0
0.20 m * 0.25 m (H*B*L))
Unskilled day 16 600 9600.0 Coarse Sand cum 1.2 730 876 Concrete Mixer hour 12.00 362 4344.0
Cement tonne 0.52 17500 9100
Water KL 0.2 400 80
Sub total of A = 12300.0 Sub total of B = 457203.8 Sub total of C = 13476.0 Sub total of D = 0.0
Sub total of A +B + C = 482979.8 Sub total of A + B + C + D= 482979.8 Contractor's overhead expenses 15% = 72447.0 Norms Rate = 555426.8
Unit Rate = 1388.57

Description of Work: Cast in Situ Cement Concrete or natural stone block for footpath, Providing and laying of precast / cast in situ 50 mm thick cement concrete slab footpath on 12 mm thick 1: 3 cement sand mortar over the prepared base, all complete as per Drawing and Technical
10 sqm
Specifications.
Spec. cl. No: 1401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Precast / cast in situ concrete block of M 20/20 ( 50 mm CC
14.2.A Skilled day 1.5 900 1350.0 sqm 11 915.3532 10068.8852
Block)
Unskilled day 4 600 2400.0 Coarse Sand cum 0.13 730 94.9
Cement tonne 0.07 17500 1225
Water KL 0.02 400 8
Sub total of A = 3750.0 Sub total of B = 11396.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 15146.8 Sub total of A + B + C + D= 15146.8 Contractor's overhead expenses 15% = 2272.0 Norms Rate = 17418.8

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 55 of 276

Unit Rate = 1741.88

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 56 of 276

Description of Work:
, Providing and laying 25 mm thick Natural stone slab footpath on 12 mm thick 1: 3 cement sand mortar over the prepared base, all complete as per specification. 10 sqm
Spec. cl. No: 1401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
14.2.B Skilled day 2 900 1800.0 Stone Slab 50 mm sqm 11 0 0
Unskilled day 3 600 1800.0 Sand cum 0.13 730 94.9
Cement tonne 0.07 17500 1225
Water KL 0.02 400 8
Sub total of A = 3600.0 Sub total of B = 1327.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 4927.9 Sub total of A + B + C + D= 4927.9 Contractor's overhead expenses 15% = 739.2 Norms Rate = 5667.1
Unit Rate = 566.71

Description of Work: Cast in Situ Cement Concrete Kerb , Providing and laying cement concrete Kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond Kerb
360 meter
stone, Kerb stone laid with Kerb laying machine, foundation concrete laid manually, all complete as per Drawing and Technical Specifications.
Spec. cl. No: 1401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
14.3 Skilled day 6 900 5400.0 Crushed Stone Aggregate 20 mm cum 21.8 1725 37605 Kerb Casting Machine hour 8.00 1522 12176.0
Unskilled day 60 600 36000.0 Coarse Sand cum 10.9 730 7957 Concrete Mixer hour 8.00 362 2896.0
Cement tonne 7.53 17500 131775
Water KL 30 400 12000
Sub total of A = 41400.0 Sub total of B = 189337.0 Sub total of C = 15072.0 Sub total of D = 0.0
Sub total of A +B + C = 245809.0 Sub total of A + B + C + D= 245809.0 Contractor's overhead expenses 15% = 36871.4 Norms Rate = 282680.4
Unit Rate = 785.22

Description of Work: Cast in Situ Cement Concrete M 20 Kerb with Channel, Providing and laying cement concrete Kerb with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on grade foundation 150 mm thick, Kerb channel 300 mm
300 meter
wide, 50 mm thick in PCC grade, sloped towards the Kerb, Kerb stone with channel laid with Kerb laying machine, foundation concrete laid manually, all complete as specification.
Spec. cl. No: 1401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
14.4 Skilled day 6 900 5400.0 Crushed Stone Aggregate 20 mm cum 36.59 1725 63117.75 Kerb Casting Machine hour 18.00 1522 27396.0
Unskilled day 70 600 42000.0 Coarse Sand cum 18.3 730 13359 Concrete Mixer hour 18.00 362 6516.0
Cement tonne 11.34 17500 198450 Water Tanker hour 18.00 1806 32508.0
Water KL 36 400 14400
Sub total of A = 47400.0 Sub total of B = 289326.8 Sub total of C = 66420.0 Sub total of D = 0.0
Sub total of A +B + C = 403146.8 Sub total of A + B + C + D= 403146.8 Contractor's overhead expenses 15% = 60472.0 Norms Rate = 463618.8
Unit Rate = 1545.4

Description of Work:
Brick work for footpath, Providing and laying brick on edge over 60 mm thick sand bed in footpath including excavation sand bedding all complete as per Drawing and Technical Specifications. 10 sqm
Spec. cl. No: 1403
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
14.5.A Skilled day 1 900 900.0 Bricks nos 725 12 8700
Unskilled day 3 600 1800.0 Coarse Sand cum 0.7 730 511
Sub total of A = 2700.0 Sub total of B = 9211.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 11911.0 Sub total of A + B + C + D= 11911.0 Contractor's overhead expenses 15% = 1786.7 Norms Rate = 13697.7
Unit Rate = 1369.77

Description of Work:
Brick work for footpath, Providing and laying flat brick over 60 mm thick sand bed in footpath including excavation sand bedding all complete as per specification. 20 sqm
Spec. cl. No: 1403
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
14.5.B Skilled day 1.5 900 1350.0 Bricks nos 750 12 9000
Unskilled day 4 600 2400.0 Sand cum 1.4 730 1022
Sub total of A = 3750.0 Sub total of B = 10022.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 13772.0 Sub total of A + B + C + D= 13772.0 Contractor's overhead expenses 15% = 2065.8 Norms Rate = 15837.8
Unit Rate = 791.89

Description of Work: Non Reflective Traffic Signs, Providing and fixing of Non reflective warning, mandatory and informatory sign board of 2 mm thick MS Sheet with back support frame fixed on heavy 50 mm tube or Channel section of 75 mm X 40 mm firmly fixed to the ground by means
4 no
of properly designed foundation with M 10/40 grade cement concrete 300 mm x 300 mm x 300 mm, l as per drawings and Technical Specification/ DOR Publication., Heavy Duty Steel Tube internal 50 mm dia., MS Sheet 60 cm height equilateral triangle
Spec. cl. No: 1501
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.1 Skilled day 1 900 900.0 Excavation for foundation cum 0.21 570 119.7 Tractor - Trolley hour 3 1110 3330.0
Unskilled day 2 600 1200.0 Cement concrete M 10 grade cum 0.11
Painting angle iron post two coats sqm 3.51
Heavy Duty Steel Tube internal 50 mm dia. m 12.6 0 0
Angle Iron 50 * 50 * 6 mm kg 4.24 105 445.2
Add 2 per cent of cost of angle iron towards cost of drilling
8.9
holes, nuts, bolts etc.

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 57 of 276

MS Sheet 60 cm height equilateral triangle sqm 0.44 1475.8 649.352


Sub total of A = 2100.0 Sub total of B = 1223.2 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 6653.2 Sub total of A + B + C + D= 6653.2 Contractor's overhead expenses 15% = 998.0 Norms Rate = 7651.1
Unit Rate = 1912.78

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 58 of 276

Description of Work: Retro-Reflectorized Traffic Signs, Providing and fixing of retro- reflectorized warning, Regulatory and informatory sign as per specification clause 1501 made of high intensity grade sheeting , fixed over aluminum sheeting, 1.5 mm thick supported on a 50 mm internal
dia steel tube or mild steel angle iron post 75 mm x 40 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M 10/40 grade cement concrete 30 cm x 30 cm , 30 cm below ground level or as per Drawing and Technical Specifications., MS 10 no
Spec. cl. No: 1501 Sheet 60 cm height equilateral triangle, Heavy Duty Steel Tube internal 50 mm dia.
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.2 Skilled day 1 900 900.0 Excavation for foundation cum 0.54 570 307.8 Tractor - Trolley hour 3 1110 3330.0
Unskilled day 3 600 1800.0 Cement concrete M 10 grade cum 0.27
Painting angle iron post two coats sqm 8.78

Aluminum sheeting fixed with encapsulated lens type reflective


sheeting of size including lettering and signs as applicable

Add 2 per cent of cost of angle iron towards cost of drilling


0
holes, nuts, bolts etc.
MS Sheet 60 cm height equilateral triangle sqm 1.04 1475.8 1534.832
Heavy Duty Steel Tube internal 50 mm dia. m 12.6 0 0
Sub total of A = 2700.0 Sub total of B = 1842.6 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 7872.6 Sub total of A + B + C + D= 7872.6 Contractor's overhead expenses 15% = 1180.9 Norms Rate = 9053.5
Unit Rate = 905.35

Description of Work: Overhead Signs, Providing and erecting overhead signs with a corrosion resistant 2 mm thick aluminum alloy sheet reflectorized with micro prismatic retro-reflective type with vertical and lateral clearance as per drawing and installed as per Specification over a
1 tonne
designed support system of aluminum alloy or galvanized steel trusses of sections and type as per structural design requirements , Drawing and Technical Specifications., Truss and Vertical Support
Spec. cl. No: 1502
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.3.A day 1 1100 1100.0 Aluminum Alloy/Galvanized Steel tonne 1.05 0 0 Crane hour 6 3102 18612.0
(Blacksmith)
Add 1 per cent on cost of Material for nuts, bolts and drilling
Unskilled day 6 600 3600.0 0.0 Truck hour 6 2014 12084.0
and welding consumables
Add 15 per cent on cost of Material for fabrication of trusses as
0.0
per approved design
Sub total of A = 4700.0 Sub total of B = 0.0 Sub total of C = 30696.0 Sub total of D = 0.0
Sub total of A +B + C = 35396.0 Sub total of A + B + C + D= 35396.0 Contractor's overhead expenses 15% = 5309.4 Norms Rate = 40705.4
Unit Rate = 40705.4

Description of Work: Overhead Signs, Providing and erecting overhead signs with a corrosion resistant 2 mm thick aluminum alloy sheet reflectorized with micro prismatic retro-reflective type with vertical and lateral clearance as per drawing and installed as per Specification over a
10 sqm
designed support system of aluminum alloy or galvanized steel trusses of sections and type as per structural design requirements , Drawing and Technical Specifications., Aluminum Alloy Plate for Over Head Sign
Spec. cl. No: 1502
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.3.B day 2 1100 2200.0 Aluminum Alloy Plate 2 mm sqm 11 0 0
(Blacksmith)
Unskilled day 3 600 1800.0 Miscellaneous
Add 1 per cent of cost of Labour for lifting arrangement, like
40.0
ladders, pulleys, ropes etc.
Sub total of A = 4000.0 Sub total of B = 40.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 4040.0 Sub total of A + B + C + D= 4040.0 Contractor's overhead expenses 15% = 606.0 Norms Rate = 4646.0
Unit Rate = 464.6

Description of Work:
Painting Two Coats on Concrete Surfaces, Providing and Painting two coats after filling the surface with synthetic enamel paint in all shades on concrete / plaster surfaces as per Drawing and Technical Specifications. 10 sqm
Spec. cl. No: 1501
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.4 Skilled (Painter) day 3 900 2700.0 Paint liter 6 603.2 3619.2

Unskilled day 2 600 1200.0 Add for scaffolding @ 1 per cent of Labour cost where required 39.0

Add @ 5 per cent cost of Labour and Materials to prepare the


surface by filling minutes roughness on the surface and priming 376.0
the surface before laying 2 coats of painting.
Sub total of A = 3900.0 Sub total of B = 4034.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 7934.2 Sub total of A + B + C + D= 7934.2 Contractor's overhead expenses 15% = 1190.1 Norms Rate = 9124.3
Unit Rate = 912.43

Description of Work:
Painting Two Coats on Steel Surfaces, Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade as per Drawing and Technical Specifications. 20 sqm
Spec. cl. No: 1501
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.5 Skilled (Painter) day 1 900 900.0 Paint liter 2.5 603.2 1508
Unskilled day 1 600 600.0 Add @ 1 per cent on cost of Material for scaffolding 15.1
Add @ 5 per cent cost of Labour and Materials to prepare the
surface by filling minutes roughness on the surface and priming 150.4
the surface before laying 2 coats of painting.

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 59 of 276

Sub total of A = 1500.0 Sub total of B = 1673.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 3173.5 Sub total of A + B + C + D= 3173.5 Contractor's overhead expenses 15% = 476.0 Norms Rate = 3649.5
Unit Rate = 182.48

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 60 of 276

Description of Work:
`, Providing and applying two coats of ready mix paint of approved brand on wood surface after thorough cleaning of surface to give an even shade as per Drawing and Technical Specifications. 15 sqm
Spec. cl. No: 1509
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.6 Skilled (Painter) day 1 900 900.0 Paint liter 2.25 603.2 1357.2
Unskilled day 1 600 600.0 Add @ 1 per cent on cost of Material for scaffolding 13.6
Add @ 5 per cent cost of Labour and Materials to prepare the
surface by filling minutes roughness on the surface and priming 142.9
the surface before laying 2 coats of painting.
Sub total of A = 1500.0 Sub total of B = 1513.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 3013.6 Sub total of A + B + C + D= 3013.6 Contractor's overhead expenses 15% = 452.0 Norms Rate = 3465.7
Unit Rate = 231.05

Description of Work: Painting Lines, Dashes, Arrows etc. on Roads in Two Coats, Providing required material and Painting lines, dashes, arrows etc. on roads in two coats on new work with ready mixed road marking paint conforming to NS 408/ IS 164 on bituminous surface, including
10 sqm
cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per Drawing and Technical Specifications., Over 10 cm in width
Spec. cl. No: 1503
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.7.i Skilled (Painter) day 1 900 900.0 Road Marking Paint liter 1.48 603.2 892.736
Unskilled day 2 600 1200.0
Sub total of A = 2100.0 Sub total of B = 892.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2992.7 Sub total of A + B + C + D= 2992.7 Contractor's overhead expenses 15% = 448.9 Norms Rate = 3441.6
Unit Rate = 344.16

Description of Work: Painting Lines, Dashes, Arrows etc. on Roads in Two Coats, Providing required material and Painting lines, dashes, arrows etc. on roads in two coats on new work with ready mixed road marking paint conforming to NS 408/ IS 164 on bituminous surface, including
10 sqm
cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per Drawing and Technical Specifications., Up to 10 cm in width
Spec. cl. No: 1503
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.7.ii Skilled (Painter) day 1 900 900.0 Road Marking Paint liter 1.48 603.2 892.736
Unskilled day 2 600 1200.0
Sub total of A = 2100.0 Sub total of B = 892.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2992.7 Sub total of A + B + C + D= 2992.7 Contractor's overhead expenses 15% = 448.9 Norms Rate = 3441.6
Unit Rate = 344.16

Description of Work: Painting Lines, Dashes, Arrows etc. on Roads in Two Coats on Old Work, Providing required materials and Painting lines, dashes, arrows etc. on roads in two coats on old work with ready mixed road marking paint conforming to NS 408/ IS: 164 on bituminous surface,
10 sqm
including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per Drawing and Technical Specifications., over 10 cm in width
Spec. cl. No: 1503
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.8.i Skilled (Painter) day 1 900 900.0 Road Marking Paint liter 0.9 603.2 542.88
Unskilled day 2 600 1200.0
Sub total of A = 2100.0 Sub total of B = 542.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2642.9 Sub total of A + B + C + D= 2642.9 Contractor's overhead expenses 15% = 396.4 Norms Rate = 3039.3
Unit Rate = 303.93

Description of Work: Painting Lines, Dashes, Arrows etc. on Roads in Two Coats on Old Work, Providing required materials and Painting lines, dashes, arrows etc. on roads in two coats on old work with ready mixed road marking paint conforming to NS 408/ IS: 164 on bituminous surface,
10 sqm
including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per Drawing and Technical Specifications., Up to 10 cm in width
Spec. cl. No: 1503
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.8.ii Skilled (Painter) day 1 900 900.0 Road Marking Paint liter 0.9 603.2 542.88
Unskilled day 2 600 1200.0
Sub total of A = 2100.0 Sub total of B = 542.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2642.9 Sub total of A + B + C + D= 2642.9 Contractor's overhead expenses 15% = 396.4 Norms Rate = 3039.3
Unit Rate = 303.93

Description of Work: Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface, On smooth surface (similar to Asphalt concrete and rigid pavement), Providing and laying of hot applied thermoplastic compound at least 2 mm thick
400 sqm
including reflectorizing glass beads as per DOR Traffic sign manual/ Specifications .The finished surface to be level, uniform and free from streaks and holes.
Spec. cl. No: 1504
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Road Marking
15.9.i Skilled (Painter) day 2 900 1800.0 Hot applied thermoplastic compound liter 930 603.2 560976 hour 10 1004 10040.0
Machine
Unskilled day 4 600 2400.0 Reflectorizing Glass Beads kg 100 267 26700 Tractor - Trolley hour 10 1110 11100.0
Sub total of A = 4200.0 Sub total of B = 587676.0 Sub total of C = 21140.0 Sub total of D = 0.0
Sub total of A +B + C = 613016.0 Sub total of A + B + C + D= 613016.0 Contractor's overhead expenses 15% = 91952.4 Norms Rate = 704968.4
Unit Rate = 1762.42

Description of Work: Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface, On rough surface ( similar to surface dressing), Providing and laying of hot applied thermoplastic compound at least 2 mm thick including reflectorizing
Prepared By:________________ Checked By:________________ Recommended By:________________ 300 sqm
Approved By:________________
glass beads as per DOR Traffic sign manual/ Specifications .The finished surface to be level, uniform and free from streaks and holes.
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 61 of 276
Description of Work: Road Marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass Beads on Bituminous Surface, On rough surface ( similar to surface dressing), Providing and laying of hot applied thermoplastic compound at least 2 mm thick including reflectorizing
300 sqm
glass beads as per DOR Traffic sign manual/ Specifications .The finished surface to be level, uniform and free from streaks and holes.
Spec. cl. No: 1504
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Road Marking
15.9.ii Skilled (Painter) day 2 900 1800.0 Hot applied thermoplastic compound liter 1200 603.2 723840 hour 10 1004 10040.0
Machine
Unskilled day 4 600 2400.0 Reflectorizing Glass Beads kg 150 267 40050 Tractor - Trolley hour 10 1110 11100.0
Sub total of A = 4200.0 Sub total of B = 763890.0 Sub total of C = 21140.0 Sub total of D = 0.0
Sub total of A +B + C = 789230.0 Sub total of A + B + C + D= 789230.0 Contractor's overhead expenses 15% = 118384.5 Norms Rate = 907614.5
Unit Rate = 3025.38

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 62 of 276

Description of Work: Providing and fixing of road stud 100x 100 mm, die-cast in aluminum, resistant to corrosive effect of salt and grit, fitted with lenses reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous
grout or epoxy mortar, all as per Specification clause 1505., Providing and fixing of road stud 100 x 100 mm, die-cast in aluminum, resistant to corrosive effect of salt and grit, fitted with lenses reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm 50 no
Spec. cl. No: 1505 upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per Drawing and Technical Specifications., Cats Eye
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.10' Skilled day 1 900 900.0 Cats Eye nos. 50 0 0
Unskilled day 2 600 1200.0 Add 10 per cent of cost of Material for fixing and installation 0.0
Sub total of A = 2100.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2100.0 Sub total of A + B + C + D= 2100.0 Contractor's overhead expenses 15% = 315.0 Norms Rate = 2415.0
Unit Rate = 48.3

Description of Work:
Kilometer Stone, Providing and Fixing Reinforced cement concrete M 15 grade kilometer Post including painting and printing as per Standard Drawing-2070 and Technical Specifications. position, Five kilometer Post (precast) 6 no
Spec. cl. No: 1506
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.11.i Skilled day 1 900 900.0 M-15 grade of concrete cum 1.2 13000 Tractor - Trolley hour 3 1110 3330.0
Unskilled day 6 600 3600.0 M-10 grade of concrete cum 1.2 12500
Steel Reinforcement tonne 0.0636 90000 5724
Excavation in soil for foundation cum 1.2 570 684.0
Painting two coats on concrete surface sqm 10.2 793.416 8092.8
cm-
Lettering on km post 1800
letter
Transportation and fixing at site
Sub total of A = 4500.0 Sub total of B = 14500.8 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 22330.8 Sub total of A + B + C + D= 22330.8 Contractor's overhead expenses 15% = 3349.6 Norms Rate = 25680.5
Unit Rate = 4280.08

