Professional Documents
Culture Documents
Cesmp Marine 04072021
Cesmp Marine 04072021
Signature
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 2 !Unexpected End of
Works Page No.
Formulaof 533
TABLE OF CONTENTS
2. SCOPE
This CESMP is applicable to the marine works associated with the project. Specifically, the
following activities are covered on this document.
Installation of silt curtain and turbidity monitoring buoys.
Construction of primary bund where required, settling basin and installation of weir boxes at
the proposed stockpile areas.
Pre-construction bathymetric survey.
Dredging of the South Access Channel & Marina (D6 & D7) to the design levels.
Dredging of South Lagoon (D1) to the design level.
Dredging of the North Lagoon (D2- D2A) from -3.0m MSL to final design levels.
Dredging / excavation of the Internal Channels (D4-D5) to the design levels.
Dredging of the North Access Channel (D3) to the design level.
Dredging / excavation of the Swimming Channels (SC1-SC6 & SC9) to the design levels.
Dredging of the proposed North Pit up to 5m in thickness.
Dredged material arising from the dredging operations by the cutter suction dredger shall be
directly pumped to the proposed stockpile areas.
Dredged material arising from the dredging operations by the backhoe dredger shall be
loaded on deck barges/dump trucks, transported and offloaded at Shurayrah Island in the
proposed stockpile areas.
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 6 !Unexpected End of
Works Page No.
Formulaof 533
Excavated material by land equipment shall be loaded on dump trucks, transported, and
offloaded in the proposed stockpile areas.
Removal of topsoil from the existing ground level.
Environmental monitoring and Quality Control.
Interim verification surveys and post dredge surveys.
Demobilization of dredging equipment, auxiliaries, and personnel.
A separate CESMP will be developed to cover the marine related activities following the
finalization of the ESIA from TRSDC for the same. These works are expected to be
complete by 23rd July 2022.
3. DOCUMENT CONTROL
This Document is a controlled document and will be issued, revised, and distributed as
required by Archirodon IMS procedure PMG-PRO-10 “Development and Control of Project
IMS Documents”.
5. PROJECT INFORMATION
The scope of works for dredging and stockpile works mainly comprise of the following
activities:
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 8 !Unexpected End of
Works Page No.
Formulaof 533
Refer to Section 2-Scope for the detailed activities covered by this document.
The RSP is located in the west of Saudi Arabia, approximately 500 km north of Jeddah and
150 km north of Yanbu, along the Red Sea coast, between the towns of Umluj and Al Wajh.
The overall location of the RSP within the context of Saudi Arabia is shown in Figure 1.
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 9 !Unexpected End of
Works Page No.
Formulaof 533
Figure 1 Red Sea Project Location (Source: Shurayrah Masterplan Environmental and Social
Impact Assessment Report - Part 1 - Main Report)
The project will be developed within a SEZ. The location of Shurayrah Island is shown on
Figure 2.
Figure 2 Project Site within Red Sea Project Boundary (Source: Shurayrah Masterplan
Environmental and Social Impact Assessment Report - Part 1 - Main Report)
Shurayrah Island is a major development within the RSP, providing luxury accommodation
and recreational facilities but also acting as a Hub Island in support of facilities on smaller
islands.
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 10 !Unexpected End of
Works Page No.
Formulaof 533
The Red Sea Development Company (TRSDC) has been established by PIF to realise the
RSP. TRSDC is responsible for all aspects of the project development and have for two
years been working on master planning, program planning and implementation of enabling
and early works in support of the project.
As part of the ongoing development of the RSP, TRSDC has developed a CMP for the
development of Shurayrah Island.
The CMP includes a major reshaping of the Island, with the Island to be divided into two by
a lagoon, with small island formations and general raising of the Island land levels by 2m to
protect against flood risk from climate changes and storm surge. The CMP as of June 2020
is shown in Figure 3. The Concept Master Plan (CMP) for Shurayrah Island includes some
11 hotel sites, a championship grade golf course and associated facilities, public open space,
and other tourist facilities.
