1 General ..................................................................................................................... 1
2 Scope ........................................................................................................................ 1
3 Acceptance Test Procedure .................................................................................... 3
3.1 Prerequisites ................................................................................................ 3
3.1.1 Hardware Tools ............................................................................................ 3
3.1.2 Software Tools ............................................................................................. 3
4 Delivery Acceptance ................................................................................................ 3
4.1 IP Switches .................................................................................................. 3
4.1.1 Hardware Acceptance .................................................................................. 3
4.1.2 Configuration Acceptance ............................................................................ 4
4.1.3 Document Acceptance ................................................................................. 5
5 Integration Acceptance ........................................................................................... 6
5.1 Connectivity.................................................................................................. 6
5.1.1 IP List reachability ........................................................................................ 6
5.1.2 IP Connectivity ............................................................................................. 6
5.2 Redundancy Test Acceptance ...................................................................... 7
5.2.1 Intra-switch link failures ................................. ¡Error! Marcador no definido.
5.2.2 IP Switch to Switch Link Failures ................... ¡Error! Marcador no definido.
6 Sign off Acceptance................................................................................................. 7
1 General
This document outlines the acceptance test procedure for a new IP Switches integration in
ITLA Dominican network.
2 Scope
This document covers customer acceptance for the IP Switches delivery and configuration
for traffic. All acceptance tests will be carried out at the customer site. Depending on time
constraints, licensing, and mutual agreement, a sub-set of these test cases may be performed
instead, or additional, customer-specific test cases may be added.
This document also serves as a test report. Each test case contains fields for reporting (notes,
signatures, etc.). If a node has passed certain test case, appropriate field should be signed.
Not performed tests, or tests that have failed for any reasons are noted in this test report and
the reason is explained in Notes..
Overall integration is considered signed-off when Final Site Acceptance has been signed off.
ATP needs to be distributed as per agreed on distribution list.
Customer Personnel
b. Integration Acceptance: These tests reflect the services provided by the solution,
including operation, maintenance, etc.
3.1 Prerequisites
This chapter describes the network configuration and tools necessary for the tests.
4 Delivery Acceptance
The scope of this chapter is to verify the configuration and connectivity of the solution.
4.1 IP Switches
Description
This check will verify that the delivery is complete and without damage. This procedure must be repeated for each Site
Switch individually.
Expected Result
Actual delivered material should match materials list.
Delivered material should be in excellent condition and without visual damage
Precondition
Ethernet Switch installed.
Test Procedure Notes
Visually check the delivered Ethernet switch, including power supply, cables, cards, Passed
and spare parts against materials list.
4) Save the configuration and reboot the switch. Wait for switch to recover then login
as user “admin”. Check the configuration is retained.
command: Cisco
command: Enable, Class
Description
This test case will ensure that the customer, before execution of integration acceptance test cases starts, accepts the
configuration of the Site Switches. The configuration file and a series of printouts will be retrieved and delivered to the
customer for acceptance. This procedure must be repeated for each Site Switch individually.
Expected Result
Configuration reflects the customer’s requirements.
Precondition
Ethernet Switch configured.
Test Procedure Notes
1. Via inbound management, open one session to the Passed
Switch: Show Version
SDQ-CH-SWA-1
command: HQ-DIST01#show ru
Show run
4. Verify the following configuration:
• Vlan tag
• Assigned port
• System IP address
command: HQ-DIST01#show vlan
HQ-DIST01#show etherchannel su
Customer Passed
5 Integration Acceptance
This section verifies the successful operation of the Solution for traffic. The log file for this
session should be saved, which should be backed up and removed before leaving site.
5.1 Connectivity
The scope of these tests is to verify that the nodes have connectivity to all connected network
elements.
5.1.2 IP Connectivity
Description
Expected Result
There is IP connectivity to all nodes in networks.
Precondition
Nodes connected and configured in the networks.
Test Procedure Notes
Make a list of all adjacent nodes (e.g. server, routers) connected to each network
interface
Passed
Ping network elements connected via this switch board:
HQDIST01 192.168.50.1
Customer Passed