CONTRACT FOR THE DESIGN, PROCUREMENT AND CONSTRUCTION WORKS IN RESPECT OF A PLANT FOR THE

PRODUCTION OF SODA ASH WITH A CAPACITY OF 500,000 TONS PER YEAR AND RESIDENTIAL TOWN IN THE SARYSU
DISTRICT OF THE ZHAMBYL REGION IN KAZAKHSTAN

Appendix I

Project Schedule

QAZAQ SODA (КАЗАХ СОДА) LIMITED LIABILITY PARTNERSHIP

(Employer)

And

CAMCE-DHDC-SEMARCO Consortium

(Contractor)
Project Schedule
The design, procurement and construction works for the creation of a plant for the production of soda ash with a capacity of 500,000 tons per year and a residential complex
The length
S/N Work Description 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
(month)
0 Site Handover (Commencement Date) 0 ● ●
1 Engineering 14
1.1 Levelling and Fencing 3
1.2 Basic and Detailed Engineering Design 13
1.2.1 Soda Ash Production Line 13
1.2.2 Salt Mine Brine Production Unit 11
1.2.3 Limestone Quarry 11
1.2.4 Co-Gen /thermal power plant 11
1.2.5 RESIDENTIAL AREA 11
1.3 Construction of Temporary Facilities 2
1.4 Drawing transformation and approval 12
2 Procurement and Shipment 18
2.1 Soda Ash Production Line 18
2.2 Salt Mine Brine Production Unit 6
2.3 Limestone Quarry 12
2.4 Thermal Power Plant 14
2.5 RESIDENTIAL AREA 14
3 Construction 33
3.1 Civil Works 21
3.1.1 Soda Ash Production Line 18
3.1.2 Salt Mine Brine Production Unit 20
3.1.2.1 Salt Mining Civil Works 11
3.1.2.2 Well Development 18
3.1.3 Limestone Quarry 10
3.1.4 Thermal Power Plant 10
3.1.5 RESIDENTIAL AREA 17
Installation of Machinery, Electronics and
3.2 30
Instruments
3.2.1 Soda Ash Production Line 24
3.2.1.1 Installation of Line 1# 18
3.2.1.2 Installation of Line 2# 18
3.2.2 Salt Mine Brine Production 14
3.2.3 Limestone Quarry 8
3.2.4 Thermal Power Plant 10
4 Pre-Commissioning test 17.5
4.1 Soda Ash Production Line 7.5
4.1.1 Thermal Power Plant 4
4.1.2 Commissioning of Line 1# 2
4.1.3 Commissioning of Line 2# 2.5
4.2 Salt Mine Brine Production Unit 2
4.3 Limestone Quarry 3
5 Commissioning test 0.5
5.1 Soda Ash Production Line 0.5
5.1.1 Thermal Power Plant 0.5
5.1.2 Commissioning of Line 1# 0.5
5.1.3 Commissioning of Line 2# 0.5
5.2 Salt Mine Brine Production Unit 0.5
5.3 Limestone Quarry 0.5
6 Trial Operation & Perfomance test 2.5 ●
6.1 Soda Ash Production Line 2.5
6.1.1 Thermal Power Plant 2.5
6.1.2 Commissioning of Line 1# 2.5
6.1.3 Commissioning of Line 2# 2.5
6.2 Salt Mine Brine Production Unit 2.5
6.3 Limestone Quarry 2.5

Notes: The starting point of schedule is the Commencement date, and the end point
of the schedule is Performance test.
●Issue Taking over Certificate after Performance test.