PT.

Sentosa Jaya Purnama


Sadai Biomass Power Plant 1x10MW
Sadai Industrial Area, South Sadai District, Bangka Belitung, 33783 Indonesia

HISTORY MAINTENANCE Project name PLTBM Sadai 1 X 10 MW


BATCHING PLANT
LIUGONG HZS60A Made By : Rusman
No. Maintenance Material Photo Result Description Status Remarks
date Used Before Repair
1 Photo The screw of hoist提升机 were not Haven't
installed Solved

Photo Haven't
Solved

Besi Photo Design of hoppers were wrong Good/ Hoppers/


Complete Pembuatan penyaring
batu/kotoran

Photo The cable tray not installed Haven't


Solved
Photo The cable was installed along the screw
conveyor machine cement, this cable should
be installed in cable tray

Photo Haven't
Solved

Photo Completed

2022-04-27 The vibration motor can not at automatic Good/


mode and installation of vibration was Complete
wrong, did not same as DCS system.
Good/
Complete

Photo Good/
Complete

Inspected By : Accepted By :