You are on page 1of 1

PROJECT : DESIGN OF RAW MATERIAL WAREHOUSE II AND BUCKET ELEVATOR TOWER/CONVEYOR

LOCATION: SAMAL BATAAN


OWNER : CHAROEN POKPHAND FOODS CORPORATION
SUBJECT : SUMMARY OF ACCOMPLISHMENT REPORT AS OF DECEMBER 31, 2022

ITEM PARTICULAR ACCOMPLISHMENT % WT. % TOTAL


1 Architectural plans 90.00% 25.00% 22.50%
2 Structural plans 90.00% 30.00% 27.00%
3 Plumbing plans 40.00% 15.00% 6.00%
4 Electrical Plans 40.00% 15.00% 6.00%
5 Estimates/BOM 90.00% 15.00% 13.50%
TOTAL 75.00%

Prepared by: Approved by :

Engr. Robby V Teresa


Asistant General Manager

Verified by:

MR. SUCHAI SAESHIH


CLIENT / REPRESENTATIVE