Description of Work:
Kilometer Stone, Providing and Fixing Reinforced cement concrete M 15 grade kilometer Post including painting and printing as per Standard Drawing-2070 and Technical Specifications. position, One kilometer post (precast) 14 no
Spec. cl. No: 1506
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.11.ii Skilled day 2 900 1800.0 M-15 grade of concrete cum 1.4 13000 Tractor - Trolley hour 3 1110 3330.0
Unskilled day 7 600 4200.0 M-10 grade of concrete cum 2.38 12500
Steel Reinforcement tonne 0.08288 90000 7459.2
Excavation in soil for foundation cum 2.38 570 1356.6
Painting two coats on concrete surface sqm 11.9 793.416 9441.7
cm -
Lettering on km post 1680
letter
Transportation and fixing at site
Sub total of A = 6000.0 Sub total of B = 18257.5 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 27587.5 Sub total of A + B + C + D= 27587.5 Contractor's overhead expenses 15% = 4138.1 Norms Rate = 31725.6
Unit Rate = 2266.11

Description of Work: Road Delineators Post, Providing and installation of 150 mm * 150 mm 1. 5 m long delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 20 cm wide strips, buried or pressed into the ground
30 no
and conforming to the drawings and Technical Specifications.
Spec. cl. No: 1507
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.12 Skilled (Mason) day 1 900 900.0 M-15 grade of concrete cum 1.01 13000 Tractor - Trolley hour 3 1110 3330.0
Steel reinforcement as per standard drawing ( 4 Nos 8 mm dia
Unskilled day 7 600 4200.0 tonne 0.1128 90000 10152
and 11 Nos 6 mm dia stirrups)
Excavation in soil for foundation cum 0.47 570 267.9
Painting two coats on concrete surface sqm 14.4 793.416 11425.2
Transportation and fixing
Sub total of A = 5100.0 Sub total of B = 21845.1 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 30275.1 Sub total of A + B + C + D= 30275.1 Contractor's overhead expenses 15% = 4541.3 Norms Rate = 34816.4
Unit Rate = 1160.55

Description of Work: Reinforced Cement Concrete Crash Barrier, Providing and Fixing Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement and dowel bars 25 mm
10 meter
dia, 450 mm long at expansion joints filled with pre-molded asphalt filler board, keyed to the structure on which it is built and installed as per design, Drawing and Technical Specifications.
Spec. cl. No: 1508
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.13.i Skilled day 1 900 900.0 M 20 grade concrete cum 3 14200
Unskilled day 2 600 1200.0 HYSD Steel Reinforcement with Dowel Bars tonne 0.28 90000 25200
Pre-molded Asphalt Filler Board sqm 0.32 0 0
Excavation and backfilling : 25 % of Labour component 525.0
Sub total of A = 2100.0 Sub total of B = 25725.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 27825.0 Sub total of A + B + C + D= 27825.0 Contractor's overhead expenses 15% = 4173.8 Norms Rate = 31998.8
Unit Rate = 3199.88

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 63 of 276

Description of Work: Metal Beam Crash Barrier, Type - A, "W" : Metal Beam Crash Barrier, Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150
40 meter
x 75 x 5 mm spaced 2 m center to center, 1.8 m high, 1.1 m below ground/road level metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per Drawing and Technical Specifications.
Spec. cl. No: 1509
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.14.A day 1 1100 1100.0 Hot dip Galvanized Corrugated W beam sheet 3 mm thick kg 563.61 0 0 Tractor - Trolley hour 3 1110 3330.0
(Blacksmith)
Unskilled day 10 600 6000.0 Hot dip Galvanized Channel post 150 x 75 , 5 mm kg 695.52 0 0
Hot dip Galvanized Spacer Channel 150 x 75 x 5 mm kg 127.51 0 0
M 20 grade concrete cum 0.99
E/W excavation for post cum 0.99 570 564.3
Add 25 per cent of the cost of Material for fabrication, nuts,
0.0
bolts and washers etc.)
Sub total of A = 7100.0 Sub total of B = 564.3 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 10994.3 Sub total of A + B + C + D= 10994.3 Contractor's overhead expenses 15% = 1649.1 Norms Rate = 12643.4
Unit Rate = 316.09

Description of Work: Metal Beam Crash Barrier, Type - B, "THRIE" : Metal Beam Crash Barrier, Providing and erecting a "Thrie" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical
40 meter
post, 150 x 75 x 5 mm spaced 2 m center to center, 2.1 m high with 1.3 m below ground level, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per Drawing and Technical specifications.
Spec. cl. No: 1509
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
15.14.B day 1 1100 1100.0 Hot dip Galvanized Corrugated thrie beam sheet 3 mm thick kg 913.19 0 0 Tractor - Trolley hour 3 1110 3330.0
(Blacksmith)
Unskilled day 12 600 7200.0 Hot dip Galvanized Channel post 150 x 75 , 5 mm kg 811.44 0 0
Hot dip Galvanized Spacer Channel 150 x 75 x 5 mm kg 137.64 0 0
M 20 grade concrete cum 1.13
E/W excavation for post cum 1.13 570 644.1
Add 25 per cent of the cost of Material for fabrication, nuts,
0.0
bolts and washers etc.)
Sub total of A = 8300.0 Sub total of B = 644.1 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 12274.1 Sub total of A + B + C + D= 12274.1 Contractor's overhead expenses 15% = 1841.1 Norms Rate = 14115.2
Unit Rate = 352.88

Metal Beam Crash Barrier, Flexible Crash Barrier, Wire Rope Safety Barrier, Providing and erecting a wire rope safety barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m
Description of Work: below ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to be embedded in M
15 meter
15 grade cement concrete foundation 2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per design , Drawing and Technical
Spec. cl. No: 1509 Specifications.
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.14.C Unskilled day 4 600 2400.0 RS Joist 100 * 75 mm - 16.5 m kg 190 0 0 Tractor - Trolley hour 3 1110 3330.0
Skilled
day 2 1100 2200.0 Struts - 2 Nos. for terminal posts, 2 m long each 2 x 2 x 11.50 kg 46 95 4370
(Blacksmith)

Tie 2 Nos. of 8 mm steel plate, 1.5 sqm each for terminal posts kg 188.4 139.1 26206.44
Steel Wire 40 mm. kg 65 148.82 9673.3
M 20 grade concrete cum 1.13
E/W excavation for post cum 1.13 570 644.1
Add 5 per cent of cost of Material for drilling, gripping, fixing,
2012.5
fabrication and welding consumables
Applying 2 coats of painting on exposed surface sqm 16.5 158.674 2618.1
Sub total of A = 4600.0 Sub total of B = 45524.4 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 53454.4 Sub total of A + B + C + D= 53454.4 Contractor's overhead expenses 15% = 8018.2 Norms Rate = 61472.6
Unit Rate = 4098.17

Description of Work: Anti-Glare Devices in Median, Anti-glare screen with 25 mm steel pipe framework fixed with circular and rectangular vans, Providing and erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one meter length and
1.75 meter height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation concrete, applying 2 coats of paint on all 10 meter
Spec. cl. No: 2800/1500 exposed surfaces, all as per design , drawings and Technical Specifications.
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.15.B Skilled day 1 900 900.0 Steel Pipe 25 mm meter 160 226.54 36246.4
Unskilled day 2 600 1200.0 MS Sheet for 600 * 300 * 3 mm rectangular vane kg 43.2 139.1 6009.12
MS Sheet for 250 mm dia circular vane 3 mm thick kg 48 139.1 6676.8
Add 5 per cent cost of Material for fabrication, welding,
2446.6
bending, nuts, bolts etc.
Applying 2 coats of painting on exposed surface sqm 18.3 158.674 2903.7
Sub total of A = 2100.0 Sub total of B = 54282.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 56382.7 Sub total of A + B + C + D= 56382.7 Contractor's overhead expenses 15% = 8457.4 Norms Rate = 64840.1
Unit Rate = 6484.01

Description of Work: Anti-Glare Devices in Median, Anti-glare screen with rectangular vane of MS sheet, Providing and erecting anti - glare screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the
direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post firmly embedded in M-15 cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, all complete as per design , 15 meter
Spec. cl. No: 2800/1500 Drawing and Technical Specifications.
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.15.C Skilled day 1 900 900.0 Angle Iron 50 * 50 * 6 mm kg 106 105 11130 Tractor - Trolley hour 3 1110 3330.0

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 64 of 276

Unskilled day 2 600 1200.0 MS Sheet 3 mm @ 24 kg/sqm kg 90 139.1 12519


Add 5 per cent of cost of Material for fabrication, nuts, bolts
1182.5
etc.
Applying 2 coats of painting sqm 8.5 793.416 6744.0
Sub total of A = 2100.0 Sub total of B = 31575.5 Sub total of C = 3330.0 Sub total of D = 0.0
Sub total of A +B + C = 37005.5 Sub total of A + B + C + D= 37005.5 Contractor's overhead expenses 15% = 5550.8 Norms Rate = 42556.3
Unit Rate = 2837.09

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 65 of 276

Description of Work: Street Lighting, Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on the footpath, fitted with
1 no
sodium vapor lamp and fixed firmly in concrete foundation as per design , Drawing and Technical Specifications..
Spec. cl. No: missing
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Steel circular hollow pole of standard specification for street
15.16 Unskilled day 1 600 600.0 nos 1 0 0
lighting to mount light at 9 m height above road level
Skilled
day 1 725 725.0 Sodium Vapor Lamp nos 1 0 0
(Electrician)
Add 5 per cent of cost of Material for holder, electric cable,
0.0
insulation, ladder, scaffolding etc.
For Fixing in Median
Providing two coats of aluminum paint over steel circular
sqm 5.75 158.674 912.4
hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of aluminum paint over steel circular
sqm 4.63 158.674 734.7
hollow pipe with overhang on one side
Sub total of A = 1325.0 Sub total of B = 1647.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 2972.0 Sub total of A + B + C + D= 2972.0 Contractor's overhead expenses 15% = 445.8 Norms Rate = 3417.8
Unit Rate = 3417.84

Description of Work: Rumble Strips, Providing and making of Rumble strips with premix bituminous carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint., Provision of 15 Nos
100 sqm
rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.
Spec. cl. No: 1300
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
The rate per sqm of premix carpet and road marking may be
15.17 adopted from chapter 13 & 15 respectively for the quantities
calculated from approved drawings
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Lettering new Letter and Figures of any Shade, Providing and lettering new letter and figures of any shade with synthetic enamel paint black or any other approved color to give an even shade, Nepali 1600 cm-letter
Spec. cl. No: 1506
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.18.i Skilled (Painter) day 4 900 3600.0 Paint liter 0.7 603.2 422.24
Unskilled day 2 600 1200.0
Sub total of A = 4800.0 Sub total of B = 422.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 5222.2 Sub total of A + B + C + D= 5222.2 Contractor's overhead expenses 15% = 783.3 Norms Rate = 6005.6
Unit Rate = 3.75

Description of Work:
Lettering new Letter and Figures of any Shade, Providing and lettering new letter and figures of any shade with synthetic enamel paint black or any other approved color to give an even shade, English and Roman 1600 cm-letter
Spec. cl. No: 1506
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
15.18.ii Skilled (Painter) day 2 900 1800.0 Paint liter 0.5 603.2 301.6
Unskilled day 2 600 1200.0
Sub total of A = 3000.0 Sub total of B = 301.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 3301.6 Sub total of A + B + C + D= 3301.6 Contractor's overhead expenses 15% = 495.2 Norms Rate = 3796.8
Unit Rate = 2.37

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings., (Class F1 Finish), Using timber (soft wood ) 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.1.a Skilled day 1.5 900 1350.0 Planks 38 mm thick. cum 0.053 29138 1529.745
Unskilled day 2 600 1200.0 Struts, Ballies, etc. cum 0.015 29138 437.07
Nails, spikes, etc. kg 1 114.4 114.4
0
Sub total of A = 2550.0 Sub total of B = 2081.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 4631.2 Sub total of A + B + C + D= 4631.2 Contractor's overhead expenses 15% = 694.7 Norms Rate = 5325.9
Unit Rate = 532.59

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings., (Class F1 Finish), Using steel 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 66 of 276

18.1.b Skilled day 1.5 900 1350.0 MS Sheet 14 gauge & Angle Stiffners kg 8.833 139.1 1228.7166667
Unskilled day 2.5 600 1500.0 MS Pipes 40 mm dia. m 0.400 226.54 90.616
Clamps nos. 0.350 46.8 16.38
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.089 200000 17800
Sub total of A = 2850.0 Sub total of B = 19135.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 21985.7 Sub total of A + B + C + D= 21985.7 Contractor's overhead expenses 15% = 3297.9 Norms Rate = 25283.6
Unit Rate = 2528.36

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 67 of 276

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using timber (soft wood ), Height upto 3 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.2.A.i Skilled day 2.2 900 1980.0 Ply Wood 9 mm thick. sqm 0.917 550 504.16666667
Unskilled day 2.2 600 1320.0 Struts, Ballies, etc. cum 0.4 29138 11655.2
Nails, spikes, etc. kg 2.5 114.4 286
Sub total of A = 3300.0 Sub total of B = 12445.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 15745.4 Sub total of A + B + C + D= 15745.4 Contractor's overhead expenses 15% = 2361.8 Norms Rate = 18107.2
Unit Rate = 1810.72

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using timber (soft wood ), Height above 3 m to 6 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.2.A.ii Skilled day 2.6 900 2340.0 Ply Wood 9 mm thick. sqm 0.917 550 504.16666667
Unskilled day 2.8 600 1680.0 Struts, Ballies, etc. cum 0.5 29138 14569
Nails, spikes, etc. kg 3.5 114.4 400.4
Sub total of A = 4020.0 Sub total of B = 15473.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 19493.6 Sub total of A + B + C + D= 19493.6 Contractor's overhead expenses 15% = 2924.0 Norms Rate = 22417.6
Unit Rate = 2241.76

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using timber (soft wood ), Height above 6 m to 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.2.A.iii Skilled day 3.2 900 2880.0 Ply Wood 9 mm thick. sqm 0.917 550 504.16666667
Unskilled day 4 600 2400.0 Struts, Ballies, etc. cum 0.6 29138 17482.8
Nails, spikes, etc. kg 4.5 114.4 514.8
Sub total of A = 5280.0 Sub total of B = 18501.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 23781.8 Sub total of A + B + C + D= 23781.8 Contractor's overhead expenses 15% = 3567.3 Norms Rate = 27349.0
Unit Rate = 2734.9

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using timber (soft wood ), Height above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.2.A.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using steel, Height upto 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.2.B.i Skilled day 1.6 900 1440.0 MS Sheet 14 gauge & Angle Stiffners kg 8.833 139.1 1228.7166667
Unskilled day 2.2 600 1320.0 MS Pipes 40 mm dia. m 0.778 226.54 176.19777778
Clamps nos. 0.667 46.8 31.2
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.089 200000 17800
Sub total of A = 2760.0 Sub total of B = 19236.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 21996.1 Sub total of A + B + C + D= 21996.1 Contractor's overhead expenses 15% = 3299.4 Norms Rate = 25295.5
Unit Rate = 2529.55

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using steel, Height above 3 m to 6 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.2.B.ii Skilled day 1.9 900 1710.0 MS Sheet 14 gauge & Angle Stiffners kg 8.833 139.1 1228.7166667
Unskilled day 2.8 600 1680.0 MS Pipes 40 mm dia. m 0.978 226.54 221.50577778
Clamps nos 0.833 46.8 39
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.089 200000 17800
Sub total of A = 3390.0 Sub total of B = 19289.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 22679.2 Sub total of A + B + C + D= 22679.2 Contractor's overhead expenses 15% = 3401.9 Norms Rate = 26081.1
Unit Rate = 2608.11

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 68 of 276

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using steel, Height above 6 m to 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.2.B.iii Skilled day 2.3 900 2070.0 MS Sheet 14 gauge & Angle Stiffners kg 8.833 139.1 1228.7166667
Unskilled day 4 600 2400.0 MS Pipes 40 mm dia. m 1.244 226.54 281.91644444
Clamps nos. 1.067 46.8 49.92
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.089 200000 17800
Sub total of A = 4470.0 Sub total of B = 19360.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 23830.6 Sub total of A + B + C + D= 23830.6 Contractor's overhead expenses 15% = 3574.6 Norms Rate = 27405.1
Unit Rate = 2740.51

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), vertical plain surface, Using steel, Height above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.2.B.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using timber, Height upto 3 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.3.A.i Skilled day 3 900 2700.0 Ply Wood 9 mm thick. sqm 1.375 550 756.25
Unskilled day 3 600 1800.0 Timber cum 0.6 187143 112285.8
Nails, spikes, etc. kg 4 114.4 457.6
Sub total of A = 4500.0 Sub total of B = 113499.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 117999.7 Sub total of A + B + C + D= 117999.7 Contractor's overhead expenses 15% = 17699.9 Norms Rate = 135699.6
Unit Rate = 13569.96

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using timber, Height above 3m to 6 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.3.A.ii Skilled day 3.5 900 3150.0 Ply Wood 9 mm thick. sqm 1.375 550 756.25
Unskilled day 3.8 600 2280.0 Timber cum 0.72 187143 134742.96
Nails, spikes, etc. kg 5 114.4 572
Sub total of A = 5430.0 Sub total of B = 136071.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 141501.2 Sub total of A + B + C + D= 141501.2 Contractor's overhead expenses 15% = 21225.2 Norms Rate = 162726.4
Unit Rate = 16272.64

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using timber, Height above 6 m to 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.3.A.iii Skilled day 4.3 900 3870.0 Ply Wood 9 mm thick. sqm 1.375 550 756.25
Unskilled day 5.4 600 3240.0 Timber cum 0.9 187143 168428.7
Nails, spikes, etc. kg 6 114.4 686.4
Sub total of A = 7110.0 Sub total of B = 169871.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 176981.4 Sub total of A + B + C + D= 176981.4 Contractor's overhead expenses 15% = 26547.2 Norms Rate = 203528.6
Unit Rate = 20352.86

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using timber, Height above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.3.A.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using steel, Height upto 3 m 10 sqm
Spec. cl. No: 1804, 1805
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 69 of 276

Norms Labour (A) Material (B) Equipment (C) Formworks (D)


No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.3.B.i Skilled day 2 900 1800.0 MS Sheet 14 gauge & Angle Stiffners kg 8.833 139.1 1228.7166667
Unskilled day 3 600 1800.0 MS Pipes 40 mm dia. m 1.167 226.54 264.29666667
Clamps nos 1.000 46.8 46.8
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.089 200000 17800
Sub total of A = 3600.0 Sub total of B = 19339.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 22939.8 Sub total of A + B + C + D= 22939.8 Contractor's overhead expenses 15% = 3441.0 Norms Rate = 26380.8
Unit Rate = 2638.08

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 70 of 276

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using steel, Height above 3 m to 6 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.3.B.ii Skilled day 2.4 900 2160.0 MS Sheet 14 gauge & Angle Stiffners kg 8.833 139.1 1228.7166667
Unskilled day 3.8 600 2280.0 MS Pipes 40 mm dia. m 1.400 226.54 317.156
Clamps nos 1.200 46.8 56.16
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.089 200000 17800
Sub total of A = 4440.0 Sub total of B = 19402.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 23842.0 Sub total of A + B + C + D= 23842.0 Contractor's overhead expenses 15% = 3576.3 Norms Rate = 27418.3
Unit Rate = 2741.83

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using steel, Height above 6 m to 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.3.B.iii Skilled day 3 900 2700.0 MS Sheet 14 gauge & Angle Stiffners kg 8.833 139.1 1228.7166667
Unskilled day 5.4 600 3240.0 MS Pipes 40 mm dia. m 1.778 226.54 402.73777778
Clamps nos 1.517 46.8 70.98
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.089 200000 17800
Sub total of A = 5940.0 Sub total of B = 19502.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 25442.4 Sub total of A + B + C + D= 25442.4 Contractor's overhead expenses 15% = 3816.4 Norms Rate = 29258.8
Unit Rate = 2925.88

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for walls., (Class F2 Finish), Vertical curve surface, using steel, Height more than above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.3.B.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using timber, Height upto 3 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.4.A.i Skilled day 2.75 900 2475.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 2.4 600 1440.0 Timber cum 0.5 187143 93571.5
Nails, spikes, etc. kg 3 114.4 343.2
Sub total of A = 3915.0 Sub total of B = 94923.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 98838.0 Sub total of A + B + C + D= 98838.0 Contractor's overhead expenses 15% = 14825.7 Norms Rate = 113663.7
Unit Rate = 11366.37

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using timber, Height upto 3 m to 6m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.4.A.ii Skilled day 3.2 900 2880.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 3.2 600 1920.0 Timber cum 0.6 187143 112285.8
Nails, spikes, etc. kg 4 114.4 457.6
Sub total of A = 4800.0 Sub total of B = 113751.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 118551.7 Sub total of A + B + C + D= 118551.7 Contractor's overhead expenses 15% = 17782.8 Norms Rate = 136334.5
Unit Rate = 13633.45

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using timber, Height upto 6 m to 9m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.4.A.iii Skilled day 4 900 3600.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 4.4 600 2640.0 Timber cum 0.75 187143 140357.25
Nails, spikes, etc. kg 5 114.4 572
Sub total of A = 6240.0 Sub total of B = 141937.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 148177.6 Sub total of A + B + C + D= 148177.6 Contractor's overhead expenses 15% = 22226.6 Norms Rate = 170404.2
Unit Rate = 17040.42

