Assembly Scrap:

Scrap that result from the production of an assembly.

-You have to maintain the assembly scrap in the material master (MRP 1 view) as a percentage in
the Assembly scrap field for the assembly header material.
-The system automatically increases the quantity to be produced by the percentage of scrap.

Note: Assembly scrap increases the order quantity of the assembly and subsequently increases the
order quantity for corresponding components. The dependent requirements of the material
components are therefore increased correspondingly.

Dependency:

 The system increases the quantity to be produced for      all of the assembly's
components accordingly.

Assembly Scrap – MRP 1 view


Now create Process Order for header material and see the effects.