Professional Documents
Culture Documents
Course PM Pro
1 | Page
Integration Management
1. A new project manager has been hired in your company, and you have been asked to mentor her.
Because she is well trained, she is planning her project in great detail. Her first project for the
company is relatively low priority, and you feel that the project manager is planning too many
project control meetings. Which of the following would be the BEST thing to tell her?
A. Strike a balance between the extent of the control system and the risk of unfavorable project
outcomes.
B. Make sure you identify more than 40 risks, and then have more than one meeting a month
C. A good project management plan should be about90 percent complete before starting work
D. Make sure you include milestones to help plan the project charter.
2. In the process of reviewing the status of your team’s work assignments, you learn that the project
has fallen behind schedule by one week. The project has high visibility within the organization and
is completely date-driven. The project finish date is still two months out and you think you can
recover the time over the next month or so. What is the BEST course of action for reporting the
project status?
A. Report the project on schedule. This is not a significant slippage and there is still time to
recove
r
B. Report the project on schedule. Most project management plans are not accurate to less than
one or two weeks
anyway
C. Report the project one week behind schedule and include recommended corrective actions
D. Report the project one week behind schedule and then issue a new report next week showing
them the problem fixed
3. The project has been going relatively well, although there have been some problems with resource
availability and the project scope has changed more than was expected. The project is now
completing one of its phases. Of all decisions the sponsor must consider during and end-of-phase
review meeting, the MOST difficult is:
A. Authorizing scope change for the next phase
B. Authorizing budget increases for the next phase based on scope changes
4. Though it was difficult, the project manager received agreement to the project charter from all four
sponsors involved on the project and the US $400,000 project was approved. Now the cost
variance for the project is -$500 and the last performance review was positive.
Just when the project entered its second phase, a team member on a noncritical path
activity
announced she was leaving the company. The float of activity L changed from two to four days.
Only one unidentified risk has occurred with a minor impact. The last quality review showed that
the project has made use of the results of the last design of experiments. Based on this
information, what should the project manager do NEXT?
D. Investigate additional risks caused by the difficulty with the senior managers.
5. All of the following are part of the Close Project or Phase process EXCEPT:
A. Collection of records
6. Which of the following BEST describes what a project charter may be used for when the work is
being
completed?
2 | Page
Practice Questions PMP Exam Prep. Course PM Pro
7. You are making another international trip and have been invited to a holiday celebration, you
discover that all of the subcontracted work for the project has been given to one of the team
member’s brothers. What should you do?
D. Tell the team member that such actions are not allowed.
8. Which of the following would be the MOST appropriate thing to do during the executing process
group?
9. You are part of a team that has been told by your management that they require you to take and
pass the PMP exam by the end of the year. After studying, you are the first of the group to take
the actual exam. When you return to work to tell everyone you passed, you are bombarded with
questions. Management tells you that since everyone else is so worried about the exam, they
want you to write out all the questions you can remember from the exam and provide copies to
the rest of the team. In this situation, you could do all of the following EXCEPT:
C. Explain that providing questions from the actual exam is specifically prohibited
D. Explain that you may have passed the exam, but you are not an expert. The team should
follow the expert advice that they were given on how to study and pass the
exam.
10. If a project manager is not satisfied with the way of gathering, integrating, and disseminating the
outputs of all project management processes, she should concentrate on creating a
better:
A. WBS
11. While reading a magazine article, you discover that there is a tool of project management that
other companies are using, but that your company has never heard of. What should you do?
D. Summarize your opinion of the benefits of using this information in your company. Present
your analysis to your
manager
12. The customer has accepted the completed project scope. However, the lessons learned required
by the project management office have not been completed. What is the status of the project?
B. The project is incomplete until all project and product deliverables are completed and accepted
C. The project is complete because the customer has accepted the deliverables
D. The project is complete because the project has reached the due date
13. You are the project manager for one part of a new program in your organization. You are four
months into a three-year project when your project team makes significant discoveries on your
project. What is the BEST thing to do?
A. Make certain the discoveries are included in the project lessons learned
C. Make certain you mention the discoveries at the senior management meeting in two months
D. At the weekly meeting, make certain you tell the other project managers involved in this
program about the
discoveries.
4 | Page
Practice Questions PMP Exam Prep. Course PM Pro
14. You are halfway through a major network rollout. There are 300 locations in the United States,
with another 20 in England. A software seller has just released a major software upgrade for some
of the equipment being installed. The upgrade would provide the customer with functionality they
requested that was not available at the time the project began. What is the BEST course of action
under these circumstances?
B. Inform the customer of the upgrade and the impacts to the project’s timeline and functionality if
the upgrade is implemented
C. Implement the change and adjust the schedule as necessary because this supports the
customer’s original
request
D. Implement the change to the remaining sites and continue with the schedule.
A. The project scope is completed, administrative closure is completed, and payment is received.
B. Formal acceptance is received, and any other requirements for project closure as stated in the
contract are
met
16. A team member notifies you that she has added extra functionality to the project. She tells you
there was no impact on the cost or schedule. What should be done as a result of this change?
17. In the course of completing work on the project, the project manager needs to complete an activity
that she has never done before. During this time, the project manager attends a professional
association discussion where the presenter discusses how he completed a difficulty activity on his
project that is similar to the project manager’s activity. He provides a handout describing his process.
The project manager should:
18. At the end of a two-year project, the key stakeholders agree that the project has met all its
objectives outlined in the project charter and further defined in the scope and statement of work.
The project was within budget and has finished on time. The management of one of the
functional areas is quite upset because over half of his staff quit during the project citing long
hours and lack of management support. What is the MOST correct statement about this project?
A. The project was within budget and time and achieved its objectives. Upper management is
responsible for providing adequate resources, and the project manager
successfully managed the project with available resources.
B. The project should be measured against how successfully it met its project charter. This was
not done during this project.
