Professional Documents
Culture Documents
CONFIDENTIAL
This document is the proprietary property of Independent Project Analysis, Inc., which retains all copyright and other ownership rights in its
contents. Information about the subject matter, content and structure of this document is confidential and proprietary. Neither this document nor
any such information may be disclosed to any third party without the prior written consent of IPA except as expressly provided by the contract
between IPA and the client to whom IPA has delivered this document.
Expandability
Flexibility
Reliability
Risks & uncertainties that can influence success of this project
identified.
Prediction maintenance
Design-to-capacity
Value Engineering
Energy optimization
Constructability reviews
3-D CAD
Incorporate "lessons learned" from historical experience with similar projects
Costs
Schedule
Operability
Feedstock composition
Process impurities
Temperature extremes
Pressure extremes
Corrosive material
Abrasive material
Mechanical problems
Corrosion testing to determine adequacy of materials of construction conducted
Constructability
Operability
Maintainability
Fire prevention/safety
Electrical area classifications defined
Underground electrical defined and drawings issued for review (duct, conduit,
manholes, etc.)
By-products
Inventory requirements
Shipment sizes and schedules
Inventory requirements
Sprinklers
Gas masks
Stretchers
Safety showers
Lunch room
Medical facilities
Laboratories
Locker rooms
Maintenance shops
Yard maintenance
General storage
Interconnecting pipe routings
Salvage yard facilities
Shipping
Warehousing
Gate house
Marine facilities
Utility requirements
Rail spurs
Marine facilities
General site requirements defined
Fences
Other paving
Railroads
Ditches and drainage
By-product
Waste
All process stream design flow rates frozen
Annual capacity
Operating hours
All process streams defined
Compressed air
Inert gas
Natural gas
Electrical
Loop functionality
Analyzer services
Start-up, shut down, off-test, clean-up and instrument test connections shown
All required tie-ins to existing lines/equipment shown
P&IDs compared with approved flow diagrams
P&IDs of design release quality -- approved by all who can influence project
outcome
Materials of construction
corrosion allowance
Internals - installation/removal
Testing procedures
Location
Milestone schedule showing timing for major tasks completed by the end of the
"select" phase
Turnover strategy and sequence complete and integrated with engineering and
construction plans and schedules
Control estimate ("A" grade ± 10%), based on an integrated network plan and
schedule, completed by the end of the "design" phase
Scope confidence
Uncertainty allowances
Linear extrapolation