You are on page 1of 3

7 STORY BNC BUILDING

So. Superhighway, Acsie Ave., La Huerta Paranaque

Section IX
ANNEX F

MATERIAL AND EQUIPMENT


ORDER / DELIVERY SCHEDULE

The Bidder shall submit the Material and Equipment Order / Delivery Schedule showing :

A. The list of major long lead materials and equipment to be used for the Project
with quantities and origin.

B. A time scaled bar showing the different activities from the time of award of the
specific item up to delivery to Project Site.

In the Form (Annex F-1) provided, major activities are identified with Symbols and shall
be used in the flow of activities as required.

Example

AWARD OF CONTRACT / SUBCONTRACT

SUBMISSION OF SHOP DRAWINGS, BROCHURES AND SAMPLES

ORDER (SERVE L/C OR PAYMENT)

ETD, SOURCE

ETA, MANILA PORT OR AIRPORT

ETA, WORK SITE


NO. OF MONTHS
MONTHS 1 MONTHS 2 MONTHS 3 MONTHS 4 MONTHS 5 MONTHS 6 MONTHS 7 MONTHS 8 MONTHS 9 MONTHS 10 MONTHS 11 MONTHS 12
ITEM QTY ORIGINAL 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

Pipes and Fittings 1 Lot

Valves and Accessories 1 Lot

Consumables, etc. 1 Lot

Portable Fire
1 Lot
Extinguisher

Fire Hose Cabinet 1 Lot

Fire Pump and


1 Lot
Controller
Jockey Pump and
1 Lot
Controller

LEGEND :

MATERIAL & EQUIPMENT ORDER / DELIVERY SCHEDULE


BIDDER :
SIGNATURE : 7 STORY BNC BUILDING
DATE : So. Superhighway, Acsie Ave., La Huerta Paranaque
REMARKS

LEGEND :
Award of Contract / Subcontracts
Submission of Shopdrawings
or Samples
ETD, Source
ETA, Manila Port or Airport
ETA, Work Site

ORDER / DELIVERY SCHEDULE

7 STORY BNC BUILDING SECTION IX


So. Superhighway, Acsie Ave., La Huerta Paranaque ANNEX F-1