Professional Documents
Culture Documents
• It is designed to assist a project manager in developing a schedule, assigning resources to tasks, tracking progress,
managing the budget, and analyzing workloads.
• Task:
• The day by day Activities are called as Task.
• Relationships
• Sequential
• Finish to Start
• Start to Finish
• Overlapping
• Start to Start
• Finish to Finish
Early Finish(EF)=ES(C)+D-1
Late Finish(LF)=LS(S)-1
Late Start(LS)=LF(C)–D+1
P – Predecessor
S – Successor
C= Current Activity
Critical Path/Flow(CP/CF):
A-B-C-E-F
A-B-D-E-F
As Soon As Possible
As Late As Possible
Finish No earlier then
Start No Earlier than
Must Start On
Must Finish On
Finish No Later then
Start No Later than
• Resources refer to the people involved in the project, the equipment and
materials used, and the costs associated with the project.
• Resources are required to perform project tasks.
• Types:
• Work ( Labor)
• Material ( Non- Labor)
• Machinery
• When it is leveling, Project does not change who is assigned to each task. Project levels only the work
resources, generic resources, and committed resources. It does not level the material resources, cost resources,
or proposed resources.
Once your project plan is ready in MS Project, it becomes essential for a project
manager to measure the actuals (in terms of work completed, resources used and costs
incurred) and to revise and change information about tasks and resources due to any changes
to the plans.
• Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed
on a project beyond the basic review of cost and schedule reports.
• EVA provides a method that permits the project to be measured by progress achieved.
Types Of Report:
Graphical Report
Textual Report