DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 10 mm Lx = 4.5 m
Selimut Beton = 25 mm
Lebar Plat = 1000 mm
Ly = 0.1701389 m
Ly = 0.1701388889 0.038
=
Lx 4.5
Interpolasi
a. 1 - 0.038 = 25 - Clx
1 - 1.2 25 - 34
0.9621914 = 25 - Clx
-0.2 -9
Clx = -18.299
b. 1 - 0.038 = 25 - Cly
1 - 1.2 25 - 22
0.9621914 = 25 - Cly
-0.2 3
Cly = 39.433
c. 1 - 0.038 = 51 - Ctx
1 - 1.2 51 - 63
0.9621914 = 51 - Ctx
-0.2 -12
Ctx = -6.731
d. 1 - 0.038 = 51 - Cty
1 - 1.2 51 - 54
0.9621914 = 51 - Cty
-0.2 -3
1 x 0.17013889 ≈ 1 x 0.1701389
15 10
0.0113425926 m ≈ 0.45 m
1 x 0.45 ≈ 2 x 0.45
2 3
0.225 m ≈ 0.300 m
β = ℓn₂
ℓn₁
= -130
4200
β = -0.031
= -130 0.8 +
( ( 0.18 ) )
36 + ( -0.278 )
= -130 ( 0.98 )
35.722
= -127.26389
35.722
= -130 0.8 +
( ( 0.18 ) )
36
= -130 ( 0.98 )
36
= -127.26389
36.00
h max = -3.535 mm = -0.354 cm ≈ -1 cm
Tebal plat yg digunakan = 120 mm ( minimum )
Tinggi Efektif
dx = 120 - 25 - ( 0.5 x 10 )
dx = 90 mm
dy = 120 - 25 - 10 - ( 0.5 x 10 )
dy = 80 mm
PERHITUNGAN PEMBEBANAN
Beban Mati ( qd )
Beban Plat = 2400 x 0.12 = 288 Kg/m²
Beban Plafond = 7 + 11 = 18 Kg/m²
qd = 306 Kg/m²
Beban Hidup ( ql )
Beban air hujan = 50 Kg/m²
Beban guna = 100 Kg/m²
ql = 150 Kg/m²
BebanTerfaktor ( qu )
qu = 1.2 x qd + 1.6 x ql
= 1.2 x 306 + 1.6 x 150
= 367.2 + 240
qu = 607.2 Kg/m²
PERHITUNGAN MOMEN
Rn = Mu
Ø x b x d²
= -827690
0.8 x 1000 x 8100
= -827689.5
6480000
Rn = (0.13) Mpa
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x (0.13) x 11.344538
( ( ) )
11.3445378 270
= 1 1 - 1 - (2.90)
( ( ) )
11.3445378 270
= 1 1 - 1 -
( ( (0.01) ) )
11.3445378
= 1 1 - 1.01
( )
11.3445378
= 1 1 - 1.01
( )
11.3445378
= 0.08814815 ( (0.01) )
ρ = (0.00047)
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 1000 x 90 = 466.66667 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
= 40 x 466.66667 = 186.66667
100 78.5
s = 1000
As perlu / As tulangan
= 1000
466.666667 / 78.5
= 1000
5.945
s = 168.214 mm ≈ 160.000 mm ≈ 16 cm
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
Rn = Mu
Ø x b x d²
= -2249961
0.8 x 1000 x 8100
= -2249960.6
6480000
Rn = (0.35) Mpa
ρb = 0.05167305
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x (0.35) x 11.344538
( ( ) )
11.3445378 270
= 1 1 - 1 - (7.88)
( ( ) )
11.3445378 270
= 1 1 - 1 -
( ( (0.03) ) )
11.3445378
= 1 1 - 1.03
( )
11.3445378
= 1 1 - 1.01
( )
11.3445378
= 0.08814815 ( (0.01) )
ρ = (0.00128)
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 1000 x 90 = 466.66667 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
s = 1000
As perlu / As tulangan
= 1000
466.666667 / 78.5
= 1000
5.945
s = 168.214 mm ≈ 160.000 mm ≈ 16 cm
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
Rn = Mu
Ø x b x d²
= 4496221.1
0.8 x 1000 x 8100
= 4496221.13
6480000
Rn = 0.69 Mpa
ρb = 0.05167305
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.69 x 11.344538
( ( ) )
11.3445378 270
= 1 1 - 1 - 15.74
( ( ) )
11.3445378 270
= 1 1 - 1 -
( ( 0.06 ) )
11.3445378
= 1 1 - 0.94
( )
11.3445378
= 1 1 - 0.97
( )
11.3445378
= 0.08814815 ( 0.03 )
ρ = 0.00261
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 1000 x 90 = 466.66667 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
= 40 x 466.66667 = 186.66667
100 78.5
s = 1000
As perlu / As tulangan
= 1000
466.666667 / 78.5
= 1000
5.945
s = 168.214 mm ≈ 160.000 mm ≈ 16 cm
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
Rn = Mu
Ø x b x d²
= 4848586.9
0.8 x 1000 x 6400
= 4848586.88
5120000
Rn = 0.95 Mpa
ρb = 0.05167305
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.95 x 11.344538
( ( ) )
11.3445378 270
= 1 1 - 1 - 21.49
( ( ) )
11.3445378 270
= 1 1 - 1 -
( ( 0.08 ) )
11.3445378
= 1 1 - 0.92
( )
11.3445378
= 1 1 - 0.96
( )
11.3445378
= 0.08814815 ( 0.04 )
ρ = 0.00358
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 1000 x 80 = 414.81481 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
s = 1000
As perlu / As tulangan
= 1000
414.815 / 78.5
= 1000
5.284
s = 189.241 mm ≈ 180.000 mm ≈ 18 cm
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 10 mm Lx = 4.5 m
Selimut Beton = 25 mm
Lebar Plat = 1000 mm
Ly = 0.170139 m
Ly = 0.1701388889 0.038
=
Lx 4.5
Interpolasi
a. 1 - 0.038 = 25 - Clx
1 - 1.2 25 - 34
0.962191 = 25 - Clx
-0.2 -9
Clx = -18.2986111
b. 1 - 0.038 = 25 - Cly
1 - 1.2 25 - 22
0.962191 = 25 - Cly
-0.2 3
Cly = 39.43287037
c. 1 - 0.038 = 51 - Ctx
1 - 1.2 51 - 63
0.962191 = 51 - Ctx
-0.2 -12
Ctx = -6.73148148
d. 1 - 0.038 = 51 - Cty
1 - 1.2 51 - 54
0.962191 = 51 - Cty
-0.2 -3
Cty = 36.56712963
Hasil Interpolasi
1 0.038 1.2
Clx 25 -18.299 34
Cly 25 39.433 22
Ctx 51 -6.731 63
Cty 51 36.567 54
1 x L ≈ 1 x L
15 10
1 x 0.170138889 ≈ 1 x 0.170139
15 10
0.0113 m ≈ 0.450 m
1 x 0.450 ≈ 2 x 0.450
2 3
0.225 m ≈ 0.30 m
β = ℓn₂
ℓn₁
= -129.86
4200.00
β = -0.03091931
= -129.86 0.8 +
( ( 0.18 ) )
36 + ( -0.278274 )
= -129.86 ( 0.98 )
35.722
= -127.263889
35.722
= -129.86 0.8 +
( ( 0.18 ) )
36
= -129.86 ( 0.98 )
36
= -127.263889
36.00
Tinggi Efektif
dx = 120 - 25 - ( 0.5 x 10 )
dx = 90 mm
dy = 120 - 25 - 10 - ( 0.5 x 10 )
dy = 80 mm
PERHITUNGAN PEMBEBANAN
Beban Mati ( qd )
Beban Plat = 2400 x 0.12 = 288 Kg/m²
Beban Plafond = 7 + 11 = 18 Kg/m²
Beban Penutup Laintai = 3 x 21 = 63 Kg/m²
Beban Spesi = 2 x 24 = 48 Kg/m²
qd = 417 Kg/m²
BebanTerfaktor ( qu )
qu = 1.2 x qd + 1.6 x ql
= 1.2 x 417 + 1.6 x 400
= 500.4 + 640
qu = 1140.4 Kg/m²
PERHITUNGAN MOMEN
Rn = Mu
Ø x b x d²
= -1554508
0.8 x 1000 x 8100
= -1554507.75
6480000
Rn = (0.24) Mpa
ρb = 0.051673052
= 270
0.85 x 28
= 270
23.8
m = 11.34453782
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x (0.24) x 11.34454
( ( ) )
11.34453782 270
= 1 1 - 1 - (5.44)
( ( ) )
11.34453782 270
= 1 1 - 1 -
( ( (0.02) ) )
11.34453782
= 1 1 - 1.02
( )
11.34453782
= 1 1 - 1.01
( )
11.34453782
= 0.088148148 ( (0.01) )
ρ = -0.00088406
Kebutuhan Tulangan
As perlu = ρ x b x d
= -0.00088 x 1000 x 90 = -79.5654 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
= 40 x -79.5654 = -31.82616
100 78.5
s = 1000
As perlu / As tulangan
= 1000
-79.5653997 / 78.5
= 1000
-1.014
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
Rn = Mu
Ø x b x d²
= -4225716.56
0.8 x 1000 x 8100
= -4225716.56
6480000
Rn = (0.65) Mpa
ρb = 0.051673052
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453782
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x (0.65) x 11.34454
( ( ) )
11.34453782 270
= 1 1 - 1 - (14.80)
( ( ) )
11.34453782 270
= 1 1 - 1 -
( ( (0.05) ) )
11.34453782
= 1 1 - 1.05
( )
11.34453782
= 1 1 - 1.03
( )
11.34453782
= 0.088148148 ( (0.03) )
ρ = -0.00238304