C. The project manager did not obtain adequate resources and did not set a realistic deadline
based on resources
available
D. The functional manager is responsible for his staff and obtaining adequate resources to meet
the schedule once it has been set. The project and project manager achieved all of its
objectives set forth in the project charter
19. A stakeholder wants to make a change to the work breakdown structure that does NOT affect the
time or cost of the project. What is the BEST thing to do?
A. Tell the stakeholder that this change cannot be made without revising the project management
plan
6 | Page
Practice Questions PMP Exam Prep. Course PM Pro
20. Your company has a policy that only a certain hotel chain may be used for business travel. You
discover that a more expensive hotel is offering a discount on the days you need to be in
town. What should you do?
A. Ask your manager for permission to use the other hotel chain
D. Provide justification on your expense report for using the other hotel chain.
21. At a critical milestone in development project, it is determined that implementation is two months
behind schedule. The project manager is concerned that the root cause is lack of conformance to
requirements in the design of the new billing system. More extensive measurements are taken to
see if this is, in fact, the problem. Such measurements are:
22. Which of the following BEST describes when a project phase is generally concluded?
A. When the work is done
23. You are a project manager on an international project of great importance to the client. The client
is from another country and is so excited by how well the project is going that he presents you
with a company automobile for your personal use. The BEST thing for you to do would be:
C. Ask that the gift be exchanged for something that can be shared by the team
7 | Page
Practice Questions PMP Exam Prep. Course PM Pro
D. Ask for a gift that can be used up before you return home
24. A company is attempting to select the BEST project from a list of possible choices. If the
information they have includes the following benefit cost ratios, which project should they
pick?
A. 2.2
B. 1.3
C. 0.8
D. 1.6
25. After a great deal of effort, the project team has finally determined the specifications for a
major
scope change to the project. In light of this, what should the project manager do FIRST?
A. Look for other changes
26. While the project is being completed, management requests a change. What is the FIRST thing
the project manager should
do?
27. A team member notifies you, after the fact, that she has added extra functionality to the project.
There was no impact on the cost or schedule. What should be done as a result of this change?
8 | Page
Practice Questions PMP Exam Prep. Course PM Pro
28. All of the following are parts of the project initiating processes EXCEPT:
29. The sponsor has asked you to require that each piece of the project scope be planned, estimated,
and scheduled. The sponsor also wants to authorize each piece of the project management plan
after the documentation is assembled. What is the MOST appropriate response to these
requests?
B. Provide the sponsor with a schedule of when the components will be ready for authorization
D. Tell the sponsor that the chance for authorization will come after the pieces of the project
management plan are
compiled
30. To accommodate a new project in your department, you need to move resources from one project
to another. Because your department is currently working at capacity, moving resources will
inevitably delay the project from which you move the resources. It would cause the LEAST
negative impact if you move resources from which of the following projects?
A. Project A with a benefit cost ratio of 0.8, no project charter, and four resources
B. Project B with a net present value of $60,000, 12 resources, and variable costs between US
$1,000 and $2,000 per
month
C. Project C with an opportunity cost of US $300,000, no project control plan, and an internal rate
of return of 12 percent
31. When it comes to change, the project manager’s attention is BEST spent
on”
A. Making changes
9 | Page
Practice Questions PMP Exam Prep. Course PM Pro
32. Which of the following processes involves creating a coherent, consistent document that can be
used to guide all the work in both project executing and project monitoring and controlling?
A. Risk management
D. Plan Quality
33. All of the following are the responsibility of a project manager EXCEPT:
C. Ensure that a conflict of interest does not compromise the legitimate interest of the
customer
34. The buyer asks the project manager for the status of the project that his team is working on. What
is the BEST way to determine the status of a
project?
C. Compare the project performance against the integrated change control plan.
D. Compare the number of people used on each work package to the planned number to be used.
35. You are assigned to a project that senior management has already decided to outsource. As a
project manager, you need to work with the contracts department to select the vendor and then
oversee the vendor through the project completion. Company policy requires that a project of this
size go through a formal bid process. A vice president in your company tells you that his friend owns
one of the companies that might bid on the project and that the company would be an
10 | Page
Practice Questions PMP Exam Prep. Course PM Pro
excellent choice as a vendor. This vice president has a reputation for making or breaking careers.
What is generally the BEST course of action?
A. Follow the bid process, and show the vice president why the favored vendor is or is not the best
choice
C. Let the evaluation team know that management has a favorite vendor
36. The project for the accounting department has been going well when the company says that it
must reduce the cost of the project without changing the quality requirements. The project manager
has looked to trim any resources, paid more attention to risk on upcoming activities, and even has
reduced product scope, but the project remains over the new budget limit. Which of the following
should the project manager do NEXT?
38. The project manager has noticed that there have been a lot of changes on the project. This has
not been considered to be a problem until one day he discovers that he cannot determine how
many scope changes are currently being reviewed. This problem would be an error in which of the
following?
11 | Page
Practice Questions PMP Exam Prep. Course PM Pro
39. You are a project manager who was just assigned to take over a project from another project
manager who is leaving the company. The previous project manager tells you that the project is
on schedule, but only because he has constantly pushed the team to perform. What is the FIRST
thing you should do as the new project manager?
41. A single point of failure (SPOF) is the part of a system that, upon failure, stops the entire system
from working or makes the system useless. Which of the following events can render a
knowledge management system ineffective?
42. While constructing a new drug manufacturing plan, you discover a leak in a pipe which has
released chemicals into the ground. It was difficult to acquire the necessary government approval
and community support for the plant, and management has told you to be particularly careful to
not upset the community. You are uncertain of whether the chemicals could leak into the
groundwater or cause any damage. What should you do?
12 | Page
Practice Questions PMP Exam Prep. Course PM Pro
B. Start to write articles in the local paper about how poorly treated the local drinking water is.
C. Wherever possible, communicate all the great benefits of the plant to the community.
43. Your organization is having a difficult time managing all of is projects. You have been asked to
help senior management get a better understanding of the problems. What do you do FIRST?