Figure 3 - Foster & Partners CMP for Shurayrah Island, Overall Layout
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 12 !Unexpected End of
Works Page No.
Formulaof 533
Contaminated Land
Shurayrah Island, with no significant historical use by humans, has a low risk factor for
existing contamination. Walk over surveys have shown no observations which would
indicate significant contamination with hydrocarbons. The coastline and some inland areas
have litter and trash present. Other than the plastic elements of this trash which will have
come from the sea, there are no significant risks of the project encountering contaminated
land during the excavation works.
Marine Ecology
The marine areas (including islands) of the Al Wajh Bank, inner lagoon area of the RSP,
have been classed as Critical Habitat based on the definition used in the IFC PS No 6
Guidance Note (IFC, 2019). The assessment for Critical Habitat was conducted using the
IFC 2012 Criterion approach and is yet to be updated. Species which qualified the area as
Critical Habitat included the Critically Endangered Hawksbill turtle, green turtle and
assembles of regional endemic species of birds which breed on the islands of the lagoon. In
addition, the whole of the RSP sits within an Important Bird Area (IBA) as declared by
Birdlife International (Birdlife International, n.d.). The marine environment within the
lagoon is considered to be sensitive to change with a mosaic of habitats present providing
supporting ecosystem services for a range of species.
Halophytic vegetation was widespread on Shurayrah Island, including the northern side of
the Island; although the more extensive areas were present to the east of the Island. Several
species of halophytes were present on the Island including Limonium sp., Arthrocnemum sp.
and Zygophyllum album, with the latter the most abundant.
Mangroves in the area were represented by a single species: Avicennia marina. Mangroves
fringed the length of the shoreline, with occasional denser stands of trees present. The most
extensive areas lie to the southeast of the survey area. Smaller trees and saplings covered
most areas, forming a narrow band within the intertidal zone.
In Shurayrah North, coral reefs within the footprint of the Island dredging sites largely
consisted of small patch and platform reefs, with numerous coral bommies scattered across
the seafloor. The coral cover of most areas was high, and even the smaller bommies on the
seafloor often supported relatively high live coral cover (25-50%). The more extensive reef
areas occur in the southeast and westward edges of the survey area. In the case of the latter
these occur as Porites dominated fringing reefs. To the southeast the reef formations were
relatively restricted in terms of their development and community structure due to the
biogeography of the area: The south and eastern lagoon adjacent to the mainland is typically
shallow and serves as a depositional area for finer sediments. Coral communities in the
wider area were relatively limited in their occurrence, with shallow patch reefs present away
from the shoreline, in areas flushed by wind-driven currents arising to the west of the Island.
The densest coral areas shown within the habitat map comprised relatively high diversity for
their sizes, dominated by Montipora, Anacropora, Stylophora, Platygyra, Porites, Cyphastrea
and Turbinaria species amongst others. Coral cover in some areas was high (>90%) within
the context of the north-eastern lagoon, alongside higher diversity of other reef-associated
fauna including fish. These reefs were also considered to be largely unimpacted, with no
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 13 !Unexpected End of
Works Page No.
Formulaof 533
visible signs of coral damage and only very limited evidence of bleaching impacts or
diseases away from the shallows. Coral communities do occur in deeper areas, visible as
small dark polygons: Typically, these areas have lower living cover due to relatively high
sedimentation rates. In Shurayrah – South, coral communities were relatively limited in their
occurrence, with shallow patch reefs present away from the shoreline, in areas flushed by
wind-driven currents arising to the west of the location. These communities were most
developed where larger patch reefs occur. Status in Shurayrah – West could not be evaluated
as part of the baseline study.
Megafauna including sea turtle and cetaceans are mobile species and those which have been
recorded in the lagoon area may be found in the waters around Shurayrah Island and along
the transportation route of the project. No turtle nesting has been recorded on Shurayrah
Island in survey years 2017 – 2020 however, as noted above, turtles may be present in the
waters around Shurayrah Island and generally within the inner lagoon.
