Professional Documents
Culture Documents
STRUCTURE
An organized combination
of connected parts designed
to carry loads and provide
adequate rigidity.
By
Er. Prof. Sujay Deshpande,
Faculty of Civil Engg.,
KLS G.I.T, Belagavi 2
Buildings Tunnels
Foundations Waterways
Pipelines
1
08-11-2022
TYPES OF STRUCTURES
1. R.C STRUCTURES 2. STEEL STRUCTURES
Pre-Stressed Concrete (P.S.C.) is a particular Pre-Stressed Concrete is a method invented for overcoming concrete's
natural weakness in tension.
form of Reinforced concrete.
Traditional reinforced concrete is based on the use of steel reinforcement
“Prestressing involves the application of an initial
bars called Rebars, present inside the poured concrete.
compressive load on the member to reduce or eliminate
The initial compressive load is imposed and sustained by highly
the internal tensile forces and thereby control or eliminate
tensioned steel reinforcement present in the body of concrete. With
deflection & cracking”.
cracking reduced or eliminated, a pre-stressed section is considerably
This initial load is called ‘pre-stress’ which is applied to stiffer than an equivalent (usually cracked) reinforced concrete
section. Prestressing may also impose internal forces which are of opposite
enable the structure to counteract the stresses arising due
sign to the external loads and may therefore significantly reduce or even
to the imposed loads during its service life.
eliminate the deflections.
The initial compressive load is imposed and sustained by It can be used to produce beams, floors/slabs & bridges with a
highly tensioned steel reinforcement present in the body of longer span which are complex and difficult with ordinary reinforced
concrete. concrete.
2
08-11-2022
EVOLUTION OF THE
CONCEPT OF PRE-STRESSING
LIMITATIONS OF PRE-STRESSING
Pre-stressing requires modern & advanced
technology and skilled labour. Hence, it is not as
common as reinforced concrete.
The use of high strength materials (HSC & HSS)
is costly as compared to conventional materials.
There is an additional cost involved in handling
the auxiliary equipment.
There is a need for better quality control and
inspection.
3
08-11-2022
COLUMNS
BEAMS / GIRDERS
4
08-11-2022
BIAXIAL PRE-STRESSING
OF A SLAB
PRE-STRESSED RAILWAY
SLEEPERS
5
08-11-2022
HYDRAULIC JACK
6
08-11-2022
Anchoring of Placing of
tendons against Jacks
the end abutments
In pre–tensioning system, the high-strength steel tendons are
pulled between two end abutments (called bulk-heads) prior to the
casting of concrete. The abutments are fixed at the end of the pre-
stressing bed. Applying
tension to the
Once the concrete attains the desires strength for pre-stressing, the
Transfer of tendons by
tendon are cut loose from the abutments. The prestress is transferred
Pre-Stress Jacks
from the tendons to the concrete, due to the bond between them.
During the transfer of pre-stress, the member undergoes elastic
shortening and there will be some loss of pre-stress. If the tendons are
located eccentrically, the member is likely to bend and deflect Cutting of the Casting of
upwards (camber) which helps to resist the gravity loads in future tendons concrete
more effectively.
7
08-11-2022
Typical Wire
Gripping
System
POST–TENSIONING
Post-Tensioning is a method of prestressing
(strengthening/reinforcing) concrete with high-
strength steel (typically referred to as tendons)
after the concrete is cast and cured.
8
08-11-2022
Stages of Post-Tensioning
Placement of
the anchorage
Transfer of
block and jack
pre-stress
Applying
Cutting of the
tendons
tension to
the tendons
PROCESS OF POST-TENSIONING
A metal tube or a flexible hose following intended
profile is placed inside the mould and concrete is
laid.
9
08-11-2022
Anchoring
Devices
Anchoring
Devices
Freyssinet system
Magnel-Blaton system
Lee-McCall system
Gifford-Udall system
10
08-11-2022
Magnel-Blaton system
This method was introduced by a famous
engineer Prof. Magnel of Belgium.
In Freyssinet system several wires are
stretched at a time. In Magnel Blaton
system, only two wires are stretched at a
time.
In this system, the anchorage device
consists of sandwich plate having grooves
to hold the wires and wedges which are
also grooved. Each plate carries eight
wires. Between the two ends the spacing
of the wires is maintained by spacers.
Anchorage for Freyssinet system
Gifford-Udall system
This system originated in Great
Britain, is widely used in India. This
is a single wire system. Each wire is
stressed independently using a
double acting jack. Any number of
wires can be grouped together to
form a cable in this system. There
are two types of anchorage device in
this system.
a) Tube anchorages
Anchorage for Lee McCall b) Plate anchorages
System
11
08-11-2022
Advantages of Post–Tensioning
Limitations of Post–Tensioning
Post-tensioning is suitable for heavy cast-in-
The limitation of post-tensioning as
situ members which are difficult to transport
The waiting period in the casting bed is less and
compared to pre-tensioning is that their
PROBABLE QUESTIONS
1) What is Prestressed Concrete? Explain its advantages and limitations.
2) With a neat sketch, explain the materials to be used in PSC.
3) With a neat sketch, explain the various stages and the process of Pre-
tensioning.
4) With a neat sketch, explain the Hoyer’s Long line method of Pre-
tensioning.
5) Explain the advantages and limitations of Pre-Tensioning method.
6) With a neat sketch, explain the various stages and the process of Post-
tensioning.
7) With a neat sketch, explain the various types of anchorages that can be
used in Post-tensioning systems.
8) Explain the advantages and limitations of Post-Tensioning method.
9) NUMERICAL PROBLEMS ON PRE- AND POST-TENSIONING METHODS
12