Professional Documents
Culture Documents
1
The following is a compilation of the
results of compressed air leak surveys
preformed at two major automotive
manufacturers, located in the Tennessee
Valley Authority’s service area. Due to
the wishes of the companies, neither of
their names will be used. As such, they
will be identified as Company ‘A’ and
Company ‘B’.
2
Company ‘A’ is partitioned into 5
major divisions:
3
Compressed air for the entire plant is generated by
up to 6 centrifugal air compressors, totaling 13,500
horsepower.
4
Company ‘A’ pays, on average, around $1,000,000 a
month for electricity.
5
In surveying the first area of the plant, the Ultraprobe
2000 was used, along with its scanning module, rubber
focusing probe and a long range adapter.
The Ultraprobe 9000 was used in all other areas along with
its scanning module, rubber focusing probe, and long
range adapter.
6
Old Engine Plant
Of Company ‘A’s 5 major areas, the Old Engine Plant was the first to be
surveyed. The survey began on July 8, 1999 and lasted until September 10,
1999. Throughout the entire survey process for Company ‘A’, a
maintenance person from one of the maintenance crews from Company
‘A’ and me - 2 people - would be locating and tagging the air leaks.
We began the survey by dividing the Old Engine Plant into grids. We
would survey each grid, identifying all the leaks we could find before
moving on to the next grid. We did this to insure that we would not
overlap areas. Along the way, we managed to locate and tag 615
compressed air leaks.
The Old Engine Plant had a total consumption rate of around 11,500 cfm
of air. The 615 leaks we found equated to about 1,500 cfm, or 13% of the
total. We calculated the cost of these leaks to be a little over $130,000 a
year. Each leak averaged a little over $210.00.
7
Body Systems
Body Systems was the second area surveyed. Surveying began on October
2, 2000, and lasted 5 months.
It is from here, through the rest of the survey, that we utilized the
Ultraprobe 9000.
Like the Old Engine Plant, Body Systems uses around 11,500 cfm of
compressed air. The results of the survey found that Body Systems was
leaking about 3,570 cfm out of 1,931 leaks. These 1,931 leaks were costing
the company about $345,000 a year and equated to a leakage rate of
slightly more than 32%. The average cost of each leak was almost $180.00.
8
Vehicle Systems
The total consumption rate was 2,000 cfm. On the ‘down-side’, even
though the area didn’t use a lot of compressed air, the results of the
survey found that this area had the large percentage of leaks.
We located and tagged 713 leaks. These leaks equaled 850 cfm of
air, or about 40% of the total. These 713 leaks equated to almost
$82,000 a year with the cost of the average leak being $115.00.
9
In trying to understand why there was such a high
percentage of compressed air being lost, we went back and
looked at the compressed air usage history for the previous
2 years.
11
Main Utilities Building
The Main Utilities Building is the area that houses the air
compressors for the entire plant. It also houses the electrical
switchyard, the natural gas head, and the chilled water system.
The last area surveyed was the New Engine Plant. It was built to
replace the Old Engine Plant which had shut down by the time we
began the survey of the New Engine Plant. The plants were different
in as much as the engine and transmission components, formally
forged at the Old Plant, were not forged at the New Plant.
13
New Engine Plant
The total amount of compressed air usage was 1,350 cfm. Totaling
the results of these 5 areas, 257 leaks were located, with a total cost
of around $28,000 a year. The leaks were calculated to be 290 cfm,
or 21%. The average cost of each leak was almost $110.00.
14
A summary the results of the compressed air leak survey for Company ‘A’:
15
In terms of total costs:
16
Company ‘B’:
17
As with Company ‘A’, Company ‘B’ divided its facilities into 5 main
divisions:
18
Compressed air for Company ‘B’ is generated by up to 9 centrifugal
compressors, with a total capacity of 40,000 cfm.
You will soon see that overall, Company ‘B’ uses considerably less
compressed air than Company ‘A’.
19
Electric utility costs for Company ‘B’ are similar to
Company ‘A’ and total around $12,000,000 a year.
21
Trim and Chassis
This was the first section to be surveyed. The survey began on April
23, 2004 and concluded on December 9, 2004. The longevity of this
survey was due to several breaks brought on by product changes
taking precedent over the survey. This section of the plant was done
as a “test” to see if our survey would yield enough information to
warrant a survey of the entire facilities.
22
Paint Plant
Company ‘B’ was VERY impressed with the results of our “test”
and decided to push forward with surveying the rest of the facilities.
However, the company was still in the process of changing their
product line and adding new vehicles. As such, we were told it
would be a while before we could resume. Finally, on April 19, 2005,
(almost a year later) we resumed our survey with the Paint Plant.
24
Body Frame
25
Stamping
As such, the Stamping Area became the next item on the agenda.
This proved to be a rather different area in that although we didn’t
find as many leaks in proportion to the other areas, those we did find
were generally much larger.
The final area surveyed at Company ‘B’ was their Boiler Room. As
with Company ‘A’s Main Utility Building, the Boiler Room houses
the 9 compressors for the compressed air system. It also is home to
Company ‘B’s steam boilers. The amount of compressed air
assigned to the Boiler Room is rather limited; only 500cfm.
27
To summarize Company ‘B’:
28
In terms of total costs:
29
Comparing Company ‘A’ to Company ‘B’:
A summary the results of the compressed air leak survey for Company ‘A’:
(Differences)
(6,700) (1976) ($440,000) (3,435) (51%)
A-B=( )
32