A. Meet with individual project managers to get a better sense of what is happening
B. Send a formal memo to all project managers requesting their project management plans
C. Meet with senior managers to help them develop a new tracking system for managing projects
D. Review the project charters and bar charts for all projects.
44. A person is writing a document identifying the business need for a project and is including a
description of the product is created by the project. She includes a list of stakeholders and
preassigned resources. What is the role of this person on the project?
B. A member of the project management team working at the direction of the project manager
D. A manager or executive in the organization who is higher in the corporate hierarchy than the
project manager.
45. An employee approaches you and asks to tell you something in confidence. He advises you that
he has been performing illegal activities within the company for the last year. He is feeling guilty
about it and is telling you in order to receive advice as to what he should do. What should you do?
46. Which of the following is the BEST method to control changes on the project?
47. A project manager has just been assigned to a project that has been in progress for two months
when a team member requests more time on an activity he is working on. The project manager
discovers that the only impact to the project will be a delay on a noncritical path activity. The customer
has emphasized the importance of completing the project on schedule. What should the project
manager do NEXT?
A. Submit the information to the change control board, determine if this event might impact the
team member’s future work, inform the team member of the board’s
decision
B. Ask the team member why they need more time, begin integrated change control, adjust the
project schedule as
needed
C. Look for impacts to quality, cut unneeded scope from the project, ask for more resources
D. See if any stakeholders object to the change, calculate the exact impact on the project, look at
removing this resource from the
project
48. You have been working on a very large software development project that has made use of more
than 230 people. Finally, all the scope has been completed. It would be BEST to:
A. Throw a party for the team members
49. Adhering to legal requirements, satisfying competing needs, providing accurate and truthful
representations, and disclosing conflicts of interest are
all:
14 | Page
Practice Questions PMP Exam Prep. Course PM Pro
50. A company is making an effort to improve its project performance and create historical records of
past projects. What is the BEST way to accomplish this?
51. Project knowledge management is concerned with managing which type of project
knowledge?
52. Jane is currently reviewing a list of project proposals. All the proposed projects achieve some of
the organizational strategic objectives and their expected costs are known. However, Jane cannot
execute all the projects due to the funding limitation. How shall Jane determine which projects she
needs to execute this year?
15 | Page
Practice Questions PMP Exam Prep. Course PM Pro
16 | Page
Scope
Management
1. During what part of the project management process is the project scope statement created?
A. Initiating
B. Planning
C. Executing
2. A project manager is performing an audit on a deliverable when she hears that the team member
who did the work is complaining to everyone that he is being picked on by having his activity
audited. You know this is not true. What lesson learned could you take to future projects?
A. Tell all the team members at the beginning of the project that their deliverables will be audited
3. A project manager receives a deliverable from one of the team members to provide to the customer.
While looking at the deliverable, the project manager notes that the document is smaller than
what he expected and does not contain what he thought it should. The project manager should
FIRST:
B. Contact the team member’s manager to get that person additional training
4. A manager has responsibility for a project that has the support of a senior manager. From the
beginning, you have disagreed with the manager as to how the project should proceed and what
the deliverables should be. You and she have disagreed over many issues in the past. Your
department has been tasked with providing some key work packages for the project. What should
you do?
C. Sit down with the manager at the beginning of the project, attempt to describe why you object
to the project, and discover a way to solve the
problem
A . The team
C. Management
D. The sponsor
7. Which of the following is a basic rule or guideline for creating a work breakdown structure?
C. A work breakdown structure should be like a to-do list, listing in chronological order every
activity that needs to be done to complete the
project.
8. A scope change is made on the project. You have determined the effect on the schedule,
performed integrated change control, and adjusted the project baselines and the
project management plan. What is the NEXT thing to do?
17 | Page
Practice Questions PMP Exam Prep. Course PM Pro
9. A new project manager is being mentored by a more experienced certified project management
professional (PMP). The new project manager is having difficulty finding enough time to manage
the project because the product and project scope are being progressively elaborated. The PMP
mentions that the basic tools of project management, such as a work breakdown structure, can
be used during project executing to assist the project manager. For which of the following can a
work breakdown structure be used?
11. You are managing a six-month project and have held bi-weekly meetings with your project
stakeholders. After five-and-a-half months of work, the project is on schedule and budget, but the
stakeholders are not satisfied with the deliverables. This situation will delay the project completion
by one month. The MOST important process that could have prevented this situation is:
B. Control Schedule
C. Define Scope
D. Control Scope
18 | Page
Practice Questions PMP Exam Prep. Course PM Pro
12. All of the following are inputs to the Validate Scope process EXCEPT:
C. WBS dictionary
D. Inspection
13. All of the following statements about work breakdown structures are true EXCEPT:
14. A project manager is in the process of scope validation of a deliverable with the customer. What is
the MOST important thing the project manager should
ensure?
A. Accuracy
B. Timeliness
C. Acceptance
D. Completeness
15. Over the last few weeks, the team has made three changes to the activities on the project. The
project manager must be MOST careful
to:
C. Make sure the changes are reflected in the project scope baseline
19 | Page
Practice Questions PMP Exam Prep. Course PM Pro
16. The construction phase of a new software product is near completion. The next phases are testing
and implementation. The project is two weeks ahead of schedule. What should the project
manager be MOST concerned with before moving on to the final phase?
A. Validate Scope
B. Control Quality
C. Performance Reports
D. Control Costs
D. Earned value
18. Two months into a design project, the customer requested a modification to the product. The
change was made without notifying the project manager. During the final testing phase, results
were different then what was planned for. This scenario is BEST thought of as an example of
which of the following?
A. Poor scope
control
19. A new project manager is planning a complex hardware installation project. The team consists of
13 people who are experts in their fields. The project manager does not want to micromanage the
project. How far should he decompose the work?
