This is a project plan showing 15 activities with dependencies and estimated time durations. The plan starts with obtaining funding approval which takes 1 week and has no predecessors. It then shows engineering, equipment delivery, tool building, installation, training, debugging, advertising planning and artwork finalization activities that depend on earlier tasks. The plan ends with shipping product after a production run which depends on advertising being completed and materials delivery.
This is a project plan showing 15 activities with dependencies and estimated time durations. The plan starts with obtaining funding approval which takes 1 week and has no predecessors. It then shows engineering, equipment delivery, tool building, installation, training, debugging, advertising planning and artwork finalization activities that depend on earlier tasks. The plan ends with shipping product after a production run which depends on advertising being completed and materials delivery.
This is a project plan showing 15 activities with dependencies and estimated time durations. The plan starts with obtaining funding approval which takes 1 week and has no predecessors. It then shows engineering, equipment delivery, tool building, installation, training, debugging, advertising planning and artwork finalization activities that depend on earlier tasks. The plan ends with shipping product after a production run which depends on advertising being completed and materials delivery.
Activity Description Immediate Predecessor Estimated Time (weeks)
A Obtain funding approval -- 1
B Finalize engineering A 1 C Deliver new equipment A 8 D Build dies and tools B 12 E Install equipment C 1 F Train workers D,E 1 G Debug process F 1 H Establish advertising plan A 1 I Finalize package and artwork H 2 J Advertise H 12 K Raw material delivery D,I 2 L Initial production run G,K 3 M Ship product J,L 1