You are on page 1of 8

FEED Engineering Man-hour 산정 기준

설계 구분 Code 공종 Task (대분류)


FEED Engineering T3 General Familiarization
FEED Engineering T3 General Familiarization
FEED Engineering T3 General Familiarization
FEED Engineering T3 General Departmental reporting
FEED Engineering T3 General Departmental reporting
FEED Engineering T3 General Departmental reporting
FEED Engineering T3 General Authorities
FEED Engineering T3 General Meetings & Site visits
FEED Engineering T3 General Meetings & Site visits
FEED Engineering T3 General Tender preparation
FEED Engineering T3 General Personnel
FEED Engineering T3 General Estimate development
FEED Engineering T4 Process Diagrams
FEED Engineering T4 Process Diagrams
FEED Engineering T4 Process Diagrams
FEED Engineering T4 Process Studies
FEED Engineering T4 Process Studies
FEED Engineering T4 Process Studies
FEED Engineering T4 Process Equipment
FEED Engineering T4 Process Schedules& Lists
FEED Engineering T4 Process Schedules& Lists
FEED Engineering T4 Process Schedules& Lists
FEED Engineering T5 Mechanical Schedules & Lists
FEED Engineering T5 Mechanical Schedules & Lists
FEED Engineering T5 Mechanical Equipment
FEED Engineering T6 Piping Diagrams
FEED Engineering T6 Piping Diagrams
FEED Engineering T6 Piping Diagrams
FEED Engineering T6 Piping Studies
FEED Engineering T6 Piping Studies
FEED Engineering T6 Piping Studies
FEED Engineering T6 Piping Schedules & Lists
FEED Engineering T6 Piping Schedules & Lists
FEED Engineering T6 Piping Schedules & Lists
FEED Engineering T6 Piping Specification(Design)
FEED Engineering T6 Piping Specification(Design)
FEED Engineering T6 Piping Specification(Design)
FEED Engineering T6 Piping Specification(Design)
FEED Engineering T7 Civil Specification(Design)
FEED Engineering T7 Civil Detail Drawings
FEED Engineering T7 Civil Detail Drawings
FEED Engineering T7 Civil Detail Drawings
FEED Engineering T7 Civil Detail Drawings
FEED Engineering T7 Civil Lay-outs & Plot plans
FEED Engineering T7 Civil Lay-outs & Plot plans
FEED Engineering T7 Civil Lay-outs & Plot plans
FEED Engineering T8 Instrumentation Configuration & Specification
FEED Engineering T8 Instrumentation Configuration & Specification
FEED Engineering T8 Instrumentation Configuration & Specification
FEED Engineering T8 Instrumentation Design Specification
FEED Engineering T8 Instrumentation Design Specification
FEED Engineering T8 Instrumentation Studies
FEED Engineering T8 Instrumentation Studies
FEED Engineering T8 Instrumentation Studies
FEED Engineering T8 Instrumentation Studies
FEED Engineering T8 Instrumentation Schedules & Lists
FEED Engineering T8 Instrumentation Schedules & Lists
FEED Engineering T8 Instrumentation Schedules & Lists
FEED Engineering T8 Instrumentation Diagrams
FEED Engineering T8 Instrumentation Diagrams
FEED Engineering T8 Instrumentation Diagrams
FEED Engineering T8 Instrumentation Diagrams
FEED Engineering T8 Instrumentation Lay-outs & Plot plans
FEED Engineering T8 Instrumentation Lay-outs & Plot plans
FEED Engineering T8 Instrumentation Lay-outs & Plot plans
FEED Engineering T9 Electrical Diagrams
FEED Engineering T9 Electrical Diagrams
FEED Engineering T9 Electrical Diagrams
FEED Engineering T9 Electrical Diagrams
FEED Engineering T9 Electrical Diagrams
FEED Engineering T9 Electrical Lay-outs & Plot plans
FEED Engineering T9 Electrical Lay-outs & Plot plans
FEED Engineering T9 Electrical Lay-outs & Plot plans
FEED Engineering T9 Electrical Lay-outs & Plot plans
FEED Engineering T10 Procurement Studies
FEED Engineering T10 Procurement Studies
FEED Engineering T10 Procurement Studies
FEED Engineering T11 Construction Man Contract Documents
FEED Engineering T11 Construction Man Contract Documents
FEED Engineering T11 Construction Man Contract Documents
FEED Engineering T12 Project ManagemeReports
FEED Engineering T12 Project ManagemeReports
FEED Engineering T12 Project ManagemeQuality
FEED Engineering T12 Project ManagemeDepartmental Control
FEED Engineering T12 Project ManagemeDepartmental Control
FEED Engineering T12 Project ManagemeDepartmental Control
FEED Engineering T12 Project ManagemeSpecial FEL Tasks
FEED Engineering T13 Safety Inventory
FEED Engineering T13 Safety Ergonomics
FEED Engineering T13 Safety Ergonomics
FEED Engineering T13 Safety Health, Safety,Environment
FEED Engineering T13 Safety Health, Safety,Environment
FEED Engineering T13 Safety Health, Safety,Environment
FEED Engineering T13 Safety Health, Safety,Environment
Descriptions
Data retrieval, meetings, read scope, etc.
Data retrieval, meetings, read scope, etc.
Data retrieval, meetings, read scope, etc.
Activity Control Chart (ACC) & Document Control Chart (DCC), Progress (meetings), etc.
Activity Control Chart (ACC) & Document Control Chart (DCC), Progress (meetings), etc.
Activity Control Chart (ACC) & Document Control Chart (DCC), Progress (meetings), etc.
Labor inspection, local laws, inspection procedures, etc.
Meetings with clients and vendors, surveys, site visits, etc.
Meetings with clients and vendors, surveys, site visits, etc.
Write tender at the end of basic engineering (depends on contract strategy)
Extra personnel needed on the project
Input to 30% (basic), 20% (basic) and 10% (detail) estimate
PFD, P&ID, UFD, ESD. Need to be set-up
PFD, P&ID, UFD, ESD. Need to be set-up
PFD, P&ID, UFD, ESD. Need to be set-up
All equipment items require studies.General studies refers to studies like HAZOP, Design conditions
All equipment items require studies.General studies refers to studies like HAZOP, Design conditions
All equipment items require studies.General studies refers to studies like HAZOP, Design conditions
Preparation of datasheets per piece of equipment type.
Equipment list, Data sheets instrumentation, Line destination table.
Equipment list, Data sheets instrumentation, Line destination table.
Equipment list, Data sheets instrumentation, Line destination table.
