CLIENT: MEANING EAST AFRICA CONNECTION COMPANY LIMITED

PROJECT: PROPOSED COMMERCIAL BLG

CONTRACTOR: SALAFY GROUP OF CONTRACTORS

COST OF LABOURS

SN ITEM / MATERIAL UNITY QTY RATE AMOUNT

EXCAVATION AND EARTHWORK

1.00 Site clearance and remove of Top soil No:Day 9.00 15,000.00 135,000.00
2.00 Excavating Footing and Trenches No:Day 10.00 20,000.00 200,000.00
3.00 Earth backfilling No:Day 8.00 13,000.00 104,000.00
4.00 Removal of surplus material No:Day 12.00 15,000.00 180,000.00
5.00 Levelling and compacting No:Day 7.00 13,000.00 91,000.00
6.00 Disposal of Water No:Day 5.00 13,000.00 65,000.00
7.00 Removal of planking and srutting No:Day 9.00 13,000.00 117,000.00
HARDCORE
8.00 Placing of 150mm thick hardcore layer No:Day 12.00 25,000.00 300,000.00

Garmmalin 20EC solution applied at a rate of 7 litres per


9.00 square metre to hardcore No:Day 2.00 13,000.00 26,000.00

Ditto at a rate of 8 liters per linear metres 300mm width x


9.00 300mm deep backfilling to one side of wall foundations No:Day 2.00 13,000.00 26,000.00

To collection Tsh 1,244,000.00

CONCRETE WORK
10.00 50mm Blinding Day 1.00 450,000.00 450,000.00
11.00 Strip footing grade 25 Day 1.00 520,000.00 520,000.00
12.00 Columns bases Day 1.00 800,000.00 800,000.00
13.00 Columns Day 1.00 1,024,000.00 1,024,000.00
14.00 Ground beams Day 1.00 690,000.00 690,000.00

REINFORCEMENT
15.00 20mm diameter Bar bender and fixer Day 4.00 180,000.00 720,000.00
16.00 16mm diameter Bar bender and fixer Day 3.00 160,000.00 480,000.00
17.00 8mm diameter Bar bender and fixer Day 3.00 130,000.00 390,000.00

Sawn formwork to:


18.00 Vertical sides of columns footing Day 4.00 230,000.00 920,000.00

19.00 Vertical side of columns Day 4.00 230,000.00 -920,000.00

20.00 Sides of ground beams Day 4.00 230,000.00 920,000.00

To collection Tsh 5,994,000.00

Vertical edges of slabs No:Day 2.00 80,000.00 160,000.00

Damp-proof Courses
Placing a dpc courde No:Day 3.00 30,000.00 90,000.00
Placing PUVC membraine No:Day 5.00 30,000.00 150,000.00

230mm Thick blockwok wall No:Day 12.00 30,000.00 360,000.00


External rendering to concrete block wall No:Day 4.00 30,000.00 120,000.00
100mm slab concrete No:Day 1.00 430,000.00 430,000.00
Floor finishing No:Day 6.00 50,000.00 300,000.00
CONCRETE WORK
Column No:Day 1.00 640,000.00 640,000.00
Horizontal beams No:Day 1.00 650,000.00 650,000.00
150mm thick gutter wall No:Day 12.00 50,000.00 600,000.00
230mm thick gutter wall No:Day 12.00 50,000.00 600,000.00
Gutter base No:Day 4.00 50,000.00 200,000.00
To collection TSH 4,300,000.00

REINFORCEMENT
20mm diuameter bar bender and fixer Day 5.00 180,000.00 900,000.00
16mm diameter bar bender and fixer Day 4.00 160,000.00 520,000.00
8mm diameter bar bender and fixer Day 4.00 130,000.00 520,000.00

Sawn formwork to:


Vertical or battering sides of columns Day 3.00 230,000.00 690,000.00
Sides and soffits of horizontal beams Day 5.00 230,000.00 1,150,000.00
Soffits of gutter Day 3.00 230,000.00 690,000.00
Sides of gutter wall day 2.00 150,000.00 300,000.00

WALL
230MM Wall No:Day 6.00 50,000.00 300,000.00
Wall copying No:Day 5.00 50,000.00 250,000.00

SAWN FORMWORK
First floor slab No:days 3.00 150,000.00 450,000.00
Beams N0:Day 2.00 230,000.00 460,000.00

REINFORCEMENT
First floor bar bender and fixer No:Day 3.00 240,000.00 720,000.00
Beam bar bender and fixer No:Day 4.00 250,000.00 1,000,000.00

CONCRETE WORK

First floor slab and beam concrete No:Day 1.00 1,350,000.00 1,350,000.00

To collection Tsh 9,300,000.00

GRAND TOTAL Tsh 20,838,000.00