PENANG SENTRAL SDN. BHD.

No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL


LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : SERVICES & MAINTENANCE WORKS OF SEWERAGE PUMP STATION AND MAIN GREASE TRAP.
SCOPE OF WORK

Equipment / Service
No Location Description Quantity Amount (RM)
Services Frequency
1 Mechanical Coarse Primary Screen Check unusual noise Monthly 1 nos 500.00
Screen Chamber
Clear screening bin
Check and clean teeth assemblies
Lubricate all lubrication points
2 Bar Screen Primary Screen Check bar screen Monthly 1 nos 250.00
Chamber
Clear screening bin
3 Raw Sewage Pump Dry Well Check unusual noise Monthly 1 nos 1,500.00

Check excessive tempreture


Check loss of power
Check meter reading
Check floats
Lubricate all lubrication points
Check power cable insulation
Check motor wirings
Check electrical connections
Check voltage supply
Check amperage rating
Check motor thermal protector

Clear, rest and check operation of level regulatios

Physical inspection
Check impeller
4 Main Grease Trap Level 1 Every two 1) Main grease 4,000.00
To desludge grease from 3 nos main grease trap (2) months trap - 3 nos.
tank by using vacuum desludging tanker 2) Enyme Liquid
- 5 nos

To use high pressure water jatter to wash and clean


the grease trap tank, to flush and clean the
incoming and outgoing pipeline from grease trap
tank.

To open the cement lid's of the grease trap and to


do housekeeping after work is completed.

To refill 4 nos Amnite 100 Enyme Liquid.

Discharge 2,500.00
To use high pressure water jatter to wash and clean
pipeline
5 Discharge pipeline Level 3 to 1 the pipeline from shop lots / F&B outlets to main Quarterly
approxmately
grease trap. (Approx 100m)
100m

TOTAL 8,750.00
PENANG SENTRAL SDN. BHD.
No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL
LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : SERVICES & MAINTENANCE WORKS OF FIRE PROTECTION SYSTEM.


SCOPE OF WORK
No Equipment / Services Location Description Service Frequency Quantity

1 Pump Set Sprinkler, wet riser and hose reel pump room Monthly Sprinkler System.
To check pump starter panel manual and automatic operation. 1) 4 way breeching inlet - 1 nos
2) Sprinkler Head (Upright/Pendent) - 7,200 nos.
To check conditions of electrical components in pump. 3) SKP-3 Jokey Vertical multistage EMVI 808 - 1 nos
To check conditions of all indication in pump stater panel. 4) SKP-1 Duty & 2 standby end suction centrifugal 80-26 - 2 nos.
To check proper functioning of all the control switches in the
pump starter panel. Hose Reel System
1) 25mmx30 swing fixed type - 61 nos.
To check pump gland packing and coupling alignment. 2) HRP-Duty & 2 Standby vertical multistage inline centrifugal EMVI808 - 2 nos.
To check Isolating valves and handwheel
To check hose reel nozzle rubber hose & free movement of Fire Alarm.
the drum. 1) Addressable MFAP - 1 nos.
2) Smoke Detector - 541 nos.
To check physical condition of water storage tank. 3) Manual Break glass - 68 nos.
4)150mm Alarm Bell - 68 nos
To check automatic activation and setting of pressure switch.
Fire Extinghuser
To check pumpsets standing pressure. 1) 2kg CO2 Fire Extinghuser - 51 nos.
To check pumpsets in auto mode. 2) 9kg ABC Dry Powder Fire Extinghuser - 70 nos.
2 RC Water Tank Sprinkler, wet riser and hose reel pump room To check Water level indicator functioning. Monthly
Wet Riser System.
To check the float valves operation. 1) 4-way breeching inlet - 1 nos.
3 Fire Alarm FCC Room, HT & TX Room, Genset Room, LV Room, DCS Ton check AC/DC rectification & charger unit. Monthly 2) Hose cradle - 50 nos.
i) MFAP TX Room, DCS HT Room, DCS MCC Room. 3) 65mmx30mm c/hose c/w couplings & 1 no jet & spray nozzle - 50 nos.
To check automatic change - Over to DC 4) 65mm landing valve - 50 nos.
ii) CO2
iii) FM200 DCS - Districh Cooling System. To check battery electrolyte level/dryfit. 5) WRP-1 Duty & 2 Standby End suction centrifugal EMVI812 - 1 nos.
To check test alarm/test fault/isolate switch. 6) WRP-3 Jokey vertical multistage inline centrifugal EMVI812 - 1 nos.
To check and test bulb/flourescent tube.
CO2 System.
To check bell ringing: continuous/intermitten. 1) CO2 cylinder - 14 nos.
To check manual breakglass/key switch. 2) 2 zone CO2 panel - 7 nos.
To check smoke/heat detectors.
FM200 System.
To check bell/buzzer isolate switch. 1) MV 250 lbs capacity cylinder c/w 101.94lbs FM200 - 1 nos.
To check fire department link. 2) 2 zones FM200 control panel -1 nos.
To check dual circuit operation.
To check gas discharge delay timer.
To check gas discharge delay timer.
To check 24V DC atuator.
To check piping cylinder bracket.
4 Monitoring signal indicators. To check lift trip. Monthly
To check AHU trip.
To check Exhaust fan trip.
To check Lift pressurisation fan.
To check smoke spill fan/extraction fan.
To check ssbestos fire curtain.
To check fixed CO2.
To check jockey, duty and standby pump: run/trip.
To check 3 phase power supply.
To check storage tank water level: high/low.
To check escalator trip.
To check magnectic door release
To check air curtain trip.
PENANG SENTRAL SDN. BHD.
No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL
LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : SERVICES & MAINTENANCE WORKS OF AIRCONDITIONING AND MECHANICAL VENTILATION SYSTEM.
SCOPE OF WORK