Equipment & Insulation input to process, spare parts list, etc.
Equipment & Insulation input to process, spare parts list, etc.
Preparation of datasheets as well as the requisition and handling of this document
It represents the time needed to add to each diagram defined by process.
It represents the time needed to add to each diagram defined by process.
It represents the time needed to add to each diagram defined by process.
Stress analysis, Site & plot plans, Piping route study
Stress analysis, Site & plot plans, Piping route study
Stress analysis, Site & plot plans, Piping route study
Tie-in list, Drawing list, Line list etc.
Tie-in list, Drawing list, Line list etc.
Tie-in list, Drawing list, Line list etc.
For piping, erection, ewlding, painting, etc.
For piping, erection, ewlding, painting, etc.
For piping, erection, ewlding, painting, etc.
For piping, erection, ewlding, painting, etc.
Update owner specifications to the current project, e.g. for paving, painting, etc.
Drawings for structural, construction, architectural and underground
Drawings for structural, construction, architectural and underground
Drawings for structural, construction, architectural and underground
Drawings for structural, construction, architectural and underground
Paving drawings (new or update), Soil Report, Draingae lay-outs, etc.
Paving drawings (new or update), Soil Report, Draingae lay-outs, etc.
Paving drawings (new or update), Soil Report, Draingae lay-outs, etc.
Software specifications, I/O configurations, control system, etc.
Software specifications, I/O configurations, control system, etc.
Software specifications, I/O configurations, control system, etc.
E.g. Fire & gas detection spec, plant automation spec
E.g. Fire & gas detection spec, plant automation spec
Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc.
Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc.
Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc.
Per piece of equipment a study needs to be made. Also studies for analyzers, temperature, level, etc.
Cable schedules, drawing lists, process data sheets (input to process). One list of each is required
Cable schedules, drawing lists, process data sheets (input to process). One list of each is required
Cable schedules, drawing lists, process data sheets (input to process). One list of each is required
Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha
Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha
Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha
Many diagrams need to be made by instrumentation e.g. input on PFDs, P&IDs, but also cause & effect cha
Input to lay-outs & plot plans need to be made. For control rooms, cables, etc.
one
Inputdrawing needs
to lay-outs to beplans
& plot prepared
need to be made. For control rooms, cables, etc.
one drawing needs to be prepared
Input to lay-outs & plot plans need to be made. For control rooms, cables, etc.
one drawing needs to be prepared
A number of diagrams need to be setup once, and require minimum 1 update e.g. logic, key on line, panel
A number of diagrams need to be setup once, and require minimum 2 update e.g. logic, key on line, panel
A number of diagrams need to be setup once, and require minimum 3 update e.g. logic, key on line, panel
A number of diagrams need to be setup once, and require minimum 4 update e.g. logic, key on line, panel
A number of diagrams need to be setup once, and require minimum 5 update e.g. logic, key on line, panel
Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee
Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee
Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee
Input to lay-outs & plot plans need to be made. For lighting, earthing, power etc. one lay-out drawing nee
The following studies need to be made by procurement: Procurement plan, purchase procedure, subcontr
The following studies need to be made by procurement: Procurement plan, purchase procedure, subcontr
The following studies need to be made by procurement: Procurement plan, purchase procedure, subcontr
E.g. constructibility procedure, subcontracting plan, temporary site facilities plan need to be setup by cons
E.g. constructibility procedure, subcontracting plan, temporary site facilities plan need to be setup by cons
E.g. constructibility procedure, subcontracting plan, temporary site facilities plan need to be setup by cons
For example, Value Improvement Processes report, Project basis of design
For example, Value Improvement Processes report, Project basis of design
Quality audit plan need to be set up which describes when and how quality audits will be held
All kind of procedures are made, e.g. control, progress and planning procedures.
All kind of procedures are made, e.g. control, progress and planning procedures.
All kind of procedures are made, e.g. control, progress and planning procedures.
ITBs for contract need to be made and send out to contractors
An inventory of all necessary safety activities must be made
Reviews are needed to check if design applies to ergonomic standards. Also, a checklist must be set up
Reviews are needed to check if design applies to ergonomic standards. Also, a checklist must be set up
HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review
HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review
HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review
HSE contains e.g. Noise allocation report, Fire & gas review, Fire fighting study, Escape routing review
Man-hour Metrics Man-hour Metrics
Task (중분류) (Min.) (Max.) Unit
Data retrieval 9 24 hrs/department
Meetings 1 1 meeing/month
Read scope 1 week
ACC & DCC
update of ACC & DCC, progress control 1 1 a week
progress planning meeting 1 1 a month
Collect information of what's needed at the projec
Site visit 1 1 day/visit
Meetings
Tender preparation 2 3 weeks/discipline
Define per discipline the extra personnel needed