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 1000 x 90 = 466.6667 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
s = 1000
As perlu / As tulangan
= 1000
466.6666667 / 78.5
= 1000
5.945
s = 168.214 mm ≈ 160.000 mm ≈ 16 cm
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
Rn = Mu
Ø x b x d²
= 8444483.813 7.5
0.8 x 1000 x 8100
= 8444483.813
6480000
Rn = 1.30 Mpa
ρb = 0.051673052
ρ maks = 0.75 x 0.051673 = 0.038755
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453782
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 1.30 x 11.34454
( ( ) )
11.34453782 270
= 1 1 - 1 - 29.57
( ( ) )
11.34453782 270
= 1 1 - 1 -
( ( 0.11 ) )
11.34453782
= 1 1 - 0.89
( )
11.34453782
= 1 1 - 0.94
( )
11.34453782
= 0.08815 ( 0.06 )
ρ = 0.004966432
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00497 x 1000 x 90 = 447 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
= 40 x 447 = 178.7915
100 78.5
s = 1000
As perlu / As tulangan
= 1000
447 / 78.5
= 1000
6.688
s = 149.522 mm ≈ 140.000 mm ≈ 14 cm
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
Rn = Mu
Ø x b x d²
= 9106272.188
0.8 x 1000 x 6400
= 9106272.188
5120000
Rn = 1.78 Mpa
ρb = 0.051673052
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453782
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 1.78 x 11.34454
( ( ) )
11.34453782 270
= 1 1 - 1 - 40.35
( ( ) )
11.34453782 270
= 1 1 - 1 -
( ( 0.15 ) )
11.34453782
= 1 1 - 0.85
( )
11.34453782
= 1 1 - 0.92
( )
11.34453782
= 0.08815 ( 0.08 )
ρ = 0.00685374
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 1000 x 80 = 414.8148 mm2
Jarak Tulangan
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 100
4
s = 1000
As perlu / As tulangan
= 1000
414.8148148 / 78.5
= 1000
5.284
s = 189.241 mm ≈ 180.000 mm ≈ 18 cm
Kontrol
Luas minimum tulangan yang digunakan untuk menahan susut
As susut = 0.002 x b x h
= 0.002 x 1000 x 120 = 240 mm2 < As perlu (OK)
Metode Amplop
Lx Lx = 4.5 m
Ly
Ly = 0.1701389 m
Sisi Trapesium Sisi Segitiga
1/2 s2 = -2.164931 m
s2 = -4.329861 m
s2
1/2 s2
t 2.25 m
t 2.25 m h/q h
h/q P
P1
P2 h
A B M.max RB
M.max RB RA
RA
2/3 s 1/3 s 1/2 L 2/3 s 1/3 s 1/2 L
s s
L
L
L = 0.1701389 m L = 4.5 m
s = 2.25 m s = 2.25 m
Ra = Rb = -2.339844
`
P1 = 1 x s x t P = 1 x s x t
2 2
P1 = 2.53125 P = 2.53125
P2 = 1/2 s2 x t
= -2.164931 x 2.25
P2 = -4.871094
Perhitungan Momen
Sisi Trapesium
M max 1 = -1.890
M max 2 = 1 x h x L²
8
= 1 x h x 0.0289472
8
M max 2 = 0.0036184 h
M max 1 = M max 2
-1.890 = 0.0036184 h
= ( 5.6953125 ) - ( 1.8984 )
M max 1 = 3.79688
M max 2 = 1 x h x L²
8
1 x h x 20.25
8
M max 2 = 2.53125 h
M max 1 = M max 2
3.797 = 2.53125 h
W1 P1 B1 P2 B1 P1
H1 0.1284722 m
W2 P3 B2 P4 B2 P3
0.1284722 m
H1
L1 L1
ket
4.5 m 4.5 m
h trapesium = -522.41139
Asumsi Tinggi Balok = 0.450 m = 0.5 m Jarak portal /2 = 0.08506944
Aasumsi Lebar Balok = 0.300 m = 0.3 m
Tebal Plat = 120 mm = 0.12 m h segitiga = 1.5 2.375
Jarak portal /2 = 0.08506944
Akibat beban mati
B1 = ( 1.5 + 1.5 ) x 306 = 918 Kg/m
B2 = ( 1.5 + 1.5 ) x 417 = 1251 Kg/m
P2 = ( -522.4114 + -522.4114 ) 306 )( 0.0850694 + 0.0850694 )+( 0.3 x 0.45 ) x ( 2400 ( 0.0850694 + 0.0850694 ) )
= -54340.961 kg
P4 = ( -522.4114 + -522.4114 ) 417 )( 0.0850694 + 0.0850694 )+( 0.3 x 0.45 ) x ( 2400 ( 0.0850694 + 0.0850694 ) )
= -74072.875 kg
Beban Angin
W1 = ( 0.0850694 + 0.0850694 ) x 0.0642361 x 40 kg/m²
= 0.4371624 kg 1.875
1 33.002
2 19.910
3 3.147
4 3.144
5 46.202
Member 3
6 71.458
7 56.365
8 62.656
9 28.806
10 32.845
1 33.002
2 19.910
3 3.144
4 3.147
5 46.202
Member 4
6 71.458
7 62.656
8 56.365
9 32.845
10 28.806
1 24.488
2 11.872
3 0.981
4 0.969
5 34.283
Member 5
6 48.380
7 40.277
8 42.227
9 21.058
10 23.008
1 24.488
2 11.872
3 0.969
4 0.981
5 34.283
Member 6
6 48.380
7 42.227
8 40.277
9 23.008
10 21.058
PERHITUNGAN PERENCANAAN BALOK MEMBER 3
DATA PERENCANAAN
Mu (Momen Terfaktor) = DATA KNm
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Selimut Beton = 30 mm
Tinggi Balok = 0.45 m = 450 mm
Lebar Balok = 0.3 m = 300 mm
Tinggi Efektif (d) = 404 mm
Mu = 36.293 Kn.m
Rn = Mu
Ø x b x d²
= 36293000
0.8 x 300 x 163216
= 36293000
39171840
Rn = 0.92651 Mpa
ρb = 0.0516730523627
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.344537815126
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.92651 x 11.3445378
( ( ) )
11.344537815126 270
= 1 1 - 1 - 21.02
( ( ) )
11.344537815126 270
= 1 1 - 1 -
( ( 0.077858 ) )
11.344537815126
= 1 1 - 0.9221
( )
11.344537815126
= 1 1 - 0.9603
( )
11.344537815126
= 0.0881481481481 ( 0.0397 )
ρ = 0.003501
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 21.215 Kn.m
Rn = Mu
Ø x b x d²
= 21215000
0.8 x 300 x 163216
= 21215000
39171840
Rn = 0.54159 Mpa
ρb = 0.0516730523627
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.344537815126
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.54159 x 11.3445378
( ( ) )
11.344537815126 270
= 1 1 - 1 - 12.29
( ( ) )
11.344537815126 270
= 1 1 - 1 -
( ( 0.045512 ) )
11.344537815126
= 1 1 - 0.9545
( )
11.344537815126
= 1 1 - 0.9770
( )
11.344537815126
= 0.0881481481481 ( 0.0230 )
ρ = 0.00203
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 57.222 Kn.m
Rn = Mu
Ø x b x d²
= 57222000
0.8 x 300 x 163216
= 57222000
39171840
Rn = 1.46079 Mpa
ρb = 0.0516730523627
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.344537815126
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 1.46079 x 11.3445378
( ( ) )
11.344537815126 270
= 1 1 - 1 - 33.14
( ( ) )
11.344537815126 270
= 1 1 - 1 -
( ( 0.122756 ) )
11.344537815126
= 1 1 - 0.8772
( )
11.344537815126
= 1 1 - 0.9366
( )
11.344537815126
= 0.0881481481481 ( 0.0634 )
ρ = 0.005587
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 9.401 Kn.m
Rn = Mu
Ø x b x d²
= 9401000
0.8 x 300 x 163216
= 9401000
39171840
Rn = 0.23999 Mpa
ρb = 0.0516730523627
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.344537815126
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.23999 x 11.3445378
( ( ) )
11.344537815126 270
= 1 1 - 1 - 5.45
( ( ) )
11.344537815126 270
= 1 1 - 1 -
( ( 0.020168 ) )
11.344537815126
= 1 1 - 0.9798
( )
11.344537815126
= 1 1 - 0.9899
( )
11.344537815126
= 0.0881481481481 ( 0.0101 )
ρ = 0.00089
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 4.709 Kn.m
Rn = Mu
Ø x b x d²
= 4709000
0.8 x 300 x 163216
= 4709000
39171840
Rn = 0.12021 Mpa
ρb = 0.0516730523627
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.344537815126
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.12021 x 11.3445378
( ( ) )
11.344537815126 270
= 1 1 - 1 - 2.73
( ( ) )
11.344537815126 270
= 1 1 - 1 -
