Index
1.
1
Chapter 1: Creating the Project
1. Create project
2
3. Create and provide a clear name project (for example: cohort + team number)
Please mention the group member names in the description.
Leave the start date as indicated and no need to assign an owner.
3
Chapter 2: Developing the project
2. In this session we are only working with task name, duration, start, finish, and predecessors
columns. So, please rearrange by selecting and moving the columns.
4
3. You can add task by clicking on insert or delete task by clicking on delete
5
4. Add the name of the task to the schedule
For example (also now you know how to make nasi goreng 😉)
6
7
5. Add Start and end time to the respective task
After entering the task interdependencies you can now see the Gantt Chart on the right side.
8
7. Order the tasks on Id number (important, otherways you cannot group activities)
9
9. Select the task that belong to that group and indent
10
Chapter 3: The final result
The schedule:
11
Chapter 4: Sharing the results
1. We are interested mainly interested in the schedule logic. Hence, please download the
excel format and upload this on Blackboard. Also, copy-paste the Gantt Chart in the
excel file. This is unfortunately not done automatically.
12