Professional Documents
Culture Documents
KARACHI
Suit No. 212 of 2019
Defendants
Nos. 1 to 3 : Getz Pharma (Private) Limited &
others, through Mr. Faisal Siddiqui,
Advocate.
ORDER
1
2. Clause 21 of the LOA read with Clause 15 of the
Instructions to Tenderers envisaged the submission of a
Performance Bond, which was to remain valid till
completion of the maintenance period under the Contract,
whereas Clause 10 of the LOA read with Clause 78 of the
General Conditions, provided inter alia that a
“Mobilization Advance of up to 10% of the Contract Price
shall be paid to the Employer in two equal parts upon
submission by the Contractor of a Mobilization Advance
Guarantee/Bond for the full amount of the advance in the
specified form from a Scheduled Bank in Pakistan or an
approved Insurance company”. In compliance of such
obligations, the Plaintiff accordingly arranged for a
Performance Bond and Mobilization Advance Bond
(hereinafter collectively referred to as the “Bonds”) in
favour of the Defendant No.1 through the Defendant
No.4/-, each being dated 01.06.2015, for the like amount
of Rs.80,938,821/- accordingly.
2
PROVIDED ALSO THAT the Employer shall be the
sole and final Judge for deciding whether the
Principal (Contractor) has duly performed his
obligations under the Contract or has defaulted in
fulfilling said obligations and the Guarantor shall
pay without objection any sum or sums up to the
amount stated above upon first Written Demand
from the Employer forthwith and without any
reference to the Principal or any other”
3
4. Whilst the Performance Bond was initially specified as
remaining in force from 01.06.2015 to 30.11.2016, vide
Endorsements dated 08.08.2017 and 09.08.2018 the
period thereof was extended with the amount secured
being reduced vide the first endorsement from
Rs.80,938,821/- to Rs.63,734,647/-, with the second of
these endorsements stipulating inter alia that:
4
6. Apparently, a dispute subsequently arose between the
Plaintiff and Defendant No.1 as to (i) alleged delays in
execution of works under the Contract, as well as (ii) the
quality of the works undertaken, and following
correspondence on the matter, the Contract then came to
be terminated by the Defendant No.1 in terms of a letter
dated 25.01.2019 (the “Termination Notice”), invoking
Sections 92(a) and 84(a) thereof, thereby calling upon the
Plaintiff to convey the factum of termination onwards to
all sub-contractors and suppliers, stop all works and quit
the project site, and to refund the unutilized Mobilization
Advance amount quantified at Rs.54,592,656/- as well as
liquidated damages in accordance with the terms of the
Contract. Vide separate letters dated 25.01.2019 and
28.01.2019, addressed to the Defendant No.4, the
Defendant No.1 also made calls for encashment in respect
of the Performance Bond and the Mobilization Advance
Bond respectively.
5
We hereby notify you by declaring in writing that the
principal has failed and committed default in
performing his obligations under the Contract.
G. Costs.” [sic]
7
10. Thereafter, an Application bearing CMA No.4702/2019
(the “Stay Application”) has also been filed under Section
34 of the Arbitration Act, 1940, quite remarkably on
behalf of the Plaintiff, seeking that the Suit be stayed in
light of the provision for settlement of disputes set out in
Clause 94 of the Contract. It is these three Applications
that are being addressed, as follows herein below.
8
S. 34. Power to stay legal proceedings where
there is an arbitration agreement. -Where any
party to an arbitration agreement or any person
claiming under him commences any legal
proceedings against any other party to the
agreement or any person claiming under him in
respect of any matter agreed to be referred, any
party to such legal proceedings may, at any time
before filing a written statement or taking any other
steps in proceedings, apply to the judicial authority
before which the proceedings are pending to stay
the proceedings; and if satisfied that there is no
sufficient reason why the matter should not be
referred in accordance with the arbitration
agreement and that the applicant was, at the time
when the proceedings were commenced, and still
remains, ready and willing to do all things necessary
to the proper conduct of the arbitration such
authority, may make an order staying the
proceedings.