( ( 0.010102 ) )
11.344537815126
= 1 1 - 0.9899
( )
11.344537815126
= 1 1 - 0.9949
( )
11.344537815126
= 0.0881481481481 ( 0.0051 )
ρ = 0.00045
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Vc = 1 x fc' x ( bw x d )
6
= 1 x 28 x ( 300.0 x 404 )
6
Vs perlu = Vu - Vc
Ø
= 71.458 - 106.888
0.6
Vu > 1 x Ø x Vc
2
Vs = 12.2083 KN
Jarak Sengkang ( s ) = Av x fy x d
Vs
s = 897.78 mm ≈ 800 mm
1 x fc' x ( bw x d )
3
maka, s = 1 x d
2
= 1 x 404
2
s = 202 mm ≈ 200 mm
Menentukan spasi maksimum yang dibutuhkan berdasarkan persyaratan luas penampang tulangan minimum
s = 3 x Av x fy
bw
= 3 x 100.48 x 270
300.0
s = 271.30 mm ≈ 270 mm
Dari tiga jarak sengkang yang dihasilkan di ambil jarak terkecil = 200 mm
PERHITUNGAN PERENCANAAN BALOK MEMBER 4
DATA PERENCANAAN
Mu (Momen Terfaktor) = DATA KNm
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Selimut Beton = 30 mm
Tinggi Balok = 0.45 m = 450 mm
Lebar Balok = 0.3 m = 300 mm
Tinggi Efektif (d) = 404 mm
Mu = 57.222 Kn.m
Rn = Mu
Ø x b x d²
= 57222000
0.8 x 300 x 163216
= 57222000
39171840
Rn = 1.46079 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 1.46079 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 33.14
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.122756 ) )
11.34453781513
= 1 1 - 0.8772
( )
11.34453781513
= 1 1 - 0.9366
( )
11.34453781513
= 0.088148148148 ( 0.0634 )
ρ = 0.005587
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 21.215 Kn.m
Rn = Mu
Ø x b x d²
= 21215000
0.8 x 300 x 163216
= 21215000
39171840
Rn = 0.54159 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.54159 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 12.29
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.045512 ) )
11.34453781513
= 1 1 - 0.9545
( )
11.34453781513
= 1 1 - 0.9770
( )
11.34453781513
= 0.088148148148 ( 0.0230 )
ρ = 0.00203
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 36.293 Kn.m
Rn = Mu
Ø x b x d²
= 36293000
0.8 x 300 x 163216
= 36293000
39171840
Rn = 0.92651 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.92651 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 21.02
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.077858 ) )
11.34453781513
= 1 1 - 0.9221
( )
11.34453781513
= 1 1 - 0.9603
( )
11.34453781513
= 0.088148148148 ( 0.0397 )
ρ = 0.003501
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 21.215 Kn.m
Rn = Mu
Ø x b x d²
= 21215000
0.8 x 300 x 163216
= 21215000
39171840
Rn = 0.54159 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.54159 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 12.29
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.045512 ) )
11.34453781513
= 1 1 - 0.9545
( )
11.34453781513
= 1 1 - 0.9770
( )
11.34453781513
= 0.088148148148 ( 0.0230 )
ρ = 0.00203
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 4.709 Kn.m
Rn = Mu
Ø x b x d²
= 4709000
0.8 x 300 x 163216
= 4709000
39171840
Rn = 0.12021 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.12021 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 2.73
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.010102 ) )
11.34453781513
= 1 1 - 0.9899
( )
11.34453781513
= 1 1 - 0.9949
( )
11.34453781513
= 0.088148148148 ( 0.0051 )
ρ = 0.00045
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Jumlah kaki = 2 bh
Selimut Beton = 30 mm
Tinggi Balok = 450 mm
Lebar Balok (bw) = 300.0 mm
Tinggi Efektif (d) = 404 mm 404 mm
Panjang Balok = 4500 mm
Luas Sengkang (Av) = 100.48 mm²
Vc = 1 x fc' x ( bw x d )
6
= 1 x 28 x ( 300.0 x 404 )
6
Vs perlu = Vu - Vc
Ø
= 71.458 - 106.888
0.6
Vu > 1 x Ø x Vc
2
Vs = 12.2083 KN
Jarak Sengkang ( s ) = Av x fy x d
Vs
s = 897.78 mm ≈ 800 mm
1 x fc' x ( bw x d )
3
maka, s = 1 x d
2
= 1 x 404
2
s = 202 mm ≈ 200 mm
Menentukan spasi maksimum yang dibutuhkan berdasarkan persyaratan luas penampang tulangan minimum
s = 3 x Av x fy
bw
= 3 x 100.48 x 270
300.0
s = 271.30 mm ≈ 270 mm
Dari tiga jarak sengkang yang dihasilkan di ambil jarak terkecil = 200 mm
PERHITUNGAN PERENCANAAN BALOK MEMBER 5
DATA PERENCANAAN
Mu (Momen Terfaktor) = DATA KNm
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Selimut Beton = 30 mm
Tinggi Balok = 0.45 m = 450 mm
Lebar Balok = 0.3 m = 300 mm
Tinggi Efektif (d) = 404 mm
Mu = 19.812 Kn.m
Rn = Mu
Ø x b x d²
= 19812000
0.8 x 300 x 163216
= 19812000
39171840
Rn = 0.50577 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.50577 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 11.48
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.042502 ) )
11.34453781513
= 1 1 - 0.9575
( )
11.34453781513
= 1 1 - 0.9785
( )
11.34453781513
= 0.088148148148 ( 0.0215 )
ρ = 0.001894
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 15.803 Kn.m
Rn = Mu
Ø x b x d²
= 15803000
0.8 x 300 x 163216
= 15803000
39171840
Rn = 0.40343 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.40343 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 9.15
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.033901 ) )
11.34453781513
= 1 1 - 0.9661
( )
11.34453781513
= 1 1 - 0.9829
( )
11.34453781513
= 0.088148148148 ( 0.0171 )
ρ = 0.00151
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 36.897 Kn.m
Rn = Mu
Ø x b x d²
= 36897000
0.8 x 300 x 163216
= 36897000
39171840
Rn = 0.94193 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.94193 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 21.37
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.079153 ) )
11.34453781513
= 1 1 - 0.9208
( )
11.34453781513
= 1 1 - 0.9596
( )
11.34453781513
= 0.088148148148 ( 0.0404 )
ρ = 0.003561
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 7.26 Kn.m
Rn = Mu
Ø x b x d²
= 7260000
0.8 x 300 x 163216
= 7260000
39171840
Rn = 0.18534 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.18534 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 4.21
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.015575 ) )
11.34453781513
= 1 1 - 0.9844
( )
11.34453781513
= 1 1 - 0.9922
( )
11.34453781513
= 0.088148148148 ( 0.0078 )
ρ = 0.00069
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 1.46 Kn.m
Rn = Mu
Ø x b x d²
= 1460000
0.8 x 300 x 163216
= 1460000
39171840
Rn = 0.03727 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.03727 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 0.85
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.003132 ) )
11.34453781513
= 1 1 - 0.9969
( )
11.34453781513
= 1 1 - 0.9984
( )
11.34453781513
= 0.088148148148 ( 0.0016 )
ρ = 0.00014
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Jumlah kaki = 2 bh
