You are on page 1of 1

DEVELOPMENT OF

A B C D E F G H NOIDA INTERNATIONAL AIRPORT (NIA)


1 4
N

T1

`1' MASTER KEY PLAN

ORIGINATOR : YAMUNA INTERNATIONAL AIRPORT PVT. LTD.


`2'
FLOOR FINISH
LEVEL
PROJECT KEY PLAN
FGL.
NOTES:
FLOOR FINISH
LEVEL
SIDE ELEVATION
FGL.

A B C D E F G H
SECTION `A-A'

B A
1

SAFETY, HEALTH & ENVIRONMENT


1 2 3 4

· LIVE LOAD ON ROOF CONSIDERED 0.75 KN/M²


· BASIC WIND SPEED CONSIDERED 39 M/S
· G.I. SHEET LOAD CONSIDERED 0.35 KN/M²

3 SBC REQUIRED AT BOTTOM OF FOOTING / PEDESTAL


IS 15 T/m² . ENSURE SBC BEFORE PLACING ON
LOCATION.

4
B A
PLAN AT TIE LEVEL

FLOOR FINISH
LEVEL VYJ SAM AAG SN
R0 FIRST ISSUE
10/08/2022 10/08/2022 10/08/2022 10/08/2022

FGL. REV.
DESCRIPTION DESIGNED DRAWN CHECKED APPROVED
NO.

CLIENT: YAMUNAINTERNATIONALAIRPORT
PVT.LTD.
VIEW `B-B'

CONTRACTOR:

SUB CONTRACTOR:
1 1

PROJECT :
CEMENT GODOWN-1 NOIDA INTERNATIONAL AIRPORT
STATUS :
DETAIL `1' CONSTRUCTION
DRAWING TITLE :

GA & DETAILS OF CEMENT GODOWN


(7.5m x 21m) (3 NOS.) 5760 BAGS

JOB No:
NAME SIGN DATE
DSGN VYJ 10/08/2022
CEMENT GODOWN-2 CEMENT GODOWN-3 DRWN SAM 10/08/2022
CHKN AAG 10/08/2022

NOIDA INTERNATIONAL AIRPORT, UTTAR-PRADESH, INDIA


APPD SN 10/08/2022
DRAWING NO. REVISION
TPL-YIAPL-PH1&2-AN-034 R0
DETAIL `2'
SECTION `1-1' SECTION `1-1' KEY PLAN SCALE : AS SHOWN SIZE: A1 SHEET: 01 OF 02
RELEASED FOR
INFORMATION TENDER APPROVAL CONSTRUCTION AS BUILT