Bird survey conducted in 2018 showed only two colonial species nesting on Shurayrah
Island. These were White-cheeked tern recorded on the south-east of the Island and bridled
tern present at the most south-west tip of the Island. Observations of Osprey nests have been
made on the Island, but no active nesting activity.
Much of the central part of the Island is very low lying and devoid of vegetation. For the
most part these areas are either sabkha or sabkha with thin layers of sand present. In the
south-east of the Island there is slightly higher ground with low dune systems present. There
are extensive areas of vegetation along the coastline. These consist of woody communities
of salt tolerant species. These include Limonium axillare, Halocnemum strobilaceum,
Arthrocnemum sp. and Tetraena alba. Finally, much of the coastline has mangrove resent.
These areas are single species mangrove (Avicennia marina) stands of various development
stages and cover. Cover varies from very sparse to dense stands.
Agriculture and Fisheries
Shurayrah Island has no agricultural activities on the Island. There are no domestic grazing
animals present. The fishing industry with the Red Sea is an important commercial and
artisanal activity. Fishing activities within this area of the Red Sea are licensed and
controlled by the Coast Guard authorities.
6. POLICY
The Integrated Management System Policy of Archirodon Group NV can be found in
Appendix A.
The policy will be communicated to all employees and those working for and on behalf of
Saudi Archirodon Ltd. through the induction course and be displayed at the site office
reception area and in prominent positions on site.
The policy will be available to all interested parties through Company website and will be
reviewed periodically to ensure that it remains relevant and appropriate to the nature and
scale of our operations.
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 14 !Unexpected End of
Works Page No.
Formulaof 533
To communicate with his colleagues, and report to his Supervisor, any condition or situation
that employee feels may be damaging to the environment.
The applicable, Environmental related, other requirements will be obtained from the contract
documents, local authorities’ web sites and the central legislation register maintained in the
Corporate Office and will be available on site, in a separate file in the Environmental office.
The Environmental Manager in cooperation with the Project Manager and Commercial
Manager will identify the interested parties that are relevant to the HSE Management
System and their needs and expectations and record them in the 11009-HSE-PRO-09-D01,
Interested Party Needs and Expectations register.
The Environmental Manager will periodically review the applicable, environmental related,
needs and expectations of interested parties, legal and other requirements and advice the
Project Manager regarding any actions to be taken to ensure compliance. The Environmental
Manager will keep records of this periodic evaluation using the 11009-HSE-PRO-09-F01,
Evaluation of Compliance Register.
The Environmental Manager will maintain and update the file containing the Environmental
related, legal and other requirements for the duration of the project.
Project Manager
Construction Manager
Section Engineers
Workshop Manager
Environmental Manager
Environmental Supervisor
PSO/Ecological Expert
For each group activity appropriate environmental aspects are identified, and their levels of
significance are discussed and classified as high, medium or low based on the HSE Risk
Assessment Matrix provided in Appendix C.
This matrix is based on the formula:
RISK (R) = Severity (S) X Likelihood (L), where severity and likelihood can have a value
between 1 to 5, with 1 being low and 5 being high.
The process will, where relevant, consider:
Air Emissions
Noise and Vibration
Waste generation
SAUDI ARCHIRODON LTD. R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Social Management Plan for Marine 22 !Unexpected End of
Works Page No.
Formulaof 533
Land contamination
Marine contamination
Groundwater contamination
Terrestrial Ecology
Marine Ecology
Use of raw materials and other natural resources
Applicable legal and other requirements
Archaeological and Heritage
Different operations conditions (e.g. day to day, abnormal, emergency situations)
Those aspects with medium to high impact significance will be taken into account in
determining the appropriate operational controls. The results of the Workshop will be
recorded in 11009-HSE-PRO-10-D01, Environmental Aspects Register while the relevant
Environmental Risk and Opportunities will be recorded in 11009-HSE-PRO-10-D02,
Environmental Risk and Opportunities Register.
Environmental aspects for individual work activities (e.g. mobilization, dredging,
stockpiling works etc.) will be also identified during the preparation of Method Statements
and will be documented in the Risk Assessment part of each Method Statement.