9
15. Accordingly, it is apparent that the Stay Application is
10
17. Pressing his case for interim relief, learned counsel for the
Plaintiff contended that (a) the Performance Bond was
security for payment of liquidated damages, which could
not be granted without evidence, (b) that the terms of the
Bonds were vague and ambiguous, requiring evidence for
purpose of proper interpretation so that the intention of
the parties could be correctly discerned, (c) that the Bonds
were a conditional security, therefore evidence was
required to be recorded prior to encashment, (d) that as
the Bonds were insurance guarantees, the principle of
encashment applicable to a bank guarantee would not
apply, and (e) that no breach of the Contract had occurred
on part of the Plaintiff as the delays were attributable to
the Defendant No.1, hence termination of the Contract
and encashment of the Bonds was unwarranted.
25. It was pointed out that in the instant case, the Plaintiff
had not even alleged fraud and as far as special equities is
concerned, it was submitted that there were none
operating in favour of the Plaintiff.
14
26. It was submitted further that the principles laid down by
the Courts in relation to Performance Bonds and
Mobilization Advance Bonds issued by banks were equally
applicable to such bonds when issued by insurance
companies, reliance being placed on the judgment of a
learned single judge of the Islamabad High Court in the
case reported as Montage Design Build v. The Republic of
Tajikistan & 2 others‟, 2015 CLD 8. On this very point, it
was stated that the reference on behalf of the Plaintiff to
SRO No.696(I)/2018 dated 01.08.2018, issued under the
Insurance Ordinance, 2000 so as to contend that the
explanation to para 3 (1) served to demonstrate that
insurance guarantee and bonds were on different footing
from such guarantee and bonds issued by banks was
entirely misconceived. It was submitted that such an
interpretation of the Explanation to para 3 (1) was
patently incorrect as the explanation itself clarified that
such guarantee and bonds issued by Insurance
Companies „shall be claimable in accordance with the
terms and conditions provided in the contract of
guarantee‟.
15
(c) With reference to the case reported at 1993 CLC
1926, it was submitted that it was not clear from that
judgment whether the terms of the instrument under
consideration in that case were conditional and
whether the instrument itself contemplated that its
encashment would only take place on the condition of
default. It was submitted that the judgment could not
be relied upon for the proposition that performance
bonds cannot be encashed unless there is default
because such a proposition ran contrary to the
judgments of the Supreme Court in the cases of
Shipyard K. Damen (supra) and National
Construction (supra). Furthermore, it was pointed
out that whilst such judgment had indeed been
upheld by the Honourable Supreme Court, the
judgment of the Apex Court reported at 1989 SCMR
379 hinged on the point that interim orders and the
discretion exercised by a High Court is not ordinarily
to be interfered with unless such exercise is found to
be arbitrary, and could not be regarded as a
precedent that a performance bond cannot be
encashed without proven default.
17
(ii) The bank guarantee should be enforced on its
own terms and realization against the bank
guarantee would not affect or prejudice the case
of contractor, if ultimately the dispute is
referred to arbitration for the reason, once the
terms and conditions of the guarantee were
fulfilled, the bank's liability under the
guarantee was absolute and it was wholly
independent of the dispute proposed to be
raised.
33. Ergo, once a call had been made, as in the instant case,
the Court cannot then grant injunctive relief against the
beneficiary as the right to payment under the instrument
already stands crystallised when the call is made.
19
34. So far as injunctive relief against the issuer is concerned,
in such situations, an injunction could be granted in
theory only if the fraud exception were satisfied.
21
39. Additionally, in State of Maharashtra and another v. M/s.
National Construction Company, Bombay and another 1996
SCC (1) 735, as referred to in the case Shipyard K. Damen
(Supra), it was observed that:--
23
justifying interference by restraining the appellant
from enforcing the bank guarantees.”
JUDGE
Karachi
Dated ___________
26