1. How to use EPMS APP

1.1 Step-1 How to install E-TSS APP - - - - - - - - - - - - - - - - - - - - - - - - - - - - - [ 3 ]

1.2 Step-2 How to login E-TSS APP - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -[ 3 ]

1.3 Step-3 How to choose the Project - - - - - - - - - - - - - - - - - - - - - - - - - - - - - [ 4 ]

1.4 Step-4 How to do Data Synchronization - - - - - - - - - - - - - - - - - - - - - - - - [ 5 ]

1.5 Step-5 How to start E-TSS - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - [ 6 ]

1.6 Step-6 How to do Data Synchronization - - - - - - - - - - - - - - - - - - - - - - - - [ 7 ]

1.7 Step-7 How to choose site ID - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -[ 8 ]

1.8 Step-8 How to start and fill site information - - - - - - - - - - - - - - - - - - - - - - [ 9 ]

1.9 Step-9 E-TT APP task icon explanations - - - - - - - - - - - - - - - - - - - - - - - - [ 10 ]

2. How to use EPMS Webpage

2.1 Step-1 How to login EPMS webpage - - - - - - - - - - - - - - - - - - - - - - - - - - - - [ 11 ]

2.2 Step-2 How to choose project - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - [ 12 ]

2.3 Step-3 How to start E-TSS webpage- - - - - - - - - - - - - - - - - - - - - - - - - - - - - [ 13 ]

2.4 Step-4 How to fill site information - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - [ 14 ]

2.5 Step-5 Purpose of “Save” and “Submit” task - - - - - - - - - - - - - - - - - - - - - [ 15 ]


© ZTE All rights reserved
2
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP

 1.1 Step-1 How to install E-TSS APP


Scan QR code and download iCenter Ex APP

 1.2 Step-2 How to login E-TSS APP


Put EPMS ID and Password in APP
And then login in system
Name/ID

Password

© ZTE All rights reserved


3
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP
 1.3 Step-3 How to choose the “Project”

© ZTE All rights reserved


4
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP
 1.4 Step-4 How to do Data Synchronization
First time choose “All” and then download all
Second time choose “Increment” and then download all

1 2 2
1

© ZTE All rights reserved


5
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP
 1.5 Step-5 How to start E-TSS

Enter the E-TSS icon

© ZTE All rights reserved


6
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP
 1.6 Step-6 How to do Data Synchronization After Data Synchronization
First time choose “All” and then download all Go back to front page
Second time choose “Increment” and then download all

1 2 1 2

© ZTE All rights reserved


7
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP
 1.7 Step-7 How to choose site ID
You can saw the task and then choose your planning site ID and start the TSS.

Task site ID
c “click” here

© ZTE All rights reserved


8
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP
 1.8 Step-8 How to start and fill site information
Click “ Fill in task “ and then fill the site information one by one

© ZTE All rights reserved


9
=======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
1.How to use EPMS APP
 1.9 Step-9 E-TSS APP task icon explanations
1. When you finished all the survey data collection,
you can click “a” for Submit For Approval task.
2. When you finished some part of survey data
collection, you can click “b” for Save To Server
task.
a b c d e 3. If the site have some problem and can't start TSS,
you can click “c” for Application Delay task and
also need to write-down reason.
4. If the site have some problem and can't start TSS,
you can click “d” for Pending Task and also need
to write-down reason.
5. If the survey person and document person are
different person, you can transfer task to other
person by “e” for Transfer Task.
© ZTE All rights reserved
10
2.How to use EPMS Webpage =======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
When finished the site survey, sub-con can login in webpage and then check and fill complete site information
When complete all the data, sub-con can submit the task;

 2.1 Step-1 How to login EPMS webpage

Login link “ http://mm.epms.zte.com.cn/ “ and then enter with Username and Password

Name/ID
c
Password

© ZTE All rights reserved


11
2.How to use EPMS Webpage =======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======

 2.2 Step-2 How to choose project

Click the “Switch Project”

2.Double Left Click

© ZTE All rights reserved


12
2.How to use EPMS Webpage =======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======

 2.3 Step-3 How to start E-TSS webpage


Site location pathway

1
2

5
© ZTE All rights reserved
13
2.How to use EPMS Webpage =======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======
 2.4 Step-4 How to fill site information
Find each function to fill the site information.

Choose each items to fill site information

Fill detail site information

© ZTE All rights reserved


14
2.How to use EPMS Webpage =======
=======
==============
=======
=======
=======
=======
Confidential▲
=======
=======
=======
=======
=======

 2.5 Step-5 Purpose of “Save" and “Submit" task

Submit Item

Save Item
When complete some part of TSS date click “Save”; [ Mean not 100% ]
When complete all the data click “submit”; [ Mean 100% complete ]
After click “submit”,can't change/update any data,it means end this task.