No Equipment / Services Location Description Service Frequency Quantity

1 Air Cooled Split Unit Level 1, 2, 2A, 3, 6 & 7A Monthly Heat Exchanger Pump (HEX) Chilled Water Pump.
Inspect and clean the air filters. 1) Hex-1 - 3 nos. 1) Chilled Water Pump capacity 70, model EHS 125-365 - 1 nos.
(375 RT x 3 nos, Total flow rate 169.20) 2) Chilled Water Pump capacity 70, model EHS 125-366 - 1 nos.
3) Chilled Water Pump capacity 70, model EHS 125-367 - 1 nos.
Inspect and clean the cooling coil when necessary. (Chemical Cleaning)
Air Handling Unit (AHU).
1) AHU-HL1-3a, model YSM1-40x70 - 1 nos. Air Cooled Split Unit.
Check compressor and refrigerant curcuit for proper operation tempreture 2) AHU-HL1-3b, model YSM1-50x70 - 1 nos. 1) Fire Control Room, capacity 28,000btu/hr/each - 2 nos.
conditiond. 3) AHU-HL1-4, model YSM1-40x80 - 1 nos. 2) SDF Room, capacity 18,000btu/hr/each - 2 nos.
4) AHU-HL2-7a, model YSM1-50x80 - 1 nos. 3) Police Office, capacity 22,000btu/hr/each - 2 nos.
Check refrigerant pressure once every three months. 5) AHU-HL2-7b, model YSM1-40x80 - 1 nos. 4) Telco Room, capacity 20,000btu/hr/each - 2 nos.
6) AHU-HL2-8, model YDM3-70x110 - 1 nos. 5) CCTV Room, capacity 14,000btu/hr/each - 2 nos.
Check crankcase heater where applicable. 7) AHU-HL3-14, model YSM1-30x50 - 1 nos. 6) Driver Room, capacity 20,000btu/hr/each - 2 nos.
8) AHU-HL3-15, model YSM1-50x80 - 1 nos. 7) Police Office, capacity 28,000btu/hr/each - 2 nos.
Inspect unit controls. 9) AHU-HL4-21a, model YSM1-50x70 - 1 nos. 8) Management Office, capacity 40,000btu/hr/each - 2 nos.
Check compressor oil level where applicable. 10) AHU-HL4-21b, model YSM1-50x80 - 1 nos. 9) DCS Control Room, capacity 14,000btu/hr/each - 2 nos.
11) AHU-HL4-22, model YSM1-70x80 - 1 nos. 10) Surau (F), capacity 22,000btu/hr/each - 1 nos.
Check unloading mechanism where applicable. 12) AHU-HL5-28a, model YSM1-50x80 - 1 nos. 11) Surau (M), capacity 28,000btu/hr/each - 1 nos.
13) AHU-HL5-28b, model YSM1-50x80 - 1 nos. 12) Dock loading bay, capacity 14,000btu/hr/each - 1 nos.
Visual check on condenser coils and cleans up when necesssary. 14) AHU-HL5-29, model YSM1-50x80 - 1 nos. 13) TOS Booth, capacity 14,000btu/hr/each - 1 nos.
14) Ferry linkway entrance, ceiling casset unit - 3 nos.
Check thermostat setting. Fan Coil Unit (FCU). 15) KTM linkway, ceiling casset - 15 nos
1) FCU HL2-7a-1, model YDFC 20 ST CB 4 - 1 nos.
Inspect control switchboard. 2) FCU HL2-7a-8(F&B), model YCF 46-6 - 1 nos. Variace Refrigerant Flow (VRF) - Indoor
2 Air Curtain Level 1, 2 & 3. Monthly 3) FCU HL2-7a-Taxi 1a&1b, model YCK 50 - 2 nos. MCC
Inspect control switch component.
4) FCU HL2-7b-2, model YGFC 12 - 1 nos. 1) FCU-MCC, model S-280ME1E5 95,500btu/hr - 10 nos.
To check the float valves operation. 5) FCU HL2-7b-3, model YDFC 20 ST CB 3 - 2 nos. 2) FCU-MCC, model S-224ME1E5 76,400btu/hr - 4 nos.