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 71 of 276

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using timber, Above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.4.A.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using steel, Height upto 3 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.4.B.i Skilled day 2 900 1800.0 MS Sheet 14 gauge & Angle Stiffners kg 10.600 139.1 1474.46
Unskilled day 2.4 600 1440.0 MS Pipes 40 mm dia. m 1.000 226.54 226.54
Clamps nos 1.020 46.8 47.736
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.102 200000 20342.857143
Sub total of A = 3240.0 Sub total of B = 22091.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 25331.6 Sub total of A + B + C + D= 25331.6 Contractor's overhead expenses 15% = 3799.7 Norms Rate = 29131.3
Unit Rate = 2913.13

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using steel, Height upto 3 m to 6m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.4.B.ii Skilled day 2.3 900 2070.0 MS Sheet 14 gauge & Angle Stiffners kg 10.600 139.1 1474.46
Unskilled day 3.1 600 1860.0 MS Pipes 40 mm dia. m 1.200 226.54 271.848
Clamps nos 1.240 46.8 58.032
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.102 200000 20342.857143
Sub total of A = 3930.0 Sub total of B = 22147.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 26077.2 Sub total of A + B + C + D= 26077.2 Contractor's overhead expenses 15% = 3911.6 Norms Rate = 29988.8
Unit Rate = 2998.88

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using steel, Height upto 6 m to 9m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.4.B.iii Skilled day 2.9 900 2610.0 MS Sheet 14 gauge & Angle Stiffners kg 10.600 139.1 1474.46
Unskilled day 4.4 600 2640.0 MS Pipes 40 mm dia. m 1.522 226.54 344.84422222
Clamps nos 1.560 46.8 73.008
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.102 200000 20342.857143
Sub total of A = 5250.0 Sub total of B = 22235.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 27485.2 Sub total of A + B + C + D= 27485.2 Contractor's overhead expenses 15% = 4122.8 Norms Rate = 31607.9
Unit Rate = 3160.79

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Square / Rectangular surface, Using steel, Above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.4.B.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using timber, Height upto 3 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.5.A.i Skilled day 3.6 900 3240.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 3.3 600 1980.0 Timber cum 0.75 187143 140357.25
Nails, spikes, etc. kg 5 114.4 572
Sub total of A = 5220.0 Sub total of B = 141937.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 147157.6 Sub total of A + B + C + D= 147157.6 Contractor's overhead expenses 15% = 22073.6 Norms Rate = 169231.2
Unit Rate = 16923.12

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using timber, Height upto 3 m to 6m 10 sqm
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 72 of 276
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using timber, Height upto 3 m to 6m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.5.A.ii Skilled day 4.2 900 3780.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 4.2 600 2520.0 Timber cum 1 187143 187143
Nails, spikes, etc. kg 6.5 114.4 743.6
Sub total of A = 6300.0 Sub total of B = 188894.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 195194.9 Sub total of A + B + C + D= 195194.9 Contractor's overhead expenses 15% = 29279.2 Norms Rate = 224474.2
Unit Rate = 22447.42

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 73 of 276

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using timber, Height upto 6 m to 9m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.5.A.iii Skilled day 5.2 900 4680.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 5.9 600 3540.0 Timber cum 1.2 187143 224571.6
Nails, spikes, etc. kg 8 114.4 915.2
Sub total of A = 8220.0 Sub total of B = 226495.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 234715.1 Sub total of A + B + C + D= 234715.1 Contractor's overhead expenses 15% = 35207.3 Norms Rate = 269922.4
Unit Rate = 26992.24

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using timber, Above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.5.A.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, Height upto 3 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.5.B.i Skilled day 2.4 900 2160.0 MS Sheet 14 gauge & Angle Stiffners kg 10.600 139.1 1474.46
Unskilled day 3.3 600 1980.0 MS Pipes 40 mm dia. m 1.500 226.54 339.81
Clamps nos 1.540 46.8 72.072
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.102 200000 20342.857143
Sub total of A = 4140.0 Sub total of B = 22229.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 26369.2 Sub total of A + B + C + D= 26369.2 Contractor's overhead expenses 15% = 3955.4 Norms Rate = 30324.6
Unit Rate = 3032.46

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, Height upto 3 m to 6m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.5.B.ii Skilled day 2.9 900 2610.0 MS Sheet 14 gauge & Angle Stiffners kg 10.600 139.1 1474.46
Unskilled day 4.2 600 2520.0 MS Pipes 40 mm dia. m 1.800 226.54 407.772
Clamps nos 1.860 46.8 87.048
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.102 200000 20342.857143
Sub total of A = 5130.0 Sub total of B = 22312.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 27442.1 Sub total of A + B + C + D= 27442.1 Contractor's overhead expenses 15% = 4116.3 Norms Rate = 31558.5
Unit Rate = 3155.85

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, Height upto 6 m to 9m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.5.B.iii Skilled day 3.6 900 3240.0 MS Sheet 14 gauge & Angle Stiffners kg 10.600 139.1 1474.46
Unskilled day 2.9 600 1740.0 MS Pipes 40 mm dia. m 2.289 226.54 518.52488889
Clamps nos 2.360 46.8 110.448
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.102 200000 20342.857143
Sub total of A = 4980.0 Sub total of B = 22446.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 27426.3 Sub total of A + B + C + D= 27426.3 Contractor's overhead expenses 15% = 4113.9 Norms Rate = 31540.2
Unit Rate = 3154.02

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for columns, (Class F3 Finish), Circular surface, Using steel, Above 9 m 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10 % for every additional meter height to
18.5.B.iv
the rate for previous height
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after
Prepared By:________________ completion
Checked for slab structure., Class F2 Finish,
By:________________ False work
Recommended not included, Using timber
By:________________ 10 sqm
Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 74 of 276
Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for slab structure., Class F2 Finish, False work not included, Using timber 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.6.A Skilled day 1.8 900 1620.0 Planks 38 mm thick. & rafters, beam, battens etc. cum 0.090 29138 2622.42
Unskilled day 2.5 600 1500.0 Nails, spikes, etc. kg 2.5 114.4 286
Sub total of A = 3120.0 Sub total of B = 2908.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 6028.4 Sub total of A + B + C + D= 6028.4 Contractor's overhead expenses 15% = 904.3 Norms Rate = 6932.7
Unit Rate = 693.27

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 75 of 276

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for slab structure., Class F2 Finish, False work not included, Using steel 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.6.B Skilled day 1.25 900 1125.0 Unit =sqm (For 10 sqm)
Unskilled day 2.5 600 1500.0 MS Sheet 14 gauge & Angle Stiffners kg 13.250 139.1 1843.075
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.102 200000 20342.857143
Sub total of A = 2625.0 Sub total of B = 22185.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 24810.9 Sub total of A + B + C + D= 24810.9 Contractor's overhead expenses 15% = 3721.6 Norms Rate = 28532.6
Unit Rate = 2853.26

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for slab structure., Class F2 Finish, False work not included, Using shuttering Ply 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.6.C Skilled day 1.5 900 1350.0 Unit =sqm (For 10 sqm)
Unskilled day 2.5 600 1500.0 Ply Wood 12 mm thick. sqm 1.833 570 1045
Rafter, Stuts, Beam, Battens etc. cum 0.1 0 0
Nails, spikes, etc. kg 2 114.4 228.8
Sub total of A = 2850.0 Sub total of B = 1273.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 4123.8 Sub total of A + B + C + D= 4123.8 Contractor's overhead expenses 15% = 618.6 Norms Rate = 4742.4
Unit Rate = 474.24

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for slab & beam structure., Class F2 Finish, False work not included, Using timber 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.7.A Skilled day 3 900 2700.0 Planks 38 mm thick. & rafters, beam, battens etc. cum 0.137 29138 3982.1933333
Unskilled day 3 600 1800.0 Nails, spikes, etc. kg 4 114.4 457.6
Sub total of A = 4500.0 Sub total of B = 4439.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 8939.8 Sub total of A + B + C + D= 8939.8 Contractor's overhead expenses 15% = 1341.0 Norms Rate = 10280.8
Unit Rate = 1028.08

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for slab & beam structure., Class F2 Finish, False work not included, Using steel 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.7.B Skilled day 2 900 1800.0 MS Sheet 14 gauge & Angle Stiffners kg 13.250 139.1 1843.075
Unskilled day 3 600 1800.0 MS Pipes 40 mm dia. m 0.533 226.54 120.82133333
Clamps nos 0.450 46.8 21.06
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.119 200000 23733.333333
Sub total of A = 3600.0 Sub total of B = 25718.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 29318.3 Sub total of A + B + C + D= 29318.3 Contractor's overhead expenses 15% = 4397.7 Norms Rate = 33716.0
Unit Rate = 3371.6

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for slab & beam structure., Class F2 Finish, False work not included, Using shuttering Ply 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.7.C Skilled day 2.5 900 2250.0 Ply Wood 12 mm thick. sqm 1.833 570 1045
Unskilled day 3 600 1800.0 Rafter, Stuts, Beam, Battens etc. cum 0.32 0 0
Nails, spikes, etc. kg 3 114.4 343.2
Sub total of A = 4050.0 Sub total of B = 1388.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 5438.2 Sub total of A + B + C + D= 5438.2 Contractor's overhead expenses 15% = 815.7 Norms Rate = 6253.9
Unit Rate = 625.39

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for arch structure., Class F2 Finish, False work not included, Using timber 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.8.A Skilled day 3.5 900 3150.0 Ply Wood 12 mm thick. sqm 1.833 570 1045
Unskilled day 3 600 1800.0 Rafter, Stuts, Beam, Battens etc. cum 0.3 0 0
Nails, spikes, etc. kg 4 114.4 457.6
Sub total of A = 4950.0 Sub total of B = 1502.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 6452.6 Sub total of A + B + C + D= 6452.6 Contractor's overhead expenses 15% = 967.9 Norms Rate = 7420.5
Unit Rate = 742.05

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 76 of 276

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for arch structure., Class F2 Finish, False work not included, Using steel 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.8.B Skilled day 2.5 900 2250.0 MS Sheet 14 gauge & Angle Stiffners kg 13.250 139.1 1843.075
Unskilled day 3 600 1800.0 MS Pipes 40 mm dia. m 0.533 226.54 120.82133333
Clamps nos 0.450 46.8 21.06
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.119 200000 23733.333333
Sub total of A = 4050.0 Sub total of B = 25718.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 29768.3 Sub total of A + B + C + D= 29768.3 Contractor's overhead expenses 15% = 4465.2 Norms Rate = 34233.5
Unit Rate = 3423.35

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for precast element., Class F3 Finish, Square / Rectangular section, Using timber 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.9.I.a Skilled day 2.5 900 2250.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 2 600 1200.0 Timber cum 0.2 187143 37428.6
Nails, spikes, etc. kg 2 114.4 228.8
Sub total of A = 3450.0 Sub total of B = 38665.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 42115.7 Sub total of A + B + C + D= 42115.7 Contractor's overhead expenses 15% = 6317.4 Norms Rate = 48433.1
Unit Rate = 4843.31

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for precast element., Class F3 Finish, Square / Rectangular section, Using steel 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.9.I.b Skilled day 2 900 1800.0 MS Sheet 14 gauge & Angle Stiffners kg 13.250 139.1 1843.075
Unskilled day 2 600 1200.0 MS Pipes 40 mm dia. m 0.533 226.54 120.82133333
Clamps nos 0.450 46.8 21.06
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.119 200000 23733.333333
Sub total of A = 3000.0 Sub total of B = 25718.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 28718.3 Sub total of A + B + C + D= 28718.3 Contractor's overhead expenses 15% = 4307.7 Norms Rate = 33026.0
Unit Rate = 3302.6

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for precast element., Class F3 Finish, Circular section, Using timber 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.9.II.a Skilled day 3 900 2700.0 Ply Wood 9 mm thick. sqm 1.833 550 1008.3333333
Unskilled day 2.5 600 1500.0 Timber cum 0.2 187143 37428.6
Nails, spikes, etc. kg 3 114.4 343.2
Sub total of A = 4200.0 Sub total of B = 38780.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 42980.1 Sub total of A + B + C + D= 42980.1 Contractor's overhead expenses 15% = 6447.0 Norms Rate = 49427.2
Unit Rate = 4942.72

Description of Work:
Providing , Preparing and Installing form work including necessary supports and removing after completion for precast element., Class F3 Finish, Circular section, Using steel 10 sqm
Spec. cl. No: 1804, 1805
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.9.II.b Skilled day 2.5 900 2250.0 MS Sheet 14 gauge & Angle Stiffners kg 13.250 139.1 1843.075
Unskilled day 2 600 1200.0 MS Pipes 40 mm dia. m 0.700 226.54 158.578
Clamps nos 0.600 46.8 28.08
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 0.119 200000 23733.333333
Sub total of A = 3450.0 Sub total of B = 25763.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 29213.1 Sub total of A + B + C + D= 29213.1 Contractor's overhead expenses 15% = 4382.0 Norms Rate = 33595.0
Unit Rate = 3359.5

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification For Slab and Box culverts, Using timber, Height upto 2 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.10.A.i Skilled day 8 900 7200.0 Timber cum 0.100 187143 18714.3
Unskilled day 8 600 4800.0 Nails, spikes, etc. kg 2.5 114.4 286
Sub total of A = 12000.0 Sub total of B = 19000.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 31000.3 Sub total of A + B + C + D= 31000.3 Contractor's overhead expenses 15% = 4650.0 Norms Rate = 35650.3
Unit Rate = 3565.03

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 77 of 276

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification For Slab and Box culverts, Using timber, Height above 2 m to 4 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.10.A.i
Skilled day 16 900 14400.0 Timber cum 0.175 187143 32750.025
i
Unskilled day 18 600 10800.0 Nails, spikes, etc. kg 4 114.4 457.6
Sub total of A = 25200.0 Sub total of B = 33207.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 58407.6 Sub total of A + B + C + D= 58407.6 Contractor's overhead expenses 15% = 8761.1 Norms Rate = 67168.8
Unit Rate = 6716.88

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification For Slab and Box culverts, Using timber, Height above 4 m to 6 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.10.A.i
Skilled day 24 900 21600.0 Timber cum 0.238 187143 44446.4625
ii
Unskilled day 28 600 16800.0 Nails, spikes, etc. kg 5.5 114.4 629.2
Sub total of A = 38400.0 Sub total of B = 45075.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 83475.7 Sub total of A + B + C + D= 83475.7 Contractor's overhead expenses 15% = 12521.3 Norms Rate = 95997.0
Unit Rate = 9599.7

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification For Slab and Box culverts, Using steel, Height upto 2 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.10.B.i Skilled day 4 900 3600.0 MS Pipes 40-50 mm dia. m 4.000 226.54 906.16
Unskilled day 6 600 3600.0 Clamps nos 3.425 46.8 160.29
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 7200.0 Sub total of B = 713066.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 720266.5 Sub total of A + B + C + D= 720266.5 Contractor's overhead expenses 15% = 108040.0 Norms Rate = 828306.4
Unit Rate = 82830.64

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification For Slab and Box culverts, Using steel, Height above 2 m to 4 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.10.B.i
Skilled day 8 900 7200.0 MS Pipes 40 mm dia. m 0.700 226.54 158.578
i
Unskilled day 14 600 8400.0 Clamps nos 0.600 46.8 28.08
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 15600.0 Sub total of B = 712186.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 727786.7 Sub total of A + B + C + D= 727786.7 Contractor's overhead expenses 15% = 109168.0 Norms Rate = 836954.7
Unit Rate = 83695.47

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification For Slab and Box culverts, Using steel, Height above 4 m to 6 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.10.B.i
Skilled day 12 900 10800.0 MS Pipes 40 mm dia. m 9.500 226.54 2152.13
ii
Unskilled day 20 600 12000.0 Clamps nos 8.125 46.8 380.25
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 22800.0 Sub total of B = 714532.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 737332.4 Sub total of A + B + C + D= 737332.4 Contractor's overhead expenses 15% = 110599.9 Norms Rate = 847932.2
Unit Rate = 84793.22

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification For Slab and Box culverts, Using steel, Height above 6 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Increase the rate by 10% for every additional meter height to
18.10.B.i
the rate for the previous height or Design as a special case and
v
derive Norms
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure andChecked
Prepared By:________________ removing after completion including designRecommended
By:________________ & drawings as per specification, for RCC Beam Bridge, Using timber, Height upto 3 m
By:________________ 10 sqm
Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 78 of 276
Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Beam Bridge, Using timber, Height upto 3 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.11.a.i Skilled day 14 900 12600.0 Timber cum 0.250 187143 46785.75
Unskilled day 14 600 8400.0 Nails, spikes, etc. kg 6 114.4 686.4
Sub total of A = 21000.0 Sub total of B = 47472.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 68472.2 Sub total of A + B + C + D= 68472.2 Contractor's overhead expenses 15% = 10270.8 Norms Rate = 78743.0
Unit Rate = 7874.3

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 79 of 276

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Beam Bridge, Using timber, Height above 3 m to 6 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.11.a.ii Skilled day 28 900 25200.0 Timber cum 0.500 187143 93571.5
Unskilled day 32 600 19200.0 Nails, spikes, etc. kg 12 114.4 1372.8
Sub total of A = 44400.0 Sub total of B = 94944.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 139344.3 Sub total of A + B + C + D= 139344.3 Contractor's overhead expenses 15% = 20901.6 Norms Rate = 160245.9
Unit Rate = 16024.59

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Beam Bridge, Using timber, Height above 6 m to 9 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.11.a.ii
Skilled day 40 900 36000.0 Timber cum 0.875 187143 163750.125
i
Unskilled day 50 600 30000.0 Nails, spikes, etc. kg 21 114.4 2402.4
Sub total of A = 66000.0 Sub total of B = 166152.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 232152.5 Sub total of A + B + C + D= 232152.5 Contractor's overhead expenses 15% = 34822.9 Norms Rate = 266975.4
Unit Rate = 26697.54

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Beam Bridge, Using steel, Height upto 3 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.11.b.i Skilled day 7 900 6300.0 MS Pipes 40-50 mm dia. m 5.000 226.54 1132.7
Unskilled day 11 600 6600.0 Clamps nos 4.275 46.8 200.07
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 12900.0 Sub total of B = 713332.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 726232.8 Sub total of A + B + C + D= 726232.8 Contractor's overhead expenses 15% = 108934.9 Norms Rate = 835167.7
Unit Rate = 83516.77

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Beam Bridge, Using steel, Height above 3 m to 6m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.11.b.i
Skilled day 14 900 12600.0 MS Pipes 40 mm dia. m 10.000 226.54 2265.4
i
Unskilled day 25 600 15000.0 Clamps nos 8.550 46.8 400.14
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 27600.0 Sub total of B = 714665.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 742265.5 Sub total of A + B + C + D= 742265.5 Contractor's overhead expenses 15% = 111339.8 Norms Rate = 853605.4
Unit Rate = 85360.54

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Beam Bridge, Using steel, Height above 3 m to 6m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.11.b.i
Skilled day 20 900 18000.0 MS Pipes 40 mm dia. m 16.333 226.54 3700.1533333
ii
Unskilled day 40 600 24000.0 Clamps nos 14.000 46.8 655.2
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 42000.0 Sub total of B = 716355.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 758355.4 Sub total of A + B + C + D= 758355.4 Contractor's overhead expenses 15% = 113753.3 Norms Rate = 872108.7
Unit Rate = 87210.87

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Arch Bridge, Using timber, Height upto 3 m 10 sqm
Spec. cl. No: 1803
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.12.A.i Skilled day 18 900 16200.0 Timber cum 0.150 187143 28071.45
Unskilled day 16 600 9600.0 Nails, spikes, etc. kg 3.5 114.4 400.4
Sub total of A = 25800.0 Sub total of B = 28471.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 54271.9 Sub total of A + B + C + D= 54271.9 Contractor's overhead expenses 15% = 8140.8 Norms Rate = 62412.6
Unit Rate = 6241.26

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Arch Bridge, Using timber, Height above 3m to 6 m 10 sqm
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 80 of 276
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Arch Bridge, Using timber, Height above 3m to 6 m 10 sqm
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.12.A.i
Skilled day 36 900 32400.0 Timber cum 0.300 187143 56142.9
i
Unskilled day 36 600 21600.0 Nails, spikes, etc. kg 7 114.4 800.8
Sub total of A = 54000.0 Sub total of B = 56943.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 110943.7 Sub total of A + B + C + D= 110943.7 Contractor's overhead expenses 15% = 16641.6 Norms Rate = 127585.3
Unit Rate = 12758.53

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 81 of 276

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Arch Bridge, Using timber, Height above 6 m to 9 m 10 sqm
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.12.A.i
Skilled day 50 900 45000.0 Timber cum 0.525 187143 98250.075
ii
Unskilled day 57 600 34200.0 Nails, spikes, etc. kg 12 114.4 1372.8
Sub total of A = 79200.0 Sub total of B = 99622.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 178822.9 Sub total of A + B + C + D= 178822.9 Contractor's overhead expenses 15% = 26823.4 Norms Rate = 205646.3
Unit Rate = 20564.63