The Risk Assessment will be communicated by the responsible engineer/foreman to all
employees involved in the activity prior of work commencing and this communication will
be recorded using the HSE Training Attendance (11009-HSE-PRO-04-F06). The original
signed off form will be available with the supervisor/foreman as long as the activity goes on.
A list and the originals of all approved Method Statements will be available with the
project’s Document Controller and the Environmental Manager will maintain a file with
copies of these approved Method Statements, a copy and register of all Risk Assessments in
the Environmental Department for easy reference.
The Project/Construction Manager, Section Engineers, HSE Manager and Environmental
Manager will revise the Risk Assessments where there is an occurrence of an
accident/incident due to the work and whenever new aspects are identified or there is a
change in one or combination of the following:
To avoid, reduce, mitigate and manage any potentially significant adverse project-related
impacts to sensitive resources and receptors arising from excessive noise issues.
D: Non-Sensitive areas 80 80 80
Source: PME Environmental Standards -Environmental Noise-Table 4 - Maximum Permissible Façade Noise
Limits for General Construction Activities
To avoid, reduce, mitigate and manage any potentially significant adverse project-related
impacts to sensitive resources and receptors arising from excessive air emissions issues.
Health and Safety related records described in Section 14 such as accident record book in
accordance with USA OSHA reporting requirements on Lost Time Injuries, health
monitoring for all workers, including COVID testing etc. will be maintained by the Health
and Safety team and will be addressed in the relevant Health and Safety Plan.
Impact Equipment
Monitoring Description Frequency Duration No of Locations
ID Required
AQ001 Visual check for black smoke being emitted from Daily Throughout All equipment None
equipment contract period
AQ002 Visual check on dust emissions Continuous Throughout All relevant areas None
contract period
Visual checks and reporting on infractions and Daily Throughout N/A None
events where vehicles or people were observed contract period
driving or utilising areas outside those clearly
demarked
ME002 PSO to keep watch for protected species including All vessels, Construction All vessels __________
marine mammals, turtles and other megafauna. when in
operation
ME004 A PSO shall be present for all marine works, to Continuous 30 minutes prior to As required __________
ensure that species of interest do not enter the start of any
work area significant noise-
generating
activity.
ME004 A PSO shall watch for 30 minutes prior to start of any As required Construction As required __________
significant noise-generating activity.
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 31 !Unexpected End of
Page No.
Formulaof 533
Impact Equipment
Monitoring Description Frequency Duration No of Locations
ID Required
ME015
Continuous water quality monitoring with real-time Continuous Throughout Variable, Continuous
data transfer and alerts. Pre-agreed contractor contract period depending on monitoring
responses at pre-set thresholds Project station (frame or
activities buoy) with
multiparameter
sonde and 3G data-
centre (or similar)
In-situ water quality measurements and visual Twice daily During all in-water Variable, Multiparameter
inspection (visible plumes, dredge pipelines, silt activities depending on sonde; GPS;
curtains, project activities, potential impacts, etc.) Project camera; vessel
around work area, control sites and at sensitive activities
receptors.
Laboratory analysis of seawater and marine Weekly Throughout Variable, Van Veen grab
sediment samples contract period depending on sampler (or
Project similar); Van
activities Doorn water
sampler (or
similar);
laboratory
supplied sample
containers Cool
box and ice;
GPS; Vessel
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 32 !Unexpected End of
Page No.
Formulaof 533
Impact Equipment
Monitoring Description Frequency Duration No of Locations
ID Required
Marine Ecology - Reef survey by experienced Monthly Throughout 12 (‘shared’ with Scuba
marine scientists (minimum, more contract period Bridge equipment;
frequently when construction) GPS;
bleaching risk underwater
increases) camera; vessel
Seabed temperature and light loggers Monthly data Throughout 12 (‘shared’ with 'Pendant'
download / contract period Bridge temperature and
continuous construction) light loggers
deployment (e.g. Hobo™)
Sedimentation - silt traps Monthly data Throughout 12 (‘shared’ Silt traps; scuba
collection contract period with Bridge diving
(continuous construction) equipment;
deployment) GPS; vessel
ME015 Health and survival of relocated corals Monthly during Minimum three years As required Scuba
construction, equipment;
quarterly GPS;
thereafter underwater
camera; vessel
ME016 Health and survival of relocated mangrove seeds Monthly during Minimum three years As required Measuring poles
and saplings construction, and calipers
quarterly
thereafter
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 33 !Unexpected End of
Page No.
