Ref No: LC/IMAC/EST/2022-23
Date: 04-01-2023

M/s. IMAC ALLOY CASTING PVT LTD


Site: Sengadu Village
Chennai.
SUB: Quotation for Warehouse - Reg
126'0" X 250'0" - Height - 40'0" - Base Height 3'3"

S.No. CIVIL WORK DESCRIPTION BASE 3'3" - N.G.L. MARK TMT NOS

1 COLUMN
Earth Work: 7'0" X 7'0" X 7'0"
Dressing & Dust Laying for 3"
PCC: Wet Mix for 6"
Footing Concrete: 6'6" X 6'6" X 1'3"
Matt 12 mm Rod 5" C/C
Corner Column 16 mm - Nos: 16
a C1 4
Size 2'6" X 2'6" Ring - 8 mm
Main Column 16 mm - Nos: 14
b C2 43
Size 2'6" X 1'3" Ring - 8 mm
PLINTH BEAM
16 mm - Nos: 5
2 PCC: Wet Mix for 3" PB -
Ring - 8 mm
Size 1'6" X 0'9"
TIE BEAMS At Base Level & At Lintel Level TB 12 mm - Nos: 4
3 -
Size 0'9" X 0'9" EB Ring - 8 mm
MASONARY WORK
4 Solid Block 8" Thk MW - -
Plastering Sponge Finish
Filling - Withing Warehouse
5 Earth Filling - 3'0" Above NGL with Two Stage Viber Max - - -
Hydraulic Roller Compaction
FLOORING
6 Wet Mix Laying 6" & Roller Compaction - 8 mm - 1'6" C/C -
RCC Concrete 6" - VDF Flooring
7 Rolling Shutter - Not Considered - - NIL
12 mm - Nos: 4
8 Wall Support Column 9" X 9" from Plinth Beam - 32
Ring - 8 mm
12 mm - Nos: 4
9 Window MS Grill only Size 6'0" X 4'0" - No Door - 32
Ring - 8 mm

Pg: 1 of 2.
LAKSHMI CONSTRUCTIONS
UNIT -I :NO. 75, KAMARAJAR SALAI, KODUNGAIYUR, CHENNAI - 118.
UNIT -II :S.F.NO. 58/1, NALLUR VILLAGE, SHOLLAVARAM, CHENNAI - 067.
Phone No.+91 99404 53309, +91 95511 13309, Web site:www.sleg.in, Email:info.lakshmiconstructions@gmail.com

Material Make:
1 Cement: 53Grade - Zuari /Penna / Coromandel / Equalent
2 TMT: GBR / Kamatchi / ARS 550Grade
3 Blue Metal & M Sand - VSI Grade

QTY
S.No. PRICING Rate Amount
Sq.Ft
1 Factory Civil work Charges 31500 505.00 15907500.00
2 Civil Loading Platform/Ramp 300 395.00 118500.00
3 SUM 16026000.00
4 GST 18% 2884680.00
5 Grand Total 18910680.00

TERMS:
1 GST 18% Extra as Above (CGST - 9% & SGST - 9%).
3 Building Plan Approval, Compound Wall, Gate, Road Work, Bore with Motor Line Extra
4 EB Connection. Electricity & Water Should be Supplied by Client at Site
5 Building One Cote White Wash Only
6 Payment: Advance 30% & Balance - 3 Stage Payments
7 All Electrical & Plumbing Works Extra
8 Sump, Water Tank, Toilet & Septic Tank Extra
9 Any Work Clearly thats not mentioned is not Included in this Estimate
10 Units Quoted are Estimated, Final Figures will Account for Billing
11 Rolling Shutter & UPVC Window Extra
We hope that you will find our rates most competetive and favour us with your valuable order.
Thanking you,

V. GANESAN - Founder
Authorised Signatory
LAKSHMI CONSTRUCTIONS
An ISO 9001:2008 Certified Company
Pg 2 of 2.

You might also like