MATERIAL REQUEST ALL DEPARTMENT

MR No : 006/BPP-LOG/GA/X/2022
Revisi : 0 Kintap, 11 Oktober 2022

No Description Serial No. Qty Uom Estimasi Harga Total Remarks Pembelian To Unit Status
1 Isi ulang gas LPG 12 Kg 2 Tabung Rp 235.000 Rp 470.000 Kintap Kantin Top Urgent P1
2 Plastik bening 10 Ikat Rp 10.000 Rp 100.000 Kintap Kantin Top Urgent P1
3
4
5
6
7
8
9
10
11
12
13
14
Sub Total Rp 570.000

Note :

Request by, Create by, Approved by,

Zingga Pramana S Muslih M. Syaiful


HRGA Adm Logistik Deputy Project Manager