Item Code Item Name Supplying of pea gravels at different rhd stack yeard in/c. cost of carrying, loading, unloading ……………
Unit of Measurement Cu. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)
Specification Item Components
Item Name Unit of Unite Rate Quantity Price of Unit Price Estimation Required Estimation Quantity Item Category Primary Item Item Type Equipment Flat Bed Truck (5 Tone) cu.metre 2000.00 1.00 2000.00 2000.000 Item Type Labour Unskilled labour for loading & unloading cu.metre 200.00 1.00 200.00 200.00 Item Type Material 1st Class Bricks cu.metre 885.00 1.00 885.00 885.00 Basic Unit Price of Specification Item : 3085.000 Plus Profit at 10.00% : 501.744 Sub-Total : 3586.744 Plus Tax & VAT at 11.7318% : 420.790 Total Unit Price of Specification Item : 4007.534