6) FCU HL2-7b-7a&7b(F&B), model YCF 62-6 - 2 nos. HT Room
3 Chilled Water Fan Coil Unit. Retail shop lot llevel 1, 2, 3, & 4. Check and clean filters. Monthly 7) FCU HL2-7b-VIP(F&B), model YCF 46-6 - 1 nos. 1) FCU-HT, model S-224ME1E5 76,400btu/hr - 4 nos.
(FCU). 8) FCU HL2-8-4(F&B), model YCF 30-6 - 1 nos. TX
Check fan belt tension and adjust if necessary.
9) FCU HL2-8-5(F&B), model YCF 46-6 - 1 nos. 1) FCU-TX, model S-280ME1E5 95,500btu/hr - 8 nos.
Inspect fan motor. 10) FCU HL2-8-6, model YDFC 18 ST CB 4 - 1nos. 2) FCU-TX, model S-73MF2E5A 25,000btu/hr - 1 nos.
11) FCU HL3-14-1(F&B), model YCF 62-6 - 1 nos. 3) FCU-TX model S-73MF2E5A - 1 nos.
Check fan shaft bearings and motor bearings, lubricate when necessary. 12) FCU HL3-14-16(F&B), model YCF 62-6 - 1 nos.
13) FCU HL3-14-2, model YDFC 29 ST CB 3 - 3 nos. Variance Refrigerant Flow (VRF) - Outdoor.
14) FCU HL3-14-3, model YDFC 18 ST CB 4 - 3 nos. MCC
Check and clean the cooling coil and drain pan when necessary. 15) FCU HL3-14-4(F&B), model YCF 46-6 - 1n nos. 1) CU-MCC, model U-72ME2H7SP 614,300btu/hr - 2 nos.
(Chemical Cleaning) 16) FCU HL3-15-7, model YDFC 14 ST CB 4 - 2 nos. HT Room
17) FCU HL3-15-8, model YDFC 14 ST CB 4 - 2 nos. 1) CU-FCU, model U-18ME2H7 153,600 - 2 nos.
Purge air trapped in cooling coil when necessary.
18) FCU HL3-15-9, model YDFC 14 ST CB 4 - 2 nos. TX
Check the operation of chilled water control valves and thermostat 19) FCY HL3-15-10, model YDFC 14 ST CB 4 - 2 nos. 1) CU-TX, model U-42ME2H7 402,700 - 2 nos.
control. 20) FCU HL3-15-11, model YDFC 20 ST CB 4 - 1 nos.
21) FCU HL3-15-12(F&B), model YCF 46-6 - 1 nos. Smoke Spill System.
4 Air Handling Unit (AHU) Level 1, 2, 3 & 4. Check and clean filters. Monthly 22) FCU HL3-15-13(F&B), model YCF 46-6 - 1 nos. 1) SEF, model AXC 1250-12/14o-4(B) smoke spill axial 1250mm - 6 nos.
23) FCU HL3-15-14(F&B), model YCF 36-6 - 1 nos. 2) SEF , model AXC 1250-12/25o-4(B) G smoke spill axial 1250mm - 1 nos.
Check fan belt tension and adjust if necessary.
24) FCU HL3-15-15(F&B), model YDFC 18 ST CB 3 - 2 nos. 3) SEF, model AXC 1250 12/26o-4(B) smoke spill axial 1250mm - 3 nos.
Inspect fan motor. 25) FCU HL3-15-5(F&B), model DB 16-6 - 1 nos
26) FCU HL3-15-6(F&B), model YCF 46-6 - 1 nos. Pressurisation Fan
Check fan shaft bearings and motor bearings, lubricate when necessary. 27) FCU HL3-Food Court, model YCF 100-6 - 1 nos. 1) LPF, model AXC9A) 1250-12/18o-4(B)GV vane axial 1250mm - 1 nos.
28) FCU HL4-21a-1, model YDFC 18 ST CB 4 - 2 nos.
29) FCU HL4-21a-2a&2b, model YCF 100-6 - 2 nos. Kitchen Exhaust and fresh air System
Check and clean the cooling coil when necessary. (Chemical Cleaning) 30) FCU HL4-21a-3, model YDFC 14 ST CB 4 - 2 nos. 1) KEF, model AW60 DWDI cabinet centrifugal 609mm - 2 nos