20 | Page
Practice Questions PMP Exam Prep. Course PM Pro
D. To about 80-hour work packages because it will make the work less
complex
21. If a project team is subdividing project work packages into smaller, more manageable components,
they
are:
A. Creating WBS
B. Decomposing
C. Network diagramming
D. Activity sequencing
22. Which of the following BEST describes when the baseline can be changed?
23. Which of the following is CORRECT in regard to the Control Scope process?
A. Effective scope definition can lead to a more complete project scope statement
C. The Scope Control process must be integrated with other control processes
21 | Page
Practice Questions PMP Exam Prep. Course PM Pro
24. A new project manager has asked you for advice on creating a work breakdown structure. After
you explain the process to him, he asks you what software he should use to create the WBS,
and what he should do with it when he is finished creating it. You might respond that it is not the
picture that is the most valuable result of creating a WBS. It is:
A. A bar chart
B. Team buy-in
C. Activities
D. A list of risks
25. A team member determines that the scope for her activity is no longer valid. She comes to you for
advice on making the change. To which of the following documents should the project manager
refer to make this change?
26. During a walk-through of a work package, you discover that a team member is completing the work
differently than stated in the WBS dictionary. How should you deal with this?
D. Determine if the changes also change the scope of the work package.
27. A project manager is concerned about the amount of gold plating that has occurred on past
projects. All the following would NOT be of use in controlling gold plating EXCEPT:
A. A team charter
B. A project
charter
22 | Page
Practice Questions PMP Exam Prep. Course PM Pro
28. The project manager had to request a change in the approved project budget because the WBS
did not contain some work that needed to be done. Which of the following is the BEST thing to do
as a result of this situation?
29. Product verification is different than scope validation in that product verification:
30. A project manager has just been assigned to a new project and has been given the approved
project charter. The FIRST thing the project manager must do is:
B. Confirm that all the stakeholders have had input to the scope
31. A work breakdown structure is an input to all of the following processes EXCEPT:
A. Define Activities
B. Estimate Costs
C. Manage Quality
D. Plan Procurements
23 | Page
Practice Questions PMP Exam Prep. Course PM Pro
32. To manage a project effectively, work should be broken down into small pieces. Which of the
following does NOT describe how far to decompose the
work?
33. All of the following are tools used in the Validate Scope process EXCEPT:
A. Product reviews
B. Audits
C. Walkthroughs
D. Sensitivity analysis
A. Control Quality
B. Sequence Activities
C. Manage Quality
D. Time Management
35. All of the following are needed to create the WBS EXCEPT:
B. Quality measurements
C. Requirements documentations
36. Which of the following includes the processes required to ensure the project includes all the work
and only the work required to complete the project
successfully?
A. Cost management
B. Scope management
C. Time management
37. The project is mostly complete. The project has a schedule variance of 300 and a cost variance of
-900. All but one of the quality control inspections have been completed and all have met the quality
requirements. All items in the issue log have been resolved. Many of the resources have been
released. The sponsor is about to call a meeting to obtain product verification when the customer
notifies the project manager that they want to make a major change to the scope. The project
manager should:
A. Meet with the project team to determine if this change can be made.
C. Explain that the change cannot be made at this point in the process
D. Inform management
38. All of the following come after the Define Scope process EXCEPT:
C. Estimate Costs
D. Collect Requirements
39. When should the Validate Scope process be done?
25 | Page
Practice Questions PMP Exam Prep. Course PM Pro
40. The customer wants to expand the product scope after the performance measurement baseline
has been established. Which document will the customer need to submit?
A. Change request
C. Performance measurements
D. Activity attributes
41. A work breakdown structures numbering system allows the project staff to:
42. You have a signed project charter, and are in the process of creating a project scope statement.
You have asked the team for input to ensure that the project scope statement is complete.
However, the team is struggling with defining the scope. Which of the following BEST describes
the problem?
C. The team is in the Define Scope process and needs the project scope statement as an input
D. The project objectives were not identified before scope statement was begun.
43. A client has asked you to add to the scope of the project. The project is under budget and a little
ahead of schedule. What should you do?
26 | Page
Practice Questions PMP Exam Prep. Course PM Pro
44. During project executing, a team member comes to the project manager because he is not sure of
what work he needs to accomplish on the project. Which of the following documents contain
detailed descriptions of work packages?
A. WBS dictionary
B. Activity list
45. Which of the following can create the MOST misinterpretation in the project scope statement?
A. Imprecise language
46. Projects with adaptive life cycles use product backlogs to define a project’s scope. The product
backlog is a set of:
B. User
stories
C. Client
lullabies
D. Non-functional
requirements
47. Which of the following is an important input to the Validate Scope process?
A. Verified deliverables
C. Accepted deliverables
D. Change requests
27 | Page
Practice Questions PMP Exam Prep. Course PM Pro
48. A project manager believes that modifying the project scope may provide added value for the
customer. What should the project manager do?
49. A customer is not happy with a project deliverable. What is your BEST course of action?
A. Tell the customer the deliverable meets the scope of work and get the customer’s agreement to
proceed.
50. After the kickoff meeting, two team members engage in a casual conversation about the project
objectives and deliverables. It is clear they heard different messages during the meeting. One
team member is so adamant that the other team member give up arguing the point. After talking to
the project manager, the second team member confirms that the first team member is mistaken. At
this point, what is the BEST course of action?
A. The second team member should send the other team member an e-mail describing what he
discovered
.
B. At the next project meeting, the team member should ask the mistaken team member to
describe his interpretation so the project manager can get everyone on the same page.
C. The project manager should send out an e-mail to the team restating the project objectives and
deliverables.
D. At the next project meeting, the project manager should spend time reviewing the documented
project scope statement for the purpose of identifying this and other false
assumptions.
51. An organization’s value chain can be represented by a special type of flowchart called
SIPOC.
SIPOC stands
for:
A. Superior service, inferior service, peak hour service, optimized service, and client
service
28 | Page
Practice Questions PMP Exam Prep. Course PM Pro
52. Which of the following is an agile prototyping technique showing sequence or navigation through
a
series of images or
illustrations?
A. Nominal group
technique
B.
