Project : Saadiyat Development - The Grove Phase - 2

system performance
Description GEMINITE CEMENT BOARD / GTI SUSPENSION

Ceiling Drop 600 mm


Deflection Limit L/360
Internal Pressure 240 Pa
Maixmum Load Bearing Capcity 514.0 N/m2 = 52.4Kg/m2

SL. No System Componets Details


1 Geminite Cement Board 12.0mm Board on Bottom
2 GTI Main Channel 38x12x12, 0.6 mm as Main Runner 900 mm max centers
3 GTI Furring Channel 64x35x23, 0.6 mm as Cross Runner 400 mm max centers
4 GTI GI L-Angle 25x25, 0.6 mm - Hanger 900 mm max centers
5 GTI GI L-Angle 25x25, 0.6 mm -Perimeter as perimeter wall angle
6 Wedge Anchor - 6x40mm as suspension anchor
7 Hammer Screw, Size: 6 x 40mm wall angle fixing 600 mm max centers
8 Waferhead screw M4.2 x13 Metal to Metal Fixing
9 Self Tapping Screw M3.5 x 25mm Boards to Metal fixing
10 Jointing Tape - Fibre For Joint Finishing
11 Jointing Compound ( Styro- Terraco ) For Joint Finishing