31) FCU HL4-21a-Nursery, model YDFC 20 ST CB 4 - 1 nos. 2) KEF, model AW65 DWDI cabinet centrifugal 675mm - 4 nos.
Check the operation of chilled water control valves and thermostat 32) FCU HL4-21b-18(F&B), model YCF 46-6 - 1 nos. 3) KEF, model AW75 DWDI cabinet centrifugal 742mm - 1 nos.
control. 33) FCU HL4-21b-19(F&B), model YCF 100-6 - 1 nos. 4) KFAF, model AW55 DWDI cabinet centrifugal 550mm - 2 nos.
34) FCU HL4-21b-20(F&B), model YCF 100-6 - 1 nos. 5) KFAF, model AW60 DWDI cabinet centrifugal 609mm - 3 nos.
5 Chilled Water Pump Unit. Hex Pump Level 7 Lubricate pumps and motor when necessary. 35) FCU HL4-21b-4, model YGCF 10 - 1 nos. 6) KFAF, model AW65 DWDI cabinet centrifugal 675mm - 2 nos.
36) FCU HL4-21b-5(F&B), model YCF 30-6 - 1 nos.
Check pumps mechanical seal and and tighten when necessary. 37) FCU Hl4-22-8(F&B), model YDFC 14 ST CB 4 - 3 nos. Mechanical Ventilation System
38) FCU HL4-22-9(F&B), model YDFC 12 ST CB 4 - 2 nos. 1) EF, model AW sileo 350E4 propeller 350mm - 2 nos.
Check water strainers and clean them when necessary. 39) FCU HL4-22-10, model YDFC 14 ST CB 4 - 2 nos. 2) EF, model AW sileo 450E4-K propeller 450mm - 2 nos.
40) FCU HL4-22-11, model YGFC 05 - 1 nos. 3) EF, model CDRE 315 cabinet in-line 315mm - 4 nos.
Check pressure gauges and valves. 41) FCU Hl4-22-12(F&B), model YCF 30-6 - 1 noa. 4) EF, model AXC 630-9/15o-4 axial 630mm - 2 nos.
Check for undue noise and vibration. 42) FCU HL4-22-13(F&B), model DB 16-6 - 1 nos. 5) EF, model AXC 630-9/10o-4 axial 630mm - 1 nos.
43) FCU HL4-22-14(F&B), model YCF 62-6 - 1 nos. 6) EF, model VF-APK10 propeller 250mm - 2 nos.
Check motor for undue tempreture rise. 44) FCU HL4-22-15(F&B) - 1 nos. 7) EF, model VF-APK6 propeller 150mm - 1 nos.
6 Water Treatment System Hex Pump Level 7 Check selnoid on/off valve is in good condition. Monthly 45) FCU HL4-22-16(F&B), model YCF 30-6 - 1 nos. 8) EF, model VF-APK12 propeller 300mm - 1 nos.
Check pressure sensor is in good condition. 46) FCU HL4-22-17(F&B), model YCF 46-6 - 1 nos. 9) EF, model AW sileo 300E4 propeller 300mm - 2 nos.
47) FCU HL4-22-6(F&B), model YCF 30-6 - 1 nos. 10) EF, model AW sileo 400E4 propeller 400mm - 1 nos.
Check wiring amp is in good condition. 48) FCU HL4-22-7(F&B), model DB 16-6 - 1 nos.
Application of chemical will be carried out by supplier. 49) FCU HL4-22-8(F&B), model YCF 46-6 - 1 nos. Toilet Exhaust Fan
1) EF, model CDRE 450 cabinet in-line 450mm - 1 nos.
On site water analysis test will be carried out during service call. Air Curtain 2) EF, model CDRE 400 cabinet in-line 400mm - 11 nos.
1) Air curtain - 42 nos. 3) EF, model CDRE 355 cabinet in-line 355mm - 5 nos.
Check and inspect each system and plant being treated.
Note : Non - Comprehensive
A complete water analysis report will be sent.