Formulaof 533
Impact Equipment
Monitoring Description Frequency Duration No of Locations
ID Required
ME017 Monitoring as per ME015 __________ __________ __________ __________
ME018 Daily coastal site walkover looking for turtle tracks Daily Throughout Whole Camera
/ nests before any site activities commence. construction phase coastline from
1 km either
side of active
works
ME021 Visual inspection of site lighting Daily Throughout One per worksite Camera
construction period
ME022 Coral gonad maturity assessment Once per month March to May, prior to One Scuba
full moon
Monitoring as per ME015 __________ __________ __________ __________
ME032 AIS (or similar) monitoring of vessel movements __________ __________ __________ __________
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 34 !Unexpected End of
Page No.
Formulaof 533
Impact Equipment
Monitoring Description Frequency Duration No of Locations
ID Required
Coral gonad maturity assessment, as per ME022 __________ __________ __________ __________
PSO monitoring during all nighttime activities __________ __________ __________ __________
MQ001 Site inspections / audits of material storage Weekly Throughout All chemical None
contract period stores
Visual observations of spills, sheen on water and Daily / Throughout All work areas None
presence of waste within work areas or water continuous contract period
column
Monitoring as per ME015 __________ __________ __________ __________
MQ003 Additional discharge water monitoring for specific Twice weekly As required As required Niskin (or
parameters (TSS, Nutrients, Metals) similar); sample
containers
Monitoring as per ME015 __________ __________ __________ __________
MQ004 Logs of transfers to waste service provider to be Weekly Throughout N/A None
maintained contract period
R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
SAUDI ARCHIRODON LTD. Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 35 !Unexpected End of
Page No.
Formulaof 533
Impact Equipment
Monitoring Description Frequency Duration No of Locations
ID Required
Laboratory analysis of seawater samples (see Weekly Throughout Variable, Van Veen grab
ecology monitoring; ME015) contract period depending on sampler (or
Project similar); Van
activities Doorn water
sampler (or
similar);
laboratory
supplied sample
containers Cool
box and ice;
GPS; Vessel
MQ011 pH monitoring required as part of the daily __________ __________ __________ __________
seawater monitoring requirements; see ME001
MQ012 Additional discharge water monitoring for specific Twice weekly As required As required Niskin (or
parameters (TSS, Nutrients, Metals) similar); sample
containers
Monitoring as per ME015 __________ __________ __________ __________
SG001 Contractor to maintain records of fuel, oil, Ongoing Throughout N/A None
chemical etc. deliveries, inventory, and usage contract period
Site inspections / audits of material storage Daily Throughout All chemical None
contract period stores
Visual check of refuelling location and other areas for During each Throughout All relevant None
evidence of hydrocarbon contamination refuelling event contract period facilities
R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
SAUDI ARCHIRODON LTD. Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 36 !Unexpected End of
Page No.
Formulaof 533
Impact Equipment
Monitoring Description Frequency Duration No of Locations
ID Required
Visual inspection of sanitary facilities, ensure Daily Throughout All relevant areas None
toilets are being used and maintained properly contract period
TE001 Visual checks and reporting on infractions and Continuous Throughout N/A None
events where vehicles or people were observed contract period
driving or utilising areas outside those clearly
demarked
TE006 Visual inspection for rat or cat tracks, or other Daily Throughout All Island facilities __________
indications of invasive species construction period
WH006 Daily count / roll call of workers on Islands Twice daily Throughout - N/A
(arrival and construction period
departure)
WM001 All solid and liquid waste management facilities to be Daily Throughout All waste None
checked daily to ensure proper use and not contract period management
overflowing facilities
Site supervisors to check all sites for evidence of Daily Throughout All work areas None
poor waste management practices or poor contract period
housekeeping
Visual checks for compliance with waste
management plan and maintenance of appropriate
records
Visual checks for compliance with waste Daily Throughout All work areas None
management plan and maintenance of appropriate contract period
records
R12-T08C05 - Shurayrah Island Stage 1
Dredging and Stockpiling Works
SAUDI ARCHIRODON LTD. Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 37 !Unexpected End of
Page No.
