1. EVM calculations.

Cv = EV – AC ; 640,000 – 650,000 = -10,000


Sv = EV – PV ; 640,000 – 630,000 = 10,000

Budget = 3 million
Pv = 630,000
Ac = 650,000
EV = 640,000

EV > PV : on schedule
EV < CV : over budget
The project is ahead of schedule and over budget
2. The first step is understanding the project goals and business case. Then you will be able to
develop a project charter. The other options come in later

D correct (first do D then c)


A comes in execution
B comes in planning
3. Ensure all change management process requirements are followed and scope creep is
reduced.
A correct
B in agile
D is engagement
4. The monitoring of communications process may improve communication by revising
communications plans and activities. Project communication management is a co…. process
You don’t have to take actions right away,
D not correct because you need a formal process and formal change request
C you have to understand
B you just cant change it, you have to review it assess it then come up with correct changes
and then approve it
A correct
5. Always follow the documented and agreed upon change control process
B correct
A wrong : never just implement change before change request
6. Always follow the documented and agreed upon change control process
C correct
B wrong, you just cant go ahead and implement the changes, you have to stick to the change
management plan
7. Fast tracking is a schedule compression technique used to shorten the schedule duration by
running a few different task in parallel. This will generally increase the risk on the project
A correct
8. Sprint/iteration/burn up/burn down etc means agile project. Choose 2
Burnup and burndown charts will display work that has to be done and that is already done
A and B
9. Team velocity is done by reviewing previous sprints to estimate how work could get done in
the next sprint.
C correct
10. You evaluate the change and then submit the change request.
Risk should be assessed against all project objectives
You evaluate the change first
A correct. You have to assess the changes,