Selimut Beton = 30 mm
Tinggi Balok = 450 mm
Lebar Balok (bw) = 300.0 mm
Tinggi Efektif (d) = 404 mm 404 mm
Panjang Balok = 4500 mm
Luas Sengkang (Av) = 100.48 mm²
Vc = 1 x fc' x ( bw x d )
6
= 1 x 28 x ( 300.0 x 404 )
6
Vs perlu = Vu - Vc
Ø
= 48.38 - 106.888
0.6
Vu > 1 x Ø x Vc
2
Vs = -26.2550 KN
Jarak Sengkang ( s ) = Av x fy x d
Vs
s = -417.46 mm ≈ -400 mm
1 x fc' x ( bw x d )
3
maka, s = 1 x d
2
= 1 x 404
2
s = 202 mm ≈ 200 mm
Menentukan spasi maksimum yang dibutuhkan berdasarkan persyaratan luas penampang tulangan minimum
s = 3 x Av x fy
bw
= 3 x 100.48 x 270
300.0
s = 271.30 mm ≈ 270 mm
Dari tiga jarak sengkang yang dihasilkan di ambil jarak terkecil = 200 mm
PERHITUNGAN PERENCANAAN BALOK MEMBER 6
DATA PERENCANAAN
Mu (Momen Terfaktor) = DATA KNm
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Selimut Beton = 30 mm
Tinggi Balok = 0.45 m = 450 mm
Lebar Balok = 0.3 m = 300 mm
Tinggi Efektif (d) = 404 mm
Mu = 36.897 KN.m
Rn = Mu
Ø x b x d²
= 36897000
0.8 x 300 x 163216
= 36897000
39171840
Rn = 0.94193 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.94193 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 21.37
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.079153 ) )
11.34453781513
= 1 1 - 0.9208
( )
11.34453781513
= 1 1 - 0.9596
( )
11.34453781513
= 0.088148148148 ( 0.0404 )
ρ = 0.003561
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 7.26 Kn.m
Rn = Mu
Ø x b x d²
= 7260000
0.8 x 300 x 163216
= 7260000
39171840
Rn = 0.18534 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.18534 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 4.21
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.015575 ) )
11.34453781513
= 1 1 - 0.9844
( )
11.34453781513
= 1 1 - 0.9922
( )
11.34453781513
= 0.088148148148 ( 0.0078 )
ρ = 0.00069
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 19.812 Kn.m
Rn = Mu
Ø x b x d²
= 19812000
0.8 x 300 x 163216
= 19812000
39171840
Rn = 0.50577 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.50577 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 11.48
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.042502 ) )
11.34453781513
= 1 1 - 0.9575
( )
11.34453781513
= 1 1 - 0.9785
( )
11.34453781513
= 0.088148148148 ( 0.0215 )
ρ = 0.001894
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 15.803 Kn.m
Rn = Mu
Ø x b x d²
= 15803000
0.8 x 300 x 163216
= 15803000
39171840
Rn = 0.40343 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.40343 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 9.15
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.033901 ) )
11.34453781513
= 1 1 - 0.9661
( )
11.34453781513
= 1 1 - 0.9829
( )
11.34453781513
= 0.088148148148 ( 0.0171 )
ρ = 0.00151
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
Mu = 1.46 Kn.m
Rn = Mu
Ø x b x d²
= 1460000
0.8 x 300 x 163216
= 1460000
39171840
Rn = 0.03727 Mpa
ρb = 0.051673052363
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453781513
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.03727 x 11.3445378
( ( ) )
11.34453781513 270
= 1 1 - 1 - 0.85
( ( ) )
11.34453781513 270
= 1 1 - 1 -
( ( 0.003132 ) )
11.34453781513
= 1 1 - 0.9969
( )
11.34453781513
= 1 1 - 0.9984
( )
11.34453781513
= 0.088148148148 ( 0.0016 )
ρ = 0.00014
Syarat : ρ min < ρ < ρ max
Jika ρ < ρmin maka digunakan ρmin, Jika ρ > ρ max maka ketebalan plat harus ditinjau ulang
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 300 x 404 = 628.444444 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
= 300 - 60 - 16 - 4.00 x 16
4.00 - 1
s = 160
3.00
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Jumlah kaki = 2 bh
Selimut Beton = 30 mm
Tinggi Balok = 450 mm
Lebar Balok (bw) = 300.0 mm
Tinggi Efektif (d) = 404 mm 404 mm
Panjang Balok = 4500 mm
Luas Sengkang (Av) = 100.48 mm²
Vc = 1 x fc' x ( bw x d )
6
= 1 x 28 x ( 300.0 x 404 )
6
Vs perlu = Vu - Vc
Ø
= 48.38 - 106.888
0.6
Vu > 1 x Ø x Vc
2
Vs = -26.2550 KN
Jarak Sengkang ( s ) = Av x fy x d
Vs
s = -417.46 mm ≈ -400 mm
1 x fc' x ( bw x d )
3
maka, s = 1 x d
2
= 1 x 404
2
s = 202 mm ≈ 200 mm
Menentukan spasi maksimum yang dibutuhkan berdasarkan persyaratan luas penampang tulangan minimum
s = 3 x Av x fy
bw
= 3 x 100.48 x 270
300.0
s = 271.30 mm ≈ 270 mm
Dari tiga jarak sengkang yang dihasilkan di ambil jarak terkecil = 200 mm
PERHITUNGAN PERENCANAAN BALOK T MEMBER - 3
DATA PERENCANAAN
Mutu beton ( fc' ) = 28 Mpa Lebar flens efektif ( b ) :
Mutu baja ( fy ) = 270 Mpa 1/4 Panjang bentang = 1125 mm
Øtulangan = 16 mm bw + 16hf = 2220 mm
Øsengkang = 8 mm jarak antar balok = 170.13889 mm
Selimut Beton = 30 mm Diambil yang terkecil = 1125 mm
Tinggi balok ( h ) = 450 mm
Lebar Balok ( bw ) = 300 mm
Panjang bentang = 4500 mm
Jarak antar balok = 170.138889 mm
Tebal plat ( hf ) = 120 mm
Tinggi Efektif ( d ) = 404 mm
Syarat : MR > Mu Maka balok T berperilaku sebagai balok persegi dengan lebar efektif
MR < Mu Maka balok T berperilaku sebagai balok T murni
Mu = 33.616 KNm
MR = Ø ( 0.85 x fc ) b x hf ( d - bf )
2
Mu = 33.616 KNm
Rn = Mu
Ø x b x d²
= 33616000
0.8 x 1125 x 163216
= 33616000
146894400
Rn = 0.22884 Mpa
ρb = 0.05167305
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 ( 1 - 1 - ( 2 x Rn x m )
)
m fy
= 1 ( 1 - 1 - ( 2 x 0.22884 x 11.344538 )
)
11.3445378 270
= 1 ( 1 - 1 - ( 5.19 )
)
11.3445378 270
= 1 ( 1 - 1 - ( 0.0192 )
)
11.3445378
= 1 ( 1 - 0.9808 )
11.3445378
= 1 ( 1 - 0.9903 )
11.3445378
= 0.08814815 ( 0.0097 )
ρ = 0.00085
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00085 x 1125 x 404 = 387.0919 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
As(aktual) = 1 x 3.14 x d² x n
4
= 1 x 3.14 x 256 x 2
4
ρaktual = As(aktual)
bw x d
= 401.92
300.0 x 404
= 5.1 x ( 1397.67 )
DATA PERENCANAAN
Mutu beton ( fc' ) = 28 Mpa Lebar flens efektif ( b ) :
Mutu baja ( fy ) = 270 Mpa 1/4 Panjang bentang = 1125 mm
Øtulangan = 16 mm bw + 16hf = 2220 mm
Øsengkang = 8 mm jarak antar balok = 170.13889 mm
Selimut Beton = 30 mm Diambil yang terkecil = 1125 mm
Tinggi balok ( h ) = 450 mm
Lebar Balok ( bw ) = 300 mm
Panjang bentang = 4500 mm
Jarak antar balok = 170.138889 mm
Tebal plat ( hf ) = 120 mm
Tinggi Efektif ( d ) = 404 mm
Syarat : MR > Mu Maka balok T berperilaku sebagai balok persegi dengan lebar efektif
MR < Mu Maka balok T berperilaku sebagai balok T murni
Mu = 33.616 KNm
MR = Ø ( 0.85 x fc ) b x hf ( d - bf )
2
Mu = 33.616 KNm
Rn = Mu
Ø x b x d²
= 33616000
0.8 x 1125 x 163216
= 33616000
146894400
Rn = 0.22884 Mpa
ρb = 0.05167305
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 ( 1 - 1 - ( 2 x Rn x m )
