You are on page 1of 85

12/9/22, 4:25 PM EX-10.

EX-10 2 d724993dex103.htm EX-10.3


Exhibit 10.3

SECTION I
FORM OF AGREEMENT

CONTRACT No. OCEANIC/FPSO/14/001/1

SUBJECT: CONTRACT OF BAREBOAT CHARTERPARTY FOR FPSO ARMADA PERDANA


IN THE OYO FIELD DEVELOPMENT.

The BAREBOAT CHARTERPARTY CONTRACT (the “CHARTERPARTY”) is made and entered into on this             Day of
            2014, but effective as of the 1st Day of January 2014, by and between the following PARTIES designated as “COMPANY” and
“OWNER”:

COMPANY: Oceanic Consultants Nigeria Limited, a corporation existing under the laws of Nigeria and having its principal place of
business at Plot 1649, Olosa Street, Victoria Island, Lagos – Nigeria.

OWNER: Armada Oyo Limited, a corporation existing under the laws of British Virgin Island and having its principal place of
business at P.O. Box 957, Offshore Incorporations Center Road Town Tortola British Virgin Islands.

WHEREAS, OWNER had entered into the NAE CHARTERPARTY (as defined in Section II of the CHARTERPARTY) and the use of
the FPSO had been made available to COMPANY by Nigeria Agip Exploration Limited during part of the term of the NAE
CHARTERPARTY, and OWNER now desires to redirect the use of the FPSO to COMPANY and COMPANY now wishes to continue
the utilization of the FPSO in the OYO FIELD by entering into this CHARTERPARTY directly with the OWNER on the terms and
conditions as more particularly described in the CHARTERPARTY; and

WHEREAS, OWNER represents it is the owner of the FPSO and that it wishes to charter to the FPSO to COMPANY in accordance
with current standards and practices of the industry and subject to the provisions of the CHARTERPARTY.

NOW THEREFORE, in consideration of mutual covenants and agreements hereinafter provided, it is hereby agreed as follows:

ART. 1 – WORDS AND EXPRESSIONS


In this Form of Agreement words and expressions have the same meanings as are respectively assigned to them in Section II of the
CHARTERPARTY.

Art. 2 – CHARTERPARTY DOCUMENTS


The provisions contained in the CHARTERPARTY and in the documents identified below, said documents being attached hereto and
made a part hereof or incorporated herein by reference for all purposes, shall be collectively known as the CHARTERPARTY. The
above-referenced CHARTERPARTY includes and shall be construed in the following order of priority:

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 1/85
12/9/22, 4:25 PM EX-10.3

Execution Version
Commercial Section
Section I Form of Agreement
Section II Conditions of CHARTERPARTY
Section III CHARTERPARTY Prices and Schedules for Variations
Appendix “1” – OWNER’s and COMPANY’s Parent Company Guarantee Forms

Technical Section
Section IV Scope of Work
Section V NOT USED
Section VI Design Basis

No change, amendment or other modifications to or in any document or provision forming part of the CHARTERPARTY shall be valid
or effective unless produced in writing and signed by duly authorized representatives of both COMPANY and OWNER.

ART. 3 – COVENANTS
3.1 – OWNER
In consideration of the payment to be made by COMPANY to OWNER as hereinafter mentioned, OWNER hereby covenants
with COMPANY to supply the FPSO in conformity in all respects with the provisions of the CHARTERPARTY.

3.2 – COMPANY
COMPANY hereby covenants to pay OWNER in consideration of the supply by OWNER of the FPSO pursuant to the terms and
conditions of the CHARTERPARTY.

ART. 4 – CHARTERPARTY VALUE


All CHARTERPARTY rates of compensation and any other price(s) agreed upon by the PARTIES include any charges and provisions
necessary for the supply of the FPSO pursuant to the CHARTERPARTY and in accordance with the CHARTERPARTY, shall be
remunerative to, and shall cover all expenses and costs borne, or to be borne, by OWNER together with all responsibilities that
OWNER has undertaken and any consequences deriving therefrom.

ART. 5 – ARTICLES WHICH SURVIVE TERMINANTION


The provisions of the CHARTERPARTY provided in Clause 45 of Section II shall remain in full force and effect after such
termination.

ART. 6 – EFFECTIVE DATE OF THE CHARTERPARTY


The CHARTERPARTY is effective as of 1 January 2014.
 
 
2

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 2/85
12/9/22, 4:25 PM EX-10.3

Execution Version
 

IN WITNESS THEREOF, the PARTIES have caused this CHARTERPARTY to be executed in duplicate:

On behalf of COMPANY:
 
 

Printed Name:    

Title:   

Witness:  

 
Printed Name:    

On behalf of OWNER:

Printed Name:    

Title:   

Witness:

 
Printed Name:    
 
3

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 3/85
12/9/22, 4:25 PM EX-10.3

Execution Version
 

BAREBOAT CHARTERPARTY

CONTRACT

SECTION II

BAREBOAT CHARTERPARTY FOR


FPSO ARMADA PERDANA IN THE
OYO FIELD DEVELOPMENT

CONDITIONS OF CHARTERPARTY
 
 
4

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 4/85
12/9/22, 4:25 PM EX-10.3

INDEX
 
1    DEFINITIONS AND INTERPRETATION    1
2    CHARTERPARTY DOCUMENT    5
3    ENTIRE AGREEMENT    5
4    SCOPE OF THE CHARTERPARTY AND OWNER’S OBLIGATIONS    6
5    DELIVERY and ACCEPTANCE    6
6    SERVICE    7
7    TERM OF CHARTERPARTY    7
8    MAINTENANCE    8
9    TERMINATION    8
10   AREA OF OPERATIONS ACQUAINTANCE    10
11    PARTY REPRESENTATIVES    10
12   COMPANY’S OBLIGATIONS    11
13   NOT USED    11
14   DEFAULT BY OWNER    11
15   LIENS AGAINST THE FPSO    12
16   ACTUAL CONSTRUCTIVE TOTAL LOSS AND COMPULSORY ACQUISITION    13
17   GENERAL AND PARTICULAR AVERAGE    13
18   REDELIVERY OF FPSO    14
19   PATENT INDEMNIFICATION    14
20   INDEPENDENT CONTRACTOR    14
21   REPRESENTATIONS AND WARRANTIES    15
22   NO WAIVER    15
23   SEVERABILITY OF PROVISIONS    15
24   INSURANCE AND INDEMNITY    15
25   COMPENSATION    18
 
i

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 5/85
12/9/22, 4:25 PM EX-10.3

 
26   NOT USED    19
27   INVARIABILITY OF PRICES    19
28   VARIATIONS    19
29   INVOICING AND PAYMENT    21
30   PARENT COMPANY GUARANTEES AND LETTER OF CREDIT    23
31   TAXES    23
32   ASSIGNMENT and SUB-CHARTER    24
33   COMPLIANCE WITH LAWS    25
34   FORCE MAJEURE    25
35   ARBITRATION    27
36   APPLICABLE LAW    27
37   CONFIDENTIALITY    27
38   NOTICES    28
39   NO DEMISE    29
40   REGISTRATION    29
41   CUSTOMS FORMALITIES AND DUTIES    29
42   LOCAL CONTENT    30
43   PURCHASE OPTION    30
44   ANTI-CORRUPTION    32
45   SURVIVAL    34
46   QUALITY ASSURANCE    34
47   ENVIRONMENTAL COMPLIANCE    34
48   OVERALL LIABILITY    35
49   PUBLICITY    35
 
ii

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 6/85
12/9/22, 4:25 PM EX-10.3

Execution Version
 
1 DEFINITIONS AND INTERPRETATION
For the purposes of the CHARTERPARTY, and unless otherwise stated in the text, certain words and expressions used in the
CHARTERPARTY shall have the following meanings, it being understood that reference to the singular includes reference to
the plural and vice-versa.
 
1.1 Definitions
 
1.1.1 “AFFILIATE” shall mean, in relation to a PARTY, any entity that controls that PARTY, is controlled by that
PARTY or is controlled by another entity that also controls or is controlled by that PARTY, and “control” and
  “controlled” mean (a) the ownership, directly or indirectly, of fifty percent (50%) or more of the voting rights in an
entity or (b) the possession, directly or indirectly, of the power to direct or cause the direction of the management
or policies of an entity, whether through ownership of voting securities, by contract or otherwise.
 
1.1.2 “APPLICABLE ANTI-CORRUPTION LAWS” means, collectively, (a) the United States Foreign Corrupt
Practices Act of 1977, as amended, (b) the U.K. Bribery Act of 2010, as amended, (c) the principles set out in the
Organization for Economic Cooperation and Development Convention Combating Bribery of Foreign Public
Officials in International Business Transactions, (d) the principles set out in the United Nations Convention against
  Corruption, (e) the anti-corruption or anti-bribery laws applicable to the AREA OF OPERATIONS, and (f) all
other anti-corruption and/or anti-bribery laws, regulations and requirements of any jurisdiction applicable to the
COMPANY, the OWNER, the CONTRACTOR or their respective AFFILIATES whether by virtue of either
PARTY’s jurisdiction of incorporation or by virtue of availing itself of the jurisdiction in which the obligations
under this CHARTERPARTY are to be performed.
 
1.1.3 “AREA OF OPERATIONS” shall mean the OYO FIELD or any other areas offshore Nigeria as may be mutually
 
agreed between OWNER and COMPANY and subject to the applicable consents.
 
1.1.4 “ASSIGNEE” shall mean any entity or person to whom the CHARTERPARTY may be assigned in the manner and
 
to the extent permitted under the terms hereof.
 
1.1.5 “BUSINESS DAY” shall mean a day (other than a Saturday or Sunday) on which banks in Nigeria and New York
 
are open for business.
 
1.1.6 “CHARTERPARTY” shall mean the documents scheduled in Clause 2 hereof and any amendment(s) to such
 
documents issued subsequent thereto.
 
1.1.7 “CLASSIFICATION AUTHORITY” shall mean the American Bureau of Shipping (ABS), or such other member
  of the International Association of Classification Societies as may be mutually agreed by OWNER and
COMPANY.
 
1.1.8 “COMPANY” and “OWNER” shall have the respective meanings ascribed to them in Section I Form of
 
Agreement.
 
1.1.9 “COMPANY GROUP” shall mean the COMPANY, each CO-VENTURER, their respective AFFILIATES, the
invitees and contractors (other than members of the OWNER GROUP) of any of the foregoing and their sub-
 
contractors (of any tier) and the directors, employees, representatives, invitees and agents of any entity mentioned
above.
 
Page 1 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 7/85
12/9/22, 4:25 PM EX-10.3

 
1.1.10 “COMPANY GROUP EQUIPMENT” shall mean any equipment or property owned or hired by COMPANY
  GROUP including (but not limited to) any offtaking tankers, but excluding the FPSO and OWNER GROUP
EQUIPMENT.
 
1.1.11 “COMPANY GROUP PERSONNEL” shall mean the officers, directors, employees, agents or invitees (as the case
 
may be) of the COMPANY GROUP, but excluding all members of OWNER GROUP (including OWNER).
 
1.1.12 “COMPENSATION” shall mean any or all of the amounts (as the context so admits) payable to or for the account
of OWNER for the satisfactory and proper performance (a) by OWNER of its obligations in accordance with the
 
provisions of the CHARTERPARTY and (b) by CONTRACTOR of its obligations in accordance with the
provisions of the O&M CONTRACT.
 
1.1.13 “COMPULSORY ACQUISITION” means requisition for title or other compulsory acquisition, requisition,
  appropriation, expropriation, deprivation, forfeiture or confiscation for any reason of the FPSO by any government
or other competent authority, whether de jure or de facto.
 
1.1.14 “CONTRACTOR” shall mean Bumi Armada (Singapore) Pte. Ltd.78, Shenton Way, #26-02A Singapore 079120,
  the contractor providing operating and maintenance services to COMPANY for the FPSO under the O&M
CONTRACT.
 
1.1.15 “CO-VENTURER” shall mean any co-venturers of the COMPANY, CAMAC Energy, Inc., and any of their
  respective affiliates having an interest in the operations for which the activities described in this
CHARTERPARTY are being performed and/or their respective permitted assignees and successors-in- interest.
 
1.1.16 “DATE OF ACCEPTANCE” shall mean the date on which COMPANY is notified of the completion of the
 
REFURBISHMENT WORK in accordance with Clause 5.2.2.
 
  1.1.17 “DATE OF REDELIVERY” shall have the meaning ascribed to it in Clause 18.
 
1.1.18 “DAILY COMPENSATION FEE” shall mean the daily compensation fee payable by COMPANY to OWNER in
  accordance with the terms of the CHARTERPARTY and Section III - CHARTERPARTY Prices and Schedules for
Variations.
 
1.1.19 “DEMOBILIZATION AND REDELIVERY FEE” shall mean the demobilization and redelivery fee as set forth in
 
Clause 25.3 and Section III – CHARTERPARTY Prices and Schedules for Variations - Clause 1.3.
 
  1.1.20 “EFFECTIVE DATE” shall mean 1 January 2014.
 
  1.1.21 “EXECUTION DATE” shall mean the date on which this CHARTERPARTY is executed.
 
  1.1.22 “FORCE MAJEURE” shall have the meaning ascribed to it in Clause 34.
 
Page 2 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 8/85
12/9/22, 4:25 PM EX-10.3

 
1.1.23 “FPSO” shall mean the ARMADA PERDANA, registered under the flag of Panama with the IMO number
  8302131, a floating, production, storage, and offloading vessel (including all of her systems (including mooring
system), equipment, tackle and apparel), but excluding any COMPANY GROUP EQUIPMENT.
 
  1.1.24 “GROUP” means COMPANY GROUP and/or OWNER GROUP, as applicable.
 
1.1.25 “INITIAL PERIOD” shall mean the established period in accordance with Clause 7.1, commencing on the
 
EFFECTIVE DATE.
 
1.1.26 “NAE CHARTERPARTY” means the charterparty previously entered into by OWNER and Nigerian Agip
  Exploration Limited on 15th April 2008 as later novated, supplemented and amended and expired on 31 December
2013.
 
1.1.27 “O&M CONTRACT” shall mean the operation and maintenance contract between COMPANY and
  CONTRACTOR under which CONTRACTOR shall provide operating and maintenance services to COMPANY in
connection with the FPSO.
 
1.1.28 “OWNER” shall mean Armada OYO Ltd of P.O. Box 957, Offshore Incorporations Center, Road Town, Tortola,
 
British Virgin Islands, the registered owner of the FPSO.
 
1.1.29 “OWNER GROUP” shall mean the OWNER, its AFFILIATES, CONTRACTOR, sub-contractors of any tier, the
  directors, employees, representatives, invitees and agents of any entity mentioned above, excluding all members of
COMPANY GROUP (including COMPANY).
 
1.1.30 “OWNER GROUP EQUIPMENT” shall mean any equipment or property owned or hired by OWNER GROUP
  including (but not limited to) the FPSO, but excluding COMPANY GROUP EQUIPMENT and any support
vessels, escort tugs and/or offtaking tankers.
 
1.1.31 “OWNER GROUP PERSONNEL” shall mean the officers, directors, employees, agents or invitees (as the case
 
may be) of the OWNER GROUP.
 
1.1.32 “OYO FIELD” shall mean the OML 120 Oyo Field located offshore Nigeria as more specifically defined in
 
Section VI – Basis of Design.
 
  1.1.33 “PARTY” shall mean either COMPANY or OWNER and the plural of same means both of them.
 
1.1.34 “PERMITTED DELAY” shall mean any delay attributable to COMPANY GROUP, including delay to the extent
 
caused by:
 
  (a) any act or omission of any member of COMPANY GROUP; or
 
(b) non-availability of or delays in providing hydrocarbon or any COMPANY facilities or services as and
when required, or delays by the COMPANY GROUP in complying with Section IV - Scope of Work -
 
Part 2.4, or resulting from other activities of the COMPANY GROUP at the AREA OF OPERATIONS,
or COMPANY delay in allowing access to the AREA OF OPERATIONS.
 
Page 3 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 9/85
12/9/22, 4:25 PM EX-10.3

1.1.35 “PERMITTED SUB-CHARTERER” shall mean any entity or person to whom the FPSO may be sub-chartered in
 
the manner and to the extent permitted under the terms hereof.
 
1.1.36 “PROHIBITED PERSON” shall mean (i) any public official (including any person holding a legislative,
administrative or judicial office), (ii) any person employed by or acting on behalf of a public agency, a public
enterprise or a public international organization, (iii) any officer or employee of a government, department, sub-
  division, agency or an entity controlled by a government (including any state-owned, state-controlled or state-
operated company), or any person acting in an official capacity on behalf of any such department, agency or entity,
(iv) any political party, (v) any official of a political party, (vi) any candidate for political office or (vii) any officer
or employee of a public international organization.
 
  1.1.37 “REPRESENTATIVES”:
 
(a) “OWNER’S REPRESENTATIVE” shall mean the person or persons notified to COMPANY and
  authorised to act on OWNER’s behalf in matters relating to the CHARTERPARTY all as specified in
accordance with Clause 11.1.
 
(b) “COMPANY’s REPRESENTATIVE” shall mean the person or persons notified to OWNER and
  authorised to act on COMPANY’s behalf in matters relating to the CHARTERPARTY as specified in
Clause 11.2.
 
1.1.38 “REFURBISHMENT WORK” means the refurbishment work to be undertaken by the OWNER during the
 
STANDBY PERIOD as set out in Appendix 1 to Section IV Scope of Work.
 
