Professional Documents
Culture Documents
Presented by:
Ooi Poh Hai
31 August 2015
o Geotechnical Capacity – BS/CP4
o Geotechnical Capacity – EC7
o Consideration of Ground Condition
o Case Study – Site A
o Case Study – Site B
GEOTECHNICAL CAPACITY
BS/CP4
𝑄𝑠 + 𝑄𝑏
𝑄𝑎 = (FS = 2 -3 , 2.5 is generally adopted)
𝐹𝑆
𝑄𝑠 𝑄𝑏
𝑄𝑎 = +
1.5 3.0
Qa = allowable geotechnical capacity,
Qs = total ultimate shaft resistance
Qb = total ultimate end bearing
𝑄𝑠 = 𝜋𝐷𝐿𝑓𝑠
𝑓𝑠 = 𝐾𝑠 × 𝑆𝑃𝑇𝑁 (𝑘𝑃𝑎) (Ks = 2 – 5, fs limited to 200kPa)
𝑄𝑏 = 𝐴𝑝 𝑓𝑏
𝑓𝑏 = 40 × 𝐾𝑏 × 𝑆𝑃𝑇𝑁 (𝑘𝑃𝑎) (Kb = 6 – 9, fb limited to 18MPa)
* The Ks and Kb values are recommended values for driven piles in CP4
GEOTECHNICAL CAPACITY
EC7
“Alternative Method”
“Alternative Method”
o Resistance calculated from characteristic soil properties, such as by correlation with SPTN
“Alternative Method”
• Designs by EC7 generally gain lower equivalent FS in total resistance and end
bearing compared to BS/CP4, but higher FS on shaft resistance
• Factors on total resistance and end bearing are the same. Hence consider
partial factor on shaft resistance and end bearing always gain higher capacity
o Characteristic resistance is then derived from the measured mean and minimum
resistance by applying 1 & 2 factor. The 1 & 2 factor drops with the increase in
number of tested piles
• Equivalent FS generally < 2.5 and dropping with number of tested piles
CONSIDERATION OF
GROUND CONDITION
o The design, site implementation and performance of end products are highly
dependent on ground condition
o Detailed desk study is essential to identify any potential issues based on the SI of each
site
o Examples….
o Re-tapping?
o Need pre-boring
o Boulders in soils
o Jacked-in Spun Piles. 500mm & 600mm, with WL = 1700kN & 2300kN, mixed with
300x300 RC piles with WL= 1000kN for light structures
o Ground condition – Bukit Timah Granite Formation with thick layer of GVI / GV (N < 50)
Approx. pile
toe level
o Pile Load Test – 6 nos. of ULT loaded to 3WL, 10 nos. of WLT loaded to 2WL
o Stiff load – settlement behavior, with pile head settlement < 6mm at1 WL, < 16mm at 2WL &
< 20 mm at 3WL
Settlement
Reference Diameter Penetration Max test
1 X WL 2 X WL
Load
ULT-1 600 mm Spun pile 31.5 1.60 3.20 7.55
ULT-2 600 mm Spun pile 30.3 3.80 6.85 10.92
ULT-3 600 mm Spun pile 35.6 4.45 9.05 15.05
ULT-4 600 mm Spun pile 34.8 2.60 6.60 10.80
ULT-5 600 mm Spun pile 28.0 1.75 6.20 10.95 Load settlement
ULT-6 600 mm Spun pile 34.8 4.45 7.35 11.35
SLT P37/7C1 500 mm Spun pile 25.7 4.50 8.40
response of ULT is
SLT P78/8C7 500 mm Spun pile 25.7 3.55 8.85 stiffer than WLT.
SLT 538/P44A 500 mm Spun pile 30.7 4.25 7.00
SLT P592/9C43 500 mm Spun pile 28.2 5.75 10.15
Installation effect???
SLT P267/7LC2 600 mm Spun pile 33.4 4.50 9.85
SLT P-300 600 mm Spun pile 33.4 4.65 14.60
SLT P161/6SC1 600 mm Spun pile 33.5 4.15 9.25
SLT P221/8LC1 600 mm Spun pile 30.4 1.70 16.05
SPT P798/2LC1 600 mm Spun pile 33.4 4.95 10.80
SLT P985/3C20 600 mm Spun pile 27.7 5.90 7.40
4
Pile head Settlement
ULT-1
6
ULT-3
8 ULT-4
10
12
14
1WL 2WL
16
Load
0 100 200 300 400 500 600
0
4
P161
Pile head Settlement
6 P221
8 P330
~9mm P762
10 P798
~12.5mm
12
14
16
18
o Jacked-in RC Precast Piles. Pile size = 250x250 & 300x300, with WL = 620kN &
900kN respectively
o Ground condition – Bukit Timah Granite Formation overlying by soft sandy clay, thin layer
of GVI / GV layers above competent layer
o Pile Load Test – 2 nos. of ULT loaded to 3WL, 10 nos. of WLT loaded to 2WL
o Pile head coordinates & levels of selected piles (49 nos. of piles) were monitored
o Stiff load – settlement behavior, with pile head settlement < 5mm at1 WL, < 10mm at
2WL
Settlement
Max test
Reference Diameter Penetration Max test
load 1 X WL 2 X WL 2.5WL
Load
ULT-1 250 X 250 RC pile 23.8 190.0 2.60 8.25 10.00 15.05
ULT-2 300 X 300 RC pile 14.7 270.5 4.15 9.00 13.00 45.85
10
20
ULT-1 (250X250)
Settlement
ULT-2 (300X300)
30
40
50
60
o Out of 10 nos. of WLT, 8 nos. completed with satisfactory results, with pile head
settlement < 6.5 mm at 1WL, < 17mm at 2WL
Load
0 20 40 60 80 100 120 140 160 180 200
0
BC4-5
4
BC9-4
6 BC10-3
BC11-5
Settlement
8 BC21-3
BC62-7
10
LW2-7
12 SW4-9
14
16
18
Load
0 20 40 60 80 100 120 140 160 180 200
0
5
8.3mm
10
15
BC11-4
Settlement
20 BC11-4 Re test
25
30
35
40
45
Load
0 20 40 60 80 100 120 140 160 180 200
0
6.75mm
10
20
BC22-1
Settlement
BC22-1 Re test
30
40
50
60
• A short 10.5m pile and the 1st pile to be installed in a group. Monitored pile heaving ~
40mm. Behaviour of end bearing more similar to virgin loading instead of reloading
response expected for jacked-in piles