Storyboarding
C. Decision
trees
D. Mind
mapping
29 | Page
Practice Questions PMP Exam Prep. Course PM Pro
30 | Page
Schedule
Management
1. Which of the following and is the BEST method of completing “what if” scenarios to determine what
combination of resources and interdependence will produce the best
schedule?
B. Monte Carlo
C. Parametric estimating
D. Resource leveling
2. In order to shorten the project duration, you want to look at fast tracking the project. Based on the
chart, which activity(s) would you consider fast
tracking?
A. Activity B or E
B. Activity C or F
C. Activity H
D. Activity D or I
3. Using the chart, in order to handle some resources changes on your project, activity H is going to be
done concurrently with activity G instead of after it. What impact will this have on the project?
4. During project executing, the forecasted remaining hours exceed planned remaining hours.
Consequently, the project takes on a negative variance. Which analysis method is the project manager
likely to use as a measurement tool to validate this information?
A. EV-PV
B. EV/AC
C. EV/PV
D. EV-AC
5. Senior management asks the project manager how the project would be affected if two resources
were removed from the project. To calculate a response, the project manager should complete:
A. Resource leveling
C. Schedule compression
D. Fast tracking
6. In attempting to complete the project faster, the project manager looks at the cost associated with
crashing each activity. The BEST approach to crashing would also include looking at the:
A. Trend analysis was used to eliminate the need for some testing
31 | Page
Practice Questions PMP Exam Prep. Course PM Pro
8. The project manager has had some difficulty in getting the team to complete work efforts but
he feels that the changes he made to the reward system will fix the problem. The number of
stakeholders on the project has grown by 20 percent and the number of activities being
completed late is growing. The project manager has heard from management that the project
might become a higher priority if their competition comes out with a new product that uses
wireless technology. Based on this, it would be BEST for the project manager to:
A. Re-estimate the activities and prepare to create a new schedule
B. Perform configuration management
C. Recreate the project work authorization system
D. Better respond to risk event triggers
9. A team member tells the project manager that her activity will be delayed four weeks. The
project
manager investigates and determines that the delay will affect the project’s completion date.
Who should approve the change?
A. Change control board
B. Project manager
C. Team member
D. Sponsor
10. Based on the chart, while working on the project, you are told that you have to remove
some
resources to support a more important project for your customer. From which activity would it be
BEST to remove resources?
10 1 4
6798463
11
A. Activity A
B. Activity B
C. Activity C
D. Activity D
32 | Page
CDE
Start
F G\ A
End
BHJK
dd
I
Practice Questions PMP Exam Prep. Course PM Pro
11. Which of the following BEST explains why the team needs to approve the final schedule?
D. To improve communications
12. You are managing the project when you discover an estimated completion date will occur after the
desired date. What should you do FIRST?
13. The project manager has a project that is three months behind but, surprisingly, markedly under
budget. She has decided to try to make up some time, but needs to minimize the project risk.
What is the BEST thing to do?
A. Crash
B. Fast track
C. Redefine the scope
D. Resource level
14. A plan for establishing the criteria for developing and controlling the project schedule is BEST
described as part of
the:
B. Schedule model
C. Activity attributes
15. Free float is the amount of time an activity can be delayed without delaying the:
33 | Page
Practice Questions PMP Exam Prep. Course PM Pro
A. Project
16. You have a project with the following activities: Activity 1 can start immediately and has an
estimated duration of four. Activity 2 can start after activity 1 is completed and has an estimated
duration of eight. Activity 3 can start after activity 2 is completed and has an estimated duration of
five. Activity 4 can start after activity 1 is completed and has an estimated duration of eight.
Activity 5 has an estimated duration of three and must take place concurrently with activity 3. It
can start after activities 4 and 2. What is the duration of the critical path of this project?
A. 15
B. 18
C. 17
D. 12
17. All of the following are inputs to the Develop Schedule process EXCEPT:
A. Vacation schedules
C. Assumption that the software will be released without any damaging bugs
34 | Page
Practice Questions PMP Exam Prep. Course PM Pro
18. Using the chart, the resource for activity A is assigned to an additional, more important,
project. As
a result, the resource will not be able to devote as much time to your project. Activity A will now
take 10 weeks. How does this affect the project?
Activity Preceding Activi ty
35 | Page
Estimate (Wee ks) Start 0 C Start 3 D C 6 A C 8 E D 4 B A,E 5 F E 3 End B,F 0
A. There are three critical paths.
B. The project will be delayed
C. The project is riskier
D. Activity D will be delayed
19. You are a project manager on a US $5,00,000 software development project. While working
with your project team to develop a network diagram, your data architects suggest that quality
could be improved if the data model is approved by senior management before moving on to
other design elements. They support this suggestion with an article from a leading software
development project. While working with your project team to develop a network diagram, your
data architects suggest that quality could be improved if the data model is approved by senior
management before moving on to other design elements. They support this suggestion with an
article from a leading software development journal. Which of the following BEST describes
what this type of input is called?
A. Mandatory dependency
B. Discretionary dependency
C. Extern al dependency
D. Heuristic
Practice Questions PMP Exam Prep. Course PM Pro
B. Network diagramming
D. Three-point estimating
22. An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9
and a late finish (LF) of day 19. What is the duration of this activity?
A. 3
B. 6
C. 7
D. 10
23. During the Define Activities process, the team discovers that they do not know enough to define
the activities for 30 percent of the work packages. What would be the BEST course of action?
B. Review the project charter with the sponsor and the team
C. Continue on to Sequence Activities process and define the activities at a later date.
36 | Page
Practice Questions PMP Exam Prep. Course PM Pro
24. A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime.
Activity A takes 3 weeks, activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and
B must be completed before Activity C can start. Activity C requires 6 weeks to complete.
Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks.
Activity F takes 4 weeks and can start as soon as activity C is completed. Activity E must be
completed before activity G starts. Activity G requires 3 weeks. Activities F and G must be
completed for the project to be completed. What is the critical path?
A. Start A, C, F, End
B. Start B, C, E, G, End
C. Start D, E, G, End
25. Total float is the amount of time an activity can be delayed without delaying the:
A. Project
B. Completion date required by the customer
26. Management wants the project completed in 40 days. The cost performance index (CPI) is 1.1,
the project critical path duration is 38 days with a standard deviation of two days. What is the
maximum project float?
A. Zero days
B. Two days
C. Four days
D. One day
B. Cost incentives
C. Schedule objectives
D. Project objectives
37 | Page
Practice Questions PMP Exam Prep. Course PM Pro
28. Based on the chart, while completing the project, a team member tells you that the team forgot
something during planning. Activity F needs the results of activity E before it can begin. Taking
this new dependency into account, what would be the effect on the project?
29. Which of the following BEST describes what a network diagram is used for when the work is being
completed
?
B. To determine if the evaluation criteria should be created before the contract statement of work
is
written
30. A project manager has increased project costs by US $100,000, but completed the project four
weeks earlier than planned. What activity is BEST described here?
A. Resource leveling
B. Schedule compression
C. Critical chain
38 | Page
Practice Questions PMP Exam Prep. Course PM Pro
31. What is the duration of the near-critical path based on the chart?
A. 33
B. 44
C. 31
D. 43
32. After analyzing the status of your project, you determine that the earned value (EV) is lower than
the planned value (PV). What should you expect as an outcome if this trend continues?
33. A problem occurs on an activity with free float and the project manager has extended its duration.
What is MOST likely to be affected?
A. Project duration
B. Resource schedules
39 | Page
Practice Questions PMP Exam Prep. Course PM Pro
35. Which of the following includes all of the relationships represented on an activity-on-node diagram?
A. Finish-to-start
B. Finish-to-finish
D. Start-to-start, start-to-finish
36. A project manager has received activity duration estimates from his team. Which of the following
does he need in order to complete the Develop Schedule
process?
A. Change requests
D. Reserves
37. Which of the following BEST describes the primary use of project management software?
A. Managing a project
A. At the beginning of the project and used to compare schedule performance on status reports
B. At the end of the project and then used to measure team performance
C. At the end of the project and included in the archive
D. At the beginning of the project and used during the project to measure performance
40 | Page
Practice Questions PMP Exam Prep. Course PM Pro
39. All of the following are inputs to the Develop Schedule process EXCEPT:
A. Schedule baseline
B. Network diagram
D. Resource requirements
41. The WBS, estimates for each work package, and the network diagram are completed. The NEXT
thing for the project manager to do
is:
A. Sequence Activities
B. Develop Schedule
C. Validate Scope
D. Resource Simulation
42. If project time and cost are not as important as the number of resources used each month, which
of the following is the BEST thing to
do?
41 | Page
Practice Questions PMP Exam Prep. Course PM Pro
C. Determining lag
D. Determining the amount of time the activity can be delayed before it delays the critical path
44. If the optimistic estimate is on, the pessimistic is nine, and the mostly estimate is eight, what is the
PERT estimate?
A. 9
B. 7
C. 8
D. 3
45. The customer on a project tells the project manager he has run out of money to pay for the project.
What should the project manager do
FIRST?
A. Shift more of the work to later in the schedule to allow time for the customer to get the funds
C. Stop work
46. You are the project manager on a project that has a total project float of negative 20. What should
you
do?
D. Fast track the project if overall project risk is already too high
42 | Page
Practice Questions PMP Exam Prep. Course PM Pro
47. Based on the chart, what is the float of activity B?
Activity Preceding Activi ty
43 | Page
Estimate (wee ks) Start 0
C Start 3
DC6
AC8
ED4
B A,E 5
FE3
End B,F 0
A. 2
B. 3
C. 5
D. 0
48. Based on the chart, if you needed to shorten the duration of the project, which activity would
you to
shorten?
Activity Preceding Activi ty
Duration
Start None 0 A Start 1 B Start 2 C Start 6 D A 10 E B,C 1 F C 2 G D 3 H E 9 I F 1 J G,H,I 0
A. Activity B
B. Activity D
Practice Questions PMP Exam Prep. Course PM Pro
C. Activity H
D. Activity C
49. A project manager for a small construction company has a project that was budgeted for US
$130,000 over a six-week period. According to her schedule, the project should have cost US
$60,000 to date. However, it has cost US 90,000 to date. The project is also behind schedule,
because the original estimates were not accurate. Who has the PRIMARY responsibility to solve
this problem?
A. Project manager
B. Senior management
C. Project sponsor
50. Which of the following does NOT need to be done if there is a major delay on a noncritical path
activity
?
A. Investigate the delay
51. On-demand scheduling is one of the techniques used in agile projects. This type of
scheduling
relies on:
C. A schedule that was developed previously for the development of the project
increments.
44 | Page
Practice Questions PMP Exam Prep. Course PM Pro
45 | Page
Cost
Management
1. Halfway through the executing process of your project, a team member alerts you to a potential cost
overrun for a specific deliverable. What do you do FIRST?
2. If earned value (EV) = 350, actual cost (AC) = 400, planned value ((PV) = 325, what is the cost
variance
(CV)?
A. 350
B. - 75
C. 400
D. - 50
A. A bribe
B. Allowed
5. You have just completed the initiating processes of a small project and are moving into the planning
processes when a project stakeholder asks you for the project’s budget and cost baseline. What
should you tell her?
A. The project budget can be found in the project charter, which has just bee completed
B. The project budget and baseline will not be finalized and accepted until the planning processes
are completed
C. The project management plan will not contain the project budget and baseline; this is a small
project
A. Asking for a percent complete form each team member and reporting that in the monthly
progress report
B. Calculating earned value and using the indexes and other calculations to report past
performance and forecast future
performance
C. Using the 50/50 rule and making sure the life cycle cost is less than the project cost
D. Focusing on the amount expended last month and what will be expended the following month
7. A large, complex construction project in a foreign country requires coordination to move the required
equipment through crowded city streets. To ensure the equipment is transported successfully, your
contact in that country informs you that you will have to pay the local police a fee for coordinating
traffic. What should you do?
A. Do not pay the fee because it is a bribe
8. All of the following are tools for of the Determine Budget process EXCEPT:
A. Aggregation
B. Reserve
analysis
46 | Page
Practice Questions PMP Exam Prep. Course PM Pro
D. Bottom-up estimating
9. A project manager is finalizaing a project that has had repeated problems with cost conformance.
He is concerned about what management will say. Which of the following types of information
would be BEST for the project manager to use to evaluate performance?
10. A trend report was given to the project manager, who reacted to the report by investigating what
activity or activities had not been done, but should have been done, to date. What did the report
show?
A. Actual cost was below planned and schedule progress was less than planned
B. The cost performance index (CPI) was 0.8 and the schedule performance index (SPI) was 1.2.
D. The schedule performance index (SPI) was 1.3 and the estimate at completion (EAC) was
greater than planned.
11. The project budget is proving to be inaccurate. The SPI is 1.1. The team has had a negative
deviation from the activity attributes, and the sponsor has inserted herself on the change
control board. What is the BEST thing for the project manager to do?
A. Try to encourage the sponsor to remove herself from the change control board
47 | Page
Practice Questions PMP Exam Prep. Course PM Pro
12. Which of the following defines things the project manager needs to do regarding cost?
A. Never just accept constraints from management, periodically recalculate the estimate to
complete, meet any agreed-upon
estimates
B. Meet any agreed-upon estimates, estimate larger-sized work components, accept constraints
from management
C. Periodically recalculate the estimate to complete, increase estimates by eliminating risks, re-
estimate when changes are
requested
D. Never recalculate the estimate to complete, never just accept constraints from management,
only use historical records for accurate
estimates.
13. You are working on a new oil purification project in a foreign country. A person informs you that
you will have to pay him a “transfer fee” for the permit to move heavy equipment through the
city. What is the FIRST thing you should do?
15. Which of the following is NOT needed in order to come up with a project estimate?
A. A WBS
B. A network
diagram
C. Risks
48 | Page
Practice Questions PMP Exam Prep. Course PM Pro
D. A change control system
16. The project manager is working on a high-profile project where completing the project within
budget is critical. The project manager is new, but well trained and is excited to see that the project is
spending less than budgeted. As a result, the project manager was planning to take a holiday when a
more senior project manager warned him tha he has some important work to do on the project. Why
would the senior project manager give such a warning on this project?
A. Under budget could mean that work that was scheduled to e done has not been completed.
The project manager should look at how the cost performance compares to the
schedule performance
B. The project manager needs to create a project control system to make sure there are no
problems in the
future.
C. A project that is under budget may also have contracts that need to be managed.
D. Team meetings should be scheduled every week and a holiday would mean that one team
meeting would have to be
cancelled.
17. Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the
following should you
do?
B. Meet with the sponsor to find out what work can be done sooner.
C. Cut quality
D. Decrease scope
18. A customer has given you a procurement of work for a complex, eight-month project that has a few
unknowns. The customer has asked you to just “get it done” and only wants to see you at the end
of eight months when you deliver the finished project. Under these circumstances, which of the
following is the BEST thing to do?
A. Complete the project as requested, but validate its scope with the customer occasionally
throughout.
B. Complete the project within eight months without contacting the customer during this time.
D. Complete the project, but document that the customer did not want contact.
49 | Page
Practice Questions PMP Exam Prep. Course PM Pro
20. The customer responsible for overseeing your project asks you to provide a written cost estimate
that is 30 percent higher than your estimate of the project’s cost. He explains that the budgeting
process requires manager to estimate pessimistically to ensure enough money is allocated for
projects. What is the BEST way to handle this?
A. Add the 30 percent as a lump sum contingency fund to handle project risks
B. Add the 30 percent to your cost estimate by spreading it evenly across all project activities
C. Create one cost baseline for budget allocation and a second one for the actual project
management plan.
D. Ask for information on risks that would cause your estimate to be low.
21. The approximate resource costs necessary for completing project activities are compiled during
which project management
process?
B. Estimate Costs
C. Cost aggregation
D. Forecasting.
A. Variable costs
B. Fixed costs
C. Overhead costs
D. Opportunity
costs 50 | Page
Practice Questions PMP Exam Prep. Course PM Pro
23. A new store development project requires the purchase of various equipment, machinery, and
furniture. The department responsible for the development recently centralized its external
purchasing process and standardized its new order system. In which document can these new
procedures be found?
B. WBS
C. Team charter
D. Organizational policies
24. You are a project manager for a small construction project. Your project was budgeted for US
$72,000 over a six week period. As of today, you’ve spent US $22,000 of your budget to complete
work that you originally expected would cost US $24,000. According to your schedule, you should
have spent US $30,000 by this point. Based on these circumstances, your project could be BEST
described as:
A. Under budget
B. Over
budget
C. On budget
25. During project executing, a new project manager is assigned to the project and finds that the
activity cost estimates for the project have rarely been accurate. Which of the following was MOST
probably not done?
A. Obtain a cost constraint from management, create a work breakdown structure, and develop a
project management
plan.
B. Obtain a cost constraint from management , perform a risk assessment, and form a team.
C. Form a team, create a work breakdown structure, and use historical records from previous
projects.
D. Form a team, develop a project management plan, and perform a risk assessment.
26. While reviewing project performance, the project manager determines that the schedule variance is
-500. What is the BEST thing to do?
51 | Page
Practice Questions PMP Exam Prep. Course PM Pro
27. Which of the following are AL items included in the cost management plan?
A. The level of accuracy needed for estimates, rules for measuring cost performance,
specifications for how duration estimates should be
stated.
B. Specifications for how estimates should be stated, rules or measuring cost performance, the
level of accuracy needed for
estimates
C. Rules for measuring team performance, the level of accuracy needed for estimates,
specifications for how estimates should be
stated.
D. Specifications for how estimates should be stated, the level of risk needed for estimates, rules
for measuring cost performance.
28. You are in the middle of a new product development project for your publicly traded company when
you discover that the previous project manager made a US $3,00,000 payment that was not
approved in accordance with your company policies. Luckily, the project cost performance index
(CPI) is 1.2. What should you do?
A. Cost aggregation
B. Bottom-up estimating
C. Reserve analysis
D. Control costs.
52 | Page
Practice Questions PMP Exam Prep. Course PM Pro
31. A project manager discovers that a work package has been completed for substantially less cost
than planned. Which of the following is NOT among the first things to consider doing?
32. Your company is in competition to win a major project for the government of a country. Your
contacts in that country inform you that you must make a large payment to the foreign minister
to be considered for the project. What should you do?
A. Budget estimate
D. Parametric estimate.
B. Estimate Costs
C. Determine Budget
53 | Page
Practice Questions PMP Exam Prep. Course PM Pro
D. Control Costs.
A. Offering to pay the country officials for not awarding the project to a particular company
36. The project manager is allocating overall cost estimates to individual activities to establish a
baseline for measuring project performance. What process is this?
A. Cost Management
B. Estimate Costs
C. Determine Budget
D. Control Costs
37. All of the following are outputs of the Estimate Costs process EXCEPT:
A. An understanding of the cost risk in the work that has been estimated.
B. The prevention of inappropriate changes from being included in the cost baseline.
38. Which of the following is a KEY way to improve activity cost estimates?
B. Let management create the management reserve and the activity cost estimate.
54 | Page
Practice Questions PMP Exam Prep. Course PM Pro
40. You have assigned as the project manager on a new project. The organization uses a strong
matrix structure. Computers needed to complete the project are an example of:
A. Limited cost
B. Diminishing cost
C. Fixed cost
D. Indirect cost.
41. You are a project manager working on a project that requires 100 items to be tested, spaced
evenly over five weeks. You have just begun week three, with an overall budget of US $10,000.
To date, you have spent US $2,000 with 40 items tested successfully. What does the cost
variance (CV) tell you in this circumstance?
42. A new project manager asks you what the 50/50 rule is used for. You would reply?
A. Crashing
B. Quality
55 | Page
Practice Questions PMP Exam Prep. Course PM Pro
C. Performance reporting
D. Cost estimating
43. A project manager has completed a detailed WBS and cost estimates for each work package. To
create a cost baseline from this data, the project manager
would:
A. Use the highest level of the WBS to estimate analogously
C. Roll up work package estimates into a project total and add management reserves.
44. Which estimating method tends to be MOST costly for creating a project cost estimate?
A. Bottom-up
B. Analogous
C. Parametric
D. 50/50 rule
45. Your company wants to assign a resource to your project and asks you to bill that resource to the
customer. This concerns you because you get a bonus for maximizing billings to the customer.
What is the BEST thing to do?
B. Ask for the customer’s approval before adding the resource to the project scope.
D. Remind the appropriate members of the billing organization that monetary compensation is not
worth compromising the integrity of the individual or the
organization.
46. A project manager is working with management to create the project estimate. During the initiating
process group, what level of accuracy should the estimate
have?
A. +/- 50 percent
47. If planned value (PV) is US $29,000, actual cost (AC) is US $32,000, and earned value (EV) is US
$30,000, what is the schedule variance
(SV)?
A. 0.938
B. $1,000
C. 1.034
D. ($2,000)
48. While visiting the country where a new branch office is being built, you are told that you must pay a
US $5,000 fee to the government permit office to obtain the facility permit required by law to start
construction. The construction company tells you this is standard practice and is required by law.
What should you do?
49. Which of the following does NOT assess the value a project brings to an organization?
C. Value analysis
D. Needs assessment
50. Which of the following information about the project would NEVER be available during project
planning?
B. Benefit cost
ratio 57 | Page
Practice Questions PMP Exam Prep. Course PM Pro
D. Budget at completion
Quality
Mangement
1. A project manager and team from a firm that designs railroad equipment are tasked to design
a
machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to
over two tons of spilled rock per day. In which of the following does the project manager document
quality control, quality management, and quality improvements for this project?
B. Quality policy
C. Control charts
2. While testing the strength of concrete poured on your project, you discover that over 35 percent of
the concrete does not meet your company’s quality standards. You feel certain the concrete will
function as it is, and you don’t think the concrete needs to meet the quality level specified. What
should you do?
3. During project executing, a project team member informs the project manager that based on her
observations, the project cannot meet the quality standards set for it. What would be the LEAST
effective thing for the project manager to do?
4. During project executing a project team member informs the project manager that, based on her
observations, the project cannot meet the quality standards set for it. The project manager meets
58 | Page
Practice Questions PMP Exam Prep. Course PM Pro
with all parties concerned to analyze the situation. Which part of the quality management process
is the project manager involved in?
A. Manage Quality
B. Quality analysis
C. Control Quality
D. Plan Quality
5. A project team is in the design stage of a new mountain bicycle prototype. The team is in the
process of identifying which type of frame and material will provide high performance at a low
cost. Which of the following is the MOST likely technique used to determine these variables?
C. Design of experiments
D. System flowchart
6. Which of the following BEST describes why quality is planned in and not inspected in?
7. A project manager and his team are using an Ishikawa diagram, trying to determine how various
factors might have contributed to project problems. The project manager is involved in which part
of the quality management process?
A. Plan Quality
C. Manage Quality
D. Control Quality
59 | Page
Practice Questions PMP Exam Prep. Course PM Pro
B. They require the preparation of change requests or the recommendation of corrective actions.
C. They occur only through experience o the project manager, team, and sponsor.
D. They are a product of cooperation between the customer and the project
manager.
A. Out of control
B. In control
C. Assigned a cause
D. Quality assured
A. Cost-benefit analysis
B. A scatter diagram
C. Benchmarking
D. Cost of quality
12. All of the following are examples of the cost of nonconformance EXCEPT:
A. Rework
B. Quality
training 60 | Page