  1.1.39 “SHUTDOWN” means any period in which the hydrocarbon production of the FPSO is zero.
 
1.1.40 “STANDBY FEE” shall mean the reduced DAILY COMPENSATION FEE payable during the STANDBY
 
PERIOD as specified in Section III - CHARTERPARTY Prices and Schedules for Variations.
 
1.1.41 “STANDBY PERIOD” shall mean the period from 1 January 2014 through 30 June 2014 during which
(a) OWNER shall perform the REFURBISHMENT WORK under Clause 5.2 and (b) the STANDBY FEE shall be
 
payable by COMPANY to OWNER regardless of the rate of hydrocarbon production of the FPSO during such
period.
 
1.1.42 “SUB-CONTRACT” shall mean any contract entered into between OWNER and any THIRD PARTY in the
  manner and to the extent permitted under the terms of the CHARTERPARTY whereunder OWNER sub-contracts
the performance of any part of the CHARTERPARTY and “to sub-contract” shall be construed accordingly.
 
1.1.43 “THIRD PARTY” shall mean any entity or person not within the COMPANY GROUP or OWNER GROUP and
 
“THIRD PARTIES” shall mean all of such entities and persons.
 
  1.1.44 “TRUE UP AMOUNT” shall have the meaning ascribed to it in Clause 29.3.
 
  1.1.45 “VARIATION ORDER” shall have the meaning ascribed to it in Clause 28.2.
 
Page 4 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 10/85
12/9/22, 4:25 PM EX-10.3

 
1.2 Interpretation
 
1.2.1 The CHARTERPARTY constitutes the entire agreement between the PARTIES with respect to the subject matter
 
hereof and shall supersede and cancel all prior agreements or understandings, whether oral or written.
 
1.2.2 The headings of all sections of the CHARTERPARTY are inserted for convenience of reference only and shall not
 
affect the construction or interpretation of the CHARTERPARTY.
 
1.2.3 Any provision herein which in any way may contravene the applicable laws or regulations of any jurisdiction to
  which the CHARTERPARTY is subject shall be deemed, to the extent of such contravention, excluded and of no
force or effect and shall not affect any other provisions of the CHARTERPARTY.
 
1.2.4 The CHARTERPARTY shall also be for the benefit of and binding upon COMPANY’s and OWNER’s respective
 
successors and ASSIGNEES.
 
1.2.5 Unless specifically stated otherwise, all references to days and/or months shall mean calendar days and/or months,
 
respectively, according to the Gregorian calendar.
 
2 CHARTERPARTY DOCUMENT
The provisions contained in the CHARTERPARTY and in the documents identified below, said documents being attached
hereto and made a part hereof or incorporated herein by reference for all purposes, shall be collectively known as the
CHARTERPARTY. The above-referenced CHARTERPARTY includes and shall be construed in the following order of
priority:
 
2.1 Commercial Section
 
  Section I Form of Agreement
 
  Section II Conditions of CHARTERPARTY
 
  Section III CHARTERPARTY Prices and Schedules for Variations
 
  Appendix “1” – OWNER’S and COMPANY’S Parent Company Guarantee Form
 
2.2 Technical Section
 
  Section IV Scope of Work
 
  Section V NOT USED
 
  Section VI Basis of Design
No change, amendment or other modifications to or in any document or provision forming part of the CHARTERPARTY
shall be valid or effective unless produced in writing and signed by duly authorised representatives of both COMPANY and
OWNER.
 
3 ENTIRE AGREEMENT
The documents referred to in Clause 2, when executed by OWNER and COMPANY, constitute the entire agreement between
OWNER and COMPANY concerning the subject matter covered thereby and neither any contrary or additional conditions
specified by either PARTY nor any subsequent amendment or supplement shall have any effect unless reduced to writing and
executed by duly authorised representatives of both PARTIES.
 
Page 5 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 11/85
12/9/22, 4:25 PM EX-10.3

 
4 SCOPE OF THE CHARTERPARTY AND OWNER’S OBLIGATIONS
 
4.1 OWNER shall furnish and deliver the FPSO to COMPANY at the OYO FIELD (and any other location within the AREA OF
OPERATIONS as may be agreed by the PARTIES) and COMPANY agrees to bareboat charter the FPSO for the period and
upon the terms and conditions stated herein.
 
4.2 OWNER shall ensure that the FPSO is fully equipped and furnished in accordance with and including all items as detailed in
Section VI – Basis of Design to receive crude oil from the subsea production system, separate oil, gas and water, store
stabilized crude oil and offload via hoses the oil to shuttle tankers moored in tandem to the FPSO.
 
4.3 OWNER shall reserve itself the right to select the flag for the FPSO provided that OWNER first notify COMPANY of
proposed change of flag.
 
4.4 [Not used].
 
4.5 OWNER undertakes that the REFURBISHMENT WORK shall, when completed, be compatible and interface with the
current OYO FIELD development project operations.
 
4.6 The FPSO, at the time of delivery and throughout the term hereof, shall be in compliance with the requirements of the
CHARTERPARTY.
 
4.7 The FPSO shall be delivered by the OWNER at the site described in Clause 4.1 hereof, equipped with all relevant mooring
and offloading equipment and risers/umbilical connection systems.
 
4.8 OWNER represents, undertakes and warrants that the FPSO will, at the time of delivery hereunder and throughout the term
hereof, comply with the requirements of the CLASSIFICATION AUTHORITY, and all applicable laws, rules, and regulations
then in force (subject to Clause 28.11, if applicable).
 
5 DELIVERY AND ACCEPTANCE
 
5.1 On the EFFECTIVE DATE and subject to CONTRACTOR compliance with the O&M CONTRACT and subject to
completion of the REFURBISHMENT WORK, the FPSO is deemed delivered at the OYO FIELD, properly equipped and
installed at site, crewed, tested, outfitted and in all respects ready to operate on a continuous basis for the purpose intended in
the CHARTERPARTY.
 
5.2 Activities During STANDBY PERIOD
 
5.2.1 During the STANDBY PERIOD and subject to PERMITTED DELAY (additional time required and costs incurred
during period of PERMITTED DELAY shall be for COMPANY account), OWNER shall perform the
 
REFURBISHMENT WORK; provided always that any time when hydrocarbon production is maintained during
the STANDBY PERIOD, such time shall not be deemed to be PERMITTED DELAY.
 
5.2.2 On the day on which the REFURBISHMENT WORK is completed and tested to the satisfaction of the
  CLASSIFICATION AUTHORITY (which, subject to Clause 5.2.1, OWNER shall ensure is no later than 1 July
2014) the OWNER shall provide written notice to COMPANY.
 
Page 6 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 12/85
12/9/22, 4:25 PM EX-10.3

 
5.2.3 Any scope of the REFURBISHMENT WORK which did not form part of OWNER’s obligations under the NAE
  CHARTERPARTY and identified in Appendix 1 to Section IV Scope of Work as not forming part of OWNER’s
obligations shall be reimbursed by COMPANY to OWNER.
 
6 SERVICE
Subject to the terms and conditions of the O&M CONTRACT, COMPANY shall have the full use of the FPSO in the AREA
OF OPERATIONS during the term of the CHARTERPARTY, including all equipment (which expression includes without
limitation, cabin, crew and galley equipment, navigation aids and technical equipment, furnishing, furniture and fittings and
spare and replacement parts, all communications equipment) and other property of OWNER on board the FPSO at the
EFFECTIVE DATE. Prior to the relocation of the FPSO, the PARTIES shall mutually agree in good faith on terms and
conditions with respect to the relocation and all the operations of the FPSO at any other safe location outside the OYO
FIELD.
 
7 TERM OF CHARTERPARTY
 
7.1 CHARTERPARTY Duration
 
7.1.1 Subject to the other provisions hereof, the CHARTERPARTY shall have an INITIAL PERIOD of seven (7) years
from the EFFECTIVE DATE, provided that COMPANY shall have the right to extend such INITIAL PERIOD for
2 (two) additional periods of 12 (twelve) months each, under the terms and conditions as set forth herein, by giving
  6 (six) months written notice to OWNER before the expiration of the INITIAL PERIOD plus any notified
extension. After COMPANY has given a notice of extension, COMPANY shall have the right to terminate any
such additional period at any time by giving 6 (six) months prior written notice in accordance with Clause 9.2.1.
No additional formal document to embody COMPANY’s option as aforesaid is required.
 
7.1.2 On expiration of the INITIAL PERIOD or additional period(s) (as applicable), the CHARTERPARTY shall come
to an end unless COMPANY and OWNER agree to extend the duration of the CHARTERPARTY beyond such
period. In such event, the PARTIES shall meet to define the new rates in respect of said extension, on the basis of
 
the principles set out in the CHARTERPARTY. Those terms and conditions shall not be less favorable than those
available elsewhere and shall be agreed before the end of the then current CHARTERPARTY period (failing which
the CHARTERPARTY will come to an end).
 
7.2 Right of extension
 
7.2.1 If COMPANY exercises the above right of extension of the INITIAL PERIOD as from the expiry of the INITIAL
  PERIOD, COMPANY shall continue to pay OWNER the DAILY COMPENSATION FEE as per Section III –
CHARTERPARTY Prices and Schedules for Variations, or as otherwise agreed between the PARTIES.
 
Page 7 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 13/85
12/9/22, 4:25 PM EX-10.3

 
8 MAINTENANCE
 
8.1 Maintenance and operation of the FPSO from the EFFECTIVE DATE is the responsibility of CONTRACTOR under the
O&M CONTRACT.
 
8.2 Notwithstanding any provisions in this CHARTERPARTY to the contrary, no dry-docking of the FPSO shall be undertaken
by OWNER (or the CONTRACTOR) for the first 5 (five) years of the INITIAL PERIOD unless agreed to in advance and in
writing by COMPANY, in its sole discretion. Any time lost, and all costs and expenses incurred, in connection with any dry-
docking of the FPSO, starting with the preparation for the disconnect of the FPSO from the mooring system and continuing
through the dry-dock until the FPSO returns to the designated location within the AREA OF OPERATIONS and is re-
connected to the mooring system and fully operational shall be for the sole account of OWNER, and no DAILY
COMPENSATION FEE shall be payable by COMPANY during any such time lost.
 
8.3 Subject to discretion of the CLASSIFICATION AUTHORITY, no dry-docking of the FPSO shall be undertaken by OWNER
(or the CONTRACTOR) provided the FPSO remains in its current location in the OYO FIELD during the 6th and 7th years of
the INITIAL PERIOD. Any dry-docking (if so required by the CLASSIFICATION AUTHORITY) shall be notified to
COMPANY as early as possible, but in no event later than the date that is 180 days before the end of the 5th year of the
INITIAL PERIOD, and OWNER (or the CONTRACTOR) shall consult COMPANY for the planning of such dry-docking. If
OWNER fails to so notify COMPANY of any dry-docking required by the CLASSIFICATION AUTHORITY, then such dry-
docking shall not be permitted during the INITIAL PERIOD.
 
8.4 The DAILY COMPENSATION FEE (or STANDBY FEE, when applicable) under this CHARTERPARTY remains payable
during any period of SHUTDOWN (except when caused by any negligent act or omission of OWNER GROUP), interruption
or delay after the EFFECTIVE DATE except as otherwise expressly provided for in this CHARTERPARTY or the O&M
CONTRACT.
 
9 TERMINATION
 
9.1 Termination Procedure
Termination of this CHARTERPARTY shall become effective as of the date and in the manner specified in a notice of
termination validly issued in accordance with the terms and conditions of this CHARTERPARTY and shall be without
prejudice to any claim which either PARTY may have against the other PARTY.
 
9.2 Early Termination
 
9.2.1 Subject to the terms of this Clause 9.2, the COMPANY may, at its sole discretion, terminate the CHARTERPARTY
 
for any reason and at any time during the INITIAL PERIOD by giving written notice thereof to OWNER.
 
9.2.2 On receipt of such notice OWNER shall, unless otherwise directed by the notice of termination, immediately
discontinue the CHARTERPARTY and/or the placing of orders in connection with the performance of the
CHARTERPARTY and shall, if so requested, use reasonable endeavors to cancel all existing commitments upon
 
terms satisfactory to COMPANY and shall thereafter perform only such portion(s) of the CHARTERPARTY as
may be necessary to preserve and protect the part of the CHARTERPARTY being performed after receipt of the
notice and to protect all OWNER’s or COMPANY’s goods located on the FPSO or in transit thereto.
 
Page 8 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 14/85
12/9/22, 4:25 PM EX-10.3

9.2.3 OWNER may by giving written notice to COMPANY terminate this CHARTERPARTY early if COMPANY
becomes insolvent, enters voluntary or involuntary bankruptcy, winding up or receivership proceedings (other than
 
a voluntary winding up for the purposes of amalgamation or reconstruction) or takes an assignment for the benefit
of its creditors
 
9.2.4 If the CHARTERPARTY is terminated by COMPANY pursuant to Clause 7.1 or 9.2.1 or by OWNER pursuant to
Clause 9.2.3 above, OWNER shall be entitled to the reimbursement of costs of that portion of the
 
CHARTERPARTY performed to the satisfaction of COMPANY up to the date of termination, evaluated at the rates
provided for in Clause 25.1, plus Early Termination Compensation (if applicable) as provided for in Clause 9.2.5.
 
9.2.5 Early Termination Compensation. If the CHARTERPARTY is terminated during the INITIAL PERIOD by
  COMPANY pursuant to Clause 9.2.1 (for reasons other than those stipulated in Clause 14.1 and 34.5) or by
OWNER pursuant to Clause 9.2.3 above, and
 
(a) the early termination becomes effective after the EFFECTIVE DATE but before the 5th anniversary date
 
of the commencement of the INITIAL PERIOD, then COMPANY shall pay to OWNER the lesser of:
 
(i) the DAILY COMPENSATION FEE for the remainder of the INITIAL PERIOD plus the
 
DEMOBILIZATION AND REDELIVERY FEE, or
 
(ii) the amount under Clause 5 of Section III - CHARTERPARTY Prices and Schedules for
 
Variations plus the DEMOBILIZATION AND REDELIVERY FEE.
 
(b) the early termination becomes effective on or after the 5th anniversary date of the commencement of the
INITIAL PERIOD but before the 6th anniversary date of the commencement of the INITIAL PERIOD,
provided that in the event of an early termination pursuant to Clause 9.2.1 (for reasons other than those
 
stipulated in Clause 14.1 and 34.5) COMPANY gives OWNER 120-days written notice, then, subject to
Clause 25.3, COMPANY shall be liable to OWNER only for the DAILY COMPENSATION FEE up to
the date of termination and OWNER shall not be entitled to any other termination compensation.
 
(c) the early termination becomes effective on or after the 6th anniversary date of the commencement of the
INITIAL PERIOD but before the 7th anniversary date of the commencement of the INITIAL PERIOD,
provided that in the event of an early termination pursuant to Clause 9.2.1 (for reasons other than those
 
stipulated in Clause 14.1 and 34.5) COMPANY gives OWNER 90-days written notice, then, subject to
Clause 25.3, COMPANY shall be liable to OWNER only for the DAILY COMPENSATION FEE up to
the date of termination and OWNER shall not be entitled to any other termination compensation.
For early termination under Clause 9.2.5(a) above, OWNER shall credit COMPANY with a share of any future daily
compensation fee equivalent earnings (net after tax) received from THIRD PARTIES during the unexpired portion of the
INITIAL PERIOD following such termination. Such share shall be net of all further costs actually incurred by OWNER that
are directly attributable to such early termination that have been incurred prior to receipt of such future earnings from THIRD
PARTIES during the INITIAL PERIOD. If such earnings are higher than the DAILY COMPENSATION FEE paid by
COMPANY to OWNER under this CHARTERPARTY, OWNER shall credit COMPANY all such excess daily compensation
fee.
 
Page 9 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 15/85
12/9/22, 4:25 PM EX-10.3

9.3 Early Termination of O&M CONTRACT


In the event that the O&M CONTRACT is terminated early pursuant to Clauses 5.1 or 6.2 of Section II of the O&M
CONTRACT, then this CHARTERPARTY shall also automatically terminate on the same date and the provisions of Clause
9.2 herein shall apply as if this CHARTERPARTY had been terminated by COMPANY pursuant to the equivalent provision
of Clause 9.2 herein.
 
10 AREA OF OPERATIONS ACQUAINTANCE
 
10.1 Acquaintance of AREA OF OPERATIONS
OWNER declares and represents that it is generally acquainted in all respects with the political, fiscal and logistics situation,
climatic and environmental conditions existing in the AREA OF OPERATIONS and that it has evaluated all typical costs and
risks connected therewith.
 
10.2 Specific Site Acquaintance
The OWNER is entitled to rely upon site information as stated and referenced in Section VI Basis of Design and in
accordance with Clause 28 “Variations”. Site information to be relied upon includes but is not limited to geographic,
geotechnical, metocean, bathymetry, and well stream fluid characteristics.
 
10.3 Latent conditions
In the event of discovery of one or more latent conditions, OWNER will evaluate impact on Scope of Work and design and
notify COMPANY in accordance with Clause 28.
 
11 PARTY REPRESENTATIVES
 
11.1 OWNER’S REPRESENTATIVE(S)
OWNER shall nominate and communicate in writing to COMPANY the person or persons who will have supervisory
authority for the CHARTERPARTY and with whom COMPANY’s REPRESENTATIVE(S) may coordinate the performance
thereof.
 
