Contents
1. Objective of the cost estimate exercise
2. Methodology
Estimate class 4
A
Accuracy -30%
30% / 50%
Currency US$
Economical conditions Q1-2008
© 2011 ‐ IFP Trraining
EP ‐ 24153_a_A_ppt_01 ‐ Cost Estimating
Methodology
Platform
The platform cost estimate shall be done in 3 steps
• Step 1: Analyze the cost data MOD‐2002
• Step 2: Actualize the cost data to MOD‐2008 using the applicable
indexes
• Step 3: Derive the necessary cost ratios (US$/ton or per
per‐cent)
cent)
• Step 4: Apply these ratios to the intended new platform given
weights
Pipelines
The pipelines cost shall be estimated on the basis of the
appropriate ratios given in the related Attachment. They have
© 2011 ‐ IFP Trraining
© 2011 ‐ IFP Trraining
Basic engineering
Surveys
Project management
Insurances
Certification
Commissioning & RFSU
CONTINGENCIES
EP ‐ 24153_a_A_ppt_01 ‐ Cost Estimating
CAMPOS Facilities description
CAMPOS O&G
Field
ONSHORE
TERMINAL WPH-C
1998 2003
DDP-A
1998
WPH-B
1998
WPH-A
2003
PIPELINE
CASES
1&2
72 km
CAMPOS
Satellite
© 2011 ‐ IFP Trraining
WPH-D
FUTURE
© 2011 ‐ IFP Trraining
line.
Facilities description ‐ Case #1 (“wet” scheme)
PIPELINES
WHP-D
72 km - 24’’ GAS
72 k
km - 3’’ MEG
Deck 826 t
CASE #1
Jacket 1160 t (excl. piles)
© 2011 ‐ IFP Trraining
© 2011 ‐ IFP Trraining
Schéma
Facilities description ‐ Case #2 (“dry” scheme)
Oil and
d gas are being
b i produced
d d and
d sent to shore
h i two separate
in
pipelines:
A 20”” gas pipeline with a 3”” diameter piggy‐back MEG line;
A 10” oil pipeline.
PIPELINES
WHP-D
72 km - 20’’ GAS
72 km - 10’’ OIL Deck 1335 t
72 km - 3’’ MEG
© 2011 ‐ IFP Trraining
CASE #2
Jacket 1350 t (excl. piles)
Summary data for cost estimating the Pipelines (Case #1 and Case
#2)
© 2011 ‐ IFP Trraining
EP ‐ 24153_a_A_ppt_01 ‐ Cost Estimating
Summary data for cost estimating WHP‐D platform
(Cases #1 and #2)
1‐WHP‐C basis 2002
TOPSIDES and JACKET FEEDBACK Existing WHP‐C "as‐built" data US$ 2002 ‐ South American Yard
2‐Index
Upstream capital costs index: Global markets index (Source IHS‐CERA) Reference Index 2002 & Q1‐2008
3‐WHP‐C basis act 2008
Existing WHP‐C topsides actualized Q1‐2008
Ratio US$/ton
4‐WPH‐D cost
TOPSIDES Dry weight
JACKET Weight
Topsides technical cost installed
Jacket technical cost installed
© 2011 ‐ IFP Trraining
5‐Pipeline basis
TECHNICAL DATA
PIPELINES TECHNICAL UNIT COST RATIO (GIVEN)
6‐Pipeline cost
CASE 1: Gas and MEG pipelines
CASE 2: Oil, gas and MEG pipelines
90
85
80
US$/inch.m (2008)
75
70
65
60
55
© 2011 ‐ IFP Trraining
50
8 10 12 14 16 18 20 22 24 26
Diam eter (inch)
Summary data for cost estimating WHP‐D platform
(Cases #1 and #2)
OFFSHORE FACILITIES PLATFORM & PIPELINES CASE#1 (only) CAPEX : EPC Cost,
COMPANY costs, Contingencies
Onshore p
pipe
p 20 15 10
Offshore pipe 20 15 10
Onshore plant 25 20 15
Fixed platform 25 20 15
Floating platform 25 20 15
Subsea development 25 20 15
© 2011 ‐ IFP Trraining
Onshore modification 30 20
Offshore modification 35 25
EMS costs
Detailed & constr. eng., procurement
Project management team 10%
Site supervision
Precommissioning 3% 1%
OWNER (COMPANY) COSTS
Basic engineering 3%
Surveys 1%
Project management 12%
Insurances 2%
Certification 1%
© 2011 ‐ IFP Trraining
Commissioning & RFSU 3%
EPC + Owner (Company) costs
CONTINGENCIES Platform 20%
Pi li
Pipelines 15%
CAPEX PLATFORM
CAPEX PIPELINES
Cost estimate table (Correction)
OFFSHORE FACILITIES
CAPEX Ref. WHP-D Case #1 Pipelines Case #1
EPC COST 96 243 546 120 623 256
Technical cost 84 207 114 108 669 600
Direct cost ex-yard 46 688 070
Equipment cost 12 225 337
Main
M i equipment
i t 10 881 475 10 881 475
Non-listed equipment allowance 5% 544 074
(Winterization) N/A
Equipment transport 7% 799 788
Bulk materials 18 173 427
Bulk 17 308 026 17 308 026
Bulk allowance 5% 865 401
Bulk transport incl
incl.
Construction cost 16 289 306
Fabrication at Yard 15 513 625 15 513 625
Construction allowance 5% 775 681
Indirect construction cost 8% 1 241 090
Offshore installation 36 277 954
Integration N/A
Transport to integration site N/A
Installation
Logistics 19 318 321 19 318 321
Hook-up
Mob-demob marine spreads 16 959 633 16 959 633
Accuracy: plus
l or minus
i 30%
% to 40‐50%
%
Methodology:
gy consecutive steps
p
© 2011 ‐ IFP Trraining
EP ‐ 24153_a_A_ppt_01 ‐ Cost Estimating