Full Report Beam Ecm366
Full Report Beam Ecm366
2020832708
EC1105G
The dimensions of the beams 200 x 450(A/1-2) and 200 x 400 (B/2-4). The reinforcement
used in the beams are 2T16(A/1-2),2T16(B/2-4) bottom reinforcement and 2T12(B/2-4) top
reinforcement. The links specification for the beams are R10-200(A/1-2) and R10-250(B/2-4).
The Grade of concrete used in this project is Grade 30 and the thickness of the formworks is
38mm and the nominal concrete cover is 25mm.
1
BASIC CONCEPTS
1) Concrete Volume
beam A/ 1-2
beam B/ 2-4
1/ 11.2 Length 11
0.2 add (+) (2) (1/2) column
0.4 (+) (2) (1/2) (0.2) 0.2
0.90 11.2
1.95
The table above shows the taking off for both beams. The total concrete required is 1.95m^3
2) Formwork
Beam A/ 1-2
1/
11.7 i) Outer
0.45 Length 11.5
add (+)(2) (1/2) column 0.2
5.27 11.7
ii) inner
1/ 11.3 Length 11.5
0.45 Less (-) (2) (1/2) Column
5.09 (-) (2) (1/2) (0.2) 0.2
11.3
beam B/ 2-4
i) Outer
1/ 11.2 Length 11
0.4 add (+)(2) (1/2) column 0.2
4.48 (+) (2)(1/2) (0.2) 11.2
ii) Inner
1/ 10.8 Length 11
0.4 Less (-) (2)(1/2) Column
4.32 (-) (2)(1/2) (0.2) 0.2
10.8
19.16
The total formwork that is required is 19.16m^2
2
3) Reinforcement
Beam A/1-2
i) Top & Bottom reinforcement 2T16
2/ Length 11.7
2/ 11.826 Less (-) (2) Cover
47.304 (-) (2) (0.025) 0.05
Add (+) (2) Bend (5.5D)
(+) (2) (5.5) (0.016) 0.176
11.826
Beam B/2-4
iii) Top reinforcement 2T12
2/ 11.762 Length 11.2
23.524 Less(-) (2) Cover
(-) (2) (0.025) 0.05
Add (+) (2) Bend (5.5D)
(+) (2) (5.5) (0.012) 0.132
Add (+) Lapping (40D)
(+) (40) (0.012) 0.48
11.762
Length 0.2
Less (-) (2) Cover
(-) (2) (0.025) 0.05
0.15
(2) (0.15) 0.3
3
(+) (2) Hook (12D)
(+) (2) (12) (0.01) 0.24
0.8
0.3
0.24
Total length 1.34
No. of R10
11.3/0.2 + 1(FOS) 57.5
Total of R10 58
Links(B/2-4)(R10-250)
Length 0.2
Less (-) (2) Cover
(-) (2) (0.025) 0.05
0.15
2(0.15) 0.3
0.7
0.3
0.24
total length 1.24
No. of R10
(10.8/0.25) + 1(FOS) 44.2
Total of R10 44
4
METHOD
Beam A/1-2
The side elevation view and the cross-sectional area of the beam A/1-2
5
Beam B/2-4
The side elevation view and the cross-sectional area of the beam B/2-4.
6
ANALYSIS OF RESULTS
The cost of the construction for the 2 beams, each material is calculated, and the total amount
comes out to RM2042.40 . The steels are converted from meter to kg using the formula Pi(r^2)
x length(m) x density of steel (7850kg/m^3).
Unit Conversion from m to kg :
T12: 23.524 m = 20.88 kg
T16: 71.236 m = 112.4 kg
R10: 132.18 m = 81.5 kg
REFERENCES
7
APPENDIX
Concrete price:
Formwork Price: