Professional Documents
Culture Documents
i
CERTIFICATE
This is to certify that the dissertation work titled “Comparative Analysis of Post
Flood Shelter Typologies” is a bona fide work of Raina Mariam Nibu, under my
guidance, submitted as Semester VII & VIII subject for the award of “Degree of
Bachelor in Architecture” during the term of 2018 to 2019 through Mahatma
Gandhi University, Kottayam.
Place:
Date:
ii
Keywords
iii
Abstract
iv
Table of content
1. INTRODUCTION………….……………………………………………………………………………………….……………..1
2. LITERATURE REVIEW………………..……………………………………………………………………………………….…3
3. METHODOLOGY………………………………………………………………………………………………………….……….9
4 RESULTS…………..……………………………………………………………………………………………………………..…..11
5 DISCUSSION…………………..……………………………………………………………………………………………………26
6 CONCLUSION……….……………………..………………………………………………………………………………….….27
7 REFERENCE………….…………………………………………………………………………………………………….……...27
v
List of Figures
vi
List of Tables
Table 2-1 factors that needs to be balanced for a successful post disaster shelter ............................. 6
Table 4-1 Analysis of the post flood shelter by Habitat Technology Group ...................................... 24
Table 4-2 Analysis of the post flood shelter by Urvi foundation ....................................................... 25
Table 5-1 Comparative analysis of both post flood shelter prototypes…………………………………………….35
vii
Acknowledgements
I would first like to acknowledge my guide and mentor, Ar. Swetha Vishwanath
and Ar. Jayadevi Venugopal (Assistant professor-KMEA College of Architecture),
who helped with their guidance, suggestions, advice, remarks, and reprimands,
who helped me to make the dissertation possible. My gratitude extends to
friends, colleagues and architects for their support, help and healthy criticism.
viii
1. Introduction
Kerala is highly vulnerable to natural disaster and varying climatic conditions given its
location along the sea coast and with a steep gradient along the slopes of western ghats.
Floods are most common of natural hazard in the state. About 14.5% of land area is prone
to flood. Landslides are a major hazard along the Western Ghats in Wayanad, Idukki,
Kozhikode and kottayam districts.
Between 1 June and 18 August, 2018, Kerala experienced the worst flood since 1924. About
42% of excess rainfall is received during that period triggering several landslides and forced
the release of excess water from 37 dams across the state, aggravating the flood impact.
Approximately 22,000 houses (NDMA estimates) were destroyed or damaged during that
period. This study is intended to understand different typologies of post flood shelters build
after the disaster. The major concern in taking up this topic is to understand the pros and
cons of each typology and to arrive at a conclusion of better design in case of construction
time, cost, materials used and liveability.
1
1.2 Central Research Question
What are the different typologies of post flood shelters in Kerala ( using different materials )
and compare their efficiency.
1.2.1 Sub Research Question
• What are the different post flood shelters constructed in global scenarios?
• What are the typologies constructed in Kerala?
• What is the method of construction used, construction cost, construction time and
materials used for construction?
1.3 Aim
To understand and compare between the different typologies of post flood shelters
in Kerala.
1.3.1 Objectives
• General idea of post flood shelter construction in global scenarios
• Different typologies of post flood shelters constructed in Kerala
• Method of construction used, construction cost, construction time and materials
used for construction
• The factors that contribute to an optimum solution
There are a lot of prototypes proposed and created by private firms. All the prototypes cannot
be analyzed. So an example of conventional and unconventional building material prototype
is chosen for the study.
2
2 LITERATURE REVIEW
3
are limited usually few weeks. They can be rented houses or prefabricated houses according
to the situation.
Temporary housing – these type are often allocated for longer time periods such as six
months or three years. They can either be rented houses or prefabricated houses provided
by government or NGOs. These shelters help people to return to their normal daily
activities.