Check and report any irregularities related to the treatment program.

7 Heat Exchange Hex Pump Level 7 Check - Performance check for predicting maintenance requirement Monthly
once every 1-2.

Cleaning of heat exchanger depends on water quality as a guideline, 4


years a more accurate indication can obtained by using check.

8 Mechanical Ventilation Fan Level 1 to Level 10 Check for undue noise and vibration.
Check motor for undue tempreture rise.

Check fan shaft bearings and motor bearings, lubricate when necessary. Monthly

Chek fan belt tension and adjust if necessary.


Check thermostat control.
Inspect control switchboard component and cable lug for tightness
\
PENANG SENTRAL SDN. BHD.
No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL
LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : SERVICES & MAINTENANCE WORKS OF BUILDING MANAGEMENT SYSTEM (BMS).


SCOPE OF WORK
No Equipment / Services Location Description Service Frequency Quantity

1 Server Fire Control Room (FCC). To check and monitor server condition. Monthly NIL
To do disk diafragment.
Clear recycle bin to reduce memory usage.
To install new updates on the operating system (PS).
To check connection on the printer and alarm printer.
2 Workstation Fire Control Room (FCC). To check and monitor server condition. Monthly

To do disk diafragment.
Clear recycle bin to reduce memory usage.
To install new updates on the operating system (PS).
To check connection on the printer and alarm printer.
To do ping test to server IP.
To check webstation connection to server.
3 Automation Server (AS) Fire Control Room (FCC). To ping test on AS from the mai server. Monthly
4 Controller Panel Level 1, 2, 3, 4, 5, 6, 7, 8, 9, & 10 To check the cleaness of the panel. Monthly
To check physical on the panel.
To check any LED error light on the controller.
To check cable IO cable condition.
To test communication test on controller.
5 Struxuware Building Fire Control Room (FCC). To do back up for all system. Monthly
Operation System To check the synchronization on time and date.
To check all alarm status.
To do binding diagnotics on the system.
To test print alarm on the printer.
6 System Control Status Fire Control Room (FCC). To check graphics on the system. Monthly
To check the status of the controller.
7 Aircondition System (BMS) Fire Control Room (FCC). To check graphics on the system. Monthly
a) AHU
b) HEX To check and review sensor and status reading value.
c) FCU To test operating sequence
8 Electrical System Fire Control Room (FCC). To check graphics on the system. Monthly
a) Switchgear
b) Transformer
c) DB lighting To check and review sensor and status reading value.
d) EDB lighting
e) Genset
f) MSB To test operating sequence