11.2 COMPANY’S REPRESENTATIVE(S)
 
11.2.1 COMPANY will nominate and communicate in writing to OWNER one or more REPRESENTATIVE(s) in the
  AREA OF OPERATIONS to whom OWNER’s REPRESENTATIVE(s) may deliver reports and other confidential
information developed from the CHARTERPARTY.
 
11.2.2 COMPANY’s REPRESENTATIVE(s) will consult with OWNER’s REPRESENTATIVE(s) in the planning and
  coordination of the CHARTERPARTY, and all instructions given by COMPANY’S REPRESENTATIVE(s) shall
be deemed those of COMPANY and shall be complied with.
 
Page 10 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 16/85
12/9/22, 4:25 PM EX-10.3

 
  11.2.3 COMPANY will also appoint a permanent on board REPRESENTATIVE, whose main tasks are:
 
  (a) to witness and certify the delivery of the oil to the offtaking tanker, both in terms of quantity and quality
 
(b) to ascertain that all the COMPANY requirements, as stated in the CHARTERPARTY and agreed by the
 
PARTIES, are correctly executed.
 
12 COMPANY’S OBLIGATIONS
COMPANY shall perform, arrange and meet the costs of the following operations and activities:
 
12.1 COMPANY shall furnish, at its expense, any and all authorizations and permits for the FPSO to operate at the AREA OF
OPERATIONS, except for authorizations and/or periodic testing relevant to FPSO, as detailed in Section IV Scope of Work.
COMPANY GROUP PERSONNEL shall have free access to the FPSO in the AREA OF OPERATIONS.
 
12.2 COMPANY will provide the facilities, services, activities and hydrocarbon required of the COMPANY GROUP under this
CHARTERPARTY and the O&M CONTRACT in accordance with Section IV - Scope of Work - Part 2.4. OWNER shall co-
operate with CONTRACTOR in order not to delay or impede the performance of the REFURBISHMENT WORK. The
COMPANY will co-ordinate its other activities in the AREA OF OPERATIONS and will keep the OWNER and
CONTRACTOR sufficiently informed in respect of it so as to facilitate the performance of the OWNER’s obligations.
 
12.3 COMPANY shall obtain and maintain at its expense any and all consents, authorizations, approvals, licensing and permits
required by it under this CHARTERPARTY. OWNER shall obtain and maintain at its expense any and all consents,
authorizations, approvals, licensing and permits required by it under this CHARTERPARTY.
 
13 NOT USED
 
14 DEFAULT BY OWNER
 
14.1 Right of termination by COMPANY
In the event:
 
14.1.1 the OWNER assigns the whole or part of the CHARTERPARTY to THIRD PARTIES or SUB-CONTRACTS the
 
whole of the CHARTERPARTY without COMPANY’s prior written consent; and/or
 
14.1.2 the OWNER shall at any time be in fundamental breach of any of its obligations under this CHARTERPARTY;
 
and/or
 
14.1.3 the OWNER suspends the performance of the CHARTERPARTY for any reason whatsoever including in the event
 
of arbitration; and/or
 
  14.1.4 the OWNER fails to take out insurance policies required by the CHARTERPARTY or fails to renew them; and/or
 
14.1.5 OWNER becomes insolvent, enters voluntary or involuntary bankruptcy, winding up or receivership proceedings
  (other than a voluntary winding up for the purposes of amalgamation or reconstruction) or takes an assignment for
the benefit of its creditors; then
 
Page 11 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 17/85
12/9/22, 4:25 PM EX-10.3

if COMPANY considers that one of the aforesaid events exists, it may give written notice thereof to OWNER referring to this
Clause 14.1 and requiring OWNER to remedy such situation. OWNER has to commence action to remedy the situation
within 2 (two) working days and has to complete the remedy in a reasonable maximum time indicated by COMPANY, taking
into account all the circumstances.
 
14.2 If, upon the expiry of the aforesaid period, such situation has not been remedied or removed or if an agreement has not been
reached on a plan to remedy or remove the situation, the CHARTERPARTY may be terminated. In no case shall the
termination of the CHARTERPARTY relieve either PARTY from any of its obligations or liabilities accrued due hereunder
prior to such termination or prejudice any provisions hereof which are expressed to survive the termination or expiry hereof.
 
14.3 In the event that COMPANY terminates the O&M CONTRACT for any reason whatsoever other than either (1) in accordance
with Clause 6.2 of Section II of the O&M CONTRACT (the consequences of which are dealt with in Clause 9.3 of this
CHARTERPARTY) or (2) for extended force majeure (which COMPANY is not entitled to do unless it also terminates this
CHARTERPARTY in accordance with Clause 34.5 herein) then this CHARTERPARTY will automatically terminate on the
date on which COMPANY terminates the O&M CONTRACT without any notice being required to be given by COMPANY
under this CHARTERPARTY.
If the CHARTERPARTY is terminated for any of the reasons set forth in this Clause 14 COMPANY shall pay OWNER the
total amount of DAILY COMPENSATION FEE as per Clause 1.2 of Section III due to the date of termination in performing
the CHARTERPARTY in conformity herewith. Said payment shall represent full and final payments for all activities
completed and for complete termination of the CHARTERPARTY.
 
15 LIENS AGAINST THE FPSO
 
15.1 COMPANY’s obligations
COMPANY shall have no right, power or authority to create, incur, or permit to be imposed upon the FPSO any liens
whatsoever. OWNER will fasten to the FPSO in a conspicuous place and maintain during the period of the
CHARTERPARTY a notice reading as follows:
“THIS FPSO IS UNDER CHARTERPARTY TO OCEANIC CONSULTANTS NIGERIA LIMITED AND, BY THE TERMS
OF THE CHARTERPARTY, NONE OF OCEANIC CONSULTANTS NIGERIA LIMITED, OWNER, OR THE MASTER
HAS ANY RIGHT, POWER OR AUTHORITY TO CREATE, INCUR OR PERMIT TO BE IMPOSED UPON THE FPSO
ANY LIENS WHATSOEVER”.
 
15.2 OWNER’s Obligations
 
15.2.1 OWNER hereby acknowledges and agrees that, during and throughout the term of this CHARTERPARTY, so long
as no default by COMPANY has occurred and is continuing hereunder, neither COMPANY nor any PERMITTED
SUB-CHARTERER or ASSIGNEE shall be disturbed or interfered with by OWNER in COMPANY’s or such
PERMITTED SUB-CHARTERER’s or ASSIGNEE’s quiet and peaceful use and enjoyment of the FPSO
(including, without limitation, their ability to utilize the FPSO in the AREA OF OPERATIONS). In the event that
OWNER, after the EFFECTIVE DATE, grants a mortgage over the FPSO or collaterally assigns its rights under
 
this CHARTERPARTY, then OWNER shall ensure that any holder of such mortgage or ASSIGNEE of such rights,
as the case may be, shall execute and deliver an agreement, in form and substance satisfactory to COMPANY
recognizing COMPANY’s (or its PERMITTED SUB-CHARTERER’s or ASSIGNEE’s, as the case may be) quiet
enjoyment rights in the FPSO pursuant to this Clause 15.2.1. In no event shall OWNER permit the existence of any
mortgage or liens on the FPSO, and/or OWNER’s compliance with the conditions thereof, to interfere or in any
way delay the performance of its obligations under the CHARTERPARTY.
 
Page 12 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 18/85
12/9/22, 4:25 PM EX-10.3

15.2.2 Subject to the rights of the OWNER under Clause 15.2.1, the OWNER shall not create, incur, or permit to be
 
imposed upon the FPSO any liens whatsoever.
 
16 ACTUAL CONSTRUCTIVE TOTAL LOSS AND COMPULSORY ACQUISITION
 
16.1 In the event of actual total loss or constructive total loss of the FPSO occurring through any acts whatsoever at any time
during the period of the CHARTERPARTY, the CHARTERPARTY shall be deemed terminated as of the date of said loss (if
the time of such loss is uncertain, then as of the date the FPSO was last heard from), and the FPSO shall be deemed to have
been redelivered to OWNER as of such date.
 
16.2 If there is a period of time between the event which constitutes actual or constructive total loss and the determination (by the
OWNER’S insurers or otherwise) that an actual or constructive total loss has occurred during which the OWNER has
received compensation hereunder at the applicable DAILY COMPENSATION FEE, the OWNER shall refund such
compensation to the COMPANY.
 
16.3 If the FPSO becomes an actual or constructive total loss pursuant to Clause 16.1, the OWNER will be responsible for the
removal of its wreck and debris if, and to the extent that, it is required to do so by law or by any contract or order binding on
either the OWNER or the COMPANY or if the wreck is a hazard to navigation or to the COMPANY’s operations in the
AREA OF OPERATIONS. If the CHARTERPARTY terminates pursuant to Clause 16.1, the OWNER shall not be entitled to
any Early Termination Compensation payable pursuant to Clause 9 or any other compensation from the COMPANY.
 
16.4 If OWNER is deprived of the FPSO by any COMPULSORY ACQUISITION by any governmental or other competent
authority, the FPSO will be deemed “off-hire” and the DAILY COMPENSATION FEE shall not be payable by COMPANY
during the period of COMPULSORY ACQUISITION.
 
16.5 If any compensation is paid by the relevant governmental or other competent authority in respect of a COMPULSORY
ACQUISITION, (“ACQUISITION COMPENSATION”), CONTRACTOR shall be entitled to receive the ACQUISITION
COMPENSATION.
 
17 GENERAL AND PARTICULAR AVERAGE
General average, if any, shall be adjusted, stated, and settled according to the York-Antwerp Rules (2004) or any subsequent
modification thereof current at the time of the relevant casualty. The DAILY COMPENSATION FEE shall not contribute to
general average. A company approved by both PARTIES shall be appointed average adjuster to attend to the settlement and
collection of both general and particular average losses subject to customary charges. OWNER and COMPANY jointly agree
to assist the adjuster in preparing the average statement and to take all other possible measures to protect the interests of
OWNER, FPSO and COMPANY.
 
Page 13 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 19/85
12/9/22, 4:25 PM EX-10.3

 
18 REDELIVERY OF FPSO
The FPSO shall be deemed to have been redelivered (“DATE OF REDELIVERY”, for which COMPANY shall give OWNER
at least 90 (ninety) days’ prior notice) and the DAILY COMPENSATION FEE shall cease when production at the AREA OF
OPERATIONS is finally shut-in and COMPANY has removed the cargo from the FPSO. The FPSO shall from the DATE OF
REDELIVERY be dismantled and removed from the AREA OF OPERATIONS by OWNER, and its ancillaries recovered,
and towed and/or transported to a port/area to be agreed and cleaned and gas-freed. Compensation for such removal, towing,
transportation etc. shall be paid in accordance with Clause 25.3 and Clause 1.3 of Section III - CHARTERPARTY Prices and
Schedules for Variations.
 
19 PATENT INDEMNIFICATION
 
19.1 In addition to any other indemnifying provisions contained herein, OWNER represents and warrants that the use or
construction of any and all procedures, equipment and/or materials, the FPSO or any process furnished by OWNER and used
in the CHARTERPARTY do not infringe any license, patent or other trade secret which has been issued or applied for, and
OWNER agrees to protect, defend, indemnify and hold COMPANY GROUP harmless from and against any and all claims,
losses, costs, demands, damages, suits, judgments, penalties, liabilities, debits, expenses and causes of action and every other
claim or litigation (including all costs thereof and attorney’s fees) of every kind and character whether known or unknown,
whether predating the CHARTERPARTY or not, made by or arising in favor of any patentee, licensee or claimant of any right
or priority to such procedures, equipment and/or materials, FPSO or process, or the use or construction thereof, which may
result or arise from furnishing or use of any such procedures, equipment and/or materials, FPSO or process by OWNER in
connection with the CHARTERPARTY.
 
19.2 All intellectual property of OWNER GROUP shall remain vested in the OWNER GROUP. OWNER GROUP reserves the
sole right to apply for patent or registrable rights in any country in respect of any article, process or idea developed by
OWNER GROUP, arising out of or conceived during the OWNER GROUP’s performance of the CHARTERPARTY.
 
19.3 OWNER hereby grants to COMPANY, an irrevocable, perpetual, world-wide, royalty-free right to use or have used (as well
as modify, transfer, adapt, copy, reproduce, exploit, apply, manipulate and otherwise enjoy) by COMPANY GROUP, and any
THIRD PARTY for the provision of goods and services by such party to COMPANY GROUP under this CHARTERPARTY,
any intellectual property rights owned by or licensed by OWNER GROUP during the term of the CHARTERPARTY to the
extent necessary or desirable for purposes of COMPANY exercising their rights and obligations under this
CHARTERPARTY.
 
20 INDEPENDENT CONTRACTOR
 
20.1 OWNER shall be an independent contractor with respect to the performance of the CHARTERPARTY and neither OWNER
nor anyone employed by OWNER shall be deemed for any purpose to be the employee, agent, servant, borrowed servant or
representative of COMPANY in the performance of any service hereunder.
 
Page 14 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 20/85
12/9/22, 4:25 PM EX-10.3

 
20.2 The actual performance and supervision of the OWNER’s duties hereunder shall be by OWNER, but COMPANY or its
REPRESENTATIVE(s) shall have full and complete access to the operations and activities of OWNER to determine whether
same are being performed by OWNER in accordance with all its provisions or for reasons otherwise stated in the
CHARTERPARTY. No provisions herein shall be construed as creating a partnership, joint venture or other association
whereby COMPANY and OWNER would be jointly liable as partners or co-venturers.
 
21 REPRESENTATIONS AND WARRANTIES
 
21.1 OWNER represents and warrants that all obligations it undertakes pursuant to the CHARTERPARTY will be performed in a
thorough, efficient and workmanlike manner with due diligence and care by qualified and competent personnel. OWNER
further warrants that it has fully acquainted itself with the information contained in the CHARTERPARTY and on the basis of
that information knows of no reason why any physical or material aspects would interrupt or delay the diligent performance
of its obligations hereunder. It is fully acquainted with the nature of the duties it hereby undertakes to perform in the
CHARTERPARTY and knows of no reason and anticipates no interruptions, whether by labor disputes or otherwise, which
would prevent it from diligently pursuing the performance of the CHARTERPARTY.
 
21.2 OWNER represents and warrants that Nigerian Agip Exploration Limited (as charterer under the NAE CHARTERPARTY)
has been released of all obligations under the NAE CHARTERPARTY and has waived all rights in and to the FPSO as of the
EFFECTIVE DATE.
 
21.3 OWNER affirms that on the DATE OF ACCEPTANCE, the FPSO will be in all material aspects in compliance with the
OWNER’s obligations as they existed under the NAE CHARTERPARTY.
 
22 NO WAIVER
 
  No failure or failures on the part of either COMPANY or OWNER to enforce their respective rights hereunder shall be
construed as a waiver of such right or rights or preclude a subsequent enforcement of a subsequent breach.
 
23 SEVERABILITY OF PROVISIONS
 
  If any provision of the CHARTERPARTY or any portion thereof, or the application thereof to any person or circumstance, is
held invalid, the application of such provision or portion thereof to other persons or circumstances or other jurisdictions, and
the remainder of such provision and the CHARTERPARTY shall not be affected thereby but shall remain in full force and
effect.
 
24 INSURANCE AND INDEMNITY
 
24.1 INSURANCE
 
24.1.1 OWNER shall, at its own expense, maintain in force during the term of the CHARTERPARTY the following
insurances with insurance companies reasonably acceptable to COMPANY. All OWNER’s policies shall contain a
 
waiver of subrogation in favour of COMPANY GROUP to the extent of the indemnities granted and liabilities
undertaken by OWNER under the CHARTERPARTY.
 
Page 15 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 21/85
12/9/22, 4:25 PM EX-10.3

 
(a) Hull and Machinery and Increased Value insurance up to the full replacement value of the FPSO on
 
terms and conditions of the Institute Time Clauses, hulls-Port Risks 207.87, form or equivalent.
 
(b) War-strikes-Confiscation insurance subject to the Institute War and Strikes Clauses Hull Time,
 
October 1, 1983, form or equivalent.
 
(c) Jointly with CONTRACTOR, Comprehensive General Liability and Automobile Liability insurance
covering premises and operations, independent contractors and contractual liability, as well as all
 
owned, hired and non-owned vehicles. Minimum policy limits for personal injury and property damage
shall be:
 
(i) Comprehensive General Liability US$ 15,000,000 (fifteen million) single limit per occurrence,
 
and
 
  (ii) Automobile liability as required by applicable law.
 
(d) Protection and Indemnity including pollution insurance, with a limit to the extent then available but not
less than US$ 500,000,000 (five hundred million), for production related vessels taken out with a
 
member of the International Group of P&I Clubs. OWNER will procure a joint entry with
CONTRACTOR for all relevant purposes.
 
24.1.2 OWNER shall promptly furnish COMPANY with Certificates of Insurance in relation to Clause 24.1 above
 
indicating:
 
  (a) the kinds and amounts of insurance as required herein;
 
  (b) insurance company or companies providing the aforesaid coverage;
 
  (c) effective and expiration dates of policies; and
 
  (d) the territorial limits of all policies.
 
24.1.3 COMPANY GROUP shall be named as co-assured on the above policies to the extent of the indemnities granted
and liabilities undertaken by OWNER under this CHARTERPARTY and in the case of the Protection and
  Indemnity insurance referred to Clause 24.1.1(d) so as to provide that COMPANY GROUP shall be provided with
coverage not less than that available to OWNER, with a limit to the extent then available but not less than US$
500,000,000 (five hundred million).
 
