1.00 Site clearance and remove of Top soil No:Day 9.00 15,000.00 135,000.00
2.00 Excavating Footing and Trenches No:Day 10.00 20,000.00 200,000.00
3.00 Earth backfilling No:Day 8.00 13,000.00 104,000.00
4.00 Removal of surplus material No:Day 12.00 15,000.00 180,000.00
5.00 Levelling and compacting No:Day 7.00 13,000.00 91,000.00
6.00 Disposal of Water No:Day 5.00 13,000.00 65,000.00
7.00 Removal of planking and srutting No:Day 9.00 13,000.00 117,000.00
HARDCORE
8.00 Placing of 150mm thick hardcore layer No:Day 12.00 25,000.00 300,000.00
CONCRETE WORK
10.00 50mm Blinding Day 1.00 450,000.00 450,000.00
11.00 Strip footing grade 25 Day 1.00 520,000.00 520,000.00
12.00 Columns bases Day 1.00 800,000.00 800,000.00
13.00 Columns Day 1.00 1,024,000.00 1,024,000.00
14.00 Ground beams Day 1.00 690,000.00 690,000.00
REINFORCEMENT
15.00 20mm diameter Bar bender and fixer Day 4.00 180,000.00 720,000.00
16.00 16mm diameter Bar bender and fixer Day 3.00 160,000.00 480,000.00
17.00 8mm diameter Bar bender and fixer Day 3.00 130,000.00 390,000.00
Damp-proof Courses
Placing a dpc courde No:Day 3.00 30,000.00 90,000.00
Placing PUVC membraine No:Day 5.00 30,000.00 150,000.00
REINFORCEMENT
20mm diuameter bar bender and fixer Day 5.00 180,000.00 900,000.00
16mm diameter bar bender and fixer Day 4.00 160,000.00 520,000.00
8mm diameter bar bender and fixer Day 4.00 130,000.00 520,000.00
WALL
230MM Wall No:Day 6.00 50,000.00 300,000.00
Wall copying No:Day 5.00 50,000.00 250,000.00
SAWN FORMWORK
First floor slab No:days 3.00 150,000.00 450,000.00
Beams N0:Day 2.00 230,000.00 460,000.00
REINFORCEMENT
First floor bar bender and fixer No:Day 3.00 240,000.00 720,000.00
Beam bar bender and fixer No:Day 4.00 250,000.00 1,000,000.00
CONCRETE WORK
First floor slab and beam concrete No:Day 1.00 1,350,000.00 1,350,000.00