Scope of Work Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18 Day 19 Day 20 Day 21
ARCHITECTURAL WORKS
Drywall 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP
Ceiling 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP 5 MP
Carpentry 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP 8 MP
Tiling 3 MP 3 MP 3 MP 3 MP 3 MP
Water Proofing 2 MP 2 MP
Painting 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP
PLUMBING WORKS
Installation of piping 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP
Installation of Drainage 4 MP 4 MP 4 MP
Tapping 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP
ELECTRICAL WORKS
Preparation of wires 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP
Installation of Lights 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP
Installation of Switches 4 MP 4 MP 4 MP 4 MP 4 MP
MECHANICAL WORKS
Installation of Aircon 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP
Installation of Sprinkler 4 MP 4 MP 4 MP 4 MP 4 MP 4 MP
*MP-Manpower