24.2 INDEMNITY
 
24.2.1 Notwithstanding anything to the contrary contained elsewhere, OWNER shall be responsible for and shall release,
 
protect, defend, indemnify and hold COMPANY GROUP harmless from and against:
 
  (a) all loss of or inability to recover, or damage to the OWNER GROUP EQUIPMENT; and
 
(b) any personal injury, including fatal injury and disease, to or death of the OWNER GROUP
 
PERSONNEL;
 
  howsoever caused (whether through the breach of contract, negligence and/or breach of duty (statutory or
  otherwise) of any of the COMPANY GROUP or otherwise) that arises out of or in connection with this
CHARTERPARTY.
 
Page 16 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 22/85
12/9/22, 4:25 PM EX-10.3

 
24.2.2 Notwithstanding anything to the contrary contained elsewhere, COMPANY shall be responsible for and shall
 
release, protect, defend, indemnify and hold OWNER GROUP harmless from and against:
 
  (a) all loss of or inability to recover, or damage to the COMPANY GROUP EQUIPMENT; and
 
(b) any personal injury, including fatal injury and disease, to or death of the COMPANY GROUP
 
PERSONNEL;
 
  howsoever caused (whether through the breach of contract, negligence and/or breach of duty (statutory or
  otherwise) of any of the OWNER GROUP or otherwise) that arises out of or in connection with this
CHARTERPARTY.
 
24.2.3 OWNER shall be responsible for and shall release, protect, defend, indemnify and hold COMPANY GROUP
harmless in respect of the injury/death of any and all THIRD PARTIES or loss of/damage to any and all THIRD
PARTY property arising from and to the extent of OWNER GROUP’s negligent act or omission in the
  performance of the CHARTERPARTY. COMPANY shall be responsible for and shall release, protect, defend,
indemnify and hold OWNER GROUP harmless in respect of the injury/death of any and all THIRD PARTIES or
loss of/damage to any and all THIRD PARTY property arising from and to the extent of COMPANY GROUP’s
negligent act or omission in the performance of the CHARTERPARTY.
 
24.2.4 Notwithstanding anything contained herein to the contrary, the responsibility for pollution or contamination arising
 
from or relating to the performance of this CHARTERPARTY shall be as follows:
 
(a) COMPANY shall be responsible for and shall release, protect, defend, indemnify and hold OWNER
GROUP harmless from and against all claims, loss, damage or expense in respect of the control,
  removal and disposal of pollution or contamination caused by crude oil or other pollutants originating or
emanating from the COMPANY GROUP’s oil or gas reservoirs or wellheads or emanating from
COMPANY GROUP EQUIPMENT; and
 
(b) OWNER shall be responsible for and shall release, protect, defend, indemnify and hold COMPANY
GROUP harmless from and against all claims, loss, damage or expense in respect of the control,
  removal and disposal of pollution or contamination caused by crude oil or other pollutants originating or
emanating from the OWNER GROUP EQUIPMENT up to the limit of the Protection and Indemnity
Insurance procured by OWNER under this CHARTERPARTY.
 
24.2.5 Notwithstanding anything contained herein to the contrary, neither COMPANY nor OWNER shall under any
 
circumstances be liable to the other PARTY for any:
 
  (a) indirect and/or consequential loss or damage; and/or
 
Page 17 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 23/85
12/9/22, 4:25 PM EX-10.3

 
(b) loss of anticipated profit, loss of contract, loss of production, loss of products, whether such losses are
direct or indirect arising out of or related to the performance of either PARTY under this
CHARTERPARTY. Each PARTY shall be responsible for and shall release, protect, defend, indemnify
 
and hold the other PARTY’s GROUP harmless from and against all such claims, demands, and causes of
action and shall waive any claim it may at any time have against the other PARTY’s GROUP in respect
of any such losses or damage.
 
24.2.6 In the event OWNER shall fail to take out the insurances required by the CHARTERPARTY or fails to renew
  them, COMPANY may at its sole discretion provide such insurances at OWNER’s charge or terminate the
CHARTERPARTY in accordance with Clause 14.1.4.
 
25 COMPENSATION
 
25.1 DAILY COMPENSATION FEE and STANDBY FEE
 
  Subject to Clause 25.4, COMPANY shall pay to OWNER for (a) OWNER meeting its obligations as defined in the
CHARTERPARTY and (b) CONTRACTOR meeting its obligations as defined in the O&M CONTRACT, the DAILY
COMPENSATION FEE (or STANDBY FEE as applicable) as set forth in Section III - CHARTERPARTY Prices and
Schedules for Variations from the EFFECTIVE DATE to the DATE OF REDELIVERY.
 
25.2 Milestone Payments
 
  COMPANY shall pay OWNER Milestone Payments on date of signature of the CHARTERPARTY and DATE OF
ACCEPTANCE as set forth in Section III - CHARTERPARTY Prices and Schedules for Variations - Clause 1.1.
 
25.3 Demobilization and Redelivery Fee
 
  COMPANY shall pay OWNER a “DEMOBILIZATION AND REDELIVERY FEE”, which shall equal the amount that is
fifty per cent (50%) of the documented reasonable costs incurred by OWNER for the dismantling, removal, and redelivery
services provided in Clause 18. No DEMOBILIZATION AND REDELIVERY FEE shall be payable by COMPANY if, upon
termination of the CHARTERPARTY, the FPSO has been committed to another party for work in direct continuance.
 
25.4 Reimbursable Expenses
 
  25.4.1 COMPANY shall reimburse OWNER for the following expenses incurred under the CHARTERPARTY:
 
(a) Food and lodging - Food and lodging or individual meals for any COMPANY or THIRD PARTY
personnel, in excess of the permanent COMPANY complement specified in Section IV – Scope of
 
Work, at the rates set forth in Section III of the O&M CONTRACT Prices and Schedules for Variations,
Clause 2.1.
 
(b) Other Expenses - All other expenses incurred by OWNER at COMPANY’s written request or otherwise
  reimbursable under this CHARTERPARTY, shall be reimbursed at documented cost, except as
otherwise expressly provided herein.
 
Page 18 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 24/85
12/9/22, 4:25 PM EX-10.3

 
26 NOT USED
 
27 INVARIABILITY OF PRICES
 
  COMPENSATION and/or fees set forth in Section III - CHARTERPARTY Prices and Schedules for Variations shall, subject
to other provisions of the CHARTERPARTY, remain unchanged during the term of the CHARTERPARTY.
 
28 VARIATIONS
 
  The PARTIES recognize and agree that provision should be made to cover a variation in the obligations of OWNER under
this CHARTERPARTY and that any such variation should only be made in accordance with the provisions of this Clause 28.
 
28.1 Without prejudice to the foregoing generality and for illustrative purposes only:
 
  28.1.1 the following would be regarded as a variation in the obligations under this CHARTERPARTY:
 
(a) instructions issued by the COMPANY which would result in a change to the specification of the FPSO
 
as detailed in the Technical Section of “Form of Agreement” (Art. 2.2);
 
(b) any request by the COMPANY to the OWNER to delay the schedule, or any delay to OWNER’s
 
schedule caused by act or omission of any member of COMPANY GROUP; or
 
  (c) discovery of latent conditions in accordance with Clause 10.3, and
 
  28.1.2 the following would not be regarded as a variation in the obligations under this CHARTERPARTY:
 
(a) Activities and/or resources to the extent necessitated, in whole or in part, by the act, error, negligence or
 
omission of the OWNER GROUP; or
 
(b) Activities and/or resources to the extent necessitated, in whole or in part, by the OWNER’s failure to
 
comply, or as are necessary in order to comply with any provision of this CHARTERPARTY.
 
28.2 The COMPANY may at its sole discretion from time to time, request a variation to the obligations the OWNER has to
perform under this CHARTERPARTY (a ‘VARIATION ORDER”) and the OWNER shall (subject to this Clause) implement
said variation and said variation shall not in any way be construed as invalidating this CHARTERPARTY or any ancillary
document but shall form part of the obligations the OWNER performs under this CHARTERPARTY.
 
28.3 The OWNER shall be obliged to proceed with any variation proposed by COMPANY, provided that such variation would not:
 
  28.3.1 be outside the general scope of its obligations provided for under this CHARTERPARTY, or
 
  28.3.2 impact detrimentally upon the safe working of the FPSO.
 
Page 19 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 25/85
12/9/22, 4:25 PM EX-10.3

 
28.4 If the COMPANY requests a variation under Clause 28.2, the OWNER will issue a variation proposal to the COMPANY
providing:
 
  28.4.1 a detailed technical narrative/description of the variation with a full and precise list of impacts/interfaces (if any);
 
28.4.2 details of the increase or decrease in compensation payable to the OWNER calculated in accordance with Clause
 
28.8; and
 
  28.4.3 an estimate of the time scale for and completion date of the variation.
 
28.5 A detailed calculation using the procedure set out in this Clause 28 of any anticipated impact upon the schedule due to the
proposed variation (together, where relevant, with any previous cumulative impacts of earlier Variation Orders) and any other
rates or fees provided for in Section III - CHARTERPARTY Prices and Schedules for Variations in relation thereto.
 
28.6 In preparing the variation proposal, the OWNER shall be obliged to have regard to:
 
  28.6.1 optimizing the cost impact for the COMPANY; and
 
  28.6.2 minimizing the adverse impact on the schedule.
 
28.7 If the OWNER considers that an occurrence has taken place for which it is entitled to receive a variation the OWNER shall,
before proceeding with any work affected by such occurrence, submit immediately in writing a variation proposal to the
COMPANY in accordance with Clause 28.4.
 
28.8 On receipt of a variation proposal from the OWNER, the COMPANY may reject the variation proposal for any reason,
including it if the request is included in the obligations undertaken by the OWNER under the terms of the CHARTERPARTY,
or the COMPANY may accept the variation proposal; in this case OWNER shall issue a VARIATION ORDER for signature
by both PARTIES incorporating the terms of the variation proposal. A VARIATION ORDER when so signed shall be binding
on both PARTIES. The VARIATION ORDER shall be governed by the provisions of this CHARTERPARTY.
 
28.9 Payment for a VARIATION ORDER shall be made by way of an agreed lump sum amount (to be invoiced and paid as agreed
in the VARIATION ORDER) or reimbursable in accordance with Clause 3 of Section III O&M CONTRACT Prices and
Schedules for Variations of the O&M CONTRACT.
 
28.10 The OWNER shall not commence implementation of a variation requested by COMPANY (other than as provided in this
Clause or in the instance of an emergency arising as determined at the OWNER’s reasonable discretion) until it has received a
VARIATION ORDER approved by the COMPANY.
 
28.11 The OWNER shall not invoice and the COMPANY will not be obliged to make any payment in respect of any variation
which has not been authorized by the COMPANY by means of a VARIATION ORDER.
 
Page 20 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 26/85
12/9/22, 4:25 PM EX-10.3

28.12 If, after the EFFECTIVE DATE, there have occurred any changes in the existing laws and regulations of Nigeria, including
but not limited to Bank Law or Exchange Control Law, or in the existing requirements of the CLASSIFICATION
AUTHORITY or of any Governmental Authority (or in the interpretation or implementation by the relevant authority) or in
the flag State’s requirements of the FPSO, which affect the OWNER’s performance (or the cost of performance) of its
obligations under the CHARTERPARTY, or the OWNER’s net return after any taxes in Nigeria, or imposing any such taxes
on dividends or distributions to OWNER’s shareholders or head office, then except to the extent such changes were known or
reasonably foreseeable by OWNER at the time of signing of the CHARTERPARTY, OWNER shall be entitled to a
VARIATION ORDER in accordance with this Clause 28. For the purposes of this Clause, Governmental Authority shall mean
the government of Nigeria or any such ministry, bureau, agency, department, office or other organization of the government
or any local governmental authority of Nigeria which may issue, request or make any authorization, consent, order, approval,
resolution, license, exemption, permission, notarization, recording, filing or registration or other similar document.
 
29 INVOICING AND PAYMENT
 
29.1 Milestone Payments shall be due and payable by COMPANY in accordance with Clause 1.1 of Section III.
 
29.2 On the EXECUTION DATE, OWNER shall prepare and send to COMPANY one invoice for all amounts covering the period
from the EFFECTIVE DATE through the end of the month in which the EXECUTION DATE occurs that are payable by
COMPANY under this CHARTERPARTY, and such invoice shall show the VAT rate and amount (where applicable).
 
29.3 Subject to Clause 29.2, on the first (1st) BUSINESS DAY of each month following the EXECUTION DATE, OWNER shall
prepare and send to COMPANY an invoice for the amount equal to the applicable day rate (pursuant to Clause 1.2 of Section
III) multiplied by the number of days in such month minus any TRUE-UP AMOUNT, and such invoice shall show the VAT
rate and amount (where applicable). The “TRUE UP AMOUNT” shall equal the sum of all reductions to be made to the prior
month’s invoice based upon any days of such invoiced month where a rate other than the invoiced day rate applied (or any
suspension of rates due to total loss, requisition, expropriation, or any other reason). Payment for the TRUE UP AMOUNT
applicable to the final invoice issued by OWNER hereunder shall be made by OWNER to COMPANY within 45 (forty-five)
days of the date of such final invoice.
 
29.4 Within 14 (fourteen) days of receipt of the relevant invoice(s), COMPANY will revert identifying any disputed amounts. If
COMPANY does not identify any disputed item, then the invoice(s) will be deemed undisputed in full.
 
29.5 Invoices shall be sent to:
 
  Oceanic Consultants Nigeria Limited
  Plot 1649, Olosa Street
  Victoria Island
  Lagos - Nigeria
 
29.6 Except for Early Termination Compensation pursuant to Clause 9 and Milestone Payments referred to in Clause 29.1,
undisputed amounts will be payable within 30 (thirty) days of the invoice.
 
29.7 All payments by COMPANY will be made in US Dollars and in immediately available freely transferable funds without
discount, set-off or deduction of any kind, except as expressly permitted by this CHARTERPARTY, by inter-bank transfer,
free of bank charges (other than those charged by OWNER’s bank) to such bank or financial institution as the OWNER shall
designate in writing on the invoice, for credit to the account nominated by OWNER, subject to the requirements of Clause
44.9.
 
Page 21 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 27/85
12/9/22, 4:25 PM EX-10.3

 
29.8 The Early Termination Compensation payable pursuant to Clause 9 will be payable on the date specified for termination in
the COMPANY’s and/or OWNER’s early termination notice. The DAILY COMPENSATION FEE and the other rates and
fees specified in Section III shall continue to be payable until the latest of:
 
  29.8.1 the date on which the Early Termination Compensation is actually paid; or
 
  29.8.2 the DATE OF REDELIVERY
 
29.9 If an invoice issued in accordance with the terms of the CHARTERPARTY becomes overdue for payment, or at any time
afterwards, OWNER may notify COMPANY in writing that such payment is overdue. After notifying COMPANY, if
COMPANY fails to make payment of any undisputed amount owing within five (5) days following its receipt of an overdue
notice from OWNER, then all money due to the OWNER shall accrue interest, compounding monthly, from the due date of
payment to the date of receipt by the OWNER and OWNER shall be entitled to exercise its rights under Clause 30.
 
29.10 The rate of interest payable under this Clause will be the aggregate of two per cent (2%) per annum and one month LIBOR
(as displayed on Reuters Screen Page LIBOR at or about 11.00 hrs London time on the date upon which the payment became
due and monthly thereafter, failing which as certified by a prime bank in London).
 
29.11 Payment by the COMPANY shall not prejudice its rights in the future to dispute any part of any invoice including any invoice
previously paid. In the instance of dispute over any part of an invoice, the COMPANY shall not delay payment of the
undisputed part of the invoice.
 
29.12 Any dispute concerning an amount contained within an invoice shall be resolved between the PARTIES in accordance with
the provisions of Clause 35 unless otherwise agreed. Following resolution of the dispute any amount agreed or found to be
payable shall be paid within thirty (30) days of the date of resolution.
 
29.13 All invoices submitted by the OWNER shall:
 
  29.13.1 be made in one (1) original and 4 (four) copies;
 
  29.13.2 show the VAT rate and amount (where applicable);
 
29.13.3 be submitted with sufficient documentation to support such invoices and permit verification by the COMPANY;
 
and
 
  29.13.4 be sent by mail, by delivery, or by any other means as may be agreed between the PARTIES from time to time.
 
29.14 Should the OWNER wish to change any bank or other financial institution to which payment is to be made, at least 10 (ten)
days prior written notice shall be given to the COMPANY of the new bank or financial institution and account details where
such payment is to be made.
 
29.15 Records
 
  OWNER shall maintain a complete and correct set of records pertaining to all aspects of the CHARTERPARTY, including the
performance hereof by OWNER. COMPANY, in order to verify that all transactions between COMPANY and OWNER under
the CHARTERPARTY satisfy all terms and conditions of the CHARTERPARTY, shall have the right at COMPANY’s sole
expense to inspect and audit any and all relevant records relating to adjustments in cost or reimbursable expenses within a
period of 5 (five) years after the transaction in question. Should the results of an audit so require, appropriate adjustments or
payments will be made by the PARTIES.
 
Page 22 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 28/85
12/9/22, 4:25 PM EX-10.3

 
30 PARENT COMPANY GUARANTEES AND LETTER OF CREDIT
 
30.1 In order to guarantee its performance of the CHARTERPARTY, OWNER will furnish a Parent Company Guarantee from
“Bumi Armada Berhad” in the same form annexed at Section III of this CHARTERPARTY. This Parent Company Guarantee
will be exchanged with the Parent Company Guarantee to be furnished by COMPANY in accordance with Clause 30.3.
 
30.2 Bumi Armada Berhad of Level 21, Menara Penak, 24 Jelan Perak 50450 Kuala Lumpur Malaysia currently directly or
indirectly owns 100% of the shares in OWNER. In the Parent Company Guarantee which will be furnished by
OWNER, Bumi Armada Berhad will agree not to transfer any of its shareholding in OWNER without COMPANY’s prior
consent, such consent not to be unreasonably withheld by COMPANY.
 
30.3 In order to guarantee its performance of the CHARTERPARTY, COMPANY will furnish a Parent Company Guarantee from
CAMAC Energy, Inc. (NYSE:CAK) in the same form annexed at Section III of this CHARTERPARTY.
 
30.4 In order to guarantee its payment obligation under the CHARTERPARTY, COMPANY will furnish OWNER an irrevocable
Standby Letter of Credit in the amount of ninety (90) days of the DAILY COMPENSATION FEE in advance upon execution
of the CHARTERPARTY. Such Letter of Credit shall be issued by an internationally reputable bank reasonably acceptable to
the OWNER; if COMPANY fails to make the monthly payment of fees when due and payable under this CHARTERPARTY,
then OWNER may make a draw against such Letter of Credit in an amount equal to the amount then due and payable by
COMPANY, and COMPANY shall, within five (5) banking days, replenish the amount of the Letter of Credit so that it again
equals the amount of ninety (90) days of the DAILY COMPENSATION FEE.
 
30.5 The Letter of Credit referred to in Clause 30.4 will be delivered by COMPANY contemporaneously with the execution of the
CHARTERPARTY. The Parent Company Guarantees referred to in the foregoing provisions of this Clause 30 will delivered
by the PARTY responsible therefor on or before a date that is 30 (thirty) days following the EXECUTION DATE.
 
31 TAXES
 
31.1 Payment.
 
  Except as expressly provided otherwise in this Clause 31, OWNER agrees to pay all taxes, levied or assessed on OWNER by
any governmental authority in connection with or incidental to the performance of the CHARTERPARTY, including but not
limited to withholding taxes, social security taxes and other social security benefits and taxes upon wages of OWNER, its
agents, employees and REPRESENTATIVES. OWNER agrees to require the same undertakings from any of member of
OWNER GROUP and to be liable for, and indemnify COMPANY GROUP from any breach of such undertakings by such
member of OWNER GROUP. OWNER agrees to reimburse COMPANY GROUP on demand for all such taxes, which
COMPANY GROUP may be required to pay on account of the agents, employees and REPRESENTATIVES of OWNER or
any member of OWNER GROUP.
 
Page 23 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 29/85
12/9/22, 4:25 PM EX-10.3

 
31.2 Withholding tax and NCD fund
 
  OWNER shall submit invoices to COMPANY grossing-up the amounts stated in Section III and other amounts due to
OWNER arising out of this CHARTERPARTY with the applicable withholding tax and NCD fund as prescribed by any
current or future relevant Nigerian legislation, directive, decree or equivalent. COMPANY shall deduct withholding tax and
NCD fund as prescribed by the applicable legislation by Federal Government of Nigeria. An official government receipt shall
be provided for any and all monies deducted by COMPANY as a result of any Government directive.
 
31.3 VAT
 
  Should payments made under the CHARTERPARTY attract Value Added tax (V.A.T.), the proper amount of such Tax shall be
shown as a separate item on the prescribed form of Tax invoice and the total amount payable under the CHARTERPARTY by
COMPANY shall include V.A.T. The rates and prices under the CHARTERPARTY are exclusive of V.A.T.
 
31.4 Penalties
 
  OWNER shall be responsible for and shall pay any fines and penalties it may have incurred due to failure to comply with the
requirements of the taxation jurisdiction when carrying out the CHARTERPARTY.
 
32 ASSIGNMENT and SUB-CHARTER
 
32.1 Assignment and Sub-charter by COMPANY
 
32.1.1 COMPANY may assign the CHARTERPARTY and/or sub-charter the FPSO to any of its AFFILIATES, any other
entity or CO-VENTURER upon receipt of OWNER’s written consent which shall not be unreasonably withheld.
Any such assignment and sub-charter shall be subject to the conditions that it will not diminish the rights or
 
increase the obligations of the OWNER, or otherwise increase the OWNER’s costs and provided the COMPANY
PARENT GUARANTEE (or a guarantee from the ASSIGNEE’s or PERMITTED SUB-CHARTERER’s parent)
remains in full force and effect.
 
32.1.2 OWNER agrees to obtain all necessary insurance policy endorsements relating to the CHARTERPARTY so that
  the ASSIGNEE or PERMITTED SUB-CHARTERER has the same rights and benefits under such policies as
COMPANY.
 
32.2 Assignment by OWNER
 
  32.2.1 The OWNER agrees not to assign the whole or part of the CHARTERPARTY except:
 
(a) subject to the provisions of Clause 15.2.1, where such assignment is to a lender by way of security
(including assignment of any receivables due to OWNER under the CHARTERPARTY) provided that
 
the OWNER shall give the COMPANY prior notification thereof and the OWNER shall remain liable
for performance of all its duties and obligations under the CHARTERPARTY; and
 
Page 24 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 30/85
12/9/22, 4:25 PM EX-10.3

 
(b) in any other case, if the COMPANY gives its prior written consent (which it shall not unreasonably
 
withhold in the case of an assignment to an AFFILIATE of the OWNER).
 
32.2.2 An assignment under Clause 32.2.1(b) shall not become effective until written notification by the COMPANY of
 
its approval to the OWNER.
 
32.2.3 If OWNER assigns the whole or part of the CHARTERPARTY other than in accordance with this Clause 32.2, the
 
CHARTERPARTY may be terminated by the COMPANY in accordance with Clause 14.
 
33 COMPLIANCE WITH LAWS
 
  Subject always to the terms of Clause 36 hereof OWNER agrees to comply with all laws, rules, regulations, ordinances,
judgements, orders and other official acts of any governmental authority which are now or may, in the future, become
applicable to OWNER, OWNER’s business, equipment and/or materials and personnel engaged in the performance of the
CHARTERPARTY, or arising out of or incidental to such performance.
 
34 FORCE MAJEURE
 
34.1 Meaning
 
  For the purpose of the CHARTERPARTY the expression FORCE MAJEURE shall mean any circumstances or events so
listed in Clause 34.2 below or of a like kind beyond the reasonable control and contemplation of the PARTY affected which
prevent or impede the due performance of the CHARTERPARTY, being circumstances or events which could not have been
prevented or avoided by the exercise of due diligence, prudence or the adoption of all precautions. Save as specifically
mentioned in Clause 34.2 below, weather conditions shall not constitute FORCE MAJEURE nor shall the shortage of labor,
materials or other resources constitute FORCE MAJEURE unless caused by circumstances which are themselves FORCE
MAJEURE.
 
34.2 Definitions
 
  34.2.1 The circumstances which shall be within the definition of FORCE MAJEURE are, such as but not limited to:
 
  (a) acts of God;
 
  (b) decrees of government;
 
  (c) fire;
 
  (d) explosion;
 
  (e) flood;
 
  (f) lightning;
 
  (g) hurricane (Beaufort Force 12 and above);
 
  (h) war, invasion, or hostilities;
 
  (i) rebellion/revolution;
 
Page 25 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 31/85
12/9/22, 4:25 PM EX-10.3

 
  (j) riot;
 
  (k) sabotage;
 
  (l) general national strikes or similar official national labour disputes;
 
  (m) ionizing radiation;
 
  (n) contamination by radio-activity;
 
  (o) pressure waves from aerial devices;
 
  (p) maritime disasters;
 
  (q) kidnapping; and
 
  (r) acts of terrorism.
 
34.2.2 The PARTIES shall be relieved from performance or delayed performance of their obligations under the
CHARTERPARTY to the extent that owing to any circumstance or event of FORCE MAJEURE they have failed
 
to comply with their respective obligations under the CHARTERPARTY. However, FORCE MAJEURE shall not
relieve a PARTY from its obligation to make a payment under this CHARTERPARTY.
 
34.3 Notification
 
  A PARTY seeking relief under this Clause shall notify the other PARTY forthwith of a circumstance or event of FORCE
MAJEURE and shall with diligence furnish such relevant information as is available appertaining to such event.
 
34.4 Effects of FORCE MAJEURE
 
  If FORCE MAJEURE occurs and the operation of the FPSO is suspended then during such suspension period the DAILY
COMPENSATION FEE shall be reduced by fifty percent (50%).
 
34.5 Termination for Force Majeure
 
34.5.1 If FORCE MAJEURE continues in excess of 120 (one hundred twenty) days COMPANY shall have the right to
 
terminate this CHARTERPARTY.
 
34.5.2 Where a termination right under Clause 34.5.1 accrues during the INITIAL PERIOD, COMPANY shall pay
 
OWNER, at COMPANY’s option, either:
 
(a) the DAILY COMPENSATION FEE for the remainder of the INITIAL PERIOD plus the
 
DEMOBILIZATION AND REDELIVERY FEE; or
 
(b) the amount under Clause 7 of Section III - CHARTERPARTY Prices and Schedules for Variations plus
 
the DEMOBILIZATION AND REDLIVERY FEE.
 
  In both cases (a) and (b), OWNER shall credit COMPANY with a share of any future DAILY COMPENSATION
FEE equivalent earnings (net after tax) received from THIRD PARTIES during the unexpired portion of the
INITIAL PERIOD following such termination. Such share shall be net of all further costs actually incurred by
OWNER that are directly attributable to such termination that have been incurred prior to receipt of such future
  earnings from THIRD PARTIES during the INITIAL PERIOD. If such earnings are higher than the DAILY
COMPENSATION FEE paid by COMPANY to OWNER under this CHARTERPARTY, OWNER shall credit
COMPANY all of such DAILY COMPENSATION FEE. In the case of total loss, requisition, expropriation, etc. of
the FPSO, OWNER will also credit the amount of any insurance recovery received by it up to (but not exceeding)
the amount paid by COMPANY under (a) or (b).
 
Page 26 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 32/85
12/9/22, 4:25 PM EX-10.3

 
35 ARBITRATION
 
35.1 Should any difference or dispute arise in connection with the interpretation or the performance of the CHARTERPARTY
which cannot be resolved by the PARTIES, the same shall be referred to arbitration, and the CHARTERPARTY performance
shall continue during the arbitration proceedings.
 
35.2 The arbitration shall be conducted in accordance with the rules of London Court of International Arbitration (LCIA) current at
the time when the arbitration proceedings are commenced.
 
35.3 The Arbitration reference will be to a tribunal of 3 (three) Arbitrators. Each PARTY will appoint its own Arbitrator. The
Arbitrators nominated by the PARTIES will appoint, by mutual agreement, the third Arbitrator,
 
35.4 The Arbitrator(s)’ decision shall be final and binding on both PARTIES and the relevant award shall be enforced in any court
having applicable jurisdiction.
 
35.5 The venue and language of arbitration shall be London and English respectively.
 
36 APPLICABLE LAW
 
36.1 Law
 
  The CHARTERPARTY shall be construed and governed in accordance with the law of England and Wales.
 
36.2 Notices
 
  OWNER shall give all notices and comply with all laws, ordinances, rules and regulations normally bearing on the conduct of
the CHARTERPARTY. If OWNER performs any acts contrary to such laws, ordinances, rules and regulations, OWNER shall
bear all costs, fines and penalties arising therefrom.
 
37 CONFIDENTIALITY
 
37.1 The PARTIES undertake to consider all information under the CHARTERPARTY strictly confidential, to keep it as such and
not to disclose or communicate it to non-authorized individuals, as well as to take all reasonable measures to assure and
protect, in whole and in part, and however in any form, the confidentiality of said information, to anyone, except with respect
to information disclosed by either PARTY to its AFFILIATES or sub-contractors or to any of their respective officers and
employees on a “need to know” basis for the purpose of this CHARTERPARTY or the O&M CONTRACT, in which event
the PARTY disclosing such information to such of its AFFILIATES, officers and/or employees shall be responsible for
ensuring the maintenance of confidentiality with respect to such information by such AFFILIATES officers and/or employees.
 
Page 27 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 33/85
12/9/22, 4:25 PM EX-10.3

 
37.2 The PARTIES shall not, and shall ensure that their employees, agents, representatives and sub-contractors shall not, use or
reproduce confidential information obtained pursuant to this CHARTERPARTY for purposes (including trading in securities
of CAMAC Energy Inc. or any other publically traded companies within the COMPANY GROUP) other than those in
furtherance of this CHARTERPARTY or the O&M CONTRACT nor shall either PARTY exchange or divulge to any THIRD
PARTY any information obtained in the conduct of, or by reason of, the performance of this CHARTERPARTY except as
expressly provided herein.
 
37.3 This Clause shall not apply confidential treatment to information:
 
37.3.1 which at the date of its disclosure is public knowledge or which subsequently becomes public knowledge other
  than by any act or failure to act on the part of the PARTY receiving such information hereunder (the
“RECIPIENT”) or any of its AFFILIATES or any of their officers or employees; or
 
37.3.2 which is already known to the RECIPIENT as evidenced by its written record and was not acquired directly or
 
indirectly from the disclosing party; or
 
37.3.3 which is at any time after the date of this CHARTERPARTY lawfully acquired by the RECIPIENT from any
  THIRD PARTY which is rightfully in possession of it and is not bound by an obligation of confidentiality in
respect of it; or
 
  37.3.4 which is required to be disclosed by law or by a court of competent jurisdiction; or
 
37.3.5 disclosed to any outside professional consultants or any bank or financial institution who may be giving financial
  advice to it or from whom it is seeking, or who is advising it in the obtaining of finance, upon obtaining a similar
undertaking of confidentiality but excluding the terms contained in this Clause 37.3.5; or
 
  37.3.6 disclosed to a PARTY’s auditors, professional tax or legal advisers; or
 
  37.3.7 to the extent required by any governmental agency or the regulations of any recognized stock exchange.
 
37.4 The provisions of this Clause 37 shall survive for a period of three (3) years following the date of termination of this
CHARTERPARTY.
 
37.5 In the event of a breach by OWNER, in whole or in part, of the confidentiality obligations imposed herein, COMPANY may
assert a claim for suffered damages in addition to any remedy set forth in Clause 14 hereof. Without limiting the foregoing, in
the event of a violation or breach, actual or threatened, in whole or in part, of the confidentiality provisions set forth in this
Clause 37, the non-breaching PARTY may obtain, in addition to any other remedies available to such PARTY hereunder or
under the O&M CONTRACT, or otherwise at law, such equitable relief as may be necessary to protect such non-breaching
PARTY against any such violation, breach or threatened breach.
 
38 NOTICES
 
38.1 All notices to be given with respect to the CHARTERPARTY shall be considered as given to COMPANY and to OWNER,
respectively, if given in writing and delivered by hand or sent by courier, registered or certified mail, return receipt requested,
or by facsimile. Such notices shall be deemed effective when delivered as follows:
 
Page 28 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 34/85
12/9/22, 4:25 PM EX-10.3

 
38.1.1 if delivered by hand, on the day of delivery, if delivered before 17:00 in the place of delivery on a BUSINESS
 
DAY, and otherwise on the next BUSINESS DAY;
 
  38.1.2 if delivered by courier, registered or certified mail, upon delivery confirmation from such service;
 
38.1.3 if sent by fax, at the time of transmission, if received before 17:00 in the place of delivery on a BUSINESS DAY,
 
and otherwise on the next BUSINESS DAY.
 
38.2 The address(es) of notice for COMPANY and OWNER shall be as below. The addresses, given may be changed by either
PARTY advising the other in writing of its new address.

OWNER:
Armada Oyo Ltd
P.O. Box 957
Offshore Incorporations Center
Road Town
Tortola
British Virgin Island
Fax: +60 3 2163 5216

COMPANY:
Oceanic Consultants Nigeria Limited
Plot 1649, Olosa Street,
Victoria Island
Lagos – Nigeria
Fax: +1 713 965 5128
 
39 NO DEMISE
 
  Nothing herein shall be construed as creating a demise of the FPSO to COMPANY.
 
40 REGISTRATION
 
  OWNER shall comply with all requirements of the laws of the country(ies) having jurisdiction over the AREA OF
OPERATIONS as regards establishing its company on a proper legal basis to operate or do business in such country(ies),
including registration, if required, and comply in all respects with any requirements of the laws in such country(ies) which are
applicable to the OWNER’s performance of its obligations under this CHARTERPARTY.
 
41 CUSTOMS FORMALITIES AND DUTIES
 
41.1 Customs formalities, where required, to export/import OWNER’s equipment and/or materials from any place to the AREA
OF OPERATIONS, shall be for OWNER’s care and cost.
 
41.2 Subject to COMPANY’S prior approval, COMPANY will reimburse OWNER for all customs and excise duties, fees, taxes
(but only to the extent related to importing of goods or materials or clearing customs with respect thereto, and excluding
without limitation any taxes on income or profits), licenses, import and export tariffs, pilotage fees, wharfage fees, canal fees,
or similar charges imposed by any competent authority, including any brokerage fees in connection therewith and which
OWNER is obligated to pay and does pay on COMPANY’s reimbursable items that are used exclusively in the performance
of the CHARTERPARTY on a temporary importation basis.
 
Page 29 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 35/85
12/9/22, 4:25 PM EX-10.3

 
41.3 Such reimbursement shall only be to the extent that OWNER does not receive credit, refund, discount or other benefit.
 
41.4 COMPANY shall not be obligated to pay OWNER for failing to pay said duties, fees, taxes, licenses or similar charges when
due.
 
41.5 PARTIES agree to cooperate with each other in seeking an extension of the current temporary importation status of the FPSO
with OWNER’s Nigerian affiliate company, Century Bumi Limited as consignee for the importation. In the event that the
competent authority in Nigeria impose the permanent importation required for the FPSO, OWNER shall be liable for the
costs of such permanent importation.
 
42 LOCAL CONTENT
 
  OWNER, in inviting to tender for SUB-CONTRACTS, shall where reasonably appropriate give to suitable Nigerian
Contractors, vendors and suppliers an opportunity to tender, provided however that nothing contained in this clause shall be
construed to require any such invitation, or the award of any SUB-CONTRACT if, in OWNER’s opinion, the terms thereof
are not technically and/or economically acceptable, or to prevent or discourage OWNER from inviting to tender or awarding
SUB-CONTRACTS to Contractors, vendors or suppliers from countries other than Nigeria. Whenever appropriate, OWNER
shall make reasonable efforts to hire local labor, according to skills, availability and the kind of work to be accomplished.
 
43 PURCHASE OPTION
 
  In consideration of the DAILY COMPENSATION FEE payable under this CHARTERPARTY, the OWNER irrevocably
grants to the COMPANY an exclusive option to purchase the FPSO (the “PURCHASE OPTION”) at a price to be agreed by
the PARTIES, on the following terms and conditions.
 
43.1 The PURCHASE OPTION may be exercised at the sole discretion of the COMPANY.
 
43.2 The PURCHASE OPTION shall be exercisable by the COMPANY at the expiry of the INITIAL PERIOD by giving at least
three (3) months’ written notice to the OWNER. The notice shall state that the Purchase Option is being exercised and shall
require completion of the purchase on expiry of the said notice period, at which time the COMPANY shall pay to the
OWNER the agreed purchase price and any other amounts if applicable and so agreed.
 
43.3 In exchange for the payment of the amounts under Clause 43.2, the OWNER shall transfer full and complete unencumbered
legal title in the FPSO to the COMPANY or its nominee and shall deliver to the COMPANY the documents referred to in
Clause 43.4. The OWNER shall deliver the FPSO in an “as is where is” condition at the time of exchange together with
everything belonging to the FPSO on board and on shore; and, subject to any necessary lessor’s consent, leasing or hiring
contracts in respect of equipment on the FPSO which is not owned by the OWNER. OWNER warrants all items belonging to
the FPSO shall be owned by it with the exception of COMPANY supplied items and those items customarily hired by FPSO
owners. OWNER shall, during the life of the CHARTERPARTY, provide COMPANY with a list of such hired items. All
spare parts and spare equipment on board including spare tail-end shaft(s) and/or spare propeller(s), if any, belonging to the
FPSO, used or unused, will be included in the sale at no additional cost. Any fuel, lubricating oils, stores and consumables
remaining onboard will be taken over by the COMPANY at the price paid for them by the OWNER, and this amount will be
added to the Purchase Option Price. The radio installation and navigational equipment shall be included in the sale without
extra payment, if same is the property of the OWNER.
 
Page 30 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 36/85
12/9/22, 4:25 PM EX-10.3

 
43.4 The documents to be delivered by the OWNER in exchange for the payment of the amounts under this Clause 43.24 are as
follows:
 
43.4.1 a legal bill of sale of the FPSO in three originals (or such other number as the COMPANY shall
reasonably require), free from all encumbrances and maritime liens or any other debts whatsoever, duly
 
attested by a licensed notary and legalized by the consul of such reasonable jurisdiction as shall be
nominated by the COMPANY;
 
43.4.2 a transcript of registry issued by the authorities of the FPSO’s flag state certifying that the FPSO is
  owned by the OWNER free from registered encumbrances (other than encumbrances to be satisfied out
of the amounts under Clause 43.2);
 
43.4.3 all classification certificates as well as all plans, etc. which are onboard the FPSO and other technical
  documentation which may be in the OWNER’S possession shall, promptly upon the COMPANY’s
instructions, be forwarded to the COMPANY provided always that:
 
(a) the OWNER may keep the log books, but the COMPANY will have the right to take copies of
 
same; and
 
(b) the OWNER may retain any confidential information belonging to it or an Affiliate provided
  that any confidential information necessary for the full use and operation by COMPANY of
the FPSO shall be disclosed by OWNER or its Affiliates on a confidential basis;
 
43.4.4 if so requested by the COMPANY, an undertaking to provide a certificate of deletion of the FPSO free
  of registered encumbrances from its registration in its flag state within 30 days of completion of the
sale;
 
  43.4.5 a protocol of delivery and acceptance confirming the date and time of delivery of the FPSO;
 
  43.4.6 an invoice in respect of the amounts payable under Clause 43.2.
 
43.5 Upon payment of the amounts under Clause 43.2 by the COMPANY to the OWNER, OWNER’s rights, title and interest in
the FPSO shall pass to the COMPANY. The amounts under Clause 43.2 shall be paid without set-off or deduction.
 
43.6 The obligation of the OWNER to sell and transfer the FPSO under this Clause is subject to the payment of all amounts then
due and payable by COMPANY to OWNER under this CHARTERPARTY and all amounts due and payable by COMPANY
to CONTRACTOR under the O&M CONTRACT.
 
43.7 The COMPANY will obtain all licenses, permits and approvals which may be required in Nigeria and will be responsible for
all taxes and duties of whatever nature chargeable in Nigeria (including any such taxes and duties chargeable on any of the
OWNER GROUP) in connection with or arising out of this purchase option, the sale and purchase of the FPSO and any fuel,
supplies, equipment and parts taken over with the FPSO, but expressly excluding any taxes on OWNER or any other member
of the OWNER GROUP relating to income attributable to such sale. The COMPANY will keep the OWNER GROUP
indemnified in respect of all such taxes and duties
 
Page 31 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 37/85
12/9/22, 4:25 PM EX-10.3

 
43.8 This CHARTERPARTY shall terminate upon the completion of this Purchase Option and the transfer of the FPSO and its title
to the COMPANY. In that case, the DAILY COMPENSATION FEE will cease to be payable and OWNER will have no
obligation to demobilize the FPSO under Clause 18.
 
43.9 The COMPANY shall not be obliged to purchase the FPSO if at any time during the three (3) month notice period, the FPSO
becomes a total loss pursuant to Clause 16.
 
43.10 COMPANY shall have the option to retain CONTRACTOR to perform the operating and maintenance services under the
O&M CONTRACT with compensation terms to be agreed.
 
44 ANTI-CORRUPTION
 
44.1 At all times from and after the date of execution of the CHARTERPARTY, the PARTIES shall, and shall procure that their
AFFILIATES shall comply with all APPLICABLE ANTI-CORRUPTION LAWS, including any future anti-corruption or
anti-bribery laws, regulations or requirements of any jurisdiction, that are or may become applicable to the PARTIES or their
AFFILIATES during the term of the CHARTERPARTY.
 
44.2 Specifically, each PARTY confirms, to the extent of its knowledge, that in connection with this CHARTERPARTY, neither it,
nor any of its AFFILIATES and its contractors and subcontractors, and its and their respective directors, officers, employees,
agents and representatives or other persons working for or on behalf of any of the foregoing with respect to this
CHARTERPARTY, has made, offered, authorized or promised to make, any payment, gift, promise or other advantage
(including any fee, gift, sample, travel expenses, entertainment, service, equipment, loan, debt forgiveness, donation, grant or
other payment or support in cash or in kind), directly or indirectly, to any PROHIBITED PERSON (a) for the purpose of
obtaining or retaining business or favourable government action, influencing any official act or decision of a PROHIBITED
PERSON or inducing such PROHIBITED PERSON to use his or her influence over any governmental act or decision or
otherwise secure any improper advantage for any party or (b) that would otherwise violate any APPLICABLE ANTI-
CORRUPTION LAW.
 
44.3 Each PARTY further agrees and undertakes, respectively, that in connection with this CHARTERPARTY, neither it, nor any
of its AFFILIATES and its contractors and subcontractors, and its and their respective directors, officers, employees, and
agents, will make, offer, authorize or promise to make, any payment, gift, promise or other advantage (including any fee, gift,
sample, travel expense, entertainment, service, equipment, loan, debt forgiveness, donation, grant or other payment or support
in cash or in kind), directly or indirectly, to any PROHIBITED PERSON (a) for the purpose of obtaining or retaining business
or favourable government action, influencing any official act or decision, of a PROHIBITED PERSON or inducing such
PROHIBITED PERSON to use his or her influence over any governmental act or decision or otherwise secure any improper
advantage for any party or (b) that would otherwise violate any APPLICABLE ANTI-CORRUPTION LAW.
 
44.4 As a matter of corporate policy, each PARTY expressly prohibits payment of bribes and also payment of any so-called
“facilitation” or “grease” payments in connection with its business operations by any contractor, agent or subcontractor
engaged to provide goods or services to such PARTY or its AFFILIATES.
 
44.5 Notwithstanding the foregoing undertakings, each PARTY agrees to notify the other promptly upon discovery of any
instances where it has formed a reasonable belief that it, any of its AFFILIATES or its contractors or subcontractors, or its or
their respective owners, directors, officers, employees, agents or representatives failed to comply with any provisions of this
Clause 44.
 
Page 32 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 38/85
12/9/22, 4:25 PM EX-10.3

 
44.6 Each PARTY agree and undertake that in connection with this CHARTERPARTY and in connection with any other business
transactions involving the other in the Federal Republic of Nigeria, each PARTY, and each of their respective AFFILIATES,
contractors and subcontractors:
 
  44.6.1 will apply effective disclosure controls and procedures;
 
44.6.2 will maintain throughout the term of the CHARTERPARTY and, except as otherwise provided herein, for at least
three (3) years following the expiration or termination of this CHARTERPARTY, books, records and accounts
 
which, in reasonable detail, accurately and fairly reflect the transactions undertaken and the disposition of assets;
and
 
44.6.3 will maintain an internal accounting control system that is sufficient to ensure the proper authorization, recording
  and reporting of all transactions and to provide reasonable assurances that violations of the anticorruption laws of
the applicable jurisdictions will be prevented, detected and deterred.
 
44.7 The OWNER agrees and acknowledges that the COMPANY, itself or through its duly appointed representatives, shall have
the right during normal business hours and upon reasonable notice to inspect and audit any and all books and records of the
OWNER relating to the OWNER’s compliance with its obligations under this Clause 44, and to make copies, at its expense,
of any such books and records.
 
44.8 Each PARTY agrees to cooperate with the other as the other may request in making its books, records and personnel available
in connection with any investigation conducted by governmental authorities of matters that may implicate transactions or
activities carried out by the PARTIES in connection with this CHARTERPARTY. Each PARTY will also provide the other
PARTY with such further assurances or certificates that such party may reasonably request from time to time during the term
of the CHARTERPARTY relating to matters covered by this Clause 44, and each PARTY shall, upon request, certify to the
other PARTY in writing its compliance with this Clause 44 on an annual basis.
 
44.9 All payments by the COMPANY to the OWNER shall be made in accordance with the terms of payment specified in this
CHARTERPARTY. In the absence of any such specific payment instructions elsewhere in this CHARTERPARTY, payments
by the COMPANY to the OWNER shall only be made by cheque or wire transfer to a bank account of the OWNER as
mutually agreed by the PARTIES in the country in which the OWNER is incorporated or where it has its head office, or to its
office in the Federal Republic of Nigeria, details of which shall be given by the OWNER to the COMPANY in writing. Such
notification shall be deemed to constitute a representation that the bank account so notified is owned solely by the OWNER
and that no person other than the OWNER has any ownership of or interest in such account.
 
44.10 Each PARTY represents represent and covenants that (a) no PROHIBITED PERSON will have, during the term of the
CHARTERPARTY, a direct or indirect interest in it or in this CHARTERPARTY, or in the proceeds thereof, and (b) it shall
notify the other PARTY promptly and in writing of any change in the foregoing.
 
44.11 Each PARTY further agrees and undertakes that with respect to any contractors and subcontractors they may engage in
connection with this CHARTERPARTY or any other business transactions in the Federal Republic of Nigeria involving the
PARTIES that it will conduct appropriate due diligence prior to appointing or engaging such contractors or subcontractors to
ensure that they are duly qualified to perform the tasks for which they have been engaged and that they are of good
reputation.
 
Page 33 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 39/85
12/9/22, 4:25 PM EX-10.3

 
45 SURVIVAL
 
     Notwithstanding any other provision of the CHARTERPARTY the following conditions shall survive expiration or
termination of the CHARTERPARTY (together with any accrued payment obligations of the PARTIES and obligations
relating to the redelivery of the FPSO):
 
     PATENT INDEMNIFICATION
 
     INSURANCE AND INDEMNITY
 
     PARENT COMPANY GUARANTEES
 
     ARBITRATION
 
     APPLICABLE LAW
 
     CONFIDENTIALITY
 
     NOTICE
 
     ANTI-CORRUPTION
 
     SURVIVAL
 
     OVERALL LIABILITY
 
     with respect to any termination pursuant to an OWNER default, PURCHASE OPTION any and other provision which by its
nature should continue to apply after termination.
 
46 QUALITY ASSURANCE
 
46.1 Quality Requirements
 
     The CHARTERPARTY shall be carried out under “Quality Assurance” conditions and in accordance with COMPANY’s
“Quality and Execution Requirements”. The Quality Assurance Documentation (i.e. Quality Plan, Management and Operating
Procedures etc.) shall be submitted to COMPANY for approval.
 
47 ENVIRONMENTAL COMPLIANCE
 
47.1 Compliance with Environmental Laws
 
     OWNER shall give all notices and otherwise fully comply with all laws, statutes, regulations, ordinances, rules, standards,
orders or determinations of any governmental authority (including related determinations, interpretations, orders or opinions
by any judicial or administrative authority) which has jurisdiction over OWNER, the CHARTERPARTY or the AREA OF
OPERATIONS pertaining to protection or conservation of the air, land, water, human health, industrial hygiene or other
aspects of the environment which are directly applicable to FPSO and supply vessel operations.
 
Page 34 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 40/85
12/9/22, 4:25 PM EX-10.3

 
47.2 Hazardous Materials
 
     OWNER represents and warrants to COMPANY that in the performance of its obligations under the CHARTERPARTY, the
operations will not contain or otherwise have incorporated into them any chemical, material or other substance defined as or
included in the definition of “hazardous substance”, “hazardous material”, “hazardous chemical”, “hazardous chemical
substance”, “hazardous waste”, or “toxic substance” or words of similar meaning and regulatory effect, as such terms are
defined under any environmental laws, any broader definition of such terms that is used by a state or locality that has
jurisdiction over the CHARTERPARTY, or the AREA OF OPERATIONS or any interpretation by administrative or judicial
authorities, or any other chemical, material or substance, exposure to which is prohibited, limited or regulated by any
governmental authority or which may or could pose a hazard to human health and safety, unless such chemical, material or
substance is necessary for the OWNER’s performance of the CHARTERPARTY and its use is agreed between the PARTIES.
Such definitions, representations and warranties shall exclude however hydrocarbons, discharged water, and production
related chemicals.
 
48 OVERALL LIABILITY
 
     Other than in respect of OWNER’s obligations under Clauses 15.2, 19.1, and 31.1, and Article 24, OWNER’s total
cumulative liability to COMPANY arising from or in connection with, the performance (or non-performance) under this
CHARTERPARTY and combined with the that of CONTRACTOR under the O&M CONTRACT shall be limited to fifty
million United States Dollars (US$50,000,000).
 
49 PUBLICITY
 
     Except to the extent required by law or nationally recognized stock exchange (in which case no such advance consent shall be
required), each PARTY shall not, and shall procure that each member of its GROUP shall not, publish or permit to be
published either alone or in conjunction with any other person any information or any other material of any kind relating to
this CHARTERPARTY, without prior reference to and approval from the other PARTY. Such consent shall only apply to each
specific application and relate only to that application. The accuracy of any information published by a PARTY or any
member of that PARTY’s Group, which was not supplied directly by the other PARTY, shall be the absolute responsibility of
PARTY publishing such information.
 
Page 35 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 41/85
12/9/22, 4:25 PM EX-10.3

BAREBOAT CHARTERPARTY

CONTRACT

SECTION III

BAREBOAT CHARTERPARTY FOR FPSO


ARMADA PERDANA IN THE OYO
FIELD DEVELOPMENT

CHARTERPARTY PRICES AND SCHEDULES FOR


VARIATIONS

CONTRACT No. OCEANIC/FPSO/14/001/1


 
Page 36 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 42/85
12/9/22, 4:25 PM EX-10.3

 
1. LUMP SUMS AND DAY RATES
 
  1.1 MILESTONE PAYMENTS
COMPANY shall pay OWNER the following COMPENSATION in accordance with Section II, Clause 25.2.
 
a) US$ 10,000,000 (ten million), of which US$ 5,000,000 (five million) shall be payable on or before the
date that is 10 (ten) BUSINESS DAYS from the EXECUTION DATE, and the remaining US$ 5,000,000
 
(five million) shall be payable on or before the date that is 90 (ninety) days from the date of the first US$
5,000,000 (five million) payment.
 
  b) US$ 10,000,000 (ten million) on DATE OF ACCEPTANCE.
 