9 Fire and Gas System Fire Control Room (FCC). To check graphics on the system.
a) Fire
b) LPG Monthly
To check and review sensor and status reading value.

10 Lift and Escalator System Fire Control Room (FCC). To check graphics on the system.
Monthly
To check and review sensor and status reading value.
11 Ventilation System Fire Control Room (FCC). To check graphics on the system. Monthly
a) KEF
b) MAF
To check and review sensor and status reading value.
c) EAF
d) TEF
To test operating sequence

12 Plumbing System Fire Control Room (FCC). To check graphics on the system. Monthly
To check and review sensor and status reading value.
PENANG SENTRAL SDN. BHD.
No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL
LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : COMPETENT ENGINEER FOR VISIT, INSPECTION AND TESTING THE ELECTRICAL EQUIPMENT INSTALLATION.
SCOPE OF WORK

Equipment /
No Location Description Service Frequency Quantity
Services
1 VCB - HT Panel Consumer 11KV Monthly
One line-up of 11KV switchgear with one TNB
ACB - LV Panel Switch 1 (HT), LV,
incoming and 3 outgoing panels in switch room.
Transformer and Genset Room
Genset Level 1 and Level
MCCB / Electrical 10. One stand-alone 11KV TNB incoming/outgoing
Riser panel in Switch Room for tenants.
Electrical riser
room Level 1 to 10. One line-up off 11KV switchgear with one incoming
and two outgoing panels in switch room for
landlord.

One line-up off 1KV switchgear with one incoming


and 2 outgoing panels for tenants

4 sets of 1250/1000 KVA 11/0.433V dry type


transformer.

Other related LV switch boards and auxiliary


equipment.

To prepare a monthly reports on the condition of


2 Report the electrical installation with copy, submission to Monthly
Pengarah Suruhajaya Tenaga Malaysia.

To carry out regular infra-red scanning of the switch


3 Other boards for any overheating or hot spots or imminent Monthly
failure of the electrical system.
PENANG SENTRAL SDN. BHD.
No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL
LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : COMPETENT ENGINEER FOR VISIT, INSPECTION AND TESTING THE ELECTRICAL EQUIPMENT INSTALLATION.
SCOPE OF WORK

Equipment /
No Location Description Service Frequency Quantity
Services
1 VCB - HT Panel Consumer 11KV Monthly
One line-up of 11KV switchgear with one TNB
ACB - LV Panel Switch 1 (HT), LV,
incoming and 3 outgoing panels in switch room.
Transformer and Genset Room
Genset Level 1 and Level
MCCB / Electrical 10. One stand-alone 11KV TNB incoming/outgoing
Riser panel in Switch Room for tenants.
Electrical riser
room Level 1 to 10. One line-up off 11KV switchgear with one incoming
and two outgoing panels in switch room for
landlord.

One line-up off 1KV switchgear with one incoming


and 2 outgoing panels for tenants

4 sets of 1250/1000 KVA 11/0.433V dry type


transformer.

Other related LV switch boards and auxiliary


equipment.

To prepare a monthly reports on the condition of


2 Report the electrical installation with copy, submission to Monthly
Pengarah Suruhajaya Tenaga Malaysia.

To carry out regular infra-red scanning of the switch


3 Other boards for any overheating or hot spots or imminent Monthly
failure of the electrical system.
PENANG SENTRAL SDN. BHD.
No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL
LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : PREVENTIVE MAINTENANCE AND SERVICES WI-FI SYSTEM.


SCOPE OF SERVICES
Service
No Work Description Description Equipment List.
Frequency
1 Preventive maintenance and services of Wi-Fi System. Include above hardware maintenance contract (Parts Quarterly 1) HPE 5510 24G 4SFP+HI Switch 1- 1 unit.
replacement and labor charges) (36 Months). 2) HPE 1950 24G 2SFP+2XGT Switch - 10 units.
Maintenance:- 3) HPE DL160 Gen 9 1 - 1 unit.
24/7/365 support and maintenance. Level email and remote troubleshooting. 4) Ligo Wave NFT 3ac Wireless AP - 37 units.
Unlimated cases for ICT related Second level onsite support after remote troubleshooting 5) ISP Load Balancer and Firewall Appliance (NTZ-300MB-1M) - 1 unit.
- Any other scope defined in basic task. Problem that require changes in programs or procedures 6) APC 3KVA UPS (Smart-UPS SRT 3000) 1 - 1 unit
- 2 hours response time. 7) ISP Load Balancer & Firewall Appliance (NTZ-300MB-1M). - 1 unit.
Quarterly health check.
- 4 hours onsite support. 8) APC 3KVA UPS (Smart-UPS SRT 3000). - 1 unit.
Wi-Fi equipment health check.
Provide quarterly health check report and maintenance.

vendors shall give its expert advice and recommendation to


client charges on the building Wi-Fi networks.

Manage and support ISP connectivity chronic problems that


require research for solution.
PENANG SENTRAL SDN. BHD.
No.5130 TERMINAL PENGANGKUTAN PENANG SENTRAL
LANDLORD, JALAN BAGAN DALAM
12100 BUTTERWORTH, PULAU PINANG.

SERVICES : PREVENTIVE MAINTENANCE AUTOMATIC DOOR SYSTEM.


SCOPE OF SERVICES
Service
No Work Description Description Equipment List.
Frequency
1 Preventive Maintenance and Services Automatic Door System. Quarterly Model : Tormax 2201
[Non-comprehensive package]. Guide system : Trolley head rollers, guide rail system, stopper. (24 Months). 1. Level 1, Gate 1 - 1 nos
2. Level 1, Gate 2 - 1 nos
Door leaves: Door profile, rubber seal (if applicable). 3. Level 1, Gate 3 - 1 nos
Drive system: Motor unit, toothed belt, belt return unit, belt 4. Level 1, Gate 4 - 1 nos
camp 5. Level 1, Gate 5 - 1 nos
Lock system (If applicable). 6. Level 1, Gate 6 - 1 nos
7. Level 1, Gate 7 - 1 nos
8. Level 1, Gate 8 - 1 nos
Inspect all electrical and electronics parts and adjust if 9. Level 1, Gate 9 - 1 nos
necessary. 10. Level 1, Gate 10 - 1nos
- Motor and control system. 11. Level 1, Gate 11 - 1 nos
- Opening activators (Which applicable). Sensor, push 12. Level 1, Gate 12 - 1 nos
button, remote control. 13. Level 1, Gate 13 - 1 nos
- Safety devices (If appliance). 14. Level 1, Gate 14 - 1 nos
- Backup battery (if appliance). 15. Level 1, Gate 15 - 1 nos
- Cabling. 16. Level 1, Gate 16 - 1 nos
17. Level 1, Gate 17 - 1 nos
18. Level 1, Gate 18 - 1 nos
19. Level 1, Gate 19 - 1 nos
20. Level 2, Surau (Male) - 1 nos
Inspect the operation and functionality of The Equipment and 21. Level 2, Surau (Female) - 1 nos
adjust if neccesary 22. Level 2, Taxi Waiting - 2 nos
- Door opening speed and closing speed. 23. Level 2 Main Entrance - 2 nos
- Door hold open time. 24. Level 2 Ferry Linkway - 3 nos
- Motion sequence adapt to situation. 25. Level 3 Main Entrance - 2 nos
- Np abnormal noise. 26. Level 3 Alfresco - 1 nos
- Environmental (No moving object). 27. Level 4 Manaegement Office - 1 nos

The equipnebt will be cleaned adjusted and calibrated to the


intended operating parameters.