TIME SCHEDULE PELAKSANAAN

PROYEK PEKERJAAN PENGGANTIAN INSTALASI ELEKTRIKAL


GEDUNG SEKOLAH AVICENNA CINERE
Jl.H.Rosyid Cinere Depok Jawa Barat

D U R A S I
NO JENIS PEKERJAAN VOL SAT OKT'22 NOV'22 DES'22 KET.
26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9
I PEKERJAAN ELEKTRIKAL LT.SATU
1 Instalasi lampu penerangan kabel 3x1,5 ex.Supreme 69.00 titik
2 Instalasi stop kontak biasa kabel 3x2,5 ex.Supreme 37.00 titik
3 Instalasi AC kabel 3x2,5 ex.Supreme 10.00 titik
4 Instalasi drain AC pipa PVC ex.Wavin Ø 1/2" 10.00 titik
5 Sakelar single ex.Panasonic 9.00 bh
6 Sakelar double ex.Panasonic 11.00 bh
7 Out let stop kontak biasa ex.Panasonic 37.00 bh
8 Out let stop kontak waterproof ex.Panasonic 6.00 bh
9 Bobokan kabel proyektor+pipa PVC 1 1/4" 6.00 titik
10 Bongkar lampu down light existing 16.00 bh
11 Bongkar lampu TKI 1x20 watt existing 17.00 bh
12 Bongkar lampu TKI 1x36 watt existing 30.00 bh
13 Ganti lampu LED TKI 2x18 w Elektrindo Vision 16.00 bh
14 Ganti lampu LED TKI 2x18 w Elektrindo Vision 17.00 bh
15 Ganti lampu LED TKI 2x18 w Elektrindo Vision 30.00 bh
16 Kabel NYY 4x6 mm (MDP-Panel lt.1) 4.00 m1
17 Kabel NYY 4x10 mm (MDP-Panel lt.1) 4.00 m1
18 Panel listrik lantai 1 2.00 unit
19 Panel listrik MDP 2.00 unit
20 Grounding BC 16 mm+pantekan 5 m 2.00 titik
21 Box panel listrik bahan besi plat 150x300x40 1.00 unit

II PEKERJAAN ELEKTRIKAL LT.DUA


1 Instalasi lampu penerangan kabel 3x1,5 ex.Supreme 70.00 titik
2 Instalasi stop kontak biasa kabel 3x2,5 ex.Supreme 39.00 titik
3 Instalasi AC kabel 3x2,5 ex.Supreme 9.00 titik
4 Instalasi drain AC pipa PVC ex.Wavin Ø 1/2" 9.00 titik
5 Sakelar single ex.Panasonic 6.00 bh
6 Sakelar double ex.Panasonic 13.00 bh
7 Out let stop kontak biasa ex.Panasonic 41.00 bh
8 Out let stop kontak waterproof ex.Panasonic 5.00 bh
9 Bobokan kabel proyektor+pipa PVC 1 1/4" 7.00 titik
10 Bongkar lampu down light existing 9.00 bh
11 Bongkar lampu TKI 1x20 watt existing 16.00 bh
12 Bongkar lampu TKI 1x36 watt existing 38.00 bh
13 Ganti lampu LED TKI 2x18 w Elektrindo Vision 9.00 bh
14 Ganti lampu LED TKI 2x18 w Elektrindo Vision 16.00 bh
15 Ganti lampu LED TKI 2x18 w Elektrindo Vision 38.00 bh
16 Kabel NYY 4x6 mm (MDP-Panel lt.2) 9.00 m1
17 Kabel NYY 4x10 mm (MDP-Panel lt.2) 9.00 m1
18 Panel listrik lantai 2 2.00 unit

III PEKERJAAN ELEKTRIKAL LT.TIGA


1 Instalasi lampu penerangan kabel 3x1,5 ex.Supreme 71.00 titik
2 Instalasi stop kontak biasa kabel 3x2,5 ex.Supreme 61.00 titik
3 Instalasi AC kabel 3x2,5 ex.Supreme 10.00 titik
4 Instalasi drain AC pipa PVC ex.Wavin Ø 1/2" 10.00 titik
5 Sakelar single ex.Panasonic 5.00 bh
6 Sakelar double ex.Panasonic 13.00 bh
7 Out let stop kontak biasa ex.Panasonic 35.00 bh
8 Out let stop kontak waterproof ex.Panasonic 5.00 bh
9 Bobokan kabel proyektor+pipa PVC 1 1/4" 7.00 titik
10 Bongkar lampu down light existing 9.00 bh
11 Bongkar lampu TKI 1x20 watt existing 15.00 bh
12 Bongkar lampu TKI 1x36 watt existing 40.00 bh
13 Ganti lampu LED TKI 2x18 w Elektrindo Vision 9.00 bh
14 Ganti lampu LED TKI 2x18 w Elektrindo Vision 15.00 bh
15 Ganti lampu LED TKI 2x18 w Elektrindo Vision 40.00 bh
16 Kabel NYY 4x6 mm+bc 6 mm (MDP-Panel lt.3) 15.00 m1
17 Kabel NYY 4x10 mm+BC 10 mm (MDP-Panel lt.3) 15.00 m1
18 Kbel NYY 4x4 mm+BC 6 mm (Panel lt.3-Lab.Com)) 18.00 m1
19 Kabel NYY 3x4 mm (Panel lt.3-Lab.IPA) 24.00 m1
20 Panel lab.computer ex.Hager 12 group lengkap 1.00 unit
21 Panel lab.IPA ex.Hager 8 group lengkap 1.00 unit
22 Panel lantai 3 2.00 unit
23 Out let stop kontak Ulticon 3 lubang lengkap 30.00 bh

IV PEKERJAAN ELEKTRIKAL KANTIN & AULA


1 Instalasi lampu penerangan kabel 3x1,5 ex.Supreme 15.00 titik
2 Instalasi stop kontak biasa kabel 3x2,5 ex.Supreme 7.00 titik
3 Sakelar single ex.Panasonic 3.00 bh
4 Sakelar double ex.Panasonic 4.00 bh
5 Out let stop kontak Ulticon 3 lubang lengkap outbow 7.00 bh
6 Ganti lampu LED TKI 2x18 w Elektrindo Vision 15.00 bh

V PEKERJAAN LAIN-LAIN
1 Plester+aci kembali bekas bobokan 1.00 ls
2 Cat kembali bekas bobokan 1.00 ls
3 Alat bantu kerja 1.00 ls
4 Mob & demobilisasi tenaga kerja 1.00 ls
5 Pembersihan akhir 1.00 ls

RENCANA
REALISASI

Menyetujui, Jakarta,25 Oktober 2022


: Kerja mulai jam 16.00-malam YAYASAN PENDIDIKAN AVICENNA PRESTASI PT DUTA BANGUN SELARAS
: Kerja mulai jam 08.00 - malam
( SIS EKO WASONO ) ( CECEP MATURIDI )
Pengawas Direktur