No : SAJR/SCS/CRF/MS/01
PT SURYACIPTA SWADAYA Date : 22 December 2020
KARAWANG Rev. :2
Desember Januari februari Maret April Mei Juni
No Uraian Pekerjaan Status Satuan Volume Bobot W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26
11-20 21-27 28-3 4-10 11-17 18-24 25-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-2 3-9 11-16 17-23 24-30 31-6 7-9
A Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi ( Tenaga,Alat Kerja Dan Matrial ) ls 1.00 0.557% 0.139% 0.139% 0.139% 0.139%
2 Keamanan Lapangan ls 1.00 0.414% 0.069% 0.069% 0.069% 0.069% 0.069% 0.069%
3 Direksi Keet + Listrik , Air kerja ls 1.00 1.588% 0.265% 0.265% 0.265% 0.265% 0.265% 0.265%
4 Shop & As-built Drawing ls 1.00 0.413% 0.103% 0.029% 0.074% 0.103% 0.088% 0.015%
5 Laporan Progress & Foto Dokumentasi ls 1.00 0.236% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020%
6 C.A.R ( Include 3 Person Owner ) ls 1.00 0.787% 0.047% 0.028% 0.028% 0.033% 0.033% 0.033% 0.033% 0.033% 0.028% 0.033% 0.033% 0.028% 0.028% 0.033% 0.033% 0.028% 0.033% 0.033% 0.033% 0.028% 0.033% 0.009% 0.033% 0.028% 0.028% 0.014%
7 Tes Kebocoran / Tes Rendam ls 1.00 0.331% 0.050% 0.116% 0.033% 0.116% 0.017%
8 Tes Tarik Besi Beton / Tes Tekan Mutu Beton ( I T B ) ls 1.00 0.427% 0.131% 0.033% 0.033% 0.066% 0.033% 0.033% 0.066% 0.033%
9 Pengukuran / bouplank ls 1.00 0.315% 0.079% 0.067% 0.011% 0.034% 0.011% 0.022% 0.011% 0.022% 0.011% 0.011% 0.011% 0.011% 0.011%
10 Proteksi Lokasi Kerja ls 1.00 0.413% 0.025% 0.015% 0.015% 0.017% 0.017% 0.017% 0.017% 0.017% 0.015% 0.017% 0.017% 0.015% 0.015% 0.017% 0.017% 0.015% 0.017% 0.017% 0.017% 0.015% 0.017% 0.005% 0.017% 0.015% 0.015% 0.007%
11 Safety / HSE ls 1.00 0.497% 0.030% 0.018% 0.018% 0.021% 0.021% 0.021% 0.021% 0.021% 0.018% 0.021% 0.021% 0.018% 0.018% 0.021% 0.021% 0.018% 0.021% 0.021% 0.021% 0.018% 0.021% 0.006% 0.021% 0.018% 0.018% 0.009%
12 Pembersihan Lokasi ls 1.00 0.241% 0.052% 0.021% 0.021% 0.016% 0.037% 0.010% 0.016% 0.005% 0.021% 0.026% 0.016%
B Pekerjaan Clarifier
1 Bor pile f 40 cm , L = 15 m ( K 350 ) nos 9.00 3.386% 0.806% 1.129% 1.129% 0.322%
Rencana 0.109%
2 Bobok Borpile f 40 cm nos 9.00 0.109%
Aktual
Rencana 0.188%
4 Lean Concrete t = 5 cm K175 m3 5.10 0.188%
Aktual
Rencana 0.167%
5 Compacted Sand t = 10 cm m3 10.20 0.167%
Aktual
13 Surface Protection setara Araldite tebal 300 mikron ( luar, dalam ) m2 488.23 5.533% 2.075% 2.421% 1.037%
1 Pipa Galvanise f 400 + Pengecatan m1 35.14 5.254% 0.233% 0.817% 0.700% 0.817% 0.817% 0.817% 0.700% 0.350%
2 Butterfly Valve f 400 ( Kitz 10 K) bh 6.00 6.752% 0.844% 1.266% 0.844% 0.844% 1.266% 0.844% 0.844%
4 Butterfly Valve f 350 ( Kitz 10 K ) bh 10.00 9.208% 0.921% 0.921% 1.381% 1.842% 0.921% 0.921% 0.921% 1.381%
1 Tee Equal f 400 + Pengecatan bh 6.00 3.015% 0.603% 0.905% 0.603% 0.905%
2 Tee Equal f 350 + Pengecatan bh 6.00 2.302% 0.691% 0.460% 0.691% 0.460%
4 Elbow 900 f 350 + Pengecatan bh 6.00 1.927% 0.385% 0.193% 1.156% 0.193%
5 Flange SO 10 K f 400 + Pengecatan bh 12.00 2.899% 0.870% 0.580% 0.580% 0.580% 0.290%
7 Relokasi PJU & Pompa + Aksesoris ls 1.00 1.023% 0.146% 0.438% 0.438%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Sub Total D 15.957%
BOBOT RENCANA MINGGU INI 1.610% 1.597% 1.247% 1.852% 3.495% 3.713% 2.928% 3.320% 2.940% 2.654% 2.207% 2.154% 3.637% 5.449% 7.862% 10.542% 12.609% 9.961% 9.163% 6.079% 4.391% 0.053% 0.187% 0.077% 0.226% 0.046%
BOBOT RENCANA KOMULIATIF 1.610% 3.207% 4.454% 6.306% 9.801% 13.514% 16.442% 19.762% 22.703% 25.357% 27.563% 29.717% 33.354% 38.803% 46.665% 57.207% 69.816% 79.777% 88.939% 95.019% 99.410% 99.463% 99.650% 99.728% 99.954% 100.000%
BOBOT AKTUAL MINGGU INI 100% 1.521% 1.884% 1.244% 0.923% 3.276% 3.378% 2.481% 4.511% 6.970%
BOBOT AKTUAL KOMULIATIF 1.521% 3.405% 4.649% 5.572% 8.848% 12.226% 14.707% 19.218% 26.188%
DEVIASI -0.089% 0.198% 0.195% -0.734% -0.953% -1.288% -1.735% -0.544% 3.485%
BOBOT RENCANA MINGGU INI (Reschedule) 1.521% 1.884% 1.244% 0.923% 3.276% 3.378% 2.481% 4.511% 6.970%
BOBOT RENCANA KOMULIATIF (Reschedule) 1.521% 3.405% 4.649% 5.572% 8.848% 12.226% 14.707% 19.218% 26.188%
BOBOT AKTUAL MINGGU INI (Reschedule) 148% 1.521% 1.884% 1.244% 0.923% 3.276% 3.378% 2.481% 4.511% 6.970%
BOBOT AKTUAL KOMULIATIF (Reschedule) 1.521% 3.405% 4.649% 5.572% 8.848% 12.226% 14.707% 19.218% 26.188%
DEVIASI 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%