Transitional shelters– these are rapid post disaster shelters that are made of materials that
can be upgraded or re-used in future permanent shelters. Or they can be reallocated to
permanent site from temporary site. They are designed to undergo transition. Such shelters
last from many months to years.
Progressive shelters– these are post disaster shelters designed and constructed so as to
upgrade later on to a permanent status. It can be achieved by integrating future
transformations by altering the basic unit of a structural component. (Societies, 2013)
Core shelters/one-room shelters– these are shelters designed with the intent to be
permanent housing in the future which includes foundation and other services like
plumbing. They allow and facilitate future process of extension by their own means and
resources. The major aim is to create one or two rooms that reaches the permanent housing
standards and facilitate development. (Societies, 2013)
Permanent housing – these are upgraded from transitional shelter or core shelter or even a
new house. Such houses should be resistant to future disasters and hazards. (socities, 2013)
(Quarantelli, 1991).
These phases approach has pros and cons, and not always constitutes a linear process. For
example, in the
emergency phase, the costs of tents are not only related to the price of fabric and poles, but
the transportation costs to get to devastated places, which sometimes increases the prices
of tents by three to four times. In addition, the life span of a tent depending on the climate
conditions, it is usually shorter than one year. On the other hand, the permanent phase,
generally takes place some years after the event.
Moreover, temporary solutions are commonly used longer than expected, and eventually
become part of the permanent housing. (Societies, 2013)
The factors that should be taken into account while designing a shelter:
Appropriateness
Developing a shelter design brief
Relocation, re-use and maintenance
Hazards, risks and safety
Timeliness and construction speed
Life span
Size and shape
Privacy, security and cultural appropriateness
Ventilation and thermal comfort
Environment
Land, sites and services
5
Cost and budgets (Abulnour, 2013) (Societies, 2013)
Some of the factors that needs to be balanced for a successful post disaster shelter
Safety Cost
Lifespan Timeliness
Privacy Number to be built
Comfort Materials availability
Size Maintenance and upgrade
Donor expectations Construction skills
Table 2-1 factors that needs to be balanced for a successful post disaster shelter
For the construction of post flood shelters different materials and construction techniques
can be used. Generally people tend to go for conventional materials as they are familiar to
them but they might not be feasible in all the cases. So there is a dilemma between
choosing of materials. Through this research I intend to analyse the advantages and
disadvantages of conventional and unconventional materials and conclude which is better
for post flood shelter construction.
6
From the literature reviews a general idea regarding post disaster shelters and the factors
that need to be considered while designing a post disaster shelter is understood in a global
scenario. After the flood in Kerala several prototypes were constructed. But all of them are
limited to only a few numbers only. This research is intended to study efficiency of the
build prototypes and to understand whether it could be built in a larger scale.
7
The building rules of urban and rural areas will be revised. Separate chapters will be
added for enhancing disaster resilience of constructions in different zones.
Relocation and resettlement planning
Culture of alternative environment friendly design (kerala, 2018)
8
3 METHODOLOGY
This chapter presents the methodology that was followed to complete the dissertation
objectives. This chapter explores the methodology and gives an overview of various
methods. Different data sources and types are explained.
Overview:
Secondary data collection
Literature case studies of post flood shelters in the global scenario
Primary data collection
Live case studies on selected post flood shelters in Kerala
Interact with engineers to find the structural stability of materials
3.1 Data sources and data types
1. Secondary data collection
Literature case studies:
Three literature case studies were done about post flood shelters from different
countries.
One room shelters from Pakistan,2010 flood
T-shelters of Haiti during 2007 flood
Emergency shelters using paper by architect Shigeru Ban
2. Primary data collection
Live case studies:
Post flood shelter by habitat technology group in Trivandrum
Post flood shelters by Urvi foundation in Wayanad
A ferrocement house in Kuttanad to understand the disadvantages of using
advanced technologies
Interact with an engineer who specialises in ferrocement structures
3.2 Data collection
Primary and secondary data’s are collected. Secondary data collection include three literature case
studies of One room shelters from Pakistan during 2010 flood, T-shelters of Haiti during 2007 flood
and Emergency shelters using paper by architect Shigeru Ban. These case studies are chosen to
understand the factors that needs to be considered while designing post flood shelters in large
numbers and how the chaos during the emergency situation can be reduced by providing paper
modules.
Primary data collection serving as the prime data source for the dissertation. Post flood shelters in
Trivandrum and Wayand were chosen for live case study. The detail of the post flood shelters were
collected from the respective firms. The collected details include the construction details, materials
used, plans and other technical details.
The primary and secondary data’s collected are analysed and categorised in the results
chapter. The data’s are reduced to analyse the factors such as acceptance by the people,
material efficiency, durability, strength, construction time, construction cost, size and
design.
9
10
4 RESULTS
Country : Pakistan
Disaster : Flood, July 2010
Materials : Unreinforced brick exterior walls, tile roof supported on steel
framing.
Material source : Locally procured
Anticipated lifespan : 10 years
Number built : 875
Approximate project cost per shelter: 90,000 INR
Shelter Description
The shelter is a rectangular structure with dimensions 4.8m x 3.9m and has a flat roof. The
walls are made of unreinforced fire burned 230mm thick brick supporting the roof. The roof
is made of ceramic tiles and are supported on steel beams. A cement plaster is also coated
above the roof tiles. The foundation is made of unreinforced brick footing and foundation
walls. The floor is mud plastered and is raised about 610mm from the ground level. The
shelter has only one door and one window and the air vents are at top of the walls.
The initial idea was to use compressed earth blocks as the building material. The pilot
shelters were made of compressed earth blocks. The affected people were trained to build
the compressed earth block from locally procured mud. This tedious process took about
nineteen months. But after constructing few shelters the authorities came to understand
the drawbacks of using compressed earth blocks.
o High cost of the shelter in comparison to local houses reduced the likelihood of
replication
o Production was slow and labour intensive
o lack of acceptance of mud houses
o difficult to transport the blocks for more than a few hundred meters
Due to the intensive beneficiary selection process and pilot shelter construction delayed the
entire process. Only after about two years after the disaster the affected people were
provided with shelters.
July – August 2010 - Disaster date
7 months - Project start
11 months - Pilot project started
12 months - Beneficiary selection
11
17 months - Material procurement
19 months - Material distribution and training
21 months - Shelter construction
23 months - Evaluation
Figure 4-2 Plan of one room shelter in Pakistan (Federation of Red Cross)
12
Figure 4-3 Section of one room shelter in Pakistan (Federation of Red Cross)
NGO-A
Foundation : Non-reinforced concrete slab
Frame : Treated wood frame
Walls : Plywood walls (will require replacement after 3 years)
Roof : Tin roof (will require replacement after 3 years)
Doors : 2 wooden doors
Windows : 4 wooden windows
Figure 4-4 NGO-A t-shelter (Avery Doninger) Figure 4-5 NGO-B t-shelter(Avery Doninger)
13
NGO-B
Foundation : Tied down into the ground in concrete footings
Frame : Pressure-treated timber frame
Walls : Tarpaulin (meant to last between 6 to 18 months, depending on exposure
climatic elements)
Roof : Coated tin-plated roofing
Doors : 3 wooden doors (two in front, one in back)
Windows : 4 wooden windows (Doninger, 2013)
NGO-A was helping extremely vulnerable hard to reach communities, the places most of the
NGOs would not tend to work. As they are hard to reach costs were steep for transportation
than expected.
None of the NGO-A beneficiaries transitioned their shelter. The chosen beneficiaries were
the most vulnerable people like elderly people and disabled people. NGO-A financially
helped the people later on to improve their temporary shelter but they didn’t provide work
force. Since the people themselves weren’t physically able to improve their shelters they
were left as such.
NGO-B was more concentrating in the urban regions. They provided financial support were
not provided for upgrading the shelters. The beneficiaries themselves need to make the
changes. Many people were unemployed and had insufficient incomes. So some people sold
the shelters and others became uninhabitable with time. (Doninger, 2013)
14
Figure 4-6 Paper partition system by Shigeru Ban (Shigeru Ban architects)
Figure 4-7 Paper partition system by Shigeru Ban (Shigeru Ban architects)
As the civil war broke out in Rwanda in 1994 about 2 two million people were homeless.
Plastic sheets and aluminium poles were used to build temporary shelters. But the Rwandan
refugees sell these aluminium poles for money and stared cutting trees which could create
massive deforestation. Shigeru ban introduced the low cost alternative – paper tubes. Three
types of prototypes shelters were designed and tested for durability, termite resistance and
cost efficiency. They could be cheaply manufactured with simple machinery on the site and
transportation cost could be rapidly reduced.
15
Figure 4-8 Earthquake reconstruction assistance in Haiti 2010 by Shigeru Ban architects (Shigeru Ban
architects)
Figure 4-9 Paper log houses built as temporary dwellings for victims of 1995 kobe earthquake (Shigeru Ban
architects)
16
4.4 LIVE CASE STUDY 1
Location : DPI junction, Trivandrum
Materials : Inter lockable mud bricks, recycled mud tiles, treated bamboo,
filler slab
Material source : Locally procured
Construction time : 23 days
Built area : 495 sq.ft
Approximate project cost : 5,50,000 INR
Architect G Shankar has come up with a model which could resist floods and other natural
calamities. The house was built on a budget of Rs 5.5 lakh and the construction was
completed in 23 days. Around 130 labourers worked for 12 hours per day to complete the
project within specified time.
The 495 sq.ft house has 3 stories, and it stands on pillars built with treated bamboo, mud
and concrete.
Figure 4-10 Plan of post flood shelter by Habitat technology group (Habitat technology group)
Amenities – living cum dining space, 2 bedroom, kitchen, 1 toilet and provision
for expansion
17
Figure 4-11 View of post flood shelter by Habitat technology group (author)
Figure 4-12 View of post flood shelter by Habitat technology group (author)
18
Figure 4-13 Interior view of post flood shelter by Habitat technology group (author)
The ground floor which is built at a height of almost 6 feet can be turned into a car porch.
Living and dining area, kitchen, bedroom and a bathroom on first floor.
Second floor have a bedroom and terrace area which could be used for future expansion.
19
Figure 4-14 Details of post flood shelter prototype by Urvi foundation
20
DAY 1 : Foundation completed
DAY 2 : Basement and Floor structure completed
DAY 3 & 4 : Wall structure completed.
DAY 5 & 6 : Roof structure completed.
DAY 7 : Flooring completed.
DAY 8 : Wall skin completed.
DAY 9 : Roofing with Mangalore tiles, Doors & windows fixing completed.
DAY 10&11 : Plumbing and electrical works completed.
DAY 12 : Floor tiling completed.
DAY 13 : Exterior Painting completed.
DAY 14 : Interior Painting completed
21
Figure 4-17 Interior view of post flood shelter by Urvi foundation
22
Literature case study 1 : One room shelters in Pakistan
Overview
• Train the people on creating compressed mud block
• Started the construction with mud blocks
• Without much knowledge about building material
• Waste time by training people
• Time consuming tasks
• It took 2 years to complete the task, intermediate sheltering was not provided
Inference
• No window for experiments
• Instead of training people try to utilize their existing skills
• Use materials that helps to finish work faster
• If materials like bricks are used (which is time consuming) intermediate temporary
shelters must be provided
Overview
NGO-A
• hard to reach rural communities
• costs were steep
• Future assistance were not provided
NGO-B
• Urban areas were covered
• Future assistance for transformation were not provided
Inference
People in these areas do not have much access to recourses and they don’t have much
expertise in handling such materials. In such areas use locally available materials
or else timely supervision and aid must be provided.