  1.2 DAY RATES
COMPANY shall pay OWNER the following COMPENSATION in accordance with Section II Clause 25.1:
 
  a) STANDBY FEE during the STANDBY PERIOD of US$60,000 per day
 
b) Following the STANDBY PERIOD, a DAILY COMPENSATION FEE during the remainder of the INITIAL
 
PERIOD of US$ 132,500 per day
Should COMPANY elect to purchase the FPSO according to the provisions of Clause 6 hereunder, the DAILY
COMPENSATION FEE shall be no longer payable.
 
  1.3 DEMOBILIZATION AND REDELIVERY FEE
COMPANY shall pay OWNER the DEMOBILIZATION AND REDELIVERY FEE in accordance with Section II, Clause
25.3. Documentary evidence of the costs supporting such fee shall be submitted to COMPANY 90 (ninety) days before
commencement of operations for approval.
 
2. NOT USED
 
3. VARIATION ORDERS
Should COMPANY request a change in Section IV - Scope of Work which affects the capital cost but excluding consumable
items, PARTIES shall agree on one of the following methods:
 
  a) Lump Sum and milestones payment to be mutually agreed by PARTIES; or
 
  b) Documented cost as per Clause 2.3 of Section III of the O&M CONTRACT.
 
4. FPSO VALUE
 
  4.1. Value of the FPSO with profit                     US$240,000,000
 
Page 37 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 43/85
12/9/22, 4:25 PM EX-10.3

 
5. EARLY TERMINATION COMPENSATION
With reference to Section II, Clause 9.2.5 the early termination compensation shall be as per the amounts shown in the
following paragraphs. The amounts shall be linearly prorated if this CHARTERPARTY is terminated at periods other than
the anniversary dates shown in the paragraphs:
 
5.1.  On EFFECTIVE DATE 78% of the value of the FPSO with profit
5.2.  Beginning of 2nd year 64% of the value of the FPSO with profit
5.3.  Beginning of 3rd year 51% of the value of the FPSO with profit
5.4.  Beginning of 4th year 37% of the value of the FPSO with profit
5.5.  Beginning of 5th year 28% of the value of the FPSO with profit
 
6. FPSO PURCHASE VALUE
COMPANY shall have the right to purchase the FPSO as provided in Section II Clause 43. The FPSO purchase price shall
be agreed by the PARTIES, with the value determined and negotiated in good faith between COMPANY and OWNER on a
‘willing buyer, willing seller’ basis.
 
7. TERMINATION FOR FORCE MAJEURE
With reference to Section II, Clause 34.5, the termination for FORCE MAJEURE compensation shall be as per the amounts
shown in the following paragraphs. The amounts shall be linearly prorated if the CHARTERPARTY is terminated at periods
other than the anniversary dates shown in the paragraphs:
 
7.1.  On EFFECTIVE DATE 78% of the value of the FPSO with profit
7.2.  Beginning of 2nd year 64% of the value of the FPSO with profit
7.3.  Beginning of 3rd year 51% of the value of the FPSO with profit
7.4.  Beginning of 4th year 37% of the value of the FPSO with profit
7.5.  Beginning of 5th year 28% of the value of the FPSO with profit
 
Page 38 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 44/85
12/9/22, 4:25 PM EX-10.3

SECTION III
APPENDIX “1”

NOT USED
 
Page 39 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 45/85
12/9/22, 4:25 PM EX-10.3

SECTION III
APPENDIX “2”

OWNER’s and COMPANY’s “GUARANTEEs”


 
Page 40 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 46/85
12/9/22, 4:25 PM EX-10.3

PARENT COMPANY GUARANTEE

This Parent Company Guarantee and Indemnity (the “Guarantee”) is entered into on this             day of             by Bumi Armada
Berhad, a Company organised and existing under the laws of Malaysia with registered office at Level 21, Menara Perak, 24 Jalan
Perak, 50450 Kuala Lumpur, Malaysia (the “Guarantor”), in favour of Oceanic Consultants Nigeria Limited (the “COMPANY”).

For and in consideration of good and valuable consideration receipt of which is hereby acknowledged by the Guarantor:
 
1 The Guarantor hereby irrevocably and unconditionally guarantees the prompt performance and execution of all obligations and
liabilities (including, without limitation, interest to date of payment under the Contract) of its subsidiary, Armada Oyo Ltd. (the
“OWNER”), under or in connection with the Bareboat Charterparty for FPSO ARMADA PERDANA IN THE OYO FIELD
DEVELOPMENT entered into between COMPANY and OWNER and effective as of 1 January 2014 in the context of the
development of the Oyo Field in OML-120, Nigeria (the “Contract”) and guarantees the due performance of the OWNER’s
obligations, and the punctual payment of all amounts due and payable by OWNER, under or in connection with the Contract.
If the OWNER fails to discharge any such obligation in accordance with the terms of the Contract the Guarantor will forthwith
discharge the same (as if it were the principal obligor) and will pay COMPANY any and all documented damages COMPANY
may incur and be entitled to under the Contract by reason of any such failure of the OWNER.
 
2 The Guarantor irrevocably and unconditionally agrees with the COMPANY that if, for any reason, any amount claimed by the
COMPANY under clause 1 is not recoverable on the basis of a guarantee, it will be liable as a principal debtor and primary
obligor to indemnify the COMPANY against any cost, loss or liability it incurs as a result of the OWNER not performing its
obligation and paying any amount expressed to be payable by it under the Contract on the date when it is expressed to be due. The
amount payable by the Guarantor under this indemnity will not exceed the amount it would have had to pay under clause 1 if the
amount claimed had been recoverable on the basis of a guarantee.
 
3 The liability of the Guarantor will not be discharged or impaired by any:
 
  (a) variation to or replacement of the Contract, or any change in the obligations undertaken by the OWNER
 
(b) any time, waiver, consent, forbearance or indulgence by COMPANY as to any matter, including as to performance, payment,
 
or any other matter whatsoever
 
(c) disability, incapacity, insolvency, change in the status or constitution, judicial reorganisation, winding up or dissolution of
 
the OWNER or the Guarantor or the COMPANY
 
  (d) change in relationship between the Guarantor and the OWNER, or
 
Page 41 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 47/85
12/9/22, 4:25 PM EX-10.3

 
(e) any assignment or transfer of the Contract or any interest in it by OWNER or by COMPANY (this Guarantee being for the
 
benefit of COMPANY and its permitted assignees of the Contract)
or any other matter which would otherwise release a guarantor.
 
4 The Guarantor waives and releases all rights of subrogation and/or set-off which it may have against the OWNER and/or any
rights to claim or prove as a creditor of the OWNER in competition with the COMPANY to any rights of COMPANY against the
OWNER or any third party.
 
5 All payments by the Guarantor are to be made in US Dollars, without set-off or counterclaim, free and clear of any restriction,
condition, deduction or withholding. If the Guarantor is required by any law to make a deduction or withholding from any
payment (including tax) the amount due from the Guarantor will be increased as necessary to ensure that, after such deduction or
withholding, COMPANY actually receives and retains an amount equal to the amount it would have received if no deduction or
withholding had been required; for the avoidance of doubt, and notwithstanding the foregoing, Guarantor shall not be required to
increase amounts as a result of deduction or withholding if, and to the extent that, under the terms and conditions of the Contract,
the COMPANY was allowed to withhold or deduct without being required to increase the amount due.
 
6 The Guarantor represents and warrants that it is a corporation duly organised and validly existing under the laws of Malaysia, it is
solvent and able to pay its debts as they fall due, it has full power and authority to enter into this Guarantee, it has taken all
necessary corporate and other action to authorise it to do so, and this Guarantee is legal, valid, binding and enforceable against it.
The Guarantor agrees to furnish to the COMPANY such evidence of the due authorisation and execution of this Guarantee as the
COMPANY may reasonably request.
 
7 The Guarantor represents and warrants that it directly owns 100% of the shares in OWNER and agrees not to transfer any of its
shareholdings in OWNER without COMPANY’s prior consent which consent shall not be unreasonably withheld by COMPANY.
 
8 No failure to exercise, or delay in exercising, a right of COMPANY under this Guarantee or the Contract will operate as a waiver
of that right, nor will a single or partial exercise of a right preclude a further exercise of that right or the exercise of another right.
No payment by the Guarantor will discharge the obligation of the Guarantor unless and until the COMPANY has received
payment in full in the currency in which the obligation is denominated.
 
9 The amount to be paid by the Guarantor under this Guarantee shall include all documented costs and expenses (including legal
fees) reasonably incurred by COMPANY in connection with the enforcement of this Guarantee or of the underlying obligation
against the OWNER.
 
10 The Guarantor agrees that it shall not be necessary, as a condition to enforce this Guarantee, that suit be first instituted against the
OWNER or that any right or remedies against the OWNER or any other party be first exhausted. Rather, it is understood and
agreed that the liability of the Guarantor hereunder shall be primary, direct and in all respects unconditional.
 
Page 42 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 48/85
12/9/22, 4:25 PM EX-10.3

 
11 This Guarantee extends to all obligations of OWNER expressed in the Contract, whether such obligations are undertaken by
OWNER as a principal or as an agent for any other party to the relevant Production Sharing Contract covering Oil Mining Lease
120 Deep Offshore Nigeria.
 
12 This Guarantee shall terminate when the OWNER has no further liability (actual or contingent) to the COMPANY under the
Contract.
 
13 All notices to be given by the COMPANY under this Guarantee to the Guarantor shall be made in writing and either delivered
personally or sent by registered mail or certified mail or transmitted by facsimile to the following address/facsimile number:
Bumi Armada Berhad
Attention: CEO/ Executive Director
Level 21, Menara Perak
24 Jalan Perak, 50450 Kuala Lumpur
Malaysia
Fax: +6.03.2163.3600
Such notices shall be effective when delivered if delivered personally or when received if sent by registered or certified mail, or if
sent by facsimile when the COMPANY receives confirmation of transmission.
This Guarantee shall be construed under English law. The Guarantor submits irrevocably to the exclusive jurisdiction of the English
courts (provided that judgement may be enforced by the courts of any jurisdiction).
This Guarantee has been executed as a deed and it has been delivered on the date stated above.

[Signature Page Follows]


 
Page 43 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 49/85
12/9/22, 4:25 PM EX-10.3

IN WITNESS THEREOF, executed as a Deed for and on behalf of:

Bumi Armada Berhad


  
 
Printed Name:                       
                                               
 
Title:                                                                   
                     
 
Witness:
 
 
Printed Name:                                        
                             
 
Page 44 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 50/85
12/9/22, 4:25 PM EX-10.3

GUARANTEE
This Guarantee and Indemnity (the “Guarantee”) is entered into on the             day of             2014 by CAMAC Energy, Inc, a
Company organised and existing under the laws of Delaware with offices at 1330 Post Oak Boulevard, Suite 2250, Houston, TX 77056
(the “Guarantor”), in favour of Armada Oyo Ltd (the “OWNER”).

For and in consideration of good and valuable consideration the receipt of which is hereby acknowledged by the Guarantor:
 
1 The Guarantor hereby irrevocably and unconditionally guarantees the prompt performance and execution of all obligations and
liabilities (including, without limitation, interest to date of payment under the Contract) of its subsidiary, Oceanic Consultants
Nigeria Limited (the “COMPANY”), under or in connection with the BAREBOAT CHARTERPARTY FOR FPSO ARMADA
PERDANA IN THE OYO FIELD DEVELOPMENT entered into between COMPANY and OWNER and effective as of
1 January 2014 in the context of the development of the Oyo Field in OML-120, Nigeria (the “Contract”) and guarantees the
punctual payment of all amounts due and payable by COMPANY under or in connection with the Contract.
If the COMPANY fails to discharge any such obligation in accordance with the terms of the Contract the Guarantor will forthwith
discharge the same (as if it were the principal obligor) and will pay OWNER any and all documented damages OWNER may
incur and be entitled to under the Contract by reason of any such failure of the COMPANY.
 
2 The Guarantor irrevocably and unconditionally agrees with the OWNER that if, for any reason, any amount claimed by the
OWNER under Clause 1 is not recoverable on the basis of a guarantee, it will be liable as a principal debtor and primary obligor
to indemnify the OWNER against any cost, loss or liability it incurs as a result of the Company not paying any amount expressed
to be payable by it under the Contract on the date when it is expressed to be due. The amount payable by the Guarantor under this
indemnity will not exceed the amount it would have had to pay under Clause 1 if the amount claimed had been recoverable on the
basis of a guarantee.
 
3 The liability of the Guarantor will not be discharged or impaired by any:
(a) variation to or replacement of the Contract, or any change in the obligations undertaken by the COMPANY
(b) any time, waiver, consent, forbearance or indulgence by OWNER as to any matter, including as to performance, payment, or
any other matter whatsoever
(c) disability, incapacity, insolvency, change in the status or constitution, judicial reorganisation, winding up or dissolution of the
COMPANY or the Guarantor or the OWNER
(d) change in relationship between the Guarantor and the COMPANY, or
(e) any assignment or transfer of the Contract or any interest in it by COMPANY or by OWNER (this Guarantee being for the
benefit of OWNER and its permitted assignees of the Contract)
or any other matter which would otherwise release a guarantor.
 
Page 45 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 51/85
12/9/22, 4:25 PM EX-10.3

 
4 The Guarantor waives and releases all rights of subrogation and/or set-off which it may have against the COMPANY and/or any
rights to claim or prove as a creditor of the COMPANY in competition with the OWNER to any rights of OWNER against the
COMPANY or any third party.
 
5 All payments by the Guarantor are to be made in US Dollars, without set-off or counterclaim, free and clear of any restriction,
condition, deduction or withholding. If the Guarantor is required by any law to make a deduction or withholding from any
payment (including tax) the amount due from the Guarantor will be increased as necessary to ensure that, after such deduction or
withholding, OWNER actually receives and retains an amount equal to the amount it would have received if no deduction or
withholding had been required; for the avoidance of doubt, and notwithstanding the foregoing, Guarantor shall not be required to
increase amounts as a result of deduction or withholding if, and to the extent that, under the terms and conditions of the Contract,
the COMPANY was allowed to withhold or deduct without being required to increase the amount due.
 
6 The Guarantor represents and warrants that it is a corporation duly organised and validly existing under the laws of Delaware, it is
solvent and able to pay its debts as they fall due, it has full power and authority to enter into this Guarantee, it has taken all
necessary corporate and other action to authorise it to do so, and this Guarantee is legal, valid, binding and enforceable against it.
The Guarantor agrees to furnish to the OWNER such evidence of the due authorisation and execution of this Guarantee as the
OWNER may reasonably request.
 
7 No failure to exercise, or delay in exercising, a right of OWNER under this Guarantee or the Contract will operate as a waiver of
that right, nor will a single or partial exercise of a right preclude a further exercise of that right or the exercise of another right. No
payment by the Guarantor will discharge the obligation of the Guarantor unless and until the OWNER has received payment in
full in the currency in which the obligation is denominated.
 
8 The amount to be paid by the Guarantor under this Guarantee shall include all documented costs and expenses (including legal
fees) reasonably incurred by OWNER in connection with the enforcement of this Guarantee or of the underlying obligation
against the COMPANY.
 
9 The Guarantor agrees that it shall not be necessary, as a condition to enforce this Guarantee, that suit be first instituted against the
COMPANY or that any right or remedies against the COMPANY or any other party be first exhausted. Rather, it is understood
and agreed that the liability of the Guarantor hereunder shall be primary, direct and in all respects unconditional.
 
10 This Guarantee extends to all obligations of COMPANY expressed in the Contract, whether such obligations are undertaken by
COMPANY as a principal or as an agent for any other party to the relevant Production Sharing Contract covering Oil Mining
Lease 120 Deep Offshore Nigeria.
 
11 This Guarantee shall terminate when the COMPANY has no further liability (actual or contingent) to the OWNER under the
Contract.
 
Page 46 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 52/85
12/9/22, 4:25 PM EX-10.3

 
12 All notices to be given by the OWNER under this Guarantee to the Guarantor shall be made in writing and either delivered
personally or sent by registered mail or certified mail or transmitted by facsimile to the following address/facsimile number:
CAMAC Energy, Inc.
1330 Post Oak Boulevard
Suite 2250
Houston, TX 77056
Fax: +1 713 965 5128
Such notices shall be effective when delivered if delivered personally or when received if sent by registered or certified mail, or if
sent by facsimile when the OWNER receives confirmation of transmission.

This Guarantee shall be construed under English law. The Guarantor submits irrevocably to the exclusive jurisdiction of the English
courts (provided that judgement may be enforced by the courts of any jurisdiction).

This Guarantee has been executed as a deed and it has been delivered on the date stated above.

[Signature Page Follows]


 
Page 47 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 53/85
12/9/22, 4:25 PM EX-10.3

IN WITNESS THEREOF, executed as a Deed for and on behalf of:

CAMAC Energy, Inc.


 
                                                                    
                              
 
Printed Name:                                        
                             
 
Title:                                                                   
                     
 
Witness:
 
                                                                 
                                 
 
Printed Name:                                        
                             
 
Page 48 of 85

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 54/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    49 of 85  
      
      
 

OML 120/121

OYO EXPANSION

SCOPE OF WORK

FPSO SUPPLY AND FIELD OPERATION


 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 55/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    50 of 85  
      
      
 
 
RECORD OF AMENDMENT
It is certified that the amendments listed below have been incorporated in this copy of the publication.
 
AMENDED PARAGRAPH
DESCRIPTION OF CHANGES
SECTION    NO.   
     
