Principles of Project Management


Estefany Rodriguez

Continuing with the Suburban Homes Construction Project case study found at the end of
chapter 6 (and reviewing previous chapters 1 through 5), CPM 4e, complete the following
individual assignment:
Stakeholder identification and prioritization matrix

Importanc Contractor Material Potenti Constructio Communit Environment


e s suppliers al n Manager y leaders al regulatory
buyers

Power 1 3 1 3 1 1

Interest 3 3 3 3 2 2

Influence 1 1 3 3 3 3

Impact 1 3 2 3 1 3

Urgency 2 1 3 1 1 1

Legitimac 2 1 2 1 3 3
y

Total 11 12 14 14 11 13

Priority other secondar key key other key


(Key or y
other)
Harrisburg University of Science and Technology
Principles of Project Management
Estefany Rodriguez

Stakeholder Matrix (Exhibit 6-4)

Stakeholder Interest in the project Supportive/Mitigation strategies


Priority

Contractors Their services are used to Other Support them by providing the
complete quality work within necessary materials and
the scheduled times, their making the changes that they
feedback is key to the day-to- indicate so that the times can
day of the project. be met.

Material They are responsible for Secondary Quality standards for the
Suppliers providing the necessary materials that they provide us,
materials to start the project. provide the necessary
information and payments to
have the materials of good
quality in the agreed times

Potential They are the target audience; Key Assertive and attractive
buyers it is necessary that they know communication to attract them
the project and its qualities so and excellent customer service
that they want to buy it to keep them interested

Construction He is the person in charge of Key Maintain clear communication


Manager advancing the project and will to know what you need at the
work hand in hand with him right time and keep
so that everything is in order. expectations clear

Community Avoid any resource that Other Clear, direct communication


leaders brings negative and relevant times to avoid any
consequences, it is misunderstandings regarding
necessary to keep them the project
informed of any changes that
affect the environment of the
community

Environmental The project must go hand in Key Maintain an expert in the area
regulatory hand with the regulations of to help us avoid breaking the
the state of construction rules of the game
Harrisburg University of Science and Technology
Principles of Project Management
Estefany Rodriguez

Stakeholder Engagement Matrix (Exhibit 6-5)

Stakeholder Role in the project Engagement strategy Follow up strategy

Contractors Supportive or neutral Internal and highly Open communication


involve to know their needs
and support their
functions on the
project
Material Supportive External and highly Clear communication
Suppliers involve about timelines and
supply all quality
materials
Potential buyers Unaware External and not Follow up
involve communication and
customer service to
show the project and
have them interested
so they can reserve
the house and start
payments
Construction Supportive Internal and highly Involve in decision
Manager involve making, timelines,
charter, and
expectations for
project performance
Community Neutral External and not Open communication
leaders involve about the project and
its objectives in the
community
Environmental Neutral External and involve in Project approvals and
regulatory the project possible denials, follow
up with state policies
Harrisburg University of Science and Technology
Principles of Project Management
Estefany Rodriguez

Communication Matrix (Exhibit 6-9)

Stakeholder Project info Stakeholder info Methods Timing


needs needs
Contractors Direction on Progress on Face to face Every week
project project meetings,
videoconference
Material Quality Status of Mail or phone Once a week
Suppliers requirements materials
Potential Information Progress of the Mail, Phone, Daily
buyers about the project project and face to face fair
as quality, size, dates and events
times
Construction Requirements, Progress Face to face, Daily – 15 min
Manager timelines, eta, videoconference
charter
Community Community Community rules Face to face, Whenever is
leaders safety phone need it
Environmental Safety, Policies and Email, phone Every 2-3 weeks
regulatory instructions, resources
approvals or
denials