DIAR RAS AL-HADD DEVELOPMENT PROJECT Annexure - 3

Item A - 1.1 of Annex-3 : Claims by Subcontractors related to Subject Claim, Additional Prelims paid to Adhi Oman
ADHI OMAN
ADHI OMAN CONTRACT Supplementary
Bill Description
AMOUNT (OMR) Agreement AMOUNT
(OMR)
1 PRELIMINARIES & GENERAL REQUIREMENTS 428,791.32 428,791.32
2 CHEDI HOTEL BUILDING 3,118,772.90 3,074,680.12
3 CHEDI VILLAS 576,173.66 5,847.85
4 CHEDI CLUB (SPA & GYM) 332,193.93 0.00
5 CHEDI BEACH CLUB 213,901.91 0.00
6 SPECIALITY RESTAURANT 105,166.29 2,732.15
7 INFRASTRUCTURE, LANDSCAPING & ANCILLARY BUILDINGS

Total (OMR): 4,775,000.00 3,512,051.44

Pro-rated Preliminaries according to reduced Scope of Work 304,190.45


Difference, Extra Prelims paid to Adhi Oman & this is Additional
124,600.87
cost to the Contractor

Add 4% for Contractor Overheads 4,984.03


Total Additional cost incurred to the Contractor due to Extra
129,584.90
Prelims paid to Adhi Oman

Item A - 1.2 of Annex-3 : Claims by Subcontractors related to Subject Claim, Additional amounts to be paid to
Adhi Oman for Material
Additional Rate Additional Cost paid to
Item Quantity after Apr-22
(OMR/Unit) Material
Concrete (m3) 16,500 2 33,000.00
Total Steel (tons) 1,705 25 42,625.00
Total 75,625.00

Add 4% for Contractor Overheads 3,025.00


Total Additional cost incurred to the Contractor due to Additional Amounts to be paid
78,650.00
to Adhi Oman for Material