Professional Documents
Culture Documents
Review of pile load test requirement
#
# Quality control test on bored piles
Number
&
Spacing
Depth
BCA/IES/ACES Advisory Note 1/03
Pile Load test requirement
for foundation of buildings of 10-storeys and above
11
8 possible designs using alternative procedure
under DA1-2
Design 1 Design 2 Design 3 Design 4
Model factor 1.2 1.2 1.4 1.4
Partial resistance 1.3 1.5 1.3 1.5
factors (γs, γb)
1.5 1.7 1.5 1.7
Overall safety factor
(approx.)
1.85 2.11 2.16 2.46
12
Illustration
Fc;d
• 1 m diameter bored pile is subject to axial
compression load, with :
L2
qs,2,k
(200 kPa) Find required pile penetration depth using:
a) CP4
If 1 ULT and 1%(ULT+WLT) If no pile load test ULT and WLT are
are carried out usually carried out
are carried out
– Recommendations in Eurocode 7
– 1 per 300m2,
– 2 per block,
– 3 per site
• Spacing of boreholes
– 1 per block
– 2 per site
• Spacing of boreholes
The deeper of :
Boulders
FCBB
Cavity
3
5
m
20
Steeply inclined bedrock
21
Hello (2)
How are
Review
you? of Pile
Load Tests
BCA/IES/ACES Advisory note 1/03
on site investigation & load test
Pile Load Tests for buildings of 10-storey or more
Joint BCA/IES/ACES/GEOSS
BCA/IES/ACES/GEOSS Circular 2016
For buildings of 10-storeys or more
• Requ
Requir
irem
emen
ents
ts on pil
pile
e load
load tes
testt & int
integ
egri
rity
ty tes
tests
ts are
are maintained
maintained..
Table 1
Type of Pile Tests Pile test schedule
(a) Ultimate Load test (ULT) 1 number or 0.5% of piles, whichever is
greater
For buildin
buildings
gs of 5 to 9 storeys
storeys with footprin larger than 100 m2
footprintt larger
Table 2
Type of Load Test Pile Test Schedule
EN 1997-1:2004 Cl 7.5.2.1(2)
• Devices for determination of loads, stresses,
strains and displacements should be calibrated
prior to the test.
28
Sonic Logging test
• Also known as Ultrasonic
Crosshole Testing, Crosshole
sonic logging
SS CP4 Cl 7.5.5.4
Limiting rate of movement = 0.25
mm/hr
Typically 4 - 6 days
A maintained load test may take 4-6 days, with each load increment 36
maintained for a duration till a limiting rate of movement is reached.
Use of Rapid Load Test
1. Rapid load test is not static load test and do not have
the same degree of reliability and precision as static
load test using maintained load.
39
Reduction factor
40
Use of Rapid Load Test
BS 8004:2015
Example of calibration test
Statrapid (3/3/2014) Static load test (24/3/2014)
Settlement at 1xWL 3.7mm 3.9mm
Settlement at 2xWL 9.5mm 7.9mm
42
Statrapid Static
Hello (4)
How are
you?
Quality control test
on bored piles
Why Quality Control Tests ?
to improper concreting
method, collapse of
unstable pile bore due
Competent Soil
to inadequate bore layer
support
Soil debris
Defects of bored pile
• Defects of bored piles can affect pile structural integrity and
their load carrying capacity.
Soft toe
Execution will affect design
Design Execution
(a) Interface coring test 5% of total number of piles, but may be reduced to
at pile base 2% if base grouting is carried out.
(to assess verticality and (i) have no steel casing going through soft or loose
shapes of pile bore prior soil layer during construction
to concreting) or
(ii) have no redundancy*.
e.g. Koden, SoniCaliper
For piles ≤1.8m, QP shall determine the
number of pile profile tests needed.
50
Why concrete core test on bored pile ?
• If adopting fcd,pile = 0.3636 fck in structural design for lightly reinforced bored pile
using EC2, minimum characteristic concrete cube strength f cu of 40 MPa is
required to achieve allowable stress of 7.5 MPa.
61
Lesson learnt
62
Proposed changes in forms
relating to specialist builder
NEW CHANGES TO PERMIT, NOTIFICATION OF BUILDER FORM AND BUILDER CERTIFICATE (BC) FORMS
ii. For the specialist building works which the General Builder is not the
Specialist Builder, he will need to declare that Specialist Builder(s) will be
appointed to carry out the specialist building works.
NEW CHANGES TO PERMIT, NOTIFICATION OF BUILDER FORM AND BUILDER CERTIFICATE (BC) FORMS
i. Specialist Builder to declare that he has e&ecuted the following specialist building
works in accordance with the plans as supplied by the 'ualified Person(s) and in
accordance with all the pro!isions in the $ct and egulations
A comparison of the OLD with the NEW
Items New Old
Circular advisory
2016 note 2003
1. Site investigation (10-storeys or more) √ √
1. Site investigation (5 to 9 storeys) √
2. Pile load test & integrity test (10-storeys or more) √ √
2. Pile load test & integrity test (5 to 9 storeys) √
3. The use of rapid load test √
4. Quality control tests on bored piles (10-storey or more) √
5. Design and construction of bored piles √
Summarising remark
• Since July 2015, BCA has engaged IES, ACES and GEOSS to work
on a joint circular on requirements of piled foundation, covering:
Ground investigation
Load test & integrity test
Use of Rapid load test
Quality Control tests for bored piles
Design and construction of bored piles
• The working group on the joint circular has taken into consideration
the following:
– Eurocodes
– CP4
– BCA/IES/ACES advisory note 1/03
– GEOSS guidelines
– Current industry practice
Summarising remark