PFD(5 equipm./PFD) 3 5 days/PFD


P&ID (4 equipm/P&ID) 14 20 hrs/P&ID
UFD (3 equipm./UFD) 18 24 hrs/UFD
1 study/equipment 15 25 hr/study
1 HAZOP study 200 300 hr
Design conditions 60 100 hrs
depending on complexity of equipment 5 20 hr/equipment
Equipment list 2 3 hrs/equipment
Data sheets 2 4 hrs/control or relief valve
Line dest. Table 0.5 1 hrs/line number
Equipment & Insulation input
Spare parts list
depending on type of equipment and complexity 20 100 hrs/equipment type
12 18 hrs/PFD
26 34 hrs/P&ID
20 24 hrs/UFD
Stress analysis 28 36 hrs/stress isometric
Site & plot plans 22 30 hrs/unit or on-site plan
Piping route study 38 46 hrs/main equipment and main pipe rack
Tie-in list: 20 tie-ins/sheet 36 40 hrs/sheet
Drawing list: 24/sheet 14 18 hrs/sheet
Line list 60 70 hrs
Piping 20 24 piping class
Erection 16 20 specification
Welding 8 12 hrs/welding class
Painting 8 12 hrs/specification
8 12 hrs/specification
Structure plan 70 80 hrs/plan
Construction plan: e.g. foundation location plan 40 50 hrs/plan
Architectural: e.g. elevation plan 30 40 hrs/plan
Underground: e.g. drainage details 40 45 hrs/drawing
paving 65 75 hrs/drawing
Soil report 120 140 hrs/report
Drainage lay-outs 18 25 hrs/drawing
Software specification 10 15 hrs/specification
I/O configuration 20 30 hrs/configuration
Control system 35 40 hrs/specification
Fire & detection spec 75 85 hrs
Plant auotmation spec 20 28 hrs
Per piece of equipment 18 25 hrs/study
Analyzers 14 20 hrs/study
Temperature 6 10 hrs/study
Level 6 10 hrs/study
Cable schedules 28 35 hrs/schedule
Drawing list 15 20 hrs/list
Process data sheets 5 10 hrs/data sheet
Input to PFD/P&ID 8 12 hrs/diagram
Cause & effect chart 40 50 hrs/chart
I/O index 60 70 hrs
Cable routing 30 40 hrs/diagram
Input to lay-outs & plot plans 80 100 hrs/lay-out & plot plan
Control room 20 25 hrs
Cable drawing 25 30 hrs
Logic diagram 50 60 hrs
Key one line diagram 60 70 hrs
Panel wiring diagram 70 80 hrs
Interconnection diagram 70 80 hrs
Updates require 20 30 hrs less
Input to lay-outs & plot plans 70 80 hrs/lay-out
Lighting lay-out 10 15 hrs/lay-out
Earthing lay-out 50 60 hrs/lay-out
Power lay-out 10 15 hrs/lay-out
Procurement plan 100 120 hrs
Purchase procedure 100 120 hrs
Subcontract procedure 80 100 hrs
Constructibility procedure 60 75 hrs
Subcontracting plan 60 75 hrs
Temporary site facilities plan 35 50 hrs
VIP report 200 240 hrs
Project basis of design 70 100 hrs
Quality audit plan 30 45 hrs
Project control procedure 40 60 hrs
Progress procedure 40 60 hrs
Planning procedure 30 45 hrs
Setting up and sending out ITBS 200 300 hrs
Inventory of safety activities 18 25 hrs
Reviews at 30%, 60%, 90% of (model) progress 80 120 hrs/review
Checklist 70 90 hrs
Noise allocation report 100 130 hrs
Fire & gas review 30 40 hrs
Fire fighting study 50 60 hrs
Escape routing review 30 40 hrs
Man-hour Metrics
(기타)

Based On no of Document & activities

Find out requirements

Strongly depends on project size

ment and main pipe rack

You might also like