)
m fy
= 1 ( 1 - 1 - ( 2 x 0.22884 x 11.344538 )
)
11.3445378 270
= 1 ( 1 - 1 - ( 5.19 )
)
11.3445378 270
= 1 ( 1 - 1 - ( 0.0192 )
)
11.3445378
= 1 ( 1 - 0.9808 )
11.3445378
= 1 ( 1 - 0.9903 )
11.3445378
= 0.08814815 ( 0.0097 )
ρ = 0.00085
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00085 x 1125 x 404 = 387.0919 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
As(aktual) = 1 x 3.14 x d² x n
4
= 1 x 3.14 x 256 x 2
4
ρaktual = As(aktual)
bw x d
= 401.92
300.0 x 404
= 5.1 x ( 1397.67 )
DATA PERENCANAAN
Mutu beton ( fc' ) = 28 Mpa Lebar flens efektif ( b ) :
Mutu baja ( fy ) = 270 Mpa 1/4 Panjang bentang = 1125 mm
Øtulangan = 16 mm bw + 16hf = 2220 mm
Øsengkang = 8 mm jarak antar balok = 170.13889 mm
Selimut Beton = 30 mm Diambil yang terkecil = 1125 mm
Tinggi balok ( h ) = 450 mm
Lebar Balok ( bw ) = 300 mm
Panjang bentang = 4500 mm
Jarak antar balok = 170.1388889 mm
Tebal plat ( hf ) = 120 mm
Tinggi Efektif ( d ) = 404 mm
Syarat : MR > Mu Maka balok T berperilaku sebagai balok persegi dengan lebar efektif
MR < Mu Maka balok T berperilaku sebagai balok T murni
Mu = 24.826 KNm
MR = Ø ( 0.85 x fc ) b x hf ( d - bf )
2
Mu = 24.826 KNm
Rn = Mu
Ø x b x d²
= 24826000
0.8 x 1125 x 163216
= 24826000
146894400
Rn = 0.16901 Mpa
ρb = 0.051673052
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453782
ρ = 1 ( 1 - 1 - ( 2 x Rn x m )
)
m fy
= 1 ( 1 - 1 - ( 2 x 0.16901 x 11.344538 )
)
11.34453782 270
= 1 ( 1 - 1 - ( 3.83 )
)
11.34453782 270
= 1 ( 1 - 1 - ( 0.0142 )
)
11.34453782
= 1 ( 1 - 0.9858 )
11.34453782
= 1 ( 1 - 0.9929 )
11.34453782
= 0.088148148 ( 0.0071 )
ρ = 0.00063
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00063 x 1125 x 404 = 285.51037 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
As(aktual) = 1 x 3.14 x d² x n
4
= 1 x 3.14 x 256 x 2
4
ρaktual = As(aktual)
bw x d
= 401.92
300.0 x 404
= 5.1 x ( 1397.67 )
DATA PERENCANAAN
Mutu beton ( fc' ) = 28 Mpa Lebar flens efektif ( b ) :
Mutu baja ( fy ) = 270 Mpa 1/4 Panjang bentang = 1125 mm
Øtulangan = 16 mm bw + 16hf = 2220 mm
Øsengkang = 8 mm jarak antar balok = 170.13889 mm
Selimut Beton = 30 mm Diambil yang terkecil = 1125 mm
Tinggi balok ( h ) = 450 mm
Lebar Balok ( bw ) = 300 mm
Panjang bentang = 4500 mm
Jarak antar balok = 170.138889 mm
Tebal plat ( hf ) = 120 mm
Tinggi Efektif ( d ) = 404 mm
Syarat : MR > Mu Maka balok T berperilaku sebagai balok persegi dengan lebar efektif
MR < Mu Maka balok T berperilaku sebagai balok T murni
Mu = 24.826 KNm
MR = Ø ( 0.85 x fc ) b x hf ( d - bf )
2
Mu = 24.826 KNm
Rn = Mu
Ø x b x d²
= 24826000
0.8 x 1125 x 163216
= 24826000
146894400
Rn = 0.16901 Mpa
ρb = 0.05167305
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 ( 1 - 1 - ( 2 x Rn x m )
)
m fy
= 1 ( 1 - 1 - ( 2 x 0.16901 x 11.344538 )
)
11.3445378 270
= 1 ( 1 - 1 - ( 3.83 )
)
11.3445378 270
= 1 ( 1 - 1 - ( 0.0142 )
)
11.3445378
= 1 ( 1 - 0.9858 )
11.3445378
= 1 ( 1 - 0.9929 )
11.3445378
= 0.08814815 ( 0.0071 )
ρ = 0.00063
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00063 x 1125 x 404 = 285.51037 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
As(aktual) = 1 x 3.14 x d² x n
4
= 1 x 3.14 x 256 x 2
4
ρaktual = As(aktual)
bw x d
= 401.92
300.0 x 404
= 5.1 x ( 1397.67 )
AXIAL MOMEN
Beam L/C Node
Pu Mu
Fx (Kn) Mz (kNm)
10 1 BEBAN MATI 4 1.398 0.027
7 1.398 0.061
2 BEBAN HIDUP 4 0.598 0.016
7 0.598 0.037
3 BEBAN ANGIN KIRI 4 0.041 0.071
7 0.041 0.070
4 BEBAN ANGIN KANAN 4 0.041 0.071
7 0.041 0.070
5 COMBINATION LOAD CASE 5 4 1.957 0.038
7 1.957 0.086
6 COMBINATION LOAD CASE 6 4 2.634 0.059
7 2.634 0.133
7 COMBINATION LOAD CASE 7 4 2.317 0.120
7 2.317 0.180
8 COMBINATION LOAD CASE 8 4 2.235 0.022
7 2.235 0.040
9 COMBINATION LOAD CASE 9 4 1.299 0.096
7 1.299 0.125
10 COMBINATION LOAD CASE 10 4 1.217 0.047
7 1.217 0.015
11 1 BEBAN MATI 5 2.645 0.000
8 2.645 0.000
2 BEBAN HIDUP 5 1.287 0.000
8 1.287 0.000
3 BEBAN ANGIN KIRI 5 0.000 0.094
8 0.000 0.095
4 BEBAN ANGIN KANAN 5 0.000 0.094
8 0.000 0.095
5 COMBINATION LOAD CASE 5 5 3.703 0.000
8 3.703 0.000
6 COMBINATION LOAD CASE 6 5 5.233 0.000
8 5.233 0.000
7 COMBINATION LOAD CASE 7 5 4.461 0.094
8 4.461 0.095
8 COMBINATION LOAD CASE 8 5 4.461 0.094
8 4.461 0.095
9 COMBINATION LOAD CASE 9 5 2.380 0.094
8 2.380 0.095
10 COMBINATION LOAD CASE 10 5 2.380 0.094
8 2.380 0.095
12 1 BEBAN MATI 6 1.398 0.027
9 1.398 0.061
2 BEBAN HIDUP 6 0.598 0.016
9 0.598 0.037
3 BEBAN ANGIN KIRI 6 0.041 0.071
9 0.041 0.070
4 BEBAN ANGIN KANAN 6 0.041 0.071
9 0.041 0.070
5 COMBINATION LOAD CASE 5 6 1.957 0.038
9 1.957 0.086
6 COMBINATION LOAD CASE 6 6 2.634 0.059
9 2.634 0.133
7 COMBINATION LOAD CASE 7 6 2.235 0.022
9 2.235 0.040
8 COMBINATION LOAD CASE 8 6 2.317 0.120
9 2.317 0.180
9 COMBINATION LOAD CASE 9 6 1.217 0.047
9 1.217 0.015
10 COMBINATION LOAD CASE 10 6 1.299 0.096
9 1.299 0.125
13 1 BEBAN MATI 7 0.615 0.095
10 0.615 0.097
2 BEBAN HIDUP 7 0.225 0.054
10 0.225 0.051
3 BEBAN ANGIN KIRI 7 0.010 0.015
10 0.010 0.026
4 BEBAN ANGIN KANAN 7 0.010 0.014
10 0.010 0.026
5 COMBINATION LOAD CASE 5 7 0.860 0.133
10 0.860 0.136
6 COMBINATION LOAD CASE 6 7 1.097 0.200
10 1.097 0.198
7 COMBINATION LOAD CASE 7 7 0.972 0.183
10 0.972 0.194
8 COMBINATION LOAD CASE 8 7 0.952 0.154
10 0.952 0.142
9 COMBINATION LOAD CASE 9 7 0.563 0.100
10 0.563 0.114
10 COMBINATION LOAD CASE 10 7 0.543 0.071
10 0.543 0.062
14 1 BEBAN MATI 8 1.147 0.000
11 1.147 0.000
2 BEBAN HIDUP 8 0.482 0.000
11 0.482 0.000
3 BEBAN ANGIN KIRI 8 0.000 0.035
11 0.000 0.041
4 BEBAN ANGIN KANAN 8 0.000 0.035
11 0.000 0.041
5 COMBINATION LOAD CASE 5 8 1.606 0.000
11 1.606 0.000
6 COMBINATION LOAD CASE 6 8 2.147 0.000
11 2.147 0.000
7 COMBINATION LOAD CASE 7 8 1.858 0.035
11 1.858 0.041
8 COMBINATION LOAD CASE 8 8 1.858 0.035
11 1.858 0.041
9 COMBINATION LOAD CASE 9 8 1.032 0.035
11 1.032 0.041
10 COMBINATION LOAD CASE 10 8 1.032 0.035
11 1.032 0.041
15 1 BEBAN MATI 9 0.615 0.095
12 0.615 0.097
2 BEBAN HIDUP 9 0.225 0.054
12 0.225 0.051
3 BEBAN ANGIN KIRI 9 0.010 0.014
12 0.010 0.026
4 BEBAN ANGIN KANAN 9 0.010 0.015
12 0.010 0.026
5 COMBINATION LOAD CASE 5 9 0.860 0.133
12 0.860 0.136
6 COMBINATION LOAD CASE 6 9 1.097 0.200
12 1.097 0.198
7 COMBINATION LOAD CASE 7 9 0.952 0.154
12 0.952 0.142
8 COMBINATION LOAD CASE 8 9 0.972 0.183
12 0.972 0.194
9 COMBINATION LOAD CASE 9 9 0.543 0.071
12 0.543 0.062
10 COMBINATION LOAD CASE 10 9 0.563 0.100
12 0.563 0.114
DATA PERANCANGAN KOLOM
Dimensi Penampang Kolom
Tinggi kolom = 0.35
lebar kolom = 0.35
PERHITUNGAN NILAI K PADA KOLOM 10 DAN 12
