Professional Documents
Culture Documents
General Confrimation :
Need to visit again or Not as Mass Pro visit follow up? [ Need / No need ]
If need, when is next visit date ? [ ]
If need, write down the reason [ ]
Judge by Judge by
Check Item Status and Problem Contents Countermeasure Due Date PIC Remark High-Low
ADM Supplier
1 (PuD) Note:
Plan & Progressive Status of Preparing Facilities ○ :Finished
△ :modif/Tuning/Repair
(including Die, Jig, C/F, Inspection Tools, Main
× :Not finish yet
machines) ××:Not start yet
- 設備の整備計画と状況 ー :No need
(型、治具、C/F、検具、主要設備含む)
2 (QE)
Preparation/Approvalstatus of PIS, QCPC Note :
<Remark> ○:Already approved
△:Already submitted
*To confirm in advance before confirmation MTG.
(Waiting approval)
*To discuss contents of PIS, QCPC on confirmation ×:Not submit yet
MTG. ー:No need
- 部品検査法、QC工程表の整備/承認状況
A A
Number of returned status:
as of Mass Pro visit Returned Total
Approved PIS 18 18 PIS , QCPC ALREADY COMPLITE AND APPROVED
Approved QCPC 18 18
3 (QE) Note :
Preparation Status of SOP, IN-PROCESS ○:Already displayed
CHECK SHEET △:Finished but not
<Remark> displayed yet in line
×:Not finish yet
*Confirmation at Genba
- SOP、工程内チ ェ ッ ク シ ー ト の現場での整備状況
A A
Target date to complete:
Date
SOP 26-Nov-22
SOP ALREADY COMPLITE AND APPROVED
IN-PROCESS CHECK SHEET 28-Nov-22
4 (DD/PPC) Note :
ECI Implement status
Plan and actual status of ECI Implementation
○:Implement by regular
<Remark> process
*Also, confirmation of Actual parts
A A
△:Implement by temporary
- 設変の織込み計画(状況) ×:Can not implement as ECI
instruction
(PARTS REVIEW/LPVV/TRY/PPMONREN)
A A (Not close yet)
ー:No monren
6 (Each PIC)
ーOPリ ス ト 記載の課題解決状況
(現場改善項目も含む)
REMAIN :
1. ACC PART < 100% 4 ITEM ( SINGLE : 2 ITEM ASSY: 2 ITEM)
2. APPROVAL PALLET STANDARD
Page : 1 / 2
7 (QE) Note :
○:prepared/Approved
×:No prepare yet
Plan and actual status of preparation of sample ー:No need
(color sample, burr sample, tolerance sample, etc)
<Remark>
*Subject is parts that needed limit sample only - -
- 見本の作成/承認計画(状況)
(色見本、ハ ゙ リ 見本、公差/寸法見本etc)
10 Waiting Approval Document Already Finish Sign ADM 15-Dec (LOG) Note :
○:Already approved
△:Already submitted
(Waiting approval)
×:Not submit yet
Preparation and Approval Status of Packing Spec
- 梱包仕様の整備と承認状況 C B
11
Production Capacity
- 生産能力
A A
Mass Pro Trial Result at Bottleneck Process
Part No :
Line Stamping 110T Normal (101,1%) Normal+DOT 3H=85%)
Part Name :
1) Required volume of N-6 7,568 Car sets 3) Can actual cycle time be satisfied with target cycle time. 4) What is the percentage of " OK parts " during trial activity ?
capacity volume. (Actual C/T #1) Avg. Total Production (Actual) 514 Pcs./Hour
7 Sec. OK 514
2)Trial conditions. 7 NG 0
Continuous prod. Time 1 Hrs. (Actual C/T #2) Sec./Pc. OK Ratio 100.0%
Operator ( Temporary / Permanent ) 12 Persons 7 Sec.
Equipment ( Temporary / Permanent ) Target
Die change/ Set-up time 7 Min. (Actual C/T #3) (Planed capacity)
7 Sec. 7
Sec./Pc.
12 Plan and Progressive Status of Operator (QE)
Education/Trainning
<Remark>
*Mainly, confirmation at Genba
*In case of changing points are little, whether need A A
plan for operator education, judgment by QE
- 作業者の教育/訓練計画(状況)
13 (QE) Note :
○:Already displayed
△:Already prepared
(Not display yet)
Parameter setting Chart(Including Check sheet for ×:Not prepare yet
parameter setting) ー:No need
<Remark>
*Mainly, confirmation at Genba
A A
- 設備条件表(設備条件チ ェ ッ ク シ ー ト 含む)
14 (QE)
Actual Status of IN-PROCESS Inspection
<Remark>
*To get sampling inspection conducted at Genba
*To confirm at current production when not A A
completed regular process
- 工程内検査の実施状況
15 (QE)
16
Control Status of Material/PurchasingPart (QE)
Stock Area, W.I.P. Part Stock Area,
finish goods stock area
<Remark>
*Mainly, confirmation at Genba
A A
- 材料/購入部品置き場/中間在庫置き場
/完成品の置き場の管理状況
17 (QE)
Page : 2 / 2