23
Live case study-1 habitat technology group
The materials used were locally available and need not be transported from different
places.
Usage of sustainable building materials.
Maintenance can be done later on without much skilled workers.
As the house is raised about six feet from the ground level, precautions are taken to
avoid future flood.
Lifespan of the shelter is same as that of any other house.
Relocation, re-use and maintenance Maintenance can be done with the help of local
workers
Hazards, risks and safety There isn’t any risk and precautions to future
disasters are also considered
Timeliness and construction speed 23 days are taken to complete the project with
around 130 labourers which is an issue considering
the number of workers for a single prototype
Table 4-1 Analysis of the post flood shelter by Habitat Technology Group
Some of the materials used for construction such as bamboo is locally available but
cement boards used for walls and flooring needs to be transported from different
locations.
Maintenance work or expansion needs to be done with the supervision of skilled
labourers since these methods are not commonly used.
As the house is raised about one meter from the ground level, precautions are taken
to avoid future flood.
Lifespan of the shelter is said to be 40 – 45 years.
24
Better thermal and sound insulation can be achieved due to the air cavity between
the panels
Timeliness and construction speed 14 days are taken to complete the project with is
a great advantage
Figure 4-19 View of ferro-cement house build in 2010 Figure 4-20 View of the same house in 2019 (author)
This ferro-cement building was build in 2010 by the government. The people using this
building doesn’t have any idea of the construction of these structures. Due to improper
foundation a part of the house is broken apart. Since the people using this building are
financially poor and doesn’t have the expertise in constructing ferro-cement structures they
are forced to live in that building in a very unhygienic environment. Even though ferro-
25
cement structures are stronger than brick structures due to negligence from the authorities
the people living in it are suffering.
This is an example to understand that even if different technologies are used timely
assistance and supervision must be arranged.
5. DISCUSSION
The factors that affect the large scale construction of a post flood shelter are:
Acceptance
Unskilled labourer
Easy accessibility to material and labourer
Material efficiency
Strength
Durability
Construction time
Construction cost
26
Size
Disabled friendly design
Apart from these factors periodical supervision is required from the part of concerned authorities to
ensure that the structures are safe especially those built of non-conventional materials.
6 CONCLUSION
In Kerala the most chaotic situation was during the emergency period. People were living in
public buildings like schools and auditoriums. In future situations paper modules created by
architect Shigeru Ban or other designs should be implemented in the existing buildings
during emergency period so as to reduce the chaos and provide privacy to the affected
people.
From the above analysis the prototype build by urvi in wayanad can be considered as a
better design for replication. It takes comparatively less duration for construction and also
last about 40 -45 years.
Since the material used and construction is unconventional methods common people won’t
have the knowledge to maintain or renovate the buildings. In that case timely support needs
to be provided from the concerned authorities.
27
7 REFERENCE
cary, j. (2017). design for good: a new era of architecture for everyone.
Colin H.Davidson, C. G. (2007). Truths and myths about community participation in post-disaster
housing projects. Truths and myths about community participation in post-disaster housing
projects.
David Sanderson, . B. (2013). Beyond Shelter after Disaster: Practice, Process and Possibilities.
hendrix, J. (2012). Architecture as the psyche of a culture. Architecture as the psyche of a culture.
Hillier, B. &. (1984). The Social Logic of Space. The Social Logic of Space.
kerala, g. o. (2018). Kerala Post Disaster Needs Assessment Floods and Landslides August 2018.
Limited, C. R. (2018). Economic and Industrial Impact of Kerala Floods. CARE Ratings Limited.
McIntyre, M. H. (2006). A Literature Review of the Social, Economic and Environmental Impact of
Architecture and Design. A Literature Review of the Social, Economic and Environmental
Impact of Architecture and Design.
Tauber, G. (2014). architects and post disaster housing: A Comparative Study in South India.
28
29