You are on page 1of 1

Numan Ltd (Numan) began manufacturing a new product named Gazza in March.

The budgeted data per unit of Gazza was as follows:


Cost Resource required
Variable materials £48 per m2 5m2
Variable labour £16 per hour 3.5 hours
Variable production overheads £6 per hour As labour
3.1
Requirement
Calculate the budgeted prime cost per Gazza for March.
£
3.2 The budgeted cost and resource requirements for March were all met except for materials price and usage. Owing to higher quality supplies, only 4.5m2 of material were actually used per Gazza but at a cost of £52 per m2. Numan absorbs fixed overheads into all its products using a rate of 115% of actual materials cost.
Requirement
Calculate the actual absorption cost per Gazza for March.
£
3.3 During April the actual absorption cost per Gazza was £592 and Numan set a target of a 33.33% margin on the selling price per Gazza.
Requirement
Calculate the selling price per Gazza in April.
£
3.5 In June, the materials usage and labour and variable overhead costs were as the March budget, but materials were 10% cheaper per m2. The labour time per unit was the same as in May. The fixed overhead absorption rate was £56 per Gazza and 1,400 units were produced.
Requirement
Calculate the actual marginal cost per Gazza in June.
£
3.6 Before finalising the selling price for July, which was to be based on the June costs, the accountant noticed an error in the costing information and this resulted in the actual marginal cost per unit for June being corrected. The fixed overhead per Gazza remained at its June level. A target mark-up on absorption cost was now set.
Requirement
Using a corrected marginal cost of £302 and a target mark-up on absorption cost of 22%, calculate the selling price for July.
£
3.7 Numan’s accountant decided to experiment with different ways of calculating the fixed overhead absorption rate in August. In particular she wanted to see the effect of using a blanket absorption rate (based on all of Numan’s products) on selling prices. The target mark up remained at 22%.
The following actual data from August is available:
Data related to Gazzas
Total variable cost per unit £305
Units produced 1,450
Fixed overheads £82,650
Labour hours per unit 3
Data related to all of Numan’s products
Total fixed overheads £1,239,500
Total number of units produced 18,500
Requirement
Calculate the difference in the selling price of Gazzas that results from switching from a fixed overhead absorption rate based on Gazza’s labour hours to a blanket fixed overhead absorption rate based on all of Numan’s products.
£
3.8 The budgeted blanket fixed overhead absorption rate for August was £66.25 per unit of output.
Requirement
Calculate the total under or over absorption of fixed overheads for all of Numan’s products using the blanket rate in August.
£ absorption
Total: 20 marks

You might also like