DATA PERENCANAAN
Tinggi Kolom (h) = 0.35 m = 35 cm
Lebar Kolom (b) = 0.35 m = 35 cm
Tinggi Balok (h) = 0.45 m = 45 cm
Lebar Balok (b) = 0.30 m = 30 cm
0.128472
13 14 15 H1
10 11 12 H1 0.128472
D 0.04375
L1 L1
4.5 4.5
35 1
I KOLOM = x b x hᶟ
35 12
1
= x 35 x 35
12
= 0.083 x 35 x 42875
= 125052 cm⁴
30 1
I BALOK = x b x hᶟ
45 12
1
= x 30 x 45
12
= 0.083 x 30 x 91125
= 227812.5 cm⁴
125052 125052.083333333
+
ᴪ Atas 12.84722 12.8472222222222
=
227812.5
450
19467.568
=
506.250
= 38.454
125052 125052.083333333
+
ᴪ Bawah 4.375 12.8472222222222
=
227812.5
450
38317
=
506.250
= 75.688
K = 1.5
PERHITUNGAN NILAI K PADA KOLOM 11
DATA PERENCANAAN
Tinggi Kolom (h) = 0.35 m = 35 cm
Lebar Kolom (b) = 0.35 m = 35 cm
Tinggi Balok (h) = 0.45 m = 45 cm
Lebar Balok (b) = 0.30 m = 30 cm
H1 0.128472
13 14 15
10 11 12 H1 0.128472
D 0.04375
L1 L1
4.5 4.5
35 1
I KOLOM = x b x hᶟ
35 12
1
= x 35 x 35
12
= 0.083 x 30 x 42875
= 107188 cm⁴
30 1
I BALOK = x b x hᶟ
45 12
1
= x 30 x 45
12
= 0.083 x 30 x 91125
= 227812.5 cm⁴
ᴪ Atas =
∑(EI/ℓk) Kolom
∑(EI/ℓk) Balok
107187.5 107187.5
+
ᴪ Atas =
12.84722 12.8472222222222
227812.5 227812.5
+
450 450
16686.486
=
1012.500
= 16.480
ᴪ Bawah =
∑(EI/ℓk) Kolom
∑(EI/ℓk) Balok
107187.5 107187.5
+
ᴪ Bawah =
4.375 12.8472222222222
227812.5 227812.500
+
450 450
32843
=
1012.500
= 32.438
K = 1.25
PERHITUNGAN NILAI K PADA KOLOM 13 DAN 15
DATA PERENCANAAN
Tinggi Kolom (h) = 0.35 m = 35 cm
Lebar Kolom (b) = 0.35 m = 35 cm
Tinggi Balok (h) = 0.45 m = 45 cm
Lebar Balok (b) = 0.30 m = 30 cm
13 14 15 H1 0.128472
10 11 12 H1 0.128472
D
0.04375
L1 L1
4.5 4.5
35 1
I KOLOM = x b x hᶟ
35 12
1
= x 35 x 35
12
= 0.0833333333 x 30 x 42875
= 107188 cm⁴
30 1
I BALOK = x b x hᶟ
45 12
1
= x 30 x 45
12
= 0.083 x 30 x 91125
= 227812.5 cm⁴
ᴪ Atas =
∑(EI/ℓk) Kolom
∑(EI/ℓk) Balok
107187.5
ᴪ Atas =
12.847222222
227812.5
450
8343.243
=
506.250
= 16.480
ᴪ Bawah =
∑(EI/ℓk) Kolom
∑(EI/ℓk) Balok
107187.5 107187.5
+
ᴪ Bawah =
12.84722 12.8472222222222
227812.5
450
16686
=
506.250
= 32.961
K = 1.17
PERHITUNGAN NILAI K PADA KOLOM 14
DATA PERENCANAAN
Tinggi Kolom (h) = 0.35 m = 35 cm
Lebar Kolom (b) = 0.35 m = 35 cm
Tinggi Balok (h) = 0.45 m = 45 cm
Lebar Balok (b) = 0.30 m = 30 cm
H1 0.128472
13 14 15
10 11 12 H1 0.128472
D 0.04375
L1 L1
4.5 4.5
35 1
I KOLOM = x b x hᶟ
35 12
1
= x 35 x 35
12
= 0.083333 x 30 x 42875
= 107188 cm⁴
30 1
I BALOK = x b x hᶟ
45 12
1
= x 30 x 45
12
= 0.083 x 30 x 91125
= 227812.5 cm⁴
ᴪ Atas =
∑(EI/ℓk) Kolom
∑(EI/ℓk) Balok
107188
ᴪ Atas =
12.84722
227812.5 227812.500
+
450 450
8343.243
=
1012.500
= 8.240
ᴪ Bawah =
∑(EI/ℓk) Kolom
∑(EI/ℓk) Balok
107187.5 107187.5
+
ᴪ Bawah =
12.84722 12.8472222222222
227812.5 227812.500
+
450 450
16686
=
1012.500
= 16.480
K = 1.07
PERHITUNGAN KOLOM LANGSING MEMBER 10
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Lebar Kolom 1 = 0.35 m = 350 mm
Lebar Kolom 2 (h) = 0.35 m = 350 mm
ℓu = 0.128472 m
Pu = 2.634
Momen Max Beban Mati = 0.061
Momen Max Bebn Kombinasi = 0.180
K = 1.5
r = 0.3 x h
= 0.3 x 350
= 105 mm
1
Ig = x h⁴
12
1 ⁴
= x 350
12
= 0.083 x 15006250000
= 1250520833.3 mm⁴
Ec = 4700 x fc'
= 4700 x 28
= 4700 x 5.292
= 24870.062324
0.061
=
0.180
= 0.340
EI Ec x Ig
=
2.5 (1 + βd)
24870.0623240072 x 1250520833.33333
=
2.5 ( 1 + 0.340 )
31100531062469
=
2.5 ( 1.340 )
31100531062469
=
3.349
= 9286.247 kNm²
Pc = π² x EI
( k x ℓu )
= 3.14 ² x 9286.247
( 1.5 x 0.128472 )²
= 9.8596 x 9286.247
( 1.5 x 0.128472 )²
= 91558.6802274554
( 0.192708 )²
= 91558.6802274554
0.0371365017361111
= 2465463.249 kN
Cm = 0.6 + 0.4
( M1b
M2b ) > 0.4
= 0.6 + 0.4
( 0.059
0.133 ) > 0.4
δb = Cm
1 - ( θ
Pu
x Pc )
= 0.777
1 - ( 0.65
3
x 2465463 )
= 0.777
1 - 0.000
= 0.7769
1.000
= 0.777 > 1
Mc = δb x M2b
= 0.777 x 0.133
= 0.103 kNm
PERHITUNGAN KOLOM LANGSING MEMBER 11
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Lebar Kolom 1 = 0.35 m = 350 mm
Lebar Kolom 2 (h) = 0.35 m = 350 mm
ℓu = 0.128472 m
Pu = 5.233
Momen Max Beban Mati = 0.000
Momen Max Bebn Kombinasi = 0.095
K = 1.25
r = 0.3 x h
= 0.3 x 350
= 105 mm
1
Ig = x h⁴
12
1 ⁴
= x 350
12
= 0.083 x 15006250000
= 1250520833.3 mm⁴
Ec = 4700 x fc'
= 4700 x 28
= 4700 x 5.292
= 24870.062324
0.000
=
0.095
= 0.000
EI Ec x Ig
=
2.5 (1 + βd)
24870.0623240072 x 1250520833.33333
=
2.5 ( 1 + 0.000 )
31100531062469
=
2.5 ( 1.000 )
31100531062469
=
2.500
= 12440.212 kNm²
Pc = π² x EI
( k x ℓu )
= 3.14 ² x 12440.212
( 1.25 x 0.128472 )²
= 9.8596 x 12440.212
( 1.25 x 0.128472 )²
= 122655.518425409
( 0.16059 )²
= 122655.518425409
0.0257892373167438
= 4756073.897 kN
Cm = 0.6 + 0.4
( M1b
M2b ) > 0.4
= 0.6 + 0.4
( 0.000
0.000 ) > 0.4
δb = Cm
1 - ( θ
Pu
x Pc )
= 1.000
1 - ( 0.65 x
5
### )
= 1.000
1 - 0.000
= 1.0000
1.000
= 1.000 > 1
Mc = δb x M2b
= 1.000 x 0.095
= 0.095 kNm
PERHITUNGAN KOLOM LANGSING MEMBER 12
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Lebar Kolom 1 = 0.35 m = 350 mm
Lebar Kolom 2 (h) = 0.35 m = 350 mm
ℓu = 0.128472 m
Pu = 2.634
Momen Max Beban Mati = 0.061
Momen Max Bebn Kombinasi = 0.180
K = 1.5
r = 0.3 x h
= 0.3 x 350
= 105 mm
1
Ig = x h⁴
12
1 ⁴
= x 350
12
= 0.083 x 15006250000
= 1250520833.3 mm⁴
Ec = 4700 x fc'
= 4700 x 28
= 4700 x 5.292
= 24870.062324
0.061
=
0.180
= 0.340
EI Ec x Ig
=
2.5 (1 + βd)
24870.0623240072 x 1250520833.33333
=
2.5 ( 1 + 0.340 )
31100531062469
=
2.5 ( 1.340 )
31100531062469
=
3.349
= 9286.247 kNm²
Pc = π² x EI
( k x ℓu )
= 3.14 ² x 9286.247
( 1.5 x 0.128472 )²
= 9.8596 x 9286.247
( 1.5 x 0.128472 )²
= 91558.6802274554
( 0.192708 )²
= 91558.6802274554
0.0371365017361111
= 2465463.249 kN
Cm = 0.6 + 0.4
( M1b
M2b ) > 0.4
= 0.6 + 0.4
( 0.059
0.133 ) > 0.4
δb = Cm
1 - ( θ
Pu
x Pc )
= 0.777
1 - ( 0.65
2.63
x 2465463.2 )
= 0.777
1 - 0.000
= 0.777
1.000
= 0.8 > 1
Mc = δb x M 2b
= 0.777 x 0.133
= 0.103 kNm
PERHITUNGAN KOLOM LANGSING MEMBER 13
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Lebar Kolom 1 = 0.35 m = 350 mm
Lebar Kolom 2 (h) = 0.35 m = 350 mm
ℓu = 0.128472 m
Pu = 1.097
Momen Max Beban Mati = 0.097
Momen Max Bebn Kombinasi = 0.200
K = 1.17
r = 0.3 x h
= 0.3 x 350
= 105 mm
1
Ig = x h⁴
12
1 ⁴
= x 350
12
= 0.083 x 15006250000
= 1250520833.3 mm⁴
Ec = 4700 x fc'
= 4700 x 28
= 4700 x 5.292
= 24870.062324
0.097
=
0.200
= 0.485
EI Ec x Ig
=
2.5 (1 + βd)
24870.0623240072 x 1250520833.33333
=
2.5 ( 1 + 0.485 )
31100531062469
=
2.5 ( 1.485 )
31100531062469
=
3.713
= 8375.448 kNm²
Pc = π² x EI
( k x ℓu )
= 3.14 ² x 8375.448
( 1.17 x 0.128472 )²
= 9.8596 x 8375.448
( 1.17 x 0.128472 )²
= 82578.5648676162
( 0.150313 )²
= 82578.5648676162
0.02259384765625
= 3654913.768 kN
Cm = 0.6 + 0.4
( M1b
M2b ) > 0.4
= 0.6 + 0.4
( 0.200
0.198 ) > 0.4
δb = Cm
1 - ( θ
Pu
x Pc )
= 1.004
1 - ( 0.65 x
1
3654914 )
= 1.004
1 - 0.000
= 1.0043
1.000
= 1.004 > 1
Mc = δb x M2b
= 1.004 x 0.198
= 0.199 kNm
PERHITUNGAN KOLOM LANGSING MEMBER 14
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Lebar Kolom 1 = 0.35 m = 350 mm
Lebar Kolom 2 (h) = 0.35 m = 350 mm
ℓu = 0.128472 m
Pu = 2.147
Momen Max Beban Mati = 0.000
Momen Max Bebn Kombinasi = 0.041
K = 1.07
r = 0.3 x h
= 0.3 x 350
= 105 mm
1
Ig = x h⁴
12
1 ⁴
= x 350
12
= 0.083 x 15006250000
= 1250520833.3 mm⁴
Ec = 4700 x fc'
= 4700 x 28
= 4700 x 5.292
= 24870.062324
0.000
=
0.041
= 0.000
EI Ec x Ig
=
2.5 (1 + βd)
24870.0623240072 x 1250520833.33333
=
2.5 ( 1 + 0.000 )
31100531062469
=
2.5 ( 1.000 )
31100531062469
=
2.500
= 12440.212 kNm²
Pc = π² x EI
( k x ℓu )
= 3.14 ² x 12440.212
( 1.07 x 0.128472 )²
= 9.8596 x 12440.212
( 1.07 x 0.128472 )²
= 122655.518425409
( 0.137465 )²
= 122655.518425409
0.0188967025945216
= 6490842.400 kN
Cm = 0.6 + 0.4
( M1b
M2b ) > 0.4
= 0.6 + 0.4
( 0.000
0.000 ) > 0.4
δb = Cm
1 - ( θ
Pu
x Pc )
= 1.000
1 - ( 0.65 x
2
6490842.4 )
= 1.000
1 - 0.000
= 1.0000
1.000
= 1.00 > 1
Mc = δb x M 2b
= 1.000 x 0.041
= 0.041 kNm
PERHITUNGAN KOLOM LANGSING MEMBER 15
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Lebar Kolom 1 = 0.35 m = 350 mm
Lebar Kolom 2 (h) = 0.35 m = 350 mm
ℓu = 0.128472 m
Pu = 1.097
Momen Max Beban Mati = 0.097
Momen Max Bebn Kombinasi = 0.200
K = 1.17
r = 0.3 x h
= 0.3 x 350
= 105 mm
1
Ig = x h⁴
12
1 ⁴
= x 350
12
= 0.083 x 15006250000
= 1250520833.3 mm⁴
Ec = 4700 x fc'
= 4700 x 28
= 4700 x 5.292
= 24870.062324
0.097
=
0.200
= 0.485
EI Ec x Ig
=
2.5 (1 + βd)
24870.0623240072 x 1250520833.33333
=
2.5 ( 1 + 0.485 )
31100531062469
=
2.5 ( 1.485 )
31100531062469
=
3.713
= 8375.448 kNm²
Pc = π² x EI
( k x ℓu )
= 3.14 ² x 8375.448
( 1.17 x 0.128472 )²
= 9.8596 x 8375.448
( 1.17 x 0.128472 )²
= 82578.5648676162
( 0.150313 )²
= 82578.5648676162
0.02259384765625
= 3654913.768 kN
Cm = 0.6 + 0.4
( M1b
M2b ) > 0.4
= 0.6 + 0.4
( 0.200
0.198 ) > 0.4
δb = Cm
1 - ( θ
Pu
x Pc )
= 1.004
1 - ( 0.65
1.0969
x 3654914 )
= 1.004
1 - 0.000
= 1.0043
1.000
= 1.004 > 1
Mc = δb x M2b
= 1.004 x 0.198
= 0.199 kNm
Tabel Momen (Mu) Setelah Dihitung Faktor Kelangsingannya
AXIAL MOMEN
MEMBER
Pu (kN) Mu (kNm)
10 2.634 0.103
11 5.233 0.095
12 2.634 0.103
13 1.097 0.199
14 2.147 0.041
15 1.097 0.199
13 14 15
10 11 12
PERHITUNGAN KOLOM MEMBER 10
DATA PERENCANAAN
Mutu Beton ( fc' ) = 28 Mpa
Mutu Baja ( fy ) = 270 Mpa
Rasio Penulangan = 1%
Ø Tulangan = 16 mm
Ø Sengkang = 8 mm
Selimut Beton = 30 mm
Lebar Kolom 1 (b) = 350 mm
Lebar Kolom 2 (h) = 350 mm
= (( -8 - ( 8 )) + 320 )
= 304 mm
Tinggi (d')
= b - d
= 350 - 304
= 46 mm
Mu = 0.103 kNm
Pu = 2.634 kN
e = Mu
Pu
= 103.100169489343
2.63448
= 39.135 mm
Menentukan Penulangan
AS = As' = ρ x b x d
2
= 1% x 350 x 304
2
= 532 mm²
= 1 x 3.14 x 16 ² x 3
4
= 1 x 3.14 x 256 x 3
4
= 602.88 mm²
Cb = 600 x d
600 + fy
= 600 x 304
600 + 270
= 182400
870
= 209.655 mm
∂b = β1 x Cb
= 0.85 x 209.655
= 178.207 mm
εs' = Cb - d' fy
x 0.003 >
Cb Es
= 209.655 - 46 270
x 0.003 >
209.655 200000
= 0.78059210526316 x 0.003
> 0.00135
fs' = Es x εs'
= 200000 x 0.0023
= 468
= 0.65 ( 1604047.86933 )
Dengan demikian kolom akan mengalami kehancuran dengan drawaii luluhnya tulangan tarik
Memeriksa Kekuatan Penampang
Pn = As' x fy b x h x fc'
+
e 3 x h x e
+ 0.5 + 1.18
d - d' d²
= 162777.6 3430000
+
0.652 1.62463802990019
= 249779.286084597 + 2111239.51112404
= 2361.019 kN
Ø x Pn > Pu
= (( -8 - ( 8 )) + 320 )
= 304 mm
Tinggi (d')
= b - d
= 350 - 304
= 46 mm
Mu = 0.095 kNm
Pu = 5.233 kN
e = Mu
Pu
= 94.6401602018661
5.23304
= 18.085 mm
Menentukan Penulangan
AS = As' = ρ x b x d
2
= 1% x 350 x 304
2
= 532 mm²
= 1 x 3.14 x 16 ² x 3
4
= 1 x 3.14 x 256 x 3
4
= 602.88 mm²
Cb = 600 x d
600 + fy
= 600 x 304
600 + 270
= 182400
870
= 209.655 mm
∂b = β1 x Cb
= 0.85 x 209.655
= 178.207 mm
εs' = Cb - d' fy
x 0.003 >
Cb Es
= 209.655 - 46 270
x 0 >
209.655 200000
= 0.78059210526316 x 0.003
> 0.00135
fs' = Es x εs'
= 200000 x 0.0023
= 468
= 0.65 ( 1604047.86933 )
Dengan demikian kolom akan mengalami kehancuran dengan drawaii luluhnya tulangan tarik
Pn = As' x fy b x h x fc'
+
e 3 x h x e
+ 0.5 + 1.18
d - d' d²
= 162777.6 3430000
+
0.570 1.38547715514522
= 285525.963405689 + 2475681.3833141
= 2761.207 kN
Ø x Pn > Pu
= (( -8 - ( 8 )) + 320 )
= 304 mm
Tinggi (d')
= b - d
= 350 - 304
= 46 mm
Mu = 0.103 kNm
Pu = 2.634 kN
e = Mu
Pu
= 103.100169489343
2.63448
= 39.135 mm
Menentukan Penulangan
AS = As' = ρ x b x d
2
= 1% x 350 x 304
2
= 532 mm²
= 1 x 3.14 x 16 ² x 3
4
= 1 x 3.14 x 256 x 3
4
= 602.88 mm²
Cb = 600 x d
600 + fy
= 600 x 304
600 + 270
= 182400
870
= 209.655 mm
∂b = β1 x Cb
= 0.85 x 209.655
= 178.207 mm
εs' = Cb - d' fy
x 0.0030 >
Cb Es
= 209.655 - 46 270
x 0.0030 >
209.655 200000
= 0.78059210526316 x 0.003
> 0.00135
fs' = Es x εs'
= 200000 x 0.002341776316
= 468
= 0.65 ( 1604047.869329 )
Dengan demikian kolom akan mengalami kehancuran dengan drawaii luluhnya tulangan tarik
Pn = As' x fy b x h x fc'
+
e 3 x h x e
+ 0.5 + 1.18
d - d' d²
= 162777.6 3430000
+
0.652 1.62463802990019
= 249779.286084597 + 2111239.51112404
= 2361.019 kN
Ø x Pn > Pu
= (( -8 - ( 8 )) + 320 )
= 304 mm
Tinggi (d')
= b - d
= 350 - 304
= 46 mm
Mu = 0.199 kNm
Pu = 1.097 kN
e = Mu
Pu
= 198.976091870788
1.0969
= 181.399 mm
Menentukan Penulangan
AS = As' = ρ x b x d
2
= 1% x 350 x 304
2
= 532 mm²
= 1 x 3.14 x 16 ² x 3
4
= 1 x 3.14 x 256 x 3
4
= 602.88 mm²
Cb = 600 x d
600 + fy
= 600 x 304
600 + 270
= 182400
870
= 209.655 mm
∂b = β1 x Cb
= 0.85 x 209.655
= 178.207 mm
εs' = Cb - d' fy
x 0.003 >
Cb Es
= 209.655 - 46 270
x 0.003 >
209.655 200000
= 0.78059210526316 x 0.003
> 0.00135
fs' = Es x εs'
= 200000 x 0.0023
= 468
= 0.65 ( 1604047.86932849 )
Dengan demikian kolom akan mengalami kehancuran dengan drawaii luluhnya tulangan tarik
Pn = As' x fy b x h x fc'
+
e 3 x h x e
+ 0.5 + 1.18
d - d' d²
= 162777.6 3430000
+
1.203 3.24099050942553
= 135299.014895591 + 1058318.43383212
= 1193.617 kN
Ø x Pn > Pu
= (( -8 - ( 8 )) + 320 )
= 304 mm
Tinggi (d')
= b - d
= 350 - 304
= 46 mm
Mu = 0.041 kNm
Pu = 2.147 kN
e = Mu
Pu
= 40.5000206099488
2.14702
= 18.863 mm
Menentukan Penulangan
AS = As' = ρ x b x d
2
= 1% x 350 x 304
2
= 532 mm²
= 1 x 3.14 x 16 ² x 3
4
= 1 x 3.14 x 256 x 3
4
= 602.88 mm²
Cb = 600 x d
600 + fy
= 600 x 304
600 + 270
= 182400
870
= 209.655 mm
∂b = β1 x Cb
= 0.85 x 209.655
= 178.207 mm
εs' = Cb - d' fy
x 0.003 >
Cb Es
= 209.655 - 46 270
x 0.003 >
209.655 200000
= 0.78059210526316 x 0.003
> 0.00135
fs' = Es x εs'
= 200000 x 0.00234
= 468
= 0.65 ( 1604047.86932849 )
Dengan demikian kolom akan mengalami kehancuran dengan drawaii luluhnya tulangan tarik
Pn = As' x fy b x h x fc'
+
e 3 x h x e
+ 0.5 + 1.18
d - d' d²
= 162777.6 3430000
+
0.573 1.39431930194117
= 284023.165397373 + 2459981.72385964
= 2744.005 kN
Ø x Pn > Pu
= (( -8 - ( 8 )) + 320 )
= 304 mm
Tinggi (d')
= b - d
= 350 - 304
= 46 mm
Mu = 0.199 kNm
Pu = 1.097 kN
e = Mu
Pu
= 198.976091870788
1.0969
= 181.399 mm
Menentukan Penulangan
AS = As' = ρ x b x d
2
= 1% x 350 x 304
2
= 532 mm²
= 1 x 3.14 x 16 ² x 3
4
= 1 x 3.14 x 256 x 3
4
= 602.88 mm²
Cb = 600 x d
600 + fy
= 600 x 304
600 + 270
= 182400
870
= 209.655 mm
∂b = β1 x Cb
= 0.85 x 209.655
= 178.207 mm
εs' = Cb - d' fy
x 0.003 >
Cb Es
= 209.655 - 46 270
x 0.003 >
209.655 200000
= 0.78059210526316 x 0.003
> 0.00135
fs' = Es x εs'
= 200000 x 0.0023
= 468
= 0.65 ( 1604047.87 )
Dengan demikian kolom akan mengalami kehancuran dengan drawaii luluhnya tulangan tarik
Pn = As' x fy b x h x fc'
+
e 3 x h x e
+ 0.5 + 1.18
d - d' d²
= 162777.6 3430000
+
1.203 3.24099050942553
= 135299.014895591 + 1058318.43383212
= 1193.617 kN
Ø x Pn > Pu
KOMBINASI Pu
NODE
L/C Fy ( KN )
1 1 1.406
2 0.602
3 0.073
4 0.073
5 1.968
6 2.651
7 2.362
8 2.216
9 1.338
10 1.192
2 1 2.630
2 1.278
3 0.000
4 0.000
5 3.681
6 5.201
7 4.434
8 4.434
9 2.367
10 2.367
3 1 1.406
2 0.602
3 0.073
4 0.073
5 1.968
6 2.651
7 2.216
8 2.362
9 1.192
10 1.338
PERHITUNGAN PONDASI FOOTPLATE MEMBER 1
DATA PERENCANAAN
Pu = 2.65074 KN
Asperlu = Pu
δ
= 265.074 0.0001
( 3
)
= 0.008836 m²
= 0.288 KN
Beban Tanah diatas Pondasi = ( 0.2 x 0.2 (( 43.75 - 300 ) 10¯³ ) 1800 ) 10¯²
= -0.1845 KN
= 2.75424
0.04
= 68.856 KN/m² = 0.689 Kg/cm² < Tegangan Ijin Tana = 3 Kg/cm³ ( AMAN )
B = Lebar Kolom + ( 1 x d ) x 2
2
= ( 350 + ( 1 x 312 ) x 2 )
2
B = 662 mm = 0.662 m
Gaya geser total terfaktor yag bekerja pada penampag kritis adalah
Vu = Pu x ( w² - B² )
Vu = -1.0556413 Kg.m
Bc = 0.2 = 1
0.2
Karena Bc = 1, maka
= 4 x 28 x 2648 x 312
Vc = 17486.8499 KN.m
Ø x Vc > Vu
Karena Vu < ØVc , maka plat pondasi aman terhadap gaya geser
Penulangan Telapak
= 1 ( 200 - 350 )
2
F = -75 mm = -0.075 m
Mu = Pu x F x 1 x F x w
2
Mu = 0.0387315 KN.m
Rn = Mu
Ø x b x d²
= 38731.5
0.8 x 200 x 97344
= 38731.5
15575040
Rn = 0.00249 Mpa
ρb = 0.05167305
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.3445378
ρ = 1 1 - 1 - 2 x Rn x m
( ( ) )
m fy
= 1 1 - 1 - 2 x 0.00249 x 11.34454
( ( ) )
11.3445378 270
= 1 1 - 1 - 0.06
( ( ) )
11.3445378 270
= 1 1 - 1 -
( ( 0.000209 ) )
11.3445378
= 1 1 - 0.9998
( )
11.3445378
= 1 1 - 0.9999
( )
11.3445378
= 0.08814815 ( 0.0001 )
ρ = 0.000009
Kebutuhan Tulangan
As perlu = ρ x b x d
= 0.00519 x 200 x 312 = 323.5556 mm2
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
As(aktual) = 1 x 3.14 x d² x n
4
= 1 x 3.14 x 256 x 2
4
= 200
323.555556 200.96
= 4081.7 KN
ldb = db x fy
4 x fc'
= 16 x 270
4 x 28
= 16 x 270
4 x 5.291503
= 0.04 x 16 x 270
ldb = 172.8 mm
Maka digunakan panjang penyaluran pondasi = 210 mm
PERHITUNGAN PONDASI FOOTPLATE MEMBER 1
DATA PERENCANAAN
Pu = 5.20054 KN
Asperlu = Pu
δ
= 520.054 0.0001
( 3
)
= 0.017335 m²
= 0.648 KN
= -0.415125 KN
= 5.433415
0.09
B = Lebar Kolom + ( 1 x
2
= ( 350 + ( 1 x
2
B = 662 mm = 0.662 m
Gaya geser total terfaktor yag bekerja pada penampag kritis adalah
Vu = Pu x ( w² - B²
Vu = -1.811056852 Kg.m
Bc = 0.3 = 1
0.3
Karena Bc = 1, maka
= 4 x 28 x 2648 x
= 4 x 5.291503 x 2648 x
Vc = 17486.84988 KN.m
Ø x Vc > Vu
0.6 x 17486.85 > -1.811056852
Karena Vu < ØVc , maka plat pondasi aman terhadap gaya geser
Penulangan Telapak
= 1 ( 300 - 350
2
F = -25 mm = -0.025 m
Mu = Pu x F x 1 x
2
= 60.37127778 x -0.025 x 1 x
2
Mu = 0.005659807 KN.m
Rn = Mu
Ø x b x d²
= 5659.807
0.8 x 300 x 97344
= 5659.807292
23362560
Rn = 0.00024 Mpa
ρb = 0.85 x fc' x β₁ x
fy
= 0.85 x 28 x 0.85 x
270
= 23.8 x 0.85 x
270
= 0.088148 x 0.85 x
ρb = 0.051673052
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.34453782
ρ = 1 1 - 1 -
(
m
= 1 1 - 1 -
(
11.34453782
= 1 1 - 1 -
(
11.34453782
= 1 1 - 1 -
(
11.34453782
= 1 1 - 1.0000
( )
11.34453782
= 1 1 - 1.0000
( )
11.34453782
= 0.088148148 ( 0.0000 )
ρ = 0.000001
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
As(aktual) = 1 x 3.14 x d² x
4
= 1 x 3.14 x 256 x
4
= 300
485.3333333 200.96
= 0.7 ( 0.85 x 28 x
= 4081.7 KN
ldb = db x fy
4 x fc'
= 16 x 270
4 x 28
= 16 x 270
4 x 5.291503
= 0.04 x 16
ldb = 172.8 mm
mm
= 0.3
5.433415 KN
Tegangan Ijin Tana = 3 Kg/cm³ ( AMAN )
d ) x 2
312 ) x 2 )
312
312
Lebar Kolom )
350 )
F x w
-0.025 x 0.3
600
600 + fy
600
600 + 270
600
870
0.689655
2 x Rn x m
( ) )
fy
2 x 0.00024 x 11.34454
( ) )
270
0.01
( ) )
270
( 0.000020 ) )
ditinjau ulang
485.3333 mm2
3 Bh
A1 ) 2
( 350 x 350 ) ) 2
( OK )
x fy
x 270
PERHITUNGAN PONDASI FOOTPLATE MEMBER 1
DATA PERENCANAAN
Pu = 2.65074 KN
Asperlu = Pu
δ
= 265.074 0.0001
( 3
)
= 0.008836 m²
= 0.288 KN
= -0.1845 KN
= 2.75424
0.04
B = Lebar Kolom + ( 1 x
2
= ( 350 + ( 1 x
2
B = 662 mm = 0.662 m
Gaya geser total terfaktor yag bekerja pada penampag kritis adalah
Vu = Pu x ( w² - B²
Vu = -1.055641301 Kg.m
Bc = 0.2 = 1
0.2
Karena Bc = 1, maka
= 4 x 28 x 2648 x
= 4 x 5.291503 x 2648 x
Vc = 17486.849881 KN.m
Ø x Vc > Vu
0.6 x 17486.85 > -1.055641301
Karena Vu < ØVc , maka plat pondasi aman terhadap gaya geser
Penulangan Telapak
= 1 ( 200 - 350
2
F = -75 mm = -0.075 m
Mu = Pu x F x 1 x
2
= 68.856 x -0.075 x 1 x
2
Mu = 0.0387315 KN.m
Rn = Mu
Ø x b x d²
= 38731.5
0.8 x 200 x 97344
= 38731.5
15575040
Rn = 0.00249 Mpa
ρb = 0.85 x fc' x β₁ x
fy
= 0.85 x 28 x 0.85 x
270
= 23.8 x 0.85 x
270
= 0.088148 x 0.85 x
ρb = 0.0516730524
m = fy
0.85 x fc'
= 270
0.85 x 28
= 270
23.8
m = 11.344537815
ρ = 1 1 - 1 -
(
m
= 1 1 - 1 -
(
11.344537815
= 1 1 - 1 -
(
11.344537815
= 1 1 - 1 -
(
11.344537815
= 1 1 - 0.9998
( )
11.344537815
= 1 1 - 0.9999
( )
11.344537815
= 0.0881481481 ( 0.0001 )
ρ = 0.000009
As tulangan = 1 x 3.14 x d²
4
= 1 x 3.14 x 256
4
As(aktual) = 1 x 3.14 x d² x
4
= 1 x 3.14 x 256 x
4
= 200
323.55555556 200.96
= 0.7 ( 0.85 x 28 x
= 4081.7 KN
ldb = db x fy
4 x fc'
= 16 x 270
4 x 28
= 16 x 270
4 x 5.291503
= 0.04 x 16
ldb = 172.8 mm
mm
= 0.2
2.75424 KN
Tegangan Ijin Tana = 3 Kg/cm³ ( AMAN )
d ) x 2
312 ) x 2 )
312
312
Lebar Kolom )
350 )
F x w
-0.075 x 0.2
600
600 + fy
600
600 + 270
600
870
0.689655
2 x Rn x m
( ) )
fy
2 x 0.00249 x 11.34454
( ) )
270
0.06
( ) )
270
( 0.000209 ) )
ditinjau ulang
323.5556 mm2
2 Bh
A1 ) 2
( 350 x 350 ) ) 2
( OK )
x fy