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Arch Bridge, Using steel, Height upto 3 m 10 sqm
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.12.B.i Skilled day 8 900 7200.0 MS Pipes 40-50 mm dia. m 6.000 226.54 1359.24
Unskilled day 12 600 7200.0 Clamps nos 5.125 46.8 239.85
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 14400.0 Sub total of B = 713599.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 727999.1 Sub total of A + B + C + D= 727999.1 Contractor's overhead expenses 15% = 109199.9 Norms Rate = 837199.0
Unit Rate = 83719.9

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Arch Bridge, Using steel, Height above 3 m to 6 m 10 sqm
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.12.B.i
Skilled day 16 900 14400.0 MS Pipes 40 mm dia. m 12.000 226.54 2718.48
i
Unskilled day 25 600 15000.0 Clamps nos 10.250 46.8 479.7
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 29400.0 Sub total of B = 715198.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 744598.2 Sub total of A + B + C + D= 744598.2 Contractor's overhead expenses 15% = 111689.7 Norms Rate = 856287.9
Unit Rate = 85628.79

Description of Work:
Providing and assembling in position falsework for the construction of RCC superstructure and removing after completion including design & drawings as per specification, for RCC Arch Bridge, Using steel, Height above 6 m to 9 m 10 sqm
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
18.12.B.i
Skilled day 25 900 22500.0 MS Pipes 40 mm dia. m 19.667 226.54 4455.2866667
ii
Unskilled day 46 600 27600.0 Clamps nos 16.850 46.8 788.58
Nuts & bolts 6 mm dia. (@approx. 2 kg per 100 nos) kg 3.56 200000 712000
Sub total of A = 50100.0 Sub total of B = 717243.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 767343.9 Sub total of A + B + C + D= 767343.9 Contractor's overhead expenses 15% = 115101.6 Norms Rate = 882445.4
Unit Rate = 88244.54

Description of Work:
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation complete as per Drawing and Technical Specifications. 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.1 Skilled day 2 900 1800.0 Aggregate 40 mm cum 13.5 1700 22950 Concrete Mixer hour 6 362 2172.0
Unskilled day 22 600 13200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Cement tonne 3.45 17500 60375
Water KL 2 400 800
Sub total of A = 15000.0 Sub total of B = 89052.5 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 113958.5 Sub total of A + B + C + D= 113958.5 Contractor's overhead expenses 15% = 17093.8 Norms Rate = 131052.3
Unit Rate = 8736.82

Description of Work:
Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation complete as per Drawing and Technical Specifications., Manual Mixing 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.1.b Skilled day 3 900 2700.0 Aggregate 40 mm cum 13.5 1700 22950
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5
Cement tonne 3.45 17500 60375
Water KL 2 400 800
Sub total of A = 22500.0 Sub total of B = 89052.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 111552.5 Sub total of A + B + C + D= 111552.5 Contractor's overhead expenses 15% = 16732.9 Norms Rate = 128285.4

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 82 of 276

Unit Rate = 8552.36

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 83 of 276

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications, PCC Grade M 15 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.A Skilled day 3 900 2700.0 Cement tonne 4.13 17500 72275 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 8.1 1700 13770
Aggregate 20 mm cum 4.05 1725 6986.25
Aggregate 10 mm cum 1.35 1800 2430
Water KL 2 400 800
Sub total of A = 20700.0 Sub total of B = 101188.8 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 131794.8 Sub total of A + B + C + D= 131794.8 Contractor's overhead expenses 15% = 19769.2 Norms Rate = 151564.0
Unit Rate = 10104.26

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications, PCC Grade M 15, Manual Mixing 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.A_a Skilled day 4.5 900 4050.0 Cement tonne 4.13 17500 72275
Unskilled day 45 600 27000.0 Coarse Sand cum 6.75 730 4927.5
Aggregate 40 mm cum 8.1 1700 13770
Aggregate 20 mm cum 4.05 1725 6986.25
Aggregate 10 mm cum 1.35 1800 2430
Water KL 2 400 800
Sub total of A = 31050.0 Sub total of B = 101188.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 132238.8 Sub total of A + B + C + D= 132238.8 Contractor's overhead expenses 15% = 19835.8 Norms Rate = 152074.6
Unit Rate = 10138.3

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications, PCC Grade M 20 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.B Skilled day 3 900 2700.0 Cement tonne 5.16 17500 90300 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 5.4 1700 9180
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 2.5 400 1000
Sub total of A = 20700.0 Sub total of B = 119582.5 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150188.5 Sub total of A + B + C + D= 150188.5 Contractor's overhead expenses 15% = 22528.3 Norms Rate = 172716.8
Unit Rate = 11514.45

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications., RCC Grade M 20 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.C Skilled day 3 900 2700.0 Cement tonne 5.21 17500 91175 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 2.5 400 1000
Sub total of A = 20700.0 Sub total of B = 120795.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 151401.0 Sub total of A + B + C + D= 151401.0 Contractor's overhead expenses 15% = 22710.2 Norms Rate = 174111.2
Unit Rate = 11607.41

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications., PCC Grade M 25 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.D Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 5.4 1700 9180
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture Kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137302.5 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 167908.5 Sub total of A + B + C + D= 167908.5 Contractor's overhead expenses 15% = 25186.3 Norms Rate = 193094.8
Unit Rate = 12872.99

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 84 of 276

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications., RCC Grade M 25 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.E Skilled day 3 900 2700.0 Cement tonne 6.05 17500 105875 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.2 125 3025
Sub total of A = 20700.0 Sub total of B = 138720.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 169326.0 Sub total of A + B + C + D= 169326.0 Contractor's overhead expenses 15% = 25398.9 Norms Rate = 194724.9
Unit Rate = 12981.66

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications., PCC Grade M 30 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.F Skilled day 3 900 2700.0 Cement tonne 6.08 17500 106400 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 5.4 1700 9180
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture kg 243.2 125 30400
Sub total of A = 20700.0 Sub total of B = 166282.5 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 196888.5 Sub total of A + B + C + D= 196888.5 Contractor's overhead expenses 15% = 29533.3 Norms Rate = 226421.8
Unit Rate = 15094.79

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications., RCC Grade M30 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.G Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 20700.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 170226.0 Sub total of A + B + C + D= 170226.0 Contractor's overhead expenses 15% = 25533.9 Norms Rate = 195759.9
Unit Rate = 13050.66

Description of Work:
Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as per Drawing and Technical Specifications., RCC Grade M 35 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.2.H Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 20700.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 174366.0 Sub total of A + B + C + D= 174366.0 Contractor's overhead expenses 15% = 26154.9 Norms Rate = 200520.9
Unit Rate = 13368.06

Description of Work:
Providing and laying , fitting and placing un-coated Mild steel / HYSD reinforcement complete in foundation as per drawing and technical specification 1 tonne
Spec. cl. No: 2014
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
20.3 day 4 1100 4400.0 MS bars tonne 1.1 90000 99000
(Blacksmith)
Unskilled day 9 600 5400.0 Binding Wire Kg 8 140 1120
Sub total of A = 9800.0 Sub total of B = 100120.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 109920.0 Sub total of A + B + C + D= 109920.0 Contractor's overhead expenses 15% = 16488.0 Norms Rate = 126408.0
Unit Rate = 126408

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 85 of 276

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 15, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.A Skilled day 3 900 2700.0 Cement tonne 4.13 17500 72275 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 8.1 1700 13770
Aggregate 20 mm cum 4.05 1725 6986.25
Aggregate 10 mm cum 1.35 1800 2430
Water KL 2 400 800
Per Cum Basic Cost of Labour, Material & Equipment (a+b+c)
of Item 20.2 (A)
Sub total of A = 20700.0 Sub total of B = 101188.8 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 131794.8 Sub total of A + B + C + D= 131794.8 Contractor's overhead expenses 15% = 19769.2 Norms Rate = 151564.0
Unit Rate = 10104.26

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M20, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Basic Cost of Labour, Material
20.4.B Skilled day 3 900 2700.0 Cement tonne 5.16 17500 90300 Concrete Mixer hour 6 362 2172.0 & Equipment (a+b+c) of Item 0.0
20.2 (B)
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0 d) formwork 15018.9
Add 10 % of cost of Material,
Aggregate 40 mm cum 5.4 1700 9180 Labour and Equipment (a+b+c) 0.0
for Formwork
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 2.5 400 1000
Sub total of A = 20700.0 Sub total of B = 119582.5 Sub total of C = 9906.0 Sub total of D = 15018.9
Sub total of A +B + C = 150188.5 Sub total of A + B + C + D= 165207.4 Contractor's overhead expenses 15% = 24781.1 Norms Rate = 189988.5
Unit Rate = 12665.9

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 25, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Basic Cost of Labour, Material
20.4.C.p Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0 & Equipment (a+b+c) of item 0.0
20.2(D)
Add 10 % of cost of Material,
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0 Labour and Equipment (a+b+c) 16790.9
for Formwork
Aggregate 40 mm cum 5.4 1700 9180
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture Kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137302.5 Sub total of C = 9906.0 Sub total of D = 16790.9
Sub total of A +B + C = 167908.5 Sub total of A + B + C + D= 184699.4 Contractor's overhead expenses 15% = 27704.9 Norms Rate = 212404.3
Unit Rate = 14160.28

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 86 of 276

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 25, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Basic Cost of Labour, Material
20.4.C.q Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0 & Equipment (a+b+c) of Item 0.0
20.2 (D)
Add 12 % of cost of Material,
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0 Labour and Equipment (a+b+c) 20149.0
for Formwork
Add 2 % of cost of Material,
Labour and Equipment
Aggregate 40 mm cum 5.4 1700 9180 3358.2
excluding formwork to cater for
extra lift
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture Kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137302.5 Sub total of C = 9906.0 Sub total of D = 23507.2
Sub total of A +B + C = 167908.5 Sub total of A + B + C + D= 191415.7 Contractor's overhead expenses 15% = 28712.4 Norms Rate = 220128.0
Unit Rate = 14675.2

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 25, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Basic Cost of Labour, Material
20.4.C.r Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0 & Equipment (a+b+c) of Item 0.0
20.2 (D)
Add 15 % of cost of Material,
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0 Labour and Equipment (a+b+c) 25186.3
for Formwork
Add 4 % of cost of Material,
Labour and Equipment
Aggregate 40 mm cum 5.4 1700 9180 6716.3
excluding formwork to cater for
extra lift
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture Kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137302.5 Sub total of C = 9906.0 Sub total of D = 31902.6
Sub total of A +B + C = 167908.5 Sub total of A + B + C + D= 199811.1 Contractor's overhead expenses 15% = 29971.7 Norms Rate = 229782.8
Unit Rate = 15318.85

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 30, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Basic Cost of Labour, Material
20.4.D.p Skilled day 3 900 2700.0 Cement tonne 6.08 17500 106400 Concrete Mixer hour 6 362 2172.0 & Equipment (a+b+c) of Item 0.0
20.2 (F)
Add 10 % of cost of Material,
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0 Labour and Equipment (a+b+c) 19688.9
for Formwork
Aggregate 40 mm cum 5.4 1700 9180
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture kg 243.2 125 30400
Sub total of A = 20700.0 Sub total of B = 166282.5 Sub total of C = 9906.0 Sub total of D = 19688.9
Sub total of A +B + C = 196888.5 Sub total of A + B + C + D= 216577.4 Contractor's overhead expenses 15% = 32486.6 Norms Rate = 249064.0
Unit Rate = 16604.26

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 87 of 276

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 30, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.D.q Skilled day 3 900 2700.0 Cement tonne 6.08 17500 106400 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 5.4 1700 9180
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture kg 243.2 125 30400
Sub total of A = 20700.0 Sub total of B = 166282.5 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 196888.5 Sub total of A + B + C + D= 196888.5 Contractor's overhead expenses 15% = 29533.3 Norms Rate = 226421.8
Unit Rate = 15094.79

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, PCC Grade M 30, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.D.r Skilled day 3 900 2700.0 Cement tonne 6.08 17500 106400 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 5.4 1700 9180
Aggregate 20 mm cum 5.4 1725 9315
Aggregate 10 mm cum 2.7 1800 4860
Water KL 3 400 1200
Admixture kg 243.2 125 30400
Sub total of A = 20700.0 Sub total of B = 166282.5 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 196888.5 Sub total of A + B + C + D= 196888.5 Contractor's overhead expenses 15% = 29533.3 Norms Rate = 226421.8
Unit Rate = 15094.79

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 20, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.E.p Skilled day 3 900 2700.0 Cement tonne 5.21 17500 91175 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 2.5 400 1000
Sub total of A = 20700.0 Sub total of B = 120795.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 151401.0 Sub total of A + B + C + D= 151401.0 Contractor's overhead expenses 15% = 22710.2 Norms Rate = 174111.2
Unit Rate = 11607.41

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 88 of 276

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 20, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.E.q Skilled day 3 900 2700.0 Cement tonne 5.21 17500 91175 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 2.5 400 1000
Sub total of A = 20700.0 Sub total of B = 120795.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 151401.0 Sub total of A + B + C + D= 151401.0 Contractor's overhead expenses 15% = 22710.2 Norms Rate = 174111.2
Unit Rate = 11607.41

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 20, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.E.r Skilled day 3 900 2700.0 Cement tonne 5.21 17500 91175 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 2.5 400 1000
Sub total of A = 20700.0 Sub total of B = 120795.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 151401.0 Sub total of A + B + C + D= 151401.0 Contractor's overhead expenses 15% = 22710.2 Norms Rate = 174111.2
Unit Rate = 11607.41

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 25, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.F.p Skilled day 3 900 2700.0 Cement tonne 6.05 17500 105875 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.2 125 3025
Sub total of A = 20700.0 Sub total of B = 138720.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 169326.0 Sub total of A + B + C + D= 169326.0 Contractor's overhead expenses 15% = 25398.9 Norms Rate = 194724.9
Unit Rate = 12981.66

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 89 of 276

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 25, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.F.q Skilled day 3 900 2700.0 Cement tonne 6.05 17500 105875 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.2 125 3025
Sub total of A = 20700.0 Sub total of B = 138720.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 169326.0 Sub total of A + B + C + D= 169326.0 Contractor's overhead expenses 15% = 25398.9 Norms Rate = 194724.9
Unit Rate = 12981.66

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 25, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.F.r Skilled day 3 900 2700.0 Cement tonne 6.05 17500 105875 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.2 125 3025
Sub total of A = 20700.0 Sub total of B = 138720.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 169326.0 Sub total of A + B + C + D= 169326.0 Contractor's overhead expenses 15% = 25398.9 Norms Rate = 194724.9
Unit Rate = 12981.66

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 30, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.G.p Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 20700.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 170226.0 Sub total of A + B + C + D= 170226.0 Contractor's overhead expenses 15% = 25533.9 Norms Rate = 195759.9
Unit Rate = 13050.66

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 90 of 276

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 30, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.G.q Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 20700.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 170226.0 Sub total of A + B + C + D= 170226.0 Contractor's overhead expenses 15% = 25533.9 Norms Rate = 195759.9
Unit Rate = 13050.66

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 30, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.G.r Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 20700.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 170226.0 Sub total of A + B + C + D= 170226.0 Contractor's overhead expenses 15% = 25533.9 Norms Rate = 195759.9
Unit Rate = 13050.66

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 35, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.H.p Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 20700.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 174366.0 Sub total of A + B + C + D= 174366.0 Contractor's overhead expenses 15% = 26154.9 Norms Rate = 200520.9
Unit Rate = 13368.06

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 91 of 276

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 35, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.H.q Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 20700.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 174366.0 Sub total of A + B + C + D= 174366.0 Contractor's overhead expenses 15% = 26154.9 Norms Rate = 200520.9
Unit Rate = 13368.06

Description of Work:
Providing and laying of Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications, RCC Grade M 35, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.4.H.r Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 20700.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 174366.0 Sub total of A + B + C + D= 174366.0 Contractor's overhead expenses 15% = 26154.9 Norms Rate = 200520.9
Unit Rate = 13368.06

Description of Work:
Providing and laying , fitting and placing HYSD bar reinforcement in sub-structure complete as per Drawing and Technical Specifications 1 tonne
Spec. cl. No: 2014
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
20.5 day 4 1100 4400.0 HYSD Bar tonne 1.1 90000 99000
(Blacksmith)
Unskilled day 9 600 5400.0 Binding Wire kg 8 140 1120
Sub total of A = 9800.0 Sub total of B = 100120.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 109920.0 Sub total of A + B + C + D= 109920.0 Contractor's overhead expenses 15% = 16488.0 Norms Rate = 126408.0
Unit Rate = 126408

Description of Work:
Providing and laying ,fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and Technical Specification 1 tonne
Spec. cl. No: 2014
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
20.6 day 4 1100 4400.0 MS bars tonne 1.15 90000 103500
(Blacksmith)
Unskilled day 10 600 6000.0 Binding Wire kg 9 140 1260
Sub total of A = 10400.0 Sub total of B = 104760.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 115160.0 Sub total of A + B + C + D= 115160.0 Contractor's overhead expenses 15% = 17274.0 Norms Rate = 132434.0
Unit Rate = 132434

Description of Work: Providing and laying weep holes in Brick dry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 110 mm dia HDPE pipe, extending through the full width of the structure with slope of 1V :20H towards drawing face Complete as per Drawing and
30 meter
Technical Specifications.
Spec. cl. No: 3109
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.7 Skilled day 1 900 900.0 HDPE pipe 110 mm dia. meter 31.5 508.6861 16023.61215
Unskilled day 1 600 600.0 MS clamp nos. 30 52 1560
Collar for AC pipe nos. 10 0 0
Cement tonne 0.0255 17500 446.25
Sand cum 0.0525 730 38.325
Sub total of A = 1500.0 Sub total of B = 18068.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 19568.2 Sub total of A + B + C + D= 19568.2 Contractor's overhead expenses 15% = 2935.2 Norms Rate = 22503.4
Unit Rate = 750.11

Description of Work: Providing and laying weep holes in Stone Masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 150mm dia HDPE pipe, extending through the full width of the structure with slope of 1V :20H towards drawing face Complete as per Drawing and
30 meter
Technical Specifications.
Spec. cl. No: 3109
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.7_a Skilled day 1 900 900.0 HDPE pipe 150 mm dia. meter 31.5 866.5287 27295.65405
Unskilled day 1 600 600.0 MS clamp nos. 30 52 1560

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 92 of 276

Collar for AC pipe nos. 10 0 0


Cement tonne 0.0255 17500 446.25
Sand cum 0.0525 730 38.325
Sub total of A = 1500.0 Sub total of B = 29340.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 30840.2 Sub total of A + B + C + D= 30840.2 Contractor's overhead expenses 15% = 4626.0 Norms Rate = 35466.3
Unit Rate = 1182.21

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 93 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, RCC Grade M 20 30 meter
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A Skilled day 3 900 2700.0 Cement tonne 5.12 17500 89600 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Sub total of A = 20700.0 Sub total of B = 119420.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150026.0 Sub total of A + B + C + D= 150026.0 Contractor's overhead expenses 15% = 22503.9 Norms Rate = 172529.9
Unit Rate = 5751

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 20, Height upto 5 m 30 meter
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A.i.
Skilled day 3 900 2700.0 Cement tonne 5.12 17500 89600 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Sub total of A = 20700.0 Sub total of B = 119420.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150026.0 Sub total of A + B + C + D= 150026.0 Contractor's overhead expenses 15% = 22503.9 Norms Rate = 172529.9
Unit Rate = 5751

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 20, Height above 5 m to 10 m 30 meter
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A.i.
Skilled day 3 900 2700.0 Cement tonne 5.12 17500 89600 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Sub total of A = 20700.0 Sub total of B = 119420.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150026.0 Sub total of A + B + C + D= 150026.0 Contractor's overhead expenses 15% = 22503.9 Norms Rate = 172529.9
Unit Rate = 5751

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 20, Height above 10 m 30 meter
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A.i.
Skilled day 3 900 2700.0 Cement tonne 5.12 17500 89600 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Sub total of A = 20700.0 Sub total of B = 119420.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150026.0 Sub total of A + B + C + D= 150026.0 Contractor's overhead expenses 15% = 22503.9 Norms Rate = 172529.9
Unit Rate = 5751

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 20, Height upto 5 m 30 meter
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A.ii.
Skilled day 3 900 2700.0 Cement tonne 5.12 17500 89600 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Sub total of A = 20700.0 Sub total of B = 119420.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150026.0 Sub total of A + B + C + D= 150026.0 Contractor's overhead expenses 15% = 22503.9 Norms Rate = 172529.9
Unit Rate = 5751