     
     
     
     
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 56/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    51 of 85  
      
      
 
TABLE OF CONTENTS
 
1.0    INTRODUCTION    52
Ø    1.1    General    52
Ø    1.2    Oyo Field Expansion Description    52
Ø    1.3    Outline of Scope of Work    53
2.0    OPERATIONS    54
Ø    2.1    General    54
Ø    2.2    Operations Organisation    54
Ø    2.3    CONTRACTOR’s Obligations    55
Ø    2.4    COMPANY’S Obligations    57
Ø    2.5    Maintenance    57
Ø    2.6    Classification Surveys    58
Ø    2.7    Personnel    59
Ø    2.8    COMPANY’s Accommodation and Facilities on Board the FPSO    59
¡    2.8.1    Accommodation Facilities    60
¡    2.8.2    Meals    60
¡    2.8.3    Laundry    60
¡    2.8.4    Office Facilities    60
¡    2.8.5     Communications    61
3.0     QUALITY ASSURANCE    62
4.0    INTERFACES AND RESPONSIBILITIES    63
Ø    4.1    General    63
Ø    4.2    Matrix of Interfaces    63
Ø    4.3    Responsibility Tables    74
5.0    HEALTH, SAFETY AND ENVIRONMENT (HSE)    79
APPENDIX 1 – FPSO Action Tracking Register    79
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 57/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    52 of 85  
      
      
 
 
1.0 INTRODUCTION
 
1.1 General
 
     In this SECTION the words and expressions established as definitions in SECTION II - CONDITIONS OF CONTRACT
shall have the same meanings as assigned to them in such section, except when the context otherwise requires.

The PROJECT Title shall be:

OML 120

OYO FIELD EXPANSION

FPSO SUPPLY & FIELD OPERATION

This title shall appear on all drawings, documents and correspondence appertaining to the CONTRACT.
 
1.2 Oyo Field Expansion Description
The information provided in this subsection is based on the best available knowledge of the COMPANY at this time. It is
provided for information purposes only.
The initial phase of Oyo Expansion will include the drilling and completion of two new producing wells and either a water
injection well or a third producing well, depending on reservoir requirements and drilling results. To bring online the first two
new producing wells (Oyo-7 and Oyo-8) as quickly as possible it is planned to shut-in and abandon the currently producing
wells (Oyo-5 and Oyo-6). The subsea systems (trees, flowlines, umbilicals, etc.) from the two abandoned wells will be
relocated and connected to the two new wells. No change is expected on the FPSO other than an increase in production; the
existing risers and umbilicals will remain in place.
The third well to be drilled will be either another producing well or a water injection well. In either case it will be necessary
to install a new riser and flowline and make any other modifications necessary to connect this new well to the FPSO systems.
During the second phase of Oyo Expansion it is envisaged to drill up to three additional producing wells.
For all phases, all excess produced gas will continue to be reinjected into Oyo-4.
Similar to the current producing wells, all future pipeline and riser systems will be designed for 5ksi (345bar) internal
pressure rating. Each producing well will be equipped with a 10kpsi horizontal tree. Choking of the well streams will occur
aboard the FPSO. Each well will be connected to its pipeline system with a vertical or horizontal connector.
As the Oyo Field Expansion may include one or more water injection wells to maintain reservoir pressure it is necessary to
commission the existing water injection system onboard the FPSO.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 58/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    53 of 85  
      
      
 
All future subsea wells will be controlled via an electro-hydraulic control system connected to the wells. The main umbilical
will be connected to the FPSO porch will be through an “I” tube and will be free-hanging to a Lazy “S” at the seabed.
During the term of the CONTRACT, COMPANY may want to consider various enhanced oil recovery upgrades for the
FPSO, including condensate stripping and stabilization.
 
1.3 Outline of Scope of Work
The CONTRACTOR shall carry out all activities required to operate and maintain the FPSO in accordance with Section VI
“Basis of Design”, to be chartered by the COMPANY for the period and under the clauses specified in the CONDITIONS of
CONTRACT. The work, as described in this Section (the “WORK”), shall include, but not be limited to, the following:
 
—   CONTRACTOR shall complete all maintenance and repair items identified as necessary to bring the FPSO back in to
 
compliance with Section IV “Basis of Design, as listed in Appendix 1 to this Scope of Work.
 
  —   The management and operation of the FPSO within the timeframe indicated in CONTRACT.
 
  —   Development of Nigerian Content
 
—   The provision all necessary services and assistance to COMPANY as necessary to implement the field expansion
plans outlined in subsection 1.2 above. Such services and assistance may include but is not limited to the items below,
 
and subject to CONDITIONS OF CONTRACT, Article 28 - Variations in the CHARTERPARTY or Article 29 -
Variations of the O&M Contract, as applicable:
 
—  Interfacing with COMPANY’s other contractors, including Flexible Contractor, Subsea Contractor, Drilling
 
Contractor, and Installation Contractor, as better defined in subsection 4.0 below.
 
  —  Provision of winches, operating personnel, and other temporary equipment as necessary to pull in new risers.
 
—  Engineering, procurement, fabrication, installation, and testing of new riser spool pieces, manifold extensions,
 
valves, and associated appurtenances to connect new risers to the FPSO system(s).
 
  —  Preparation of engineering studies if requested by company to evaluate enhanced oil recovery schemes.
 
  —  Support for commissioning and decommissioning of flowlines.
 
  —  Support for clean-up of new production wells.
 
—   Provision of logistic support (e.g. personnel, systems, facilities, marshalling sites, shore base support, security,
  transportation, telecommunications, lodging and catering) for CONTRACTOR personnel, including subcontractors
and vendors.
 
—   Preservation, retention, and updating, where applicable, of all documents, drawings, dossiers, procedures, and
 
manuals originally produced during the design and conversion process under the NAE CHARTERPARTY.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 59/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    54 of 85  
      
      
 
2.0 OPERATIONS
 
2.1 General
The CONTRACTOR shall provide a dedicated Operation Organization for the proper and continuous supervision and control
of the Operations at Oyo field.
The CONTRACTOR warrants that it has the necessary management, support and overall experience necessary to provide
effective management of both the onshore and offshore parts of the Operations at field and that sufficient corporate resources
shall be made available in the numbers of management personnel having the levels of corporate authority necessary to
exercise such management, co-ordination and direction over its work force, suppliers, sub-contractors and the constituent
members of any consortium or joint venture in order to achieve the CONTRACT requirements of quality and program.
 
2.2 Operations Organisation
A structured organization shall be established by CONTRACTOR to manage the overall operation of the FPSO at Oyo field.
The operations will be directed from the CONTRACTOR Central Office and managed on a day to day basis by the FPSO
Management Team reporting to the onshore base Management in Nigeria.
The activities to be carried out by the Central Office shall include, but not be limited to:
 
  —   Overall management and administration of the Contract with the COMPANY.
 
  —   Overall direction of onshore base and FPSO.
 
—   Liaison with and reporting to the COMPANY where necessary; normal contact with the COMPANY will be kept by
 
onshore base.
 
  —   Establishment of the formal SMS system.
 
  —   Establishment of budget, preparation of financial reporting and forecasting.
 
  —   Procurement services for spare parts, stores and consumables.
 
  —   Technical back-up to the offshore operations through the onshore Base.
The activities on charge the Onshore Base shall include, but not to be limited to:
 
  —   Management of onshore and offshore facilities.
 
  —   Management of office, storage and transit facilities.
 
  —   Management of the supply of spare part, consumables and other materials for the FPSO.
 
  —   Procurement of local materials and consumables.
 
  —   Organisation and co-ordination of the transport of materials and personnel to/from the FPSO.
 
—   Periodic reporting of activities, performances and results to the Operation Manager in accordance with formal
 
procedures.
 
  —   Establishment of budgets and management of financial aspects for all onshore activities.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 60/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    55 of 85  
      
      
 

The FPSO team shall have in charge the following task:


 
  —   Management and operation of the FPSO, including offloading activities.
 
  —   Offshore liaison with and reporting to the Client.
 
  —   Implementation of Central Office prescribed policies, procedures and SMS.
 
  —   Responsibility for offshore safety under the formal HSE.
 
  —   Receipt, processing, storage and offloading crude oil.
 
—   Maintenance of the FPSO under a formal planned Maintenance System in accordance with Classification Society
 
requirements.
 
  —   Inspection and ordinary maintenance (minor consumables and personnel) of flowline and subsea system.
 
  —   Accommodation of FPSO complement and supply of catering services.
 
  —   Co-ordination and direction of stand-by and supply vessels.
 
  —   Periodic reporting of all activities to the onshore Base.
 
2.3 CONTRACTOR’s Obligations
CONTRACTOR shall operate the FPSO for the duration of the O&M Contract in an efficient and competent manner, in order
to meet all the operative requirements and to achieve the target performances as specified in documents of Section VI -
“Design Basis”. It is responsible for all the field management activities including process plant, vessel utilities and offloading
system.
CONTRACTOR shall deliver hereunder and manage and operate the FPSO in accordance with the terms of Section II -
CONDITIONS of CONTRACT.
CONTRACTOR shall exercise due diligence to maintain the FPSO in an efficient and good operating condition for the entire
life and any extensions, according to the maintenance Scope of Work described in the following paragraphs.
CONTRACTOR shall exercise due diligence to provide competent personnel and maintain the complement of officer(s) and
crew and, when required, by a safe management of the system, additional competent and/or specialised personnel. In
particular CONTRACTOR shall supply a well trained Mooring Master, who will have in charge the supervision of the
offloading operations.
CONTRACTOR shall provide a crew member who can be trained by COMPANY to operate the Subsea Control System
under COMPANY’s instructions, and personnel to manage chemicals required for topsides facilities and fuels and lubricants
required for normal operations.
CONTRACTOR will furnish replacements for those items used from its inventory for day to day operation.
CONTRACTOR will furnish a laboratory equipment for crude analysis in accordance to the Nigeria requirements.
CONTRACTOR shall use reasonable skill and care in conducting the offloading of cargo from the FPSO to off-taking tankers
in accordance with operating procedures as specified in the agreed Terminal Regulations (NEED REFENCE).
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 61/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    56 of 85  
      
      
 

CONTRACTOR shall provide all bunker oil, grease, lubricants, and fresh water required for operation and maintenance of
the FPSO.
CONTRACTOR shall procure and provide all diesel fuel, chemicals, and fluids related to operation and maintenance of the
FPSO. Costs for these items will be reimbursed by COMPANY in accordance with the O&M CONTRACT.
CONTRACTOR shall provide and maintain all necessary oil spill response equipment in accordance with the agreed and
approved Oil Spill Response and Contingency Plan.
 
  —  Oil Spill Response Manual: AMO-CBGF-ALL-HSE-MAN-0004
 
  —  APK: Shipboard oil Pollution Emergency Plan (SOPEP): 21002-BAB-OP-0490
 
  —  APD: Shipboard oil Pollution Emergency Plan (SOPEP): 21004-BAB-OP-0490
 
  —  TGT: Shipboard oil Pollution Emergency Plan (SOPEP): 21006-BAB-OP-0490
 
  —  Facility Oil Spill Response Plan: AMO-INDI-ARS-HSE-PLN-0006
CONTRACTOR shall be responsible to furnish to COMPANY at the scheduled date all documents and drawings it may have
in its possession regarding the FPSO (in respect of the Nigerian law and regulations) necessary for COMPANY to obtain the
authorisations and permits for the operations at the AREA OF OPERATIONS.
CONTRACTOR shall provide logistic support including:
 
  —   an onshore base for personnel reception and good storage,
CONTRACTOR shall identify and agree with the COMPANY the limitations for the offloading operations. Terminal
availability for berthing and loading will remain under full responsibility and control of the FPSO Mooring Master.
CONTRACTOR shall design, supply and enforce adequate systems and procedures, in addition to standard notices to ships
and lights and fog horns, to ensure the highest safety level of the FPSO against risk of collisions with passing vessels. The
procedures shall include, but not be limited to, reliable measures to detect at a distance the passing vessel, and react by alarms
and communication, to warn off any vessel entering a specified distance range from the FPSO.
CONTRACTOR shall carry out all the actions to prevent wax and hydrate blockage during planned and unplanned well shut
down, on COMPANY Representative request. This includes flowlines flushing with Oyo fluids, flowline flushing and
cleaning using a batch of diesel and Oyo produced fluids, receiving and disposal of the waxy deposits. Provisions to be made
to meet the requirements of Basis of Design.
CONTRACTOR shall perform all the laboratory tests on the incoming oil from wells, under Company request and witness,
by supplying and operating all the laboratory equipment required to perform the above quality tests. It shall also perform at its
charge all the quality tests on the product to be delivered to the shuttle tanker, to prove to COMPANY Representative that it is
in compliance with the export specification.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 62/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    57 of 85  
      
      
 

CONTRACTOR shall keep onboard the FPSO and maintain the agreed and approved O&M Manuals for the FPSO.
CONTRACTOR shall maintain a complete and correct set of records pertaining to all aspects of this Contract, including, but
not limited to, meteorological information, vessel performances, offloading sequences and parameters, production
performances, system failures and damages, maintenance activities. It shall also keep regularly updated the manuals and the
drawing according to any modification introduced during the operating phases.
CONTRACTOR shall perform all the actions required for the system abandonment and removal of FPSO at the end of the
service life, including dismission and recovery of risers and mooring system, under COMPANY’s Specification and in
accordance with terms of the CHARTERPARTY and O&M CONTRACT.
 
2.4 COMPANY’S Obligations
COMPANY will prepare the subsea production system so as to permit the proper installation of the flowline system.
COMPANY will furnish any and all authorisations and permits required for the installation of the system, and for the FPSO to
operate at the AREA OF OPERATIONS, except for authorisations and/or periodic testing relevant to the vessel.
COMPANY will provide crude oil from the wells.
COMPANY will provide helicopter for transfer of Company and Contractor’s crew members.
COMPANY will supply the shuttle tankers for periodic crude oil offloading. Planning of terminal operations will be
performed on a three months basis and shall be agreed with CONTRACTOR, according to the expected production profile.
COMPANY will provide support vessel(s) and escort tug(s) required for CONTRACTOR performance under the O&M
Contract.
COMPANY will coordinate the interface with the Nigerian governmental authorities for the offshore petroleum activities and
any other relevant authorities with regard to permits, authorizations and consents for the FPSO.
COMPANY will reimburse at cost the bunker oil and/or diesel fuel required for offloading, well shut down and start up.
 
2.5 Maintenance
CONTRACTOR shall at all times maintain and preserve the FPSO in good condition, working order and repair, by
performing all the required intervention and modifications in order to maintain the design level of safety, reliability and
operativity of the system.
CONTRACTOR shall perform all the maintenance activities on the FPSO system in accordance to SECTION II -
CONDITIONS of CONTRACT”. COMPANY will supply all means and equipment to perform maintenance activities on the
subsea system. Company shall agree with CONTRACTOR the intervention procedures and shall ensure that the above work
minimize the impact on the production process and the interference with the FPSO.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 63/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    58 of 85  
      
      
 
 
     CONTRACTOR shall maintain the FPSO including its associated processing equipment so as to entitle it to the classification
and rating of appointed Classification Authority, submitting the FPSO to all required surveys. Annually, during each year of
the CONTRACT, it shall furnish to COMPANY reproduced copies of all annual certificates required and issued by the
Classification Authority dated within the previous 30 days, evidencing the maintenance of such classification.
 
     CONTRACTOR shall agree with the appointed Classification Authority the maintenance schedule for classification purposes,
so to minimize the impact on the production regularity.
 
     CONTRACTOR shall keep regularly informed COMPANY of the maintenance activities performed on FPSO, by issuing a
periodic report on maintenance activities. COMPANY shall verify the good performance of the maintenance activities
specified in the report.
 
     CONTRACTOR shall procure all the materials, items, consumables and support vessels/equipment required to carry out the
inspection and maintenance activities.
 
     CONTRACTOR shall maintain an inventory of spare and replacement parts and equipment, either on board the FPSO or at
the onshore base, of sufficient type and quantity to ensure compliance with the uptime requirements specified in SECTION
VI – Basis of Design.
 
     CONTRACTOR undertakes that, apart from repairs following accidental damages or due to FORCE MAJEURE, under no
circumstances the maintenance activities shall impose the disconnection of the tanker and the transfer to a dry dock.
 
     CONTRACTOR shall perform all maintenance and repairs without causing the production train(s) aboard the FPSO to be
shut-down, except for an annual credited period as “Maintenance Allowance”, established under SECTION II -
CONDITIONS of CONTRACT”.
 
     CONTRACTOR shall coordinate and liaise with COMPANY to minimise disruption to production in respect of such
maintenance.
 
     CONTRACTOR agrees to use all reasonable dispatch in order to complete necessary maintenance in the event the FPSO is
required to be shut down from service and further agrees not to delay the FPSO’s return to service because the unused
Maintenance Allowance exceeds the time required to perform such maintenance. The maintenance programme shall be
optimised by ensuring the safety minimum requirements provided for in the specifications.
 
     Any dry-docking, if required, shall be performed in accordance with the terms stated in SECTION II – CONDITIONS OF
CONTRACT.
 
2.6 Classification Surveys
 
     All parts of the system shall be submitted to initial and periodic survey, according to the requirements of the appointed
Classification Authority. The surveys shall be performed in situ, with the minimum interference with the production
regularity, under the supervision of the Classification Authority Surveyor and the witness of the Company Representative.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 64/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    59 of 85  
      
      
 
 
     CONTRACTOR shall carry out all the survey activities prescribed by the Classification Authority, including but not limited
to:
