SECOND SCHEDULE - PART VI

PART VI

(regulations 65)

COMPETENT PERSONS TO SUBMIT PLANS,


DRAWINGS AND SPECIFICATIONS

Competent Person Prepare and Submit to Voltage/Ampere Limit of


Installation

(a) Wireman with Single Phase Licensee or supply Low voltage single
Restriction authority phase only

(b) Wireman with Three Phase Licensee or supply Low voltage and
Restriction authority receiving electricity from
licensee or supply
authority via a
switchgear rated at 60
amperes and below

(c) Electrical Supervisor Licensee or supply Low voltage and


authority receiving electricity from
licensee or supply
authority via a
switchgear rated at 100
amperes and below

(d) Competent Electrical Licensee or supply Low voltage only


Engineer who is not authority
registered with the Board of
Engineers as a Professional
Engineer

(e) Competent Electrical Any person or authority No limit


Engineer who is registered in Malaysia
with the Board of Engineers
as a Professional Engineer

(f) Competent Electrical Any person or authority No limit


Engineer who is registered in Malaysia
with the Board of Engineers
as a Professional Engineer