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 94 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 20, Height above 5 m to 10 m 30 meter
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A.ii.
Skilled day 3 900 2700.0 Cement tonne 5.12 17500 89600 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Sub total of A = 20700.0 Sub total of B = 119420.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150026.0 Sub total of A + B + C + D= 150026.0 Contractor's overhead expenses 15% = 22503.9 Norms Rate = 172529.9
Unit Rate = 5751

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 20, Height above 10 m 30 meter
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.A.ii.
Skilled day 3 900 2700.0 Cement tonne 5.12 17500 89600 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Sub total of A = 20700.0 Sub total of B = 119420.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 150026.0 Sub total of A + B + C + D= 150026.0 Contractor's overhead expenses 15% = 22503.9 Norms Rate = 172529.9
Unit Rate = 5751

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, RCC Grade M 25 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.B Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137640.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 168246.0 Sub total of A + B + C + D= 168246.0 Contractor's overhead expenses 15% = 25236.9 Norms Rate = 193482.9
Unit Rate = 12898.86

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 25, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.B.i.
Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137640.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 168246.0 Sub total of A + B + C + D= 168246.0 Contractor's overhead expenses 15% = 25236.9 Norms Rate = 193482.9
Unit Rate = 12898.86

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 25, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.B.i.
Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137640.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 168246.0 Sub total of A + B + C + D= 168246.0 Contractor's overhead expenses 15% = 25236.9 Norms Rate = 193482.9

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 95 of 276

Unit Rate = 12898.86

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 96 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 25, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.B.i. d) Formwork and staging 30 %
Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0 50473.8
r of (a+b+c)
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137640.0 Sub total of C = 9906.0 Sub total of D = 50473.8
Sub total of A +B + C = 168246.0 Sub total of A + B + C + D= 218719.8 Contractor's overhead expenses 15% = 32808.0 Norms Rate = 251527.8
Unit Rate = 16768.52

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 25, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.B.ii. d) Formwork and staging 25 %
Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0 42061.5
p of (a+b+c)
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137640.0 Sub total of C = 9906.0 Sub total of D = 42061.5
Sub total of A +B + C = 168246.0 Sub total of A + B + C + D= 210307.5 Contractor's overhead expenses 15% = 31546.1 Norms Rate = 241853.6
Unit Rate = 16123.58

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 25, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.B.ii.
Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137640.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 168246.0 Sub total of A + B + C + D= 168246.0 Contractor's overhead expenses 15% = 25236.9 Norms Rate = 193482.9
Unit Rate = 12898.86

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 25, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.B.ii.
Skilled day 3 900 2700.0 Cement tonne 5.99 17500 104825 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 23.96 125 2995
Sub total of A = 20700.0 Sub total of B = 137640.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 168246.0 Sub total of A + B + C + D= 168246.0 Contractor's overhead expenses 15% = 25236.9 Norms Rate = 193482.9
Unit Rate = 12898.86

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, RCC Grade M 30 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.C Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 97 of 276

Sub total of A = 21900.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 171426.0 Sub total of A + B + C + D= 171426.0 Contractor's overhead expenses 15% = 25713.9 Norms Rate = 197139.9
Unit Rate = 13142.66

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 98 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 30, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.C.i.
Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 21900.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 171426.0 Sub total of A + B + C + D= 171426.0 Contractor's overhead expenses 15% = 25713.9 Norms Rate = 197139.9
Unit Rate = 13142.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 30, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.C.i.
Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 21900.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 171426.0 Sub total of A + B + C + D= 171426.0 Contractor's overhead expenses 15% = 25713.9 Norms Rate = 197139.9
Unit Rate = 13142.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC Grade M 30, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.C.i.
Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 21900.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 171426.0 Sub total of A + B + C + D= 171426.0 Contractor's overhead expenses 15% = 25713.9 Norms Rate = 197139.9
Unit Rate = 13142.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 30, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.C.ii.
Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 21900.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 171426.0 Sub total of A + B + C + D= 171426.0 Contractor's overhead expenses 15% = 25713.9 Norms Rate = 197139.9
Unit Rate = 13142.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 30, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.C.ii.
Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 99 of 276

Admixture kg 24.4 125 3050


Sub total of A = 21900.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 171426.0 Sub total of A + B + C + D= 171426.0 Contractor's overhead expenses 15% = 25713.9 Norms Rate = 197139.9
Unit Rate = 13142.66

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 100 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC Grade M 30, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.C.ii.
Skilled day 3 900 2700.0 Cement tonne 6.1 17500 106750 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 24.4 125 3050
Sub total of A = 21900.0 Sub total of B = 139620.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 171426.0 Sub total of A + B + C + D= 171426.0 Contractor's overhead expenses 15% = 25713.9 Norms Rate = 197139.9
Unit Rate = 13142.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.i.
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.i.
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in solid slab super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.i.
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 101 of 276

Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 102 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.ii.
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.ii.
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.ii.
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder and balanced cantilever super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.iii
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
.p
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder and balanced cantilever super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.iii
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
.q
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 103 of 276

Admixture kg 25.32 125 3165


Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 104 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in box girder and balanced cantilever super-structure as per drawing and Technical Specification, RCC/PSC Grade M 35, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.D.iii
Skilled day 3 900 2700.0 Cement tonne 6.33 17500 110775 Concrete Mixer hour 6 362 2172.0
.r
Unskilled day 32 600 19200.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Water KL 3 400 1200
Admixture kg 25.32 125 3165
Sub total of A = 21900.0 Sub total of B = 143760.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 175566.0 Sub total of A + B + C + D= 175566.0 Contractor's overhead expenses 15% = 26334.9 Norms Rate = 201900.9
Unit Rate = 13460.06

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in super-structure as per drawing and Technical Specification, PSC Grade M-40 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.E Skilled day 4 900 3600.0 Cement tonne 6.45 17500 112875 Concrete Mixer hour 6 362 2172.0
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Admixture kg 25.8 125 3225
Water KL 3 400 1200
Sub total of A = 23400.0 Sub total of B = 145920.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 179226.0 Sub total of A + B + C + D= 179226.0 Contractor's overhead expenses 15% = 26883.9 Norms Rate = 206109.9
Unit Rate = 13740.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab super-structure as per drawing and Technical Specification, PSC Grade M-40, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.E.i.
Skilled day 4 900 3600.0 Cement tonne 6.45 17500 112875 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Admixture kg 25.8 125 3225
Water KL 3 400 1200
Sub total of A = 23400.0 Sub total of B = 145920.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 179226.0 Sub total of A + B + C + D= 179226.0 Contractor's overhead expenses 15% = 26883.9 Norms Rate = 206109.9
Unit Rate = 13740.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab super-structure as per drawing and Technical Specification, PSC Grade M-40, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.E.i.
Skilled day 4 900 3600.0 Cement tonne 6.45 17500 112875 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Admixture kg 25.8 125 3225
Water KL 3 400 1200
Sub total of A = 23400.0 Sub total of B = 145920.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 179226.0 Sub total of A + B + C + D= 179226.0 Contractor's overhead expenses 15% = 26883.9 Norms Rate = 206109.9
Unit Rate = 13740.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in sollid slab super-structure as per drawing and Technical Specification, PSC Grade M-40, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.E.i.
Skilled day 4 900 3600.0 Cement tonne 6.45 17500 112875 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Admixture kg 25.8 125 3225
Water KL 3 400 1200

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 105 of 276

Sub total of A = 23400.0 Sub total of B = 145920.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 179226.0 Sub total of A + B + C + D= 179226.0 Contractor's overhead expenses 15% = 26883.9 Norms Rate = 206109.9
Unit Rate = 13740.66

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 106 of 276

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, PSC Grade M-40, Height upto 5 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.E.ii.
Skilled day 4 900 3600.0 Cement tonne 6.45 17500 112875 Concrete Mixer hour 6 362 2172.0
p
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Admixture kg 25.8 125 3225
Water KL 3 400 1200
Sub total of A = 23400.0 Sub total of B = 145920.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 179226.0 Sub total of A + B + C + D= 179226.0 Contractor's overhead expenses 15% = 26883.9 Norms Rate = 206109.9
Unit Rate = 13740.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, PSC Grade M-40, Height above 5 m to 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.E.ii.
Skilled day 4 900 3600.0 Cement tonne 6.45 17500 112875 Concrete Mixer hour 6 362 2172.0
q
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Admixture kg 25.8 125 3225
Water KL 3 400 1200
Sub total of A = 23400.0 Sub total of B = 145920.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 179226.0 Sub total of A + B + C + D= 179226.0 Contractor's overhead expenses 15% = 26883.9 Norms Rate = 206109.9
Unit Rate = 13740.66

Description of Work:
Providing and laying of Reinforced/ Pre-stressed cement concrete in T-beam and slab super-structure as per drawing and Technical Specification, PSC Grade M-40, Height above 10 m 15 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.8.E.ii.
Skilled day 4 900 3600.0 Cement tonne 6.45 17500 112875 Concrete Mixer hour 6 362 2172.0
r
Unskilled day 33 600 19800.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 20 mm cum 8.1 1725 13972.5
Aggregate 10 mm cum 5.4 1800 9720
Admixture kg 25.8 125 3225
Water KL 3 400 1200
Sub total of A = 23400.0 Sub total of B = 145920.0 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 179226.0 Sub total of A + B + C + D= 179226.0 Contractor's overhead expenses 15% = 26883.9 Norms Rate = 206109.9
Unit Rate = 13740.66

Description of Work:
Providing and laying , fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications 1 tonne
Spec. cl. No: 2014
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Skilled
20.9 day 4 1100 4400.0 HYSD Bar tonne 1.1 90000 99000
(Blacksmith)
Unskilled day 12 600 7200.0 Binding Wire Kg 8 140 1120
Sub total of A = 11600.0 Sub total of B = 100120.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 111720.0 Sub total of A + B + C + D= 111720.0 Contractor's overhead expenses 15% = 16758.0 Norms Rate = 128478.0
Unit Rate = 128478

Description of Work:
Providing and laying of PCC M 15 Grade leveling course below approach slab complete as per drawing and Technical specification 15 cum
Spec. cl. No: no number
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
"20.10" Skilled day 3 900 2700.0 Cement tonne 4.13 17500 72275 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Coarse Sand cum 6.75 730 4927.5 Generator hour 6 1289 7734.0
Aggregate 40 mm cum 8.1 1700 13770
Aggregate 20 mm cum 4.05 1725 6986.25
Aggregate 10 mm cum 1.35 1800 2430
Water KL 2 400 800
Sub total of A = 20700.0 Sub total of B = 101188.8 Sub total of C = 9906.0 Sub total of D = 0.0
Sub total of A +B + C = 131794.8 Sub total of A + B + C + D= 131794.8 Contractor's overhead expenses 15% = 19769.2 Norms Rate = 151564.0
Unit Rate = 10104.26

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 107 of 276

Description of Work:
Providing and laying of Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and Technical specification 1 cum
Spec. cl. No: 2014
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Cement concrete Grade ( excluding formwork i.e. per cum
20.11 cum 1 10093.4 10093.4
basic cost (a+b+c) )
( Refer relevant item of concrete in item except that form work
may be added at the rate of 2 per cent of cost against 3.5 per
cent provided in the foundation concrete.
HYSD bar reinforcement Rate tonne 0.05 111720 5586.0
Sub total of A = 0.0 Sub total of B = 15679.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 15679.4 Sub total of A + B + C + D= 15679.4 Contractor's overhead expenses 15% = 2351.9 Norms Rate = 18031.3
Unit Rate = 18031.31

Description of Work:
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications 1 cum
Spec. cl. No: 2000
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
20.12 Skilled day 2 900 1800.0 Concrete, Rate as per item No. 20.2 (G) excluding formworks cum 1 11348.4 11348.4
Unskilled day 2 600 1200.0 HYSD bar reinforcementRate as per item no 20.9 tonne 0.08 111720 8937.6
Sub total of A = 3000.0 Sub total of B = 20286.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 23286.0 Sub total of A + B + C + D= 23286.0 Contractor's overhead expenses 15% = 3492.9 Norms Rate = 26778.9
Unit Rate = 26778.9

Description of Work:
Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete excluding Pointing and Plastering, as per Drawing and Technical Specifications., Cement sand mortar (1:4) 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.1.C Skilled day 6 900 5400.0 Bricks 1st class nos 2800 12 33600
Unskilled day 12 600 7200.0 Cement tonne 0.48 17500 8400
Sand cum 1.35 730 985.5
Water KL 0.1 400 40
Sub total of A = 12600.0 Sub total of B = 43025.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 55625.5 Sub total of A + B + C + D= 55625.5 Contractor's overhead expenses 15% = 8343.8 Norms Rate = 63969.3
Unit Rate = 12793.87

Description of Work:
Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete excluding Pointing and Plastering, as per Drawing and Technical Specifications., Cement sand mortar (1:4), Using Concrete Mixer 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.1.C_a Skilled day 6 900 5400.0 Bricks 1st class nos 2800 12 33600 Concrete Mixer hr 0.75 362 271.5
Unskilled day 9 600 5400.0 Cement tonne 0.48 17500 8400
Sand cum 1.35 730 985.5
Water KL 0.1 400 40
Sub total of A = 10800.0 Sub total of B = 43025.5 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 54097.0 Sub total of A + B + C + D= 54097.0 Contractor's overhead expenses 15% = 8114.6 Norms Rate = 62211.6
Unit Rate = 12442.31

Description of Work:
Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete excluding Pointing and Plastering, as per Drawing and Technical Specifications., Cement sand mortar (1:6) 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.1.D Skilled day 6 900 5400.0 Bricks 1st class nos 2800 12 33600
Unskilled day 12 600 7200.0 Cement tonne 0.35 17500 6125
Sand cum 1.45 730 1058.5
Water KL 0.1 400 40
Sub total of A = 12600.0 Sub total of B = 40823.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 53423.5 Sub total of A + B + C + D= 53423.5 Contractor's overhead expenses 15% = 8013.5 Norms Rate = 61437.0
Unit Rate = 12287.41

Description of Work:
Providing and laying Brick Masonry Work in Cement mortar in Foundation / structure complete excluding Pointing and Plastering, as per Drawing and Technical Specifications., Cement sand mortar (1:6), Using Concrete Mixer 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.1.D_a Skilled day 6 900 5400.0 Bricks 1st class nos 2800 12 33600 Concrete Mixer hr 0.75 362 271.5
Unskilled day 9 600 5400.0 Cement tonne 0.35 17500 6125

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 108 of 276

Sand cum 1.45 730 1058.5


Water KL 0.1 400 40
Sub total of A = 10800.0 Sub total of B = 40823.5 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 51895.0 Sub total of A + B + C + D= 51895.0 Contractor's overhead expenses 15% = 7784.3 Norms Rate = 59679.3
Unit Rate = 11935.85

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 109 of 276

Description of Work:
Providing and laying Brick masonry work in superstructure/ sub-structure complete excluding pointing and plastering, as per drawing and Technical Specifications, Cement Mortar 1:4 (1 cement : 4 sand) 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.2.C Skilled day 7 900 6300.0 Bricks 1st class nos 2800 12 33600
Unskilled day 14 600 8400.0 Cement tonne 0.48 17500 8400
Sand cum 1.35 730 985.5
Water KL 0.1 400 40
Add 5 per cent of cost of Labour and material for scaffolding 2886.3
Sub total of A = 14700.0 Sub total of B = 45911.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 60611.8 Sub total of A + B + C + D= 60611.8 Contractor's overhead expenses 15% = 9091.8 Norms Rate = 69703.5
Unit Rate = 13940.71

Description of Work:
Providing and laying Brick masonry work in superstructure/ sub-structure complete excluding pointing and plastering, as per drawing and Technical Specifications, Cement Mortar 1:4 (1 cement : 4 sand), Using Concrete Mixer 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.2.C_a Skilled day 7 900 6300.0 Bricks 1st class nos 2800 12 33600 Concrete Mixer hr 0.75 362 271.5
Unskilled day 11 600 6600.0 Cement tonne 0.48 17500 8400
Sand cum 1.35 730 985.5
Water KL 0.1 400 40
Add 5 per cent of cost of Labour and material for scaffolding 2796.3
Sub total of A = 12900.0 Sub total of B = 45821.8 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 58993.3 Sub total of A + B + C + D= 58993.3 Contractor's overhead expenses 15% = 8849.0 Norms Rate = 67842.3
Unit Rate = 13568.45

Description of Work:
Providing and laying Brick masonry work in superstructure/ sub-structure complete excluding pointing and plastering, as per drawing and Technical Specifications, Cement Mortar 1:6 (1 cement : 6 sand) 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.2.D Skilled day 7 900 6300.0 Bricks 1st class nos 2800 12 33600
Unskilled day 14 600 8400.0 Cement tonne 0.35 17500 6125
Sand cum 1.45 730 1058.5
Water KL 0.1 400 40
Add 5 per cent of cost of Labour and material for scaffolding 2776.2
Sub total of A = 14700.0 Sub total of B = 43599.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 58299.7 Sub total of A + B + C + D= 58299.7 Contractor's overhead expenses 15% = 8745.0 Norms Rate = 67044.6
Unit Rate = 13408.93

Description of Work:
Providing and laying Brick masonry work in superstructure/ sub-structure complete excluding pointing and plastering, as per drawing and Technical Specifications, Cement Mortar 1:6 (1 cement : 6 sand), Using Concrete Mixer 5 cum
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.2.D_a Skilled day 7 900 6300.0 Bricks 1st class nos 2800 12 33600 Concrete Mixer hr 0.75 362 271.5
Unskilled day 11 600 6600.0 Cement tonne 0.35 17500 6125
Sand cum 1.45 730 1058.5
Water KL 0.1 400 40
Add 5 per cent of cost of Labour and material for scaffolding 2686.2
Sub total of A = 12900.0 Sub total of B = 43509.7 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 56681.2 Sub total of A + B + C + D= 56681.2 Contractor's overhead expenses 15% = 8502.2 Norms Rate = 65183.4
Unit Rate = 13036.67

Description of Work:
Providing, and applying Pointing with cement mortar (1:3 ) on brick work in structure as per Technical Specifications . 100 sqm
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.3 Skilled day 10 900 9000.0 Cement tonne 0.15 17500 2625
Unskilled day 12 600 7200.0 Sand cum 0.32 730 233.6
Water KL 1 400 400
Sub total of A = 16200.0 Sub total of B = 3258.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 19458.6 Sub total of A + B + C + D= 19458.6 Contractor's overhead expenses 15% = 2918.8 Norms Rate = 22377.4
Unit Rate = 223.77

Description of Work:
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications , Cement Mortar 1:2 (1 cement : 2 sand) 10 sqm
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 110 of 276
Description of Work:
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications , Cement Mortar 1:2 (1 cement : 2 sand) 10 sqm
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.4.A Skilled day 10 900 9000.0 Cement tonne 0.96 17500 16800
Unskilled day 12 600 7200.0 Sand cum 1.38 730 1007.4
Water KL 0.3 400 120
Sub total of A = 16200.0 Sub total of B = 17927.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 34127.4 Sub total of A + B + C + D= 34127.4 Contractor's overhead expenses 15% = 5119.1 Norms Rate = 39246.5
Unit Rate = 3924.65

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 111 of 276

Description of Work:
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications , Cement Mortar 1:2 (1 cement : 2 sand), Using Concrete Mixer 10 sqm
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.4.A_a Skilled day 10 900 9000.0 Cement tonne 0.96 17500 16800 Concrete Mixer hr 0.75 362 271.5
Unskilled day 10 600 6000.0 Sand cum 1.38 730 1007.4
Water KL 0.3 400 120
Sub total of A = 15000.0 Sub total of B = 17927.4 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 33198.9 Sub total of A + B + C + D= 33198.9 Contractor's overhead expenses 15% = 4979.8 Norms Rate = 38178.7
Unit Rate = 3817.87

Description of Work:
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications , Cement Mortar 1:3 (1 cement : 3 sand) 10 sqm
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.4.B Skilled day 10 900 9000.0 Cement tonne 0.72 17500 12600
Unskilled day 12 600 7200.0 Sand cum 1.5 730 1095
Water KL 0.2 400 80
Sub total of A = 16200.0 Sub total of B = 13775.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 29975.0 Sub total of A + B + C + D= 29975.0 Contractor's overhead expenses 15% = 4496.3 Norms Rate = 34471.3
Unit Rate = 3447.13

Description of Work:
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications , Cement Mortar 1:3 (1 cement : 3 sand), Using Concrete Mixer 100 sqm
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.4.B_a Skilled day 10 900 9000.0 Cement tonne 0.72 17500 12600 Concrete Mixer hr 0.75 362 271.5
Unskilled day 10 600 6000.0 Sand cum 1.5 730 1095
Water KL 0.2 400 80
Sub total of A = 15000.0 Sub total of B = 13775.0 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 29046.5 Sub total of A + B + C + D= 29046.5 Contractor's overhead expenses 15% = 4357.0 Norms Rate = 33403.5
Unit Rate = 334.03

