Professional Documents
Culture Documents
Vijay Birsingh
2008 May 28
vbirsingh@gmail.com
Typical WBS
Information
System
1.
Stress
Engr.
Mech.
Engr.
• WBS roll-up facility – used to roll-up estimates and budgets
House £32000
1. BCWP = EV
2. BCWS = PV
3. ACWP = AC
Cost Control
EV Terms
Data Element Term Old Term
Budgeted Cost of
Scheduled Work Planned Value (PV) Work Scheduled (BCWS)
Budgeted Cost of
Work Accomplished Earned Value (EV) Work Performed (BCWP)
Actual Cost of Work Actual Cost of
Actual Costs (AC) Work Performed (ACWP)
Accomplished
Authorized Work Budget at Completion Same
Forecasted Cost Estimate at Completion Same
Work Variance Schedule Variance Same
Cost Variance Cost Variance Same
Completion Variance Variance at Completion Same
Cost Control
Performance Measurement
Baseline (PMB)
Time-Phased Budget
4500
BAC
4000
3500
3000
BCWS $K
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun
Reporting Period
Budgeted Cost of Work
Scheduled
z Abbreviated BCWS.
z It is the total budgeted cost up to the
analysis date.
z Approximated by the total budget
multiplied by the fraction of total project
duration at the analysis date.
z “How much work should have been done?”
Cost Control
80000
70000
BAC
PV
60000
CURRENT
JANUARY 0
50000
PV
FEBRUARY 2500
40000 MARCH 8000
30000 APRIL 13000
20000 MAY 42000
10000
JUNE 62000
JULY 70700
0
JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY
Budgeted Cost of Work
Performed
z This is the “Earned Value.”
z Abbreviated as BCWP.
z For completed work, it is the cost originally
budgeted to accomplish that work.
z “How much work was actually done?”
Cost Control
Earned Value
Budgeted value of completed or in-process work
Performance Measurement Baseline
80000
CURRENT
70000
60000 PV EV
JANUARY 0 0
50000
PV
FEBRUARY 2500 3600
MARCH 8000 8000
40000 EV APRIL 13000 10000
MAY 42000 38000
30000
JUNE 62000
JULY 70700
20000
10000
0
JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY
Actual Cost of Work
Performed
z Abbreviated ACWP.
z What it actually cost to accomplish all the
work completed as of the analysis date.
z “What did the work that was actually done
actually cost?”
Cost Control
80000
CURRENT
70000
60000
50000 ACWP
PV EV AC
JANUARY 0 0 0
BCWS
40000 FEBRUARY 2500 3600 6000
BCW
MARCH 8000 8000 8000
30000 APRIL 13000 10000 8000
MAY 42000 38000 48000
20000 JUNE 62000
JULY 70700
10000
0
JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY
Derived Metrics
z Schedule Variance (SV)
z Schedule Performance Index (SPI)
z Cost Variance (CV)
z Cost Performance Index (CPI)
A Few More Acronyms
z BAC - Budget At Completion
– = Total Original Budgeted Cost
– Same as BCWS at completion
z EAC - Estimate At Completion
– = Cumulative Actuals + Estimate-To-
Complete
z VAC - Variance At Completion
– = Forecast of final cost variance
Doing The Math
z SV = BCWP - BCWS
z Negative means Behind Schedule
z CV = BCWP - ACWP
z Negative means Over Budget
Schedule Variance
SV = EV – PV
SV Example
PV = $42,000
EV = $38,000
AC = $48,000
SV = EV – PV
= $38,000 – $42,000 = -
$4,000
SV% = SV / PV
= - $4000 / $42,000 = - 0.095
= - 9.5%
Cost Control
Cost Variance
• CV = EV – AC
PV = $42,000
EV = $38,000
AC = $48,000
CV = EV - AC
= $38,000 – $48,000 = -
$10,000
CV% = CV / EV
= - $10,000 / $38,000
= - 26%
Cost Control
Performance Indices
Dfn: Cost- and schedule-performance
