Professional Documents
Culture Documents
2
substandard AC = Actual Cost and SPI), otherwise, this
performance BAC = Budget at completion formula is not likely to be used
continues EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index
To-Complete TCPI = (BAC – EV)/ < 1 Under budget
Performance Index (BAC – AC) = 1 On budget
(TCPI) BAC = Budget at completion > 1 Over budget
EV = Earned value
AC = Actual Cost
TCPI = Remaining Work
/Remaining Funds
BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
Estimate to ETC = EAC -AC
Completion EAC = Estimate at Completion
AC = Actual Cost
Variance at VAC = BAC – EAC < 0 Over budget
Completion BAC = Budget at completion = 0 On budget
EAC = Estimate at Completion > 0 Under budget
PERT Estimation (O + 4M + P)/6
O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate
Standard Deviation (P – O)/6 this is a rough estimate for
O= Optimistic estimate the standard deviation
P= Pessimistic estimate
Float/Slack LS – ES = 0 On critical path
LS = Late start < 0 Behind schedule
ES = Early start
LF – EF
LF = Late finish
EF = Early finish
The above 17 PMP® formulas are all that you’ll need for the PMP® Exam in the latest PMBOK®
Guide edition. Try to learn them and understand their applications by heart and you will be able to
solve the calculation questions in the real PMP® Exam.