Description of Work:
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications , Cement Mortar 1:4 (1 cement : 4 sand) 100 sqm
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.4.C Skilled day 10 900 9000.0 Cement tonne 0.58 17500 10150
Unskilled day 12 600 7200.0 Sand cum 1.6 730 1168
Water KL 0.17 400 68
Sub total of A = 16200.0 Sub total of B = 11386.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 27586.0 Sub total of A + B + C + D= 27586.0 Contractor's overhead expenses 15% = 4137.9 Norms Rate = 31723.9
Unit Rate = 317.24

Description of Work:
Providing and applying 12.5 mm thick Plaster with cement mortar on brick work structure as per Technical Specifications , Cement Mortar 1:4 (1 cement : 4 sand), Using Concrete Mixer 100 sqm
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.4.C_a Skilled day 10 900 9000.0 Cement tonne 0.58 17500 10150 Concrete Mixer hr 0.75 362 271.5
Unskilled day 10 600 6000.0 Sand cum 1.6 730 1168
Water KL 0.17 400 68
Sub total of A = 15000.0 Sub total of B = 11386.0 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 26657.5 Sub total of A + B + C + D= 26657.5 Contractor's overhead expenses 15% = 3998.6 Norms Rate = 30656.1
Unit Rate = 306.56

Description of Work:
Providing and laying weep holes in Brick works / Masonry/ Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia HDPE pipe as per Drawing and Technical Specifications. 30 meter
Spec. cl. No: 2500
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
25.5 Skilled day 1 900 900.0 AC pipe 100 mm dia. meter 31.5 0 0
Unskilled day 1 600 600.0 MS clamp nos 30 52 1560
Collar for AC pipe (average) taking 10% of above pipe rate nos 10 0 0
Cement tonne 0.02 17500 350
Sand cum 0.06 730 43.8
Sub total of A = 1500.0 Sub total of B = 1953.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 3453.8 Sub total of A + B + C + D= 3453.8 Contractor's overhead expenses 15% = 518.1 Norms Rate = 3971.9

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 112 of 276

Unit Rate = 132.4

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 113 of 276

Description of Work:
Providing and laying of dry Stone Masonry Work as per Drawing and Technical Specifications 5 cum
Spec. cl. No: 2602, 2603,
2608
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.1 Skilled day 4 900 3600.0 Stone cum 5.75 3328 19136
Unskilled day 8 600 4800.0
Sub total of A = 8400.0 Sub total of B = 19136.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 27536.0 Sub total of A + B + C + D= 27536.0 Contractor's overhead expenses 15% = 4130.4 Norms Rate = 31666.4
Unit Rate = 6333.28

Description of Work:
Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement Mortar 1:4 in Foundation complete as per Drawing and Technical Specifications. 5 cum
Spec. cl. No: 2602, 2603,
2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Concrete mixer or
26.3.B Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136 735.0
other tools
Unskilled day 14 600 8400.0 Cement tonne 0.62 17500 10850
Sand cum 1.74 730 1270.2
Water KL 1 400 400
Sub total of A = 14700.0 Sub total of B = 31656.2 Sub total of C = 735.0 Sub total of D = 0.0
Sub total of A +B + C = 47091.2 Sub total of A + B + C + D= 47091.2 Contractor's overhead expenses 15% = 7063.7 Norms Rate = 54154.9
Unit Rate = 10830.98

Description of Work:
Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement Mortar 1:4 in Foundation complete as per Drawing and Technical Specifications., Using Concrete Mixer 5 cum
Spec. cl. No: 2602, 2603,
2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.3.B_a Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136 Concrete Mixer hr 0.75 362 271.5
Unskilled day 9 600 5400.0 Cement tonne 0.62 17500 10850
Sand cum 1.74 730 1270.2
Water KL 1 400 400
Sub total of A = 11700.0 Sub total of B = 31656.2 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 43627.7 Sub total of A + B + C + D= 43627.7 Contractor's overhead expenses 15% = 6544.2 Norms Rate = 50171.9
Unit Rate = 10034.37

Description of Work:
Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement Mortar 1:6 in Foundation complete as per Drawing and Technical Specifications. 5 cum
Spec. cl. No: 2602, 2603,
2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.3.C Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136
Unskilled day 14 600 8400.0 Cement tonne 0.45 17500 7875
Sand cum 2.08 730 1518.4
Water KL 1 400 400
Sub total of A = 14700.0 Sub total of B = 28929.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 43629.4 Sub total of A + B + C + D= 43629.4 Contractor's overhead expenses 15% = 6544.4 Norms Rate = 50173.8
Unit Rate = 10034.76

Description of Work:
Random Rubble Masonry, Providing and laying of Stone Masonry Work in Cement Mortar 1:6 in Foundation complete as per Drawing and Technical Specifications., Using Concrete Mixer 5 cum
Spec. cl. No: 2602, 2603,
2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.3.C_a Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136 Concrete Mixer hr 0.75 362 271.5
Unskilled day 9 600 5400.0 Cement tonne 0.45 17500 7875
Sand cum 2.08 730 1518.4
Water KL 1 400 400
Sub total of A = 11700.0 Sub total of B = 28929.4 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 40900.9 Sub total of A + B + C + D= 40900.9 Contractor's overhead expenses 15% = 6135.1 Norms Rate = 47036.0
Unit Rate = 9407.21

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete as per Drawing and Technical, Random Rubble Masonry 5 cum
Spec. cl. No: 2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.5.A Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136
Unskilled day 20 600 12000.0 Cement tonne 0.66 17500 11550
Sand cum 1.85 730 1350.5
Water KL 1 400 400

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 114 of 276

@ 5 per cent of cost of Labour and material for scaffolding 2536.8


Sub total of A = 18300.0 Sub total of B = 34973.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 53273.3 Sub total of A + B + C + D= 53273.3 Contractor's overhead expenses 15% = 7991.0 Norms Rate = 61264.3
Unit Rate = 12252.86

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 115 of 276

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete as per Drawing and Technical, Random Rubble Masonry, Using Concrete Mixer 5 cum
Spec. cl. No: 2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.5.A_a Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136 Concrete Mixer hr 0.75 362 271.5
Unskilled day 15 600 9000.0 Cement tonne 0.66 17500 11550
Sand cum 1.85 730 1350.5
Water KL 1 400 400
@ 5 per cent of cost of Labour and material for scaffolding 2386.8
Sub total of A = 15300.0 Sub total of B = 34823.3 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 50394.8 Sub total of A + B + C + D= 50394.8 Contractor's overhead expenses 15% = 7559.2 Norms Rate = 57954.0
Unit Rate = 11590.81

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete as per Drawing and Technical, Coursed rubble Masonry (first sort ) 5 cum
Spec. cl. No: 2606
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.5.B Skilled day 8 900 7200.0 Stone cum 5.75 3328 19136
Unskilled day 22 600 13200.0 Cement tonne 0.6 17500 10500
Sand cum 1.68 730 1226.4
Water KL 1 400 400
@ 5 per cent of cost of Labour and material for scaffolding 2583.1
Sub total of A = 20400.0 Sub total of B = 33845.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 54245.5 Sub total of A + B + C + D= 54245.5 Contractor's overhead expenses 15% = 8136.8 Norms Rate = 62382.3
Unit Rate = 12476.47

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete as per Drawing and Technical, Coursed rubble Masonry (first sort ), Using Concrete Mixer 5 cum
Spec. cl. No: 2606
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.5.B_a Skilled day 8 900 7200.0 Stone cum 5.75 3328 19136 Concrete Mixer hr 0.75 362 271.5
Unskilled day 17 600 10200.0 Cement tonne 0.6 17500 10500
Sand cum 1.68 730 1226.4
Water KL 1 400 400
@ 5 per cent of cost of Labour and material for scaffolding 2433.1
Sub total of A = 17400.0 Sub total of B = 33695.5 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 51367.0 Sub total of A + B + C + D= 51367.0 Contractor's overhead expenses 15% = 7705.1 Norms Rate = 59072.1
Unit Rate = 11814.41

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:6 in structure complete as per Drawing and Technical Specifications, Random Rubble Masonry (coursed/uncoursed) 5 cum
Spec. cl. No: 2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.6.A Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136
Unskilled day 20 600 12000.0 Cement tonne 0.48 17500 8400
Sand cum 1.98 730 1445.4
Water KL 1 400 400
@ 5 per cent of cost of Labour and material for scaffolding 2384.1
Sub total of A = 18300.0 Sub total of B = 31765.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 50065.5 Sub total of A + B + C + D= 50065.5 Contractor's overhead expenses 15% = 7509.8 Norms Rate = 57575.3
Unit Rate = 11515.06

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:6 in structure complete as per Drawing and Technical, Random Rubble Masonry, Using Concrete Mixer 5 cum
Spec. cl. No: 2607
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.6.A_a Skilled day 7 900 6300.0 Stone cum 5.75 3328 19136 Concrete Mixer hr 0.75 362 271.5
Unskilled day 15 600 9000.0 Cement tonne 0.48 17500 8400
Sand cum 1.98 730 1445.4
Water KL 1 400 400
@ 5 per cent of cost of Labour and material for scaffolding 2234.1
Sub total of A = 15300.0 Sub total of B = 31615.5 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 47187.0 Sub total of A + B + C + D= 47187.0 Contractor's overhead expenses 15% = 7078.0 Norms Rate = 54265.0
Unit Rate = 10853

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 116 of 276

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:6 in structure complete as per Drawing and Technical Specifications, Coursed rubble Masonry (first sort ) 5 cum
Spec. cl. No: 2606
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.6.B Skilled day 8 900 7200.0 Stone cum 5.75 3328 19136
Unskilled day 22 600 13200.0 Cement tonne 0.44 17500 7700
Sand cum 1.8 730 1314
Water KL 1 400 400
@ 5 per cent of cost of Labour and material for scaffolding 2447.5
Sub total of A = 20400.0 Sub total of B = 30997.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 51397.5 Sub total of A + B + C + D= 51397.5 Contractor's overhead expenses 15% = 7709.6 Norms Rate = 59107.1
Unit Rate = 11821.43

Description of Work:
Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete as per Drawing and Technical, Coursed rubble Masonry (first sort ), Using Concrete Mixer 5 cum
Spec. cl. No: 2606
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.6.B_a Skilled day 8 900 7200.0 Stone cum 5.75 3328 19136 Concrete Mixer hr 0.75 362 271.5
Unskilled day 17 600 10200.0 Cement tonne 0.44 17500 7700
Sand cum 1.8 730 1314
Water KL 1 400 400
@ 5 per cent of cost of Labour and material for scaffolding 2297.5
Sub total of A = 17400.0 Sub total of B = 30847.5 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 48519.0 Sub total of A + B + C + D= 48519.0 Contractor's overhead expenses 15% = 7277.9 Norms Rate = 55796.9
Unit Rate = 11159.37

Description of Work:
Providing and Pointing with cement mortar on masonry work in structure as per Technical Specifications, cement mortar (1:3 ) 100 sqm
Spec. cl. No: 2600
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.7.A Skilled day 9 900 8100.0 Cement tonne 0.31 17500 5425
Unskilled day 9 600 5400.0 Sand cum 0.63 730 459.9
Water KL 0.05 400 20
Sub total of A = 13500.0 Sub total of B = 5904.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 19404.9 Sub total of A + B + C + D= 19404.9 Contractor's overhead expenses 15% = 2910.7 Norms Rate = 22315.6
Unit Rate = 223.16

Description of Work:
Providing and Pointing with cement mortar on masonry work in structure as per Technical Specifications, cement mortar (1:3 ), Using Concrete Mixer 100 sqm
Spec. cl. No: 2600
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.7.A_a Skilled day 9 900 8100.0 Cement tonne 0.31 17500 5425 Concrete Mixer hr 0.75 362 271.5
Unskilled day 8 600 4800.0 Sand cum 0.63 730 459.9
Water KL 0.05 400 20
Sub total of A = 12900.0 Sub total of B = 5904.9 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 19076.4 Sub total of A + B + C + D= 19076.4 Contractor's overhead expenses 15% = 2861.5 Norms Rate = 21937.9
Unit Rate = 219.38

Description of Work:
Providing and Pointing with cement mortar on masonry work in structure as per Technical Specifications, cement mortar (1:2 ) 100 sqm
Spec. cl. No: 2600
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.7.B Skilled day 9 900 8100.0 Cement tonne 0.4 17500 7000
Unskilled day 9 600 5400.0 Sand cum 0.56 730 408.8
Water KL 0.07 400 28
Sub total of A = 13500.0 Sub total of B = 7436.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 20936.8 Sub total of A + B + C + D= 20936.8 Contractor's overhead expenses 15% = 3140.5 Norms Rate = 24077.3
Unit Rate = 240.77

Description of Work:
Providing and Pointing with cement mortar on masonry work in structure as per Technical Specifications, cement mortar (1:2 ), Using Concrete Mixer 100 sqm
Spec. cl. No: 2600
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
26.7.B_a Skilled day 9 900 8100.0 Cement tonne 0.4 17500 7000 Concrete Mixer hr 0.75 362 271.5
Unskilled day 8 600 4800.0 Sand cum 0.56 730 408.8
Water KL 0.07 400 28

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 117 of 276

Sub total of A = 12900.0 Sub total of B = 7436.8 Sub total of C = 271.5 Sub total of D = 0.0
Sub total of A +B + C = 20608.3 Sub total of A + B + C + D= 20608.3 Contractor's overhead expenses 15% = 3091.2 Norms Rate = 23699.5
Unit Rate = 237

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 118 of 276

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 3 X 1 X 1 m ( 16 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.i Unskilled day 7 600 4200.0 Mesh wire kg 70.2 114.4 8030.88
Skilled day 3 900 2700.0 Selvedge Wire kg 7.82 101 789.82
Binding Wire kg 3.62 140 506.8
Boulder cum 6.6 3328 21964.8
Sub total of A = 6900.0 Sub total of B = 31292.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 38192.3 Sub total of A + B + C + D= 38192.3 Contractor's overhead expenses 15% = 5728.8 Norms Rate = 43921.1
Unit Rate = 7320.19

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 2 X 1 X 1 m ( 11 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.ii Unskilled day 7 600 4200.0 Mesh wire kg 72.45 114.4 8288.28
Skilled day 3 900 2700.0 Selvedge Wire kg 8.88 101 896.88
Binding Wire kg 3.9 140 546
Boulder cum 6.6 3328 21964.8
Sub total of A = 6900.0 Sub total of B = 31696.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 38596.0 Sub total of A + B + C + D= 38596.0 Contractor's overhead expenses 15% = 5789.4 Norms Rate = 44385.4
Unit Rate = 7397.56

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 1.5 X 1 X 1 m ( 9 sqm ) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.iii Unskilled day 8 600 4800.0 Mesh wire kg 79 114.4 9037.6
Skilled day 3 900 2700.0 Selvedge Wire kg 10.8 101 1090.8
Binding Wire kg 5 140 700
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 32793.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 40293.2 Sub total of A + B + C + D= 40293.2 Contractor's overhead expenses 15% = 6044.0 Norms Rate = 46337.2
Unit Rate = 7722.86

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 1.0 X 1 X 1 m ( 6 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.iv Unskilled day 8 600 4800.0 Mesh wire kg 78.96 114.4 9033.024
Skilled day 3 900 2700.0 Selvedge Wire kg 12.06 101 1218.06
Binding Wire kg 4.56 140 638.4
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 32854.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 40354.3 Sub total of A + B + C + D= 40354.3 Contractor's overhead expenses 15% = 6053.1 Norms Rate = 46407.4
Unit Rate = 7734.57

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 3.0 X 1 X 0 .75 m ( 13.5 sqm) 4.5 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.v Unskilled day 6 600 3600.0 Mesh wire kg 59.24 114.4 6777.056
Skilled day 2 900 1800.0 Selvedge Wire kg 7.18 101 725.18
Binding Wire kg 3.34 140 467.6
Boulder cum 4.95 3328 16473.6
Sub total of A = 5400.0 Sub total of B = 24443.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 29843.4 Sub total of A + B + C + D= 29843.4 Contractor's overhead expenses 15% = 4476.5 Norms Rate = 34320.0
Unit Rate = 7626.66

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 2.0 X 1 X 0 .75 m ( 9. 25 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.vi Unskilled day 8 600 4800.0 Mesh wire kg 81.16 114.4 9284.704
Skilled day 3 900 2700.0 Selvedge Wire kg 10.8 101 1090.8

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 119 of 276

Binding Wire kg 4.72 140 660.8


Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 33001.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 40501.1 Sub total of A + B + C + D= 40501.1 Contractor's overhead expenses 15% = 6075.2 Norms Rate = 46576.3
Unit Rate = 7762.71

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 120 of 276

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 1.0 X 1 X 0 .75 m ( 5 sqm m) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.vi
Unskilled day 8 600 4800.0 Mesh wire kg 87.76 114.4 10039.744
i
Skilled day 3 900 2700.0 Selvedge Wire kg 14.4 101 1454.4
Binding Wire kg 5.92 140 828.8
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 34287.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 41787.7 Sub total of A + B + C + D= 41787.7 Contractor's overhead expenses 15% = 6268.2 Norms Rate = 48055.9
Unit Rate = 8009.32

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 3.0 X 1 X 0 .5 m ( 11 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.vi
Unskilled day 8 600 4800.0 Mesh wire kg 96.6 114.4 11051.04
ii
Skilled day 3 900 2700.0 Selvedge Wire kg 13.12 101 1325.12
Binding Wire kg 4.76 140 666.4
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 35007.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 42507.4 Sub total of A + B + C + D= 42507.4 Contractor's overhead expenses 15% = 6376.1 Norms Rate = 48883.5
Unit Rate = 8147.24

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 2.0 X 1 X 0 .5 m ( 7.5 sqm m) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.ix Unskilled day 9 600 5400.0 Mesh wire kg 98.7 114.4 11291.28
Skilled day 3 900 2700.0 Selvedge Wire kg 14.57 101 1471.57
Binding Wire kg 5.1 140 714
Boulder cum 6.6 3328 21964.8
Sub total of A = 8100.0 Sub total of B = 35441.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 43541.7 Sub total of A + B + C + D= 43541.7 Contractor's overhead expenses 15% = 6531.2 Norms Rate = 50072.9
Unit Rate = 8345.48

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 1 X 1 X 0 .5 m (4 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.x Unskilled day 9 600 5400.0 Mesh wire kg 105.36 114.4 12053.184
Skilled day 4 900 3600.0 Selvedge Wire kg 19.08 101 1927.08
Binding Wire kg 6.24 140 873.6
Boulder cum 6.6 3328 21964.8
Sub total of A = 9000.0 Sub total of B = 36818.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 45818.7 Sub total of A + B + C + D= 45818.7 Contractor's overhead expenses 15% = 6872.8 Norms Rate = 52691.5
Unit Rate = 8781.91

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 3 X 1 X 0 .3 m ( 9 sqm) 6.3 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.xi Unskilled day 10 600 6000.0 Mesh wire kg 138.25 114.4 15815.8
Skilled day 4 900 3600.0 Selvedge Wire kg 21.18 101 2139.18
Binding Wire kg 5.53 140 774.2
Boulder cum 6.93 3328 23063.04
Sub total of A = 9600.0 Sub total of B = 41792.2 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 51392.2 Sub total of A + B + C + D= 51392.2 Contractor's overhead expenses 15% = 7708.8 Norms Rate = 59101.1
Unit Rate = 9381.12

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 2 X 1 X 0 .3 m ( 6.1 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 121 of 276

24.1.A.xi
Unskilled day 9 600 5400.0 Mesh wire kg 134 114.4 15329.6
i
Skilled day 3 900 2700.0 Selvedge Wire kg 22.2 101 2242.2
Binding Wire kg 5.8 140 812
Boulder cum 6.6 3328 21964.8
Sub total of A = 8100.0 Sub total of B = 40348.6 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 48448.6 Sub total of A + B + C + D= 48448.6 Contractor's overhead expenses 15% = 7267.3 Norms Rate = 55715.9
Unit Rate = 9285.98

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 122 of 276

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( 0.1057 kg/m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 100 mm X 120 mm,, Box size 1 X 1 X 0 .3 m ( 2.2 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.A.xi
Unskilled day 9 600 5400.0 Mesh wire kg 96.6 114.4 11051.04
ii
Skilled day 3 900 2700.0 Selvedge Wire kg 28.27 101 2855.27
Binding Wire kg 7.2 140 1008
Boulder cum 6.6 3328 21964.8
Sub total of A = 8100.0 Sub total of B = 36879.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 44979.1 Sub total of A + B + C + D= 44979.1 Contractor's overhead expenses 15% = 6746.9 Norms Rate = 51726.0
Unit Rate = 8621

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 3 X 1 X 1 m ( 16 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.i Unskilled day 8 600 4800.0 Mesh wire kg 82.6 114.4 9449.44
Skilled day 3 900 2700.0 Selvedge Wire kg 7.82 101 789.82
Binding Wire kg 4.12 140 576.8
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 32780.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 40280.9 Sub total of A + B + C + D= 40280.9 Contractor's overhead expenses 15% = 6042.1 Norms Rate = 46323.0
Unit Rate = 7720.5

