DIAR RAS AL HADD DEVELOPMENT PROJECT – OMAN Annexure 3

Item B - 1 of Annex-3 : Claims by Subcontractors related to Subject Claim,Difference between Adhi Oman & AL-Rawdha Rates

ADHI OMAN Al-Rawdha Amount


AL RAWDHA CONTRACT ADHI OMAN CONTRACT Supplementary Equivalent to Adhi Additional Cost
Section Description
AMOUNT (OMR) AMOUNT (OMR) Agreement AMOUNT Oman Supplementary Excluding Prelims (OMR)
(OMR) Agreement
A B A-B
1 PRELIMINARIES & GENERAL REQUIREMENTS 230,000.00 428,791.32 428,791.32 134,060.17
2 CHEDI HOTEL BUILDING 2,968,689.40 3,118,772.90 3,074,680.12 2,685,763.40 388,916.72
3 CHEDI VILLAS 547,543.90 576,173.66 5,847.85 5,650.29 197.56
4 CHEDI CLUB (SPA & GYM) 307,365.00 332,193.93 0.00 0.00 -
5 CHEDI BEACH CLUB 187,773.20 213,901.91 0.00 0.00 -
6 SPECIALITY RESTAURANT 97,821.20 105,166.29 2,732.15 2,612.91 119.24
7 INFRASTRUCTURE, LANDSCAPING & ANCILLARY BUILDINGS 512,807.30

Total (OMR): 4,852,000.00 4,775,000.00 3,512,051.44 2,828,086.77 389,233.53

Add 4% Contractor Overheads 15,569.34


Total Additional cost incurred to the Contractor due to Hiring Adhi Oman after Al-Rawdha Left 404,802.87