efficiency calculations; expressed in $
Cost Performance Index (CPI)
CPI = EV/AC
CPI Example
PV = $42,000
EV = $38,000
AC = $48,000
CPI = EV / AC
= $38,000 / $48,000 =
0.79
$0.79 worth of work was actually
done for each $1.00 spent
Cost Control
SPI Example
PV = $42,000
EV = $38,000
AC = $48,000
SPI = EV / PV
= $38,000 / $42,000 = 0.90
$0.90 worth of work has been done
for each $1.00 worth of work that was
planned to be done
Cost Control
EAC Example
One methodology:
Variance at Completion
BAC = $80,000
EAC = $101,265
= ($ 80,000 – $ 38,000) / ($
101,265 – $ 48,000)
= $ 42,000 / $ 53,265
= 1.4
An Example: Lemonade
z Make 1,000 cups over 50 days
z Steady rate of 20 cups per day
z Budgeted cost per cup is $0.50
z Total project budget is $500
Lemonade Progress
z Atend of day 10:
z 150 cups have been made
z Total actual cost is $90 (ACWP)
Lemonade Status
BCWS = $100
10 days x 20 cups per day x .50/cup
budget
BCWP = $75 (Earned Value)
150 cups x .50/cup budget
Satisfaction of Needs
Value =
Use of Resources
Value
= Function Worth / Function Cost
Barriers
Waste
Too
of Time
No Time Expensive
The
The Not
Too Interested
Difficult Barriers
Barriers
Too Don’t I Do It
Complex Want Anyway
Outsiders
Project Life Cycle
Value Enhancement
Opportunity
Spend
Key Decisions
PROJECT LIFE-CYCLE
Value is
Performance Resource
Subjective
Perform
ance
Resourc
e
P = Functional Performance
R = Life Cycle Cost / NPV
Value Management is not about cost cutting, You can improve value
even if you increase project cost !!!!!!
The VM Concepts
The 3 concepts of VM
Function based
Structured process
What is a Function?
Expression of the need in terms of performances rather than
solutions
Link between the need and the product
Basis of creative problem solving in VM
Need
FUNCTION
Product
VM as a Structured Process
Thought Processes
Analytical Creative
1 - Analyse information
2 - Brainstorm Functions
3 - Organise Functions
4 - Generate Ideas for
Alternatives
5 - Evaluate Alternatives
6 - Develop Proposals
7 - Appraise Options
8 - Recommend Solutions
The VM Job Plan
The Stages in then VM Job Plan:
Information
Function Analysis
Creative
Evaluation
Development
Implementation
VM Job Plan - Analysis Stage
HOW WHY
BASIC/HIGHEST
ORDER
FUNCTION
NEEDS
WANTS
PROJECT SCOPE
PROJECT SCOPE
Value enhancement
Cost to Implement
•Costly Projects
• Complex Projects
• Repetitive Projects
• Projects with compressed Programmes
• Projects with Restricted Budgets
• Projects with High Visibility
Classes of Contractual Documents
LOW HIGH
Seller Risk
Buyer Risk
HIGH LOW
Cost Plus Cost Plus Fixed Cost Plus Fixed Price Firm Fixed Price
Percentage of Incentive Fee Incentive (FPI)
Fee (CPFF)
Costs (CPPC) (CPIF)
Spectrum of risk
Planning Controlling
11.1 Risk
Management
Planning 11.4
11.3 Risk 11.5 Risk Risk
Qualitative Response Monitoring
Analysis Planning
11.2 Risk &
Identification 11.4 Risk Control
Quantitative
Analysis
Quantitative Risk Analysis
Decision Trees
High Demand
Probability =0.3
$ 550,000
Production Successful
Probability = 0.7 Low Demand
Probability = 0.7
Decide to pursue - $100,000
Production Unsuccessful
Expect Value of Pursuing Project A
Probability = 0.3 0.7 x 0.3 x $ 550,000 = $ 115,500
Terminate = - $ 200,000 0.7 x 0.7 x – $ 100,000 = – $ 49,000
Payback Method
Project Selection – Economic Criteria
Time Value of Money Concept
A dollar received today is worth more