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 2 X 1 X 1 m ( 11 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.ii Unskilled day 8 600 4800.0 Mesh wire kg 85.2 114.4 9746.88
Skilled day 3 900 2700.0 Selvedge Wire kg 8.87 101 895.87
Binding Wire kg 4.38 140 613.2
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 33220.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 40720.8 Sub total of A + B + C + D= 40720.8 Contractor's overhead expenses 15% = 6108.1 Norms Rate = 46828.9
Unit Rate = 7804.81

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 1.5 X 1 X 1 m ( 9 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.iii Unskilled day 8 600 4800.0 Mesh wire kg 93 114.4 10639.2
Skilled day 3 900 2700.0 Selvedge Wire kg 10.75 101 1085.75
Binding Wire kg 5.68 140 795.2
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 34485.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 41985.0 Sub total of A + B + C + D= 41985.0 Contractor's overhead expenses 15% = 6297.7 Norms Rate = 48282.7
Unit Rate = 8047.12

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 1 X 1 X 1 m (6 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.iv Unskilled day 8 600 4800.0 Mesh wire kg 92.94 114.4 10632.336
Skilled day 3 900 2700.0 Selvedge Wire kg 12.07 101 1219.07
Binding Wire kg 5.22 140 730.8
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 34547.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 42047.0 Sub total of A + B + C + D= 42047.0 Contractor's overhead expenses 15% = 6307.1 Norms Rate = 48354.1
Unit Rate = 8059.01

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 3.0 X 1 X 0 .75 m (13.5 sqm) 4.5 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.v Unskilled day 8 600 4800.0 Mesh wire kg 69.7 114.4 7973.68
Skilled day 3 900 2700.0 Selvedge Wire kg 7.18 101 725.18

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 123 of 276

Binding Wire kg 3.8 140 532


Boulder cum 4.95 3328 16473.6
Sub total of A = 7500.0 Sub total of B = 25704.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 33204.5 Sub total of A + B + C + D= 33204.5 Contractor's overhead expenses 15% = 4980.7 Norms Rate = 38185.1
Unit Rate = 8485.58

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 124 of 276

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 2.0 X 1 X 0 .75 m ( 9.25 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.vi Unskilled day 8 600 4800.0 Mesh wire kg 95.52 114.4 10927.488
Skilled day 3 900 2700.0 Selvedge Wire kg 10.79 101 1089.79
Binding Wire kg 5.4 140 756
Boulder cum 6.6 3328 21964.8
Sub total of A = 7500.0 Sub total of B = 34738.1 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 42238.1 Sub total of A + B + C + D= 42238.1 Contractor's overhead expenses 15% = 6335.7 Norms Rate = 48573.8
Unit Rate = 8095.63

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 1.0 X 1 X 0 .75 m ( 5 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.vi
Unskilled day 9 600 5400.0 Mesh wire kg 103.28 114.4 11815.232
i
Skilled day 3 900 2700.0 Selvedge Wire kg 14.36 101 1450.36
Binding Wire kg 6.4 140 896
Boulder cum 6.6 3328 21964.8
Sub total of A = 8100.0 Sub total of B = 36126.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 44226.4 Sub total of A + B + C + D= 44226.4 Contractor's overhead expenses 15% = 6634.0 Norms Rate = 50860.4
Unit Rate = 8476.73

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 3.0 X 1 X 0 .5 m ( 11 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.vi
Unskilled day 9 600 5400.0 Mesh wire kg 113.6 114.4 12995.84
ii
Skilled day 3 900 2700.0 Selvedge Wire kg 13.11 101 1324.11
Binding Wire kg 5.44 140 761.6
Boulder cum 6.6 3328 21964.8
Sub total of A = 8100.0 Sub total of B = 37046.4 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 45146.4 Sub total of A + B + C + D= 45146.4 Contractor's overhead expenses 15% = 6772.0 Norms Rate = 51918.3
Unit Rate = 8653.05

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 2.0 X 1 X 0 .5 m ( 7.5 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.ix Unskilled day 9 600 5400.0 Mesh wire kg 116.4 114.4 13316.16
Skilled day 3 900 2700.0 Selvedge Wire kg 14.57 101 1471.57
Binding Wire kg 6.18 140 865.2
Boulder cum 6.6 3328 21964.8
Sub total of A = 8100.0 Sub total of B = 37617.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 45717.7 Sub total of A + B + C + D= 45717.7 Contractor's overhead expenses 15% = 6857.7 Norms Rate = 52575.4
Unit Rate = 8762.56

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 1 X 1 X 0 .5 m ( 4 sqm) 1 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.x Unskilled day 10 600 6000.0 Mesh wire kg 123.96 114.4 14181.024
Skilled day 3 900 2700.0 Selvedge Wire kg 19.04 101 1923.04
Binding Wire kg 7.56 140 1058.4
Boulder cum 6.6 3328 21964.8
Sub total of A = 8700.0 Sub total of B = 39127.3 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 47827.3 Sub total of A + B + C + D= 47827.3 Contractor's overhead expenses 15% = 7174.1 Norms Rate = 55001.4
Unit Rate = 55001.35

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 3 X 1 X 0 .3 m ( 9 sqm) 6.3 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 125 of 276

24.1.B.xi Unskilled day 11 600 6600.0 Mesh wire kg 162.75 114.4 18618.6
Skilled day 4 900 3600.0 Selvedge Wire kg 21.18 101 2139.18
Binding Wire kg 6.93 140 970.2
Boulder cum 6.93 3328 23063.04
Sub total of A = 10200.0 Sub total of B = 44791.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 54991.0 Sub total of A + B + C + D= 54991.0 Contractor's overhead expenses 15% = 8248.7 Norms Rate = 63239.7
Unit Rate = 10038.04

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 126 of 276

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 2 X 1 X 0 .3 m ( 6.1 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.xi
Unskilled day 11 600 6600.0 Mesh wire kg 157.5 114.4 18018
i
Skilled day 4 900 3600.0 Selvedge Wire kg 22.2 101 2242.2
Binding Wire kg 7.2 140 1008
Boulder cum 6.6 3328 21964.8
Sub total of A = 10200.0 Sub total of B = 43233.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 53433.0 Sub total of A + B + C + D= 53433.0 Contractor's overhead expenses 15% = 8015.0 Norms Rate = 61448.0
Unit Rate = 10241.33

Description of Work:
Gabion Structure for Retaining Earth, Mesh wire- 10 Swg(0.0615 kg/m), Selvedge Wire 8 Swg ( /m), binding wire 12 Swg (0.0409 kg/m) Hexagonal mesh Type 80 mm X 100 mm,, Box size 1 X 1 X 0 .3 m ( 2.2 sqm) 6 cum
Spec. cl. No: 2401
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.1.B.xi
Unskilled day 11 600 6600.0 Mesh wire kg 113.6 114.4 12995.84
ii
Skilled day 3 900 2700.0 Selvedge Wire kg 28.27 101 2855.27
Binding Wire kg 9 140 1260
Boulder cum 6.6 3328 21964.8
Sub total of A = 9300.0 Sub total of B = 39075.9 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 48375.9 Sub total of A + B + C + D= 48375.9 Contractor's overhead expenses 15% = 7256.4 Norms Rate = 55632.3
Unit Rate = 9272.05

Description of Work: Providing mechanically woven double twisted crates / mattress including rolling, cutting and with lacing wire and binding wire as per specification.
1 sqm
, Hexagonal mesh type 100 mm x 120 mm, mesh wire 3 mm, selvage wire 3.9 mm, lacing wire 2.4 mm
Spec. cl. No: 2402
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Heavy Zinc Coated Hexagonal Mesh 100 * 120 mm, Mesh
24.2.A sqm 1 172.5 172.5
wire 3 mm, Selvage wire 3.9 mm, Lacing wire 2.4 mm
Sub total of A = 0.0 Sub total of B = 172.5 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 172.5 Sub total of A + B + C + D= 172.5 Contractor's overhead expenses 15% = 25.9 Norms Rate = 198.4
Unit Rate = 198.38

Description of Work: Providing mechanically woven double twisted crates / mattress including rolling, cutting and with lacing wire and binding wire as per specification.
1 sqm
, Hexagonal mesh type 100 mm x 120 mm, mesh wire 2.7 mm, selvage wire 3.4 mm, lacing wire 2.2 mm
Spec. cl. No: 2402
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Heavy Zinc Coated Hexagonal Mesh 100 * 120 mm, Mesh
24.2.B sqm 1 230 230
wire 2.7 mm, Selvage wire 3.4 mm, Lacing wire 2.2 mm
Sub total of A = 0.0 Sub total of B = 230.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 230.0 Sub total of A + B + C + D= 230.0 Contractor's overhead expenses 15% = 34.5 Norms Rate = 264.5
Unit Rate = 264.5

Description of Work: Providing mechanically woven double twisted crates / mattress including rolling, cutting and with lacing wire and binding wire as per specification.
1 sqm
, Hexagonal mesh type 80 mm x 100 mm, mesh wire 2.7 mm, selvage wire 3.4 mm, lacing wire 2.2 mm
Spec. cl. No: 2402
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Heavy Zinc Coated Hexagonal Mesh 80 * 100 mm, Mesh wire
24.2.D sqm 1 230 230
2.7 mm, Selvage wire 3.4 mm, Lacing wire 2.2 mm
Sub total of A = 0.0 Sub total of B = 230.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 230.0 Sub total of A + B + C + D= 230.0 Contractor's overhead expenses 15% = 34.5 Norms Rate = 264.5
Unit Rate = 264.5

Description of Work: Providing mechanically woven double twisted crates / mattress including rolling, cutting and with lacing wire and binding wire as per specification.
1 sqm
, Hexagonal mesh type 60 mm x 80 mm, mesh wire 2.7 mm, selvage wire 3.4 mm, lacing wire 2.2 mm
Spec. cl. No: 2402
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Heavy Zinc Coated Hexagonal Mesh50 * 80 mm, Mesh wire
24.2.E sqm 1 0 0
2.7 mm, Selvage wire 3.4 mm, Lacing wire 2.2 mm
Sub total of A = 0.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 0.0 Sub total of A + B + C + D= 0.0 Contractor's overhead expenses 15% = 0.0 Norms Rate = 0.0
Unit Rate = 0

Description of Work: Providing mechanically woven double twisted crates / mattress including rolling, cutting and with lacing wire and binding wire as per specification.
, Zinc + PVC coated Hexagonal mesh type 100 mm x 120 mm, mesh wire 2.7 mm/3.7 mm, selvage wire 3.4 mm/4.4 mm, lacing wire 2.2 mm/3.2 mm with Pac coating thickness nominal 0.5 mm 1 sqm
Spec. cl. No: 2402 ( minimum 0.38 mm)
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No.
Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________
District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 127 of 276
Norms
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Heavy Zinc Coated Hexagonal Mesh 100 * 120 mm, Mesh
24.2.F wire 2.7/3.7 mm, Selvage wire 3.4/4.4 mm, Lacing wire sqm 1 230 230
2.2//3.2 mm with Pac Coating thickness 0.55 mm
Sub total of A = 0.0 Sub total of B = 230.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 230.0 Sub total of A + B + C + D= 230.0 Contractor's overhead expenses 15% = 34.5 Norms Rate = 264.5
Unit Rate = 264.5

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 128 of 276

Description of Work: Providing mechanically woven double twisted crates / mattress including rolling, cutting and with lacing wire and binding wire as per specification.
, Zinc + PVC coated Hexagonal mesh type 80 mm x 100 mm, mesh wire 2.2 mm/3.2 mm, selvage wire 2.7 mm/3.7 mm, lacing wire 2.2 mm/3.2 mm with Pac coating thickness nominal 0.5 mm 1 sqm
Spec. cl. No: 2402 ( minimum 0.38 mm)
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Heavy Zinc Coated Hexagonal Mesh 100 * 120 mm, Mesh
24.2.G wire 2.7/3.7 mm, Selvage wire 3.4/4.4 mm, Lacing wire sqm 1 230 230
2.2//3.2 mm with Pac Coating thickness 0.55 mm
Sub total of A = 0.0 Sub total of B = 230.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 230.0 Sub total of A + B + C + D= 230.0 Contractor's overhead expenses 15% = 34.5 Norms Rate = 264.5
Unit Rate = 264.5

Description of Work: Assembling mechanical woven Gabion boxes /mattresses, placing in position including stretching; forming compartments; tying the sides and diaphragms with binding wire in each mesh; tying with bracing wires and tie wires; and tying down the lid complete as per
160 sqm
specification (stone filling not included
Spec. cl. No: 2402
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.3 Skilled day 2 900 1800.0
Unskilled day 10 600 6000.0
Sub total of A = 7800.0 Sub total of B = 0.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 7800.0 Sub total of A + B + C + D= 7800.0 Contractor's overhead expenses 15% = 1170.0 Norms Rate = 8970.0
Unit Rate = 56.06

Description of Work:
Providing and filling stone/boulder in gabion boxes/mattress etc.. Including dressing, bedding, bonding all complete as per Drawing and Technical Specifications. 10 cum
Spec. cl. No: 2402
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.4 Skilled day 2 900 1800.0 Boulder cum 11 3328 36608
Unskilled day 8 600 4800.0
Sub total of A = 6600.0 Sub total of B = 36608.0 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 43208.0 Sub total of A + B + C + D= 43208.0 Contractor's overhead expenses 15% = 6481.2 Norms Rate = 49689.2
Unit Rate = 4968.92

Description of Work:
Laying and fixing of Geo-Textile all complete as per specification., Providing and laying of a geotextile filter between pitching and embankment slopes as per Drawing and Technical Specifications. 300 sqm
Spec. cl. No: 2404
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.5 Skilled day 1 900 900.0 Geotextile sqm 360 #VALUE! #VALUE!
Unskilled day 2 600 1200.0
Sub total of A = 2100.0 Sub total of B = #VALUE! Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = #VALUE! Sub total of A + B + C + D= #VALUE! Contractor's overhead expenses 15% = #VALUE! Norms Rate = #VALUE!
Unit Rate = #VALUE!

Description of Work:
Laying and fixing of Geo-Textile all complete as per specification., Providing and laying and fixing of Geo-membrane all complete as per specification. 300 sqm
Spec. cl. No: 2404
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.06 Skilled day 1 900 900.0 Geotextile sqm 360 #VALUE! #VALUE!
Unskilled day 2 600 1200.0
Sub total of A = 2100.0 Sub total of B = #VALUE! Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = #VALUE! Sub total of A + B + C + D= #VALUE! Contractor's overhead expenses 15% = #VALUE! Norms Rate = #VALUE!
Unit Rate = #VALUE!

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 129 of 276

Description of Work: GEOSYNTHETIC AND REINFORCED EARTH, Sub-Surface Drain with Geotextiles, Providing and laying sub surface drain 200 mm dia using geotextiles treated with carbon black to a stable network and a planar geo-composite structure, joints wrapped with
10 meter
geotextile to prevent ingress of soil, including excavation and backfilling as per Drawing and Technical Specifications.
Spec. cl. No: 2404
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Geonets, geomembrane and geotextile to make planar


24.7 Skilled day 2 900 1800.0 geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .

Unskilled day 10 600 6000.0 Geonets sqm 11 #VALUE! #VALUE!


Geomembrane sqm 11 #VALUE! #VALUE!
Geotextile sqm 22 #VALUE! #VALUE!
Add 2 per cent cost of Material for miscellaneous items like
#VALUE!
synthetic cord
Sub total of A = 7800.0 Sub total of B = #VALUE! Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = #VALUE! Sub total of A + B + C + D= #VALUE! Contractor's overhead expenses 15% = #VALUE! Norms Rate = #VALUE!
Unit Rate = #VALUE!

Description of Work: Narrow Filter Sub-Surface Drain, Providing and making narrow filter sub- surface drain consisting of porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed including
10 meter
excavation and backfilling
Spec. cl. No: 2404
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.8 Skilled day 2 900 1800.0 Perforated Geosynthetic pipe 150 mm dia. meter 11 866.5287 9531.8157
Unskilled day 10 600 6000.0 Geotextile Filter Fabric sqm 12.5 #VALUE! #VALUE!
Add 2 per cent cost of Material for miscellaneous item like
#VALUE!
synthetic cord
Sub total of A = 7800.0 Sub total of B = #VALUE! Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = #VALUE! Sub total of A + B + C + D= #VALUE! Contractor's overhead expenses 15% = #VALUE! Norms Rate = #VALUE!
Unit Rate = #VALUE!

Description of Work: Laying Paving Fabric Beneath a Pavement Overlay, Providing and laying paving fabric over a tack coat of paving grade Bitumen, laid at the rate of 1 kg per sqm over thoroughly cleaned and repaired surface to provide a water resistant membrane and crack retarding
2800 sqm
layer as per Drawing and Technical Specifications.
Spec. cl. No: 2410
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.9 Skilled day 1 900 900.0 Paving Fabric sqm 2940 0 0 Road Sweeper hour 6 0 0.0
Unskilled day 30 600 18000.0 Paving Bitumen tonne 2.8 77600 217280 Pneumatic Roller hour 6 3319 19914.0
Bitumen Distributor hour 6 4377 26262.0
Sub total of A = 18900.0 Sub total of B = 217280.0 Sub total of C = 46176.0 Sub total of D = 0.0
Sub total of A +B + C = 282356.0 Sub total of A + B + C + D= 282356.0 Contractor's overhead expenses 15% = 42353.4 Norms Rate = 324709.4
Unit Rate = 115.97

Description of Work:
Laying Boulder Apron in Crates of Synthetic Geogrids, Providing and laying of Geogrids crated apron 1 m x 5 m, 600 mm thick with baffles at 1 meter interval, made with Geogrids as per Design, Drawing and Technical specifications. design. 3 cum
Spec. cl. No: 2400
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.10' Skilled day 1 900 900.0 Geogrids sqm 21 #VALUE! #VALUE!
Unskilled day 2 600 1200.0 Connectors / Staples nos. 50 0 0
Polymer Braids meter 20 0 0
Stones with minimum size of 200 mm cum 3.45 3328 11481.6
Stones spall for filling voids cum 0.45 1588.5 714.825
Sub total of A = 2100.0 Sub total of B = #VALUE! Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = #VALUE! Sub total of A + B + C + D= #VALUE! Contractor's overhead expenses 15% = #VALUE! Norms Rate = #VALUE!
Unit Rate = #VALUE!