Formulaof 533
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and Social ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Management Plan for Marine Works 38 !Unexpected End of
Page No.
Formulaof 533
Project status and a summary of Project activities undertaken during the week
Daily inspection and weekly audit checklists
Accident and Near Miss Records
Protected Species Observation (PSO) summary
Training summary records
Hazardous materials:
o Chemical store inspections
o Emergency response equipment checks
Waste manifests / metrics
o Recycling / reuse volumes
o Disposal volumes
Traffic metrics
o Volume of materials transported
o No. of trucks and frequency of travel
o Incidents / near miss and related corrective actions
Environmental Monitoring result tables (where applicable), including simple summary
statistics
Other performance indicators, general observations, identification of issues, complaints, etc.
as necessary.
Project status and a summary of Project activities during the reporting period;
Summary of internal daily inspection and weekly audit checklists;
Second party audits
o Non-conformance numbers, trends and close out rates and summary statistics
o Detailed discussion of Major Non-Conformances (if any) including immediate actions,
root cause investigation results, corrective actions
o Analysis of Minor Non-conformances for trends and recurrent issues
Waste manifests / metrics
o Recycling / reuse volumes
o Disposal volumes
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and Social ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Management Plan for Marine Works 39 !Unexpected End of
Page No.
Formulaof 533
List of environmental incidents, including immediate actions, root cause investigation results,
subsequent corrective actions
Overall environmental performance, upcoming environmental and ecological considerations
(e.g. nesting seasons, wildlife, etc.), additional planned initiatives
Protected Species Observation (PSO): summary and trend analysis;
Equipment and vehicles maintenance records
Training summary
Other performance indicators, general observations, issues, etc.
Environmental Monitoring result tables (where applicable)
Number of Toolbox
Increase Staff Awareness, Environmental 1/Week
talks
participation, and consultation
on HSE Aspects Number of HSE Meetings 4/month
Aspects)
18. REVIEW
This Construction Environmental and Social Management Plan is a dynamic document and
will be reviewed as appropriate by the Environmental Manager to ensure continual
improvement and compliance with applicable legal and other requirements. It will then be
amended, if appropriate, to address changes to the activities, services or operating conditions
and to set new and additional project specific objectives, targets and program or operational
controls. Any changes made will be communicated to the various Managers and where
applicable communicated to the workforce and recorded via toolbox talks and posters.
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
Construction, Environmental and Social ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Management Plan for Marine Works 41 !Unexpected End of
Page No.
Formulaof 533
Project Manager
Christos Biliouris
Environmental Manager
Christina Tsitoura
Environmental Manager
Lola Okunrinboye
LEGEND
Reporting Communication
.
R12-T08C05 - Shurayrah Island Stage 1
SAUDI ARCHIRODON LTD. Dredging and Stockpiling Works
Rev.
Issued For Review
Reference No. N/A
ARCO Ref. No. 11009-SAR-HSE-PLN-005 0
Construction, Environmental and Social Management Plan for Marine Works 45 !Unexpected End of
Page No.
Formulaof 533
LIKELIHOOD
CONSEQUENCE
1 2 3 4 5
Incident has Happens several Happens
Never heard of Heard of in
occurred in times per year several times
in industry/ industry/
industry/ in industry/ per year in a
SEVERITY
company company
PEOPLE ASSETS ENVIRONMENT Activity is Activity is
company company location
Activity is Activity is Activity is
taking place taking place
taking place taking place taking place
rarely occasionally
frequently regularly continuously