PROJECT PROJECT START PROJECT END

PROJECT NAME
DURATION DATE DATE

RESTORATION OF ARTIFICIAL BOULDERS 8 14-Dec-21 22-Dec-21

WEEK 1 WEEK 2 WEEK 3

12/14/2021

12/15/2021

12/16/2021

12/17/2021

12/18/2021

12/19/2021

12/20/2021

12/21/2021

12/22/2021

12/23/2021

12/24/2021

12/25/2021

12/26/2021

12/27/2021

12/28/2021

12/29/2021

12/30/2021

12/31/2021
Task
Task Description Duration Start Date End Date
Location

A. PHASE 1 BRIDGE RAILING (A= 36.00 sq.m) 2 14-Dec-21 16-Dec-21


x x x
Application of Stain 2 14-Dec-21 16-Dec-21 x x x
Application of Sealer (Matt Finished) 2 14-Dec-21 16-Dec-21 x x x

B. PHASE 2 NEAR SHOWER POST 1(A= 22.39 sq.m) 2 16-Dec-21 18-Dec-21


x x x
Application of Stain 2 16-Dec-21 18-Dec-21 x x x
Application of Sealer (Matt Finished) 2 16-Dec-21 18-Dec-21 x x x

C. PHASE 3 JACUZZI AREA (A= 129.25 sq.m) 2 18-Dec-21 20-Dec-21


x x x
Application of Stain 2 18-Dec-21 20-Dec-21 x x x
Application of Sealer (Matt Finished) 2 18-Dec-21 20-Dec-21 x x x
D. PHASE 4 INFRONT OF THE GYM AREA (A= 437.93
6 14-Dec-21 20-Dec-21
sq.m) x x x x x x x
Installation of Temporary Barricade 1 14-Dec-21 15-Dec-21 x x
Installation of GFRC Over lay 3 15-Dec-21 18-Dec-21 x x x x
Curing of GFRC Over Lay 3 15-Dec-21 18-Dec-21 x x x x
Application of Stain 2 16-Dec-21 18-Dec-21 x x x
Application of Sealer (Matt Finished) 2 18-Dec-21 20-Dec-21 x x x
PUNCHLIST INSPECTION & HANDOVER 1 20-Dec-21 21-Dec-21 x x
DEMOBILIZATION 1 21-Dec-21 22-Dec-21 x x

Prepared By:

Engr. Fernando D. Panelo Jr.


Project Engineer