Description of Work:
Providing and laying HDPE pipes with perforations including joining, series II, HDPE pipe 200 mm dia 100 meter
Spec. cl. No: 2414
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.20.A Semiskilled day 2 880 1760.0 HDPE pipe 200 mm dia. meter 110 1759.34 193527.73 Generator hour 24 1289 30936.0
Skilled day 3 900 2700.0 Screw Jack hour 18 14 252.0
Unskilled day 10 600 6000.0 Electric Heating Plate hour 18 25 450.0
Electric Hand Driller hour 12 20 240.0
Sub total of A = 10460.0 Sub total of B = 193527.7 Sub total of C = 31878.0 Sub total of D = 0.0
Sub total of A +B + C = 235865.7 Sub total of A + B + C + D= 235865.7 Contractor's overhead expenses 15% = 0.0 Norms Rate = 235865.7
Unit Rate = 2358.66

Description of Work:
Providing and laying HDPE pipes with perforations including joining, series II, HDPE pipe 160 mm dia 100 M
Spec. cl. No: 2414
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 130 of 276

24.20.B Semiskilled day 2 880 1760.0 HDPE pipe 160 mm dia. meter 110 1126.9951 123969.461 Generator hour 0 1289 0.0
Skilled day 3 900 2700.0 Screw Jack hour 18 14 252.0
Unskilled day 10 600 6000.0 Electric Heating Plate hour 0 25 0.0
Electric Hand Driller hour 12 20 240.0
Sub total of A = 10460.0 Sub total of B = 123969.5 Sub total of C = 492.0 Sub total of D = 0.0
Sub total of A +B + C = 134921.5 Sub total of A + B + C + D= 134921.5 Contractor's overhead expenses 15% = Norms Rate = 134921.5
Unit Rate = 1349.21

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 131 of 276

Description of Work:
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and Specifications, 60% M 15 concrete and 40% boulders/stones, using Mechanical Aids 10 cum
Spec. cl. No: 2421
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.21.A.
Skilled day 3 900 2700.0 Cement tonne 1.7 17500 29750 Concrete Mixer hour 6 362 2172.0
I
Unskilled day 30 600 18000.0 Aggregates Concrete Vibrator hour 6 0 0.0
Aggregate 20-40 mm cum 3.45 1700 5865
Aggregate 10-20 mm cum 1.56 1725 2691
Aggregate 10 mm cum 0.72 1800 1296
Sand cum 3 730 2190
Boulder cum 4.4 3328 14643.2
Sub total of A = 20700.0 Sub total of B = 56435.2 Sub total of C = 2172.0 Sub total of D = 0.0
Sub total of A +B + C = 79307.2 Sub total of A + B + C + D= 79307.2 Contractor's overhead expenses 15% = 11896.1 Norms Rate = 91203.3
Unit Rate = 9120.33

Description of Work:
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and Specifications, 60% M 15 concrete and 40% boulders/stones, Manual means 1 cum
Spec. cl. No: 2421
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.21.A.
Skilled day 1 900 900.0 Cement tonne 0.185 17500 3237.5
II
Unskilled day 4 600 2400.0 Aggregates
Aggregate 20-40 mm cum 0.156 1700 265.2
Aggregate 10-20 mm cum 0.072 1725 124.2
Aggregate 10 mm cum 0.299 1800 538.2
Sand cum 0.299 730 218.27
Boulder cum 0.44 3328 1464.32
Sub total of A = 3300.0 Sub total of B = 5847.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 9147.7 Sub total of A + B + C + D= 9147.7 Contractor's overhead expenses 15% = 1372.2 Norms Rate = 10519.8
Unit Rate = 10519.84

Description of Work:
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and Specifications, 70% M 15 concrete and 30% boulders/stones, Using Mechanical Aids 10 cum
Spec. cl. No: 2421
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.21.B.I Skilled day 4 900 3600.0 Cement tonne 1.95 17500 34125 Concrete Mixer hour 6 362 2172.0
Unskilled day 30 600 18000.0 Aggregates Concrete Vibrator hour 6 0 0.0
Aggregate 20-40 mm cum 4 1700 6800
Aggregate 10-20 mm cum 1.8 1725 3105
Aggregate 10 mm cum 0.8 1800 1440
Sand cum 3.45 730 2518.5
Boulder cum 3.3 3328 10982.4
Sub total of A = 21600.0 Sub total of B = 58970.9 Sub total of C = 2172.0 Sub total of D = 0.0
Sub total of A +B + C = 82742.9 Sub total of A + B + C + D= 82742.9 Contractor's overhead expenses 15% = 12411.4 Norms Rate = 95154.3
Unit Rate = 9515.43

Description of Work:
Providing and laying Plum concrete ( Boulder mixed concrete) as per Drawing and Specifications, 70% M 15 concrete and 30% boulders/stones, Manual means 10 cum
Spec. cl. No: 2421
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.21.B.I
Skilled day 1 900 900.0 Cement tonne 0.214 17500 3745
I
Unskilled day 4 600 2400.0 Aggregates
Aggregate 20-40 mm cum 0.398 1700 676.6
Aggregate 10-20 mm cum 0.18 1725 310.5
Aggregate 10 mm cum 0.082 1800 147.6
Sand cum 0.345 730 251.85
Boulder cum 0.33 3328 1098.24
Sub total of A = 3300.0 Sub total of B = 6229.8 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 9529.8 Sub total of A + B + C + D= 9529.8 Contractor's overhead expenses 15% = 1429.5 Norms Rate = 10959.3
Unit Rate = 1095.93

Description of Work: Sub-Surface Drains with Perforated Pipe, Providing and laying subsurface drain with perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon size of
10 meter
material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the pipe,. as per Drawing and Specifications.
Spec. cl. No: 2414
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.22 Skilled day 1 900 900.0 Perforated Pipe of Cement Concrete, internal 100 mm dia. meter 11 1254 13794
Unskilled day 3 600 1800.0 Crushed Stone Aggregate cum 2.4 #NAME? #NAME?

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 132 of 276

Sub total of A = 2700.0 Sub total of B = #NAME? Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = #NAME? Sub total of A + B + C + D= #NAME? Contractor's overhead expenses 15% = #NAME? Norms Rate = #NAME?
Unit Rate = #NAME?

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


District: MORANG SUNSARI ROAD RATE ANALYSIS Fiscal Year: 2077/78 Page 133 of 276

Description of Work:
Aggregate Sub-Surface Drains, Providing and laying aggregate sub surface drain 300 mm x 450 mm with aggregates conforming to table 300-4, excavated material to be utilized in roadway. 10 meter
Spec. cl. No: 2414
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.23 Skilled day 1 900 900.0 Crushed Stone Aggregate cum 1.35 #NAME? #NAME?
Unskilled day 3 600 1800.0
Sub total of A = 2700.0 Sub total of B = #NAME? Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = #NAME? Sub total of A + B + C + D= #NAME? Contractor's overhead expenses 15% = #NAME? Norms Rate = #NAME?
Unit Rate = #NAME?

Description of Work:
Underground Drain at Edge of Pavement, Providing and laying an underground drain 1 m x 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab 10 cm in thickness on urban roads. 1 meter
Spec. cl. No: 2414
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
24.24 Earthwork in soil cum 1.5 67 100.5
RCC work M-20 cum 0.495 10093.4 4996.2
Reinforcement work @ 3 % of concrete volume tonne 0.117 90000 10530
Sub total of A = 0.0 Sub total of B = 15626.7 Sub total of C = 0.0 Sub total of D = 0.0
Sub total of A +B + C = 15626.7 Sub total of A + B + C + D= 15626.7 Contractor's overhead expenses 15% = 2344.0 Norms Rate = 17970.7
Unit Rate = 17970.74

Prepared By:________________ Checked By:________________ Recommended By:________________ Approved By:________________


Collection of Materials Page 1 of 276
Section 800: Collection

Collectio
S.N. Description Unit Washing Amount Remarks Washing
n
Gravel
a 5 mm - 70 mm cum 1236 0 1236.0 Without Washing
b 40 mm cum 1854 0 1854.0 Without Washing
c 20 mm cum 2472 0 2472.0 Without Washing
d 8 mm cum 3708 0 3708.0 Without Washing
e 40 mm - 70 mm cum 2472 0 2472.0 Without Washing
f 70 mm - 100 mm cum 1854 0 1854.0 Without Washing
Sand
a Quarry output less than 33% cum 2472 0 2472.0 Without Washing
b Quarry output 33 - 66% cum 1854 0 1854.0 Without Washing
c Quarry output more than 66% cum 927 0 927.0 Without Washing
Collection, quarrying and sieving
d cum 927 0 927.0 Without Washing
sand in local river
3 Rubble cum 865.2 0 865.2 Without Washing
4 Aggregate cum 865.2 0 865.2 Without Washing
a 70 mm - 100 mm cum 865.2 0 865.2 Without Washing
b 40 mm - 70 mm cum 865.2 0 865.2 Without Washing
c 20 mm - 40 mm cum 865.2 0 865.2 Without Washing
d 10 mm - 20 mm cum 865.2 0 865.2 Without Washing
e 10 mm cum 865.2 0 865.2 Without Washing
Mechanical
a 13.2 mm cum 1341.766 0 1341.8 Without Washing
b 20 mm cum 1204.164 0 1204.2 Without Washing
c 40 mm cum 1071.595 0 1071.6 Without Washing

Collection
Unskille
S.N. Description Unit Rate Amount
d

Gravel
a 5 mm - 70 mm cum 2.060 600 1236.0
b 40 mm cum 3.090 600 1854.0
c 20 mm cum 4.120 600 2472.0
d 8 mm cum 6.180 600 3708.0
e 40 mm - 70 mm cum 4.120 600 2472.0
f 70 mm - 100 mm cum 3.090 600 1854.0
Sand
a Quarry output less than 33% cum 4.120 600 2472.0
b Quarry output 33 - 66% cum 3.090 600 1854.0
c Quarry output more than 66% cum 1.545 600 927.0
Collection, quarrying and sieving
d cum 1.545 600 927.0
sand in local river

3 Rubble cum 1.442 600 865.2


4 Aggregate cum 1.442 600 865.2

Washing
Unskille
S.N. Description Unit Rate Amount
d
1 Gravel cum 0.515 600 309.000
2 Sand cum 0.515 600 309.000
3 Rubble cum 0.206 600 123.600
4 Aggregate cum 0.210 600 126.000

Manually Breaking Stones (excluding Collection of Rubble)


Unskille
S.N. Description Unit Total
d
Aggregate
a 70 mm - 100 mm cum 1.545 927.000
b 40 mm - 70 mm cum 2.060 1236.000
c 20 mm - 40 mm cum 3.090 1854.000
d 10 mm - 20 mm cum 4.120 2472.000
e 10 mm cum 6.180 3708.000
Mechanical
f 13.2 mm cum 1.545 927.000
g 20 mm cum 2.060 1236.000

Prepared By:________________ Checked By:________________ Approved By:________________


Collection of Materials Page 2 of 276

Making rubbles of required size including and stacking.(Without Blasting)


Unskille
S.N. Description Unit Skilled Total
d
1 Rubbles cum 4.120 0.103 2564.7

Making rubbles of required size including and stacking.(Blasting)


Unskille
S.N. Description Unit Skilled Gelatin Detonator Fuse Wire Total
d
1 Rubbles cum 2.575 0.103 0.250 2.000 2.000 1637.7

Mechanically Crushing of Stone Aggregates


Stone Boulder
Unskille Stone Crusher
S.N. Description Unit Skilled of size 150mm Loader Tipper Total
d with Screen
and below
Aggregate
a 13.2 mm cum 0.030 0.003 1.3 0.020 0.030 0.030 1341.8
b 20 mm cum 0.027 0.003 1.2 0.018 0.027 0.027 1204.2
c 40 mm cum 0.023 0.003 1.1 0.008 0.027 0.027 1071.6

Prepared By:________________ Checked By:________________ Approved By:________________


Description of Work: Construction of Embankment with Material obtained from Borrow pits, Providing, laying, spreading and compacting embankment with borrow material(Grannular material ) as per Drawing and
300 cum
Spec. cl. No: Technical Specifications.
909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Hydraulic
9.8 Skilled day 1 900 900.0 Water KL 72 400 28800 hour 6 3570 21420.0
Excavator

Unskille River Bed Gravel Tractor with


day 4 600 2400.0 cum 360 1150 414000 hour 12 1133 13596.0
d material Rotavator

Dozer hour 3 5891 17673.0


Mortar
hour 3 3618 10854.0
Grader
Water
hour 6 1806 10836.0
Tanker

Vibratory
hour 6 1806 10836.0
Road Roller

Sub total of A = 3300.0 Sub total of B = 442800.0 Sub total of C = 85215.0 Sub total of D = 0.0
Sub total of A +B + C = 531315.0 Sub total of A + B + C + D= 531315.0 Contractor's overhead expenses 15% = 79697.3 Norms Rate = 611012.3
Unit Rate = 2036.71

Description of Work: Construction of Embankment with Material obtained from Borrow pits, Providing, laying, spreading and compacting embankment with borrow material as per Drawing and Technical
300 cum
Spec. cl. No: Specifications.
909910
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Hydraulic
9.8 Skilled day 1 900 900.0 Water KL 72 400 28800 hour 6 3570 21420.0
Excavator

Unskille Borrowpit Tractor with


day 4 600 2400.0 cum 360 400 144000 hour 12 1133 13596.0
d Material Rotavator

Dozer hour 3 5891 17673.0


Mortar
hour 3 3618 10854.0
Grader
Water
hour 6 1806 10836.0
Tanker

Vibratory
hour 6 1806 10836.0
Road Roller

Sub total of A = 3300.0 Sub total of B = 172800.0 Sub total of C = 85215.0 Sub total of D = 0.0
Sub total of A +B + C = 261315.0 Sub total of A + B + C + D= 261315.0 Contractor's overhead expenses 15% = 39197.3 Norms Rate = 300512.3
Unit Rate = 1001.71

Description of Work: Providing and laying granular sub-base on prepared surface, mixing at OMC, and compacting to achieve the desired density, complete as per Drawing and Technical Specifications., By
300 cum
Mechanical means
Spec. cl. No:
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Sub-base Material Mortar


12.1.A Skilled day 2 900 1800.0 cum 384 1150 441600 hour 6 3618 21708.0
S1 type or S2 type Grader

Unskille Vibratory
day 12 600 7200.0 Water KL 18 400 7200 hour 12 2413 28956.0
d Road Roller
Tractor /
hour 12 1110 13320.0
Loader
Sub total of A = 9000.0 Sub total of B = 448800.0 Sub total of C = 63984.0 Sub total of D = 0.0
Sub total of A +B + C = 521784.0 Sub total of A + B + C + D= 521784.0 Contractor's overhead expenses 15% = 78267.6 Norms Rate = 600051.6
Unit Rate = 2000.17

Description of Work: Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 600 mm
12.5 meter
internal dia.
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of
Labour cost
for bellies,
7.3.C Skilled day 1 900 900.0 Sand cum 0.1 730 73 crow bars, 153.0
chain pulley
and other
T&P
Unskille
day 7 600 4200.0 Cement tonne 0.08 17500 1400
d
NP3 RCC Pipe
meter 12.5 6010.4 75130
600 mm dia
NP3 RCC Collar
nos. 4 0 0
600 mm dia
Sub total of A = 5100.0 Sub total of B = 76603.0 Sub total of C = 153.0 Sub total of D = 0.0
Sub total of A +B + C = 81856.0 Sub total of A + B + C + D= 81856.0 Contractor's overhead expenses 15% = 12278.4 Norms Rate = 94134.4
Unit Rate = 7530.75

Description of Work: Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 450 mm
12.5 meter
internal dia.
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of
Labour cost
for bellies,
7.3.B Skilled day 1 900 900.0 Sand cum 0.09 730 65.7 crow bars, 135.0
chain pulley
and other
T&P
Unskille
day 6 600 3600.0 Cement tonne 0.07 17500 1225
d
NP3 RCC Pipe
meter 12.5 4558.4 56980
450 mm dia
NP3 RCC Collar
nos. 4 0 0
450 mm dia
Sub total of A = 4500.0 Sub total of B = 58270.7 Sub total of C = 135.0 Sub total of D = 0.0
Sub total of A +B + C = 62905.7 Sub total of A + B + C + D= 62905.7 Contractor's overhead expenses 15% = 9435.9 Norms Rate = 72341.6
Unit Rate = 5787.32

Description of Work: Providing and Laying Reinforced cement concrete NP3 Collar jointed pipe for culverts including fixing collar with cement mortar 1:2 as per Drawing and Technical Specifications., 900 mm
12.5 meter
internal dia.
Spec. cl. No: 701
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount
Add 3 % of
Labour cost
for bellies,
7.3.D Skilled day 1 900 900.0 Sand cum 0.12 730 87.6 crow bars, 171.0
chain pulley
and other
T&P
Unskille
day 8 600 4800.0 Cement tonne 0.09 17500 1575
d
NP3 RCC Pipe
meter 12.5 10780 134750
900 mm dia
NP3 RCC Collar
nos. 4 0 0
900 mm dia
Sub total of A = 5700.0 Sub total of B = 136412.6 Sub total of C = 171.0 Sub total of D = 0.0
Sub total of A +B + C = 142283.6 Sub total of A + B + C + D= 142283.6 Contractor's overhead expenses 15% = 21342.5 Norms Rate = 163626.1
Unit Rate = 13090.09

Description of Work: Providing suitable material and Back filling behind abutment, wing wall and return wall complete as per Drawing and Technical Specifications., Locally available Material including compaction by
10 cum
tamping rod ( without watering)
Spec. cl. No: 908
Norms Labour (A) Material (B) Equipment (C) Formworks (D)
No. Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount Type Unit Quantity Rate Amount

Compensation for
9.11.C Skilled day 0.2 900 180.0 Locally available cum 12 0 0 Tamping 95.4
Material

Unskille
day 5 600 3000.0 Water KL 1 400 400
d
Sub total of A = 3180.0 Sub total of B = 400.0 Sub total of C = 95.4 Sub total of D = 0.0
Sub total of A +B + C = 3675.4 Sub total of A + B + C + D= 3675.4 Contractor's overhead expenses 15% = 551.3 Norms Rate = 4226.7
Unit Rate = 422.67
Price List of HDPE Pipe

F.Y. : 075/76

Series III
Pipe size Series II 2.5Kg/sqcm Series IV 6Kg/sqcm Series V 10Kg/sqcm
4Kg/sqcm
(Outer
S.No.
side Ø
mm)
Ave.Wt. Ave.Wt. Ave.Wt. Ave.Wt.
Price Rs./m Price Rs./m Price Rs./m
kg/m kg/m kg/m kg/m

1 16mm – – – – – – 0.092
2 20mm – – – – – – 0.134
3 25mm – – – – – – 0.202
4 32mm – – – – 0.226 67.51 0.334
5 40mm – – 0.251 74.97 0.350 104.55 0.514
6 50mm – – 0.378 112.91 0.542 161.90 0.796
7 63mm 0.403 120.38 0.585 174.74 0.850 253.90 1.269
8 75mm 0.557 166.38 0.846 252.70 1.191 355.75 1.782
9 90mm 0.799 238.66 1.220 364.41 1.715 512.27 2.568
10 110mm 1.185 353.96 1.703 508.69 2.545 760.19 3.801
11 125mm 1.530 457.01 2.289 683.72 3.293 983.62 4.962
12 140mm 1.897 566.63 2.901 866.53 4.150 1239.61 6.209
13 160mm 2.453 732.71 3.773 1127.00 5.355 1599.54 8.079
14 180mm 3.148 940.31 4.762 1422.41 6.800 2031.16 10.256
15 200mm 3.876 1157.76 5.890 1759.34 8.391 2506.39 12.620
16 225mm 4.822 1440.33 7.445 2223.82 10.544 3149.49 16.014
17 250mm 6.012 1795.78 9.187 2744.16 13.041 3895.35 19.757
18 280mm 7.417 2215.46 11.455 3421.61 16.327 4876.87 24.708
19 315mm 9.417 2812.86 14.508 4333.54 20.694 6181.30 31.160
20 355mm 11.957 3571.56 18.382 5490.70 26.243 7838.78 39.635
21 400mm 15.221 4546.51 23.343 6972.55 33.309 9949.40 50.344

Notes :
1 Prices are based on ex–factory.
2 The above value include all GOV. Taxes except VAT which will be charged extra 13 %
3 All pipes are manufactured as NS–40
4 Rate of HDPE Pipes Based on Rs. 290.00 Per Kg.
5 Add 3% Transportation Charge.
Series V 10Kg/sqcm Pipe size
(Outer
side Ø
mm)
Contractor
Price Rs./m price per
Rate
kg trans 3%
27.48 31.60 290 8.7 298.7
40.03 46.03 1/2" 290 8.7 298.7
60.34 69.39 3/4" 290 8.7 298.7
99.77 114.73 1" 290 8.7 298.7
153.53 176.56 1-1/4" 290 8.7 298.7
237.77 273.43 1-1/2" 290 8.7 298.7
379.05 435.91 2" 290 8.7 298.7
532.28 612.13 2-1/2" 290 8.7 298.7
767.06 882.12 3" 290 8.7 298.7
1135.36 1305.66 4" 290 8.7 298.7
1482.15 1704.47 4-1/2" 290 8.7 298.7
1854.63 2132.82 5" 290 8.7 298.7
2413.20 2775.18 6" 290 8.7 298.7
3063.47 3522.99 7" 290 8.7 298.7
3769.59 4335.03 8" 290 8.7 298.7
4783.38 5500.89 9" 290 8.7 298.7
5901.42 6786.63 10" 290 8.7 298.7
7380.28 8487.32 11" 290 8.7 298.7
9307.49 10703.62 12" 290 8.7 298.7
11838.97 13614.82 355mm 290 8.7 298.7
15037.75 17293.42 400mm 290 8.7 298.7

ed extra 13 %
References Page 1 of 276
References

Densities of some materials:


S.N. Name Density Remarks
Excavated earth work
Soil Material 1400 kg/m3
Rock Material 2400 kg/m3
Sand 1600 kg/m3
Gravel, river shingle, broken stone aggregates, and bats.
Gravel 1800 kg/m3
River shingle (round aggregate) 1800 kg/m3
Broken stone aggregates 2400 kg/m3
Surface Dressing Chips 2400 kg/m3
Brick bats 1420 kg/m3
Boulder, Cobbles, quarry stone 2400 kg/m3
Dressed Stone 2400 kg/m3
wt.of 1 brick
Bricks 1900 kg/m3 (240*115*57
mm3)=2.98 Kg
Cement 1440 kg/m3
Reinforcement Steel 7850 kg/m3
Gabion wire 7850 kg/m3
Bitumen 1010 kg/m3
GI, CI, Pipe and fittings 7850 kg/m3
Timber for temporary works 350 kg/m3
Fabricated Structural Timber 850 kg/m3
Fabricated Structural Steel 7850 kg/m3
RCC Precast Element 2500 kg/m3
RCC hume pipe
900mm dia wt./m= 785 kg
750 mm dia wt./m= 667.25 kg
600mm dia wt./m= 549.5 kg
450 mm dia wt./m= 431.75 kg
300 mm dia wt./m= 314 kg
Water 1000 kg/m3
Petrol 720 kg/m3 0.770 Kg/l
Diesel 720 kg/m3 0.770 Kg/l
Kerosene 720 kg/m3 0.770 Kg/l
Thermoplastic Paint 2100 kg/m3

You might also like