Tender ID

Item Code
Item Name Supplying of pea gravels at different rhd stack yeard in/c. cost of carrying, loading, unloading ……………

Unit of Measurement Cu. Metre


Quantity for Estimation 1.00
(All Prices Are in Taka)

Specification Item Components


Item Name Unit of Unite Rate Quantity Price of Unit Price
Estimation Required Estimation
Quantity
Item Category Primary Item
Item Type Equipment
Flat Bed Truck (5 Tone) cu.metre 2000.00 1.00 2000.00 2000.000
Item Type Labour
Unskilled labour for loading & unloading cu.metre 200.00 1.00 200.00 200.00
Item Type Material
1st Class Bricks cu.metre 885.00 1.00 885.00 885.00
Basic Unit Price of Specification Item : 3085.000
Plus Profit at 10.00% : 501.744
Sub-Total : 3586.744
Plus Tax & VAT at 11.7318% : 420.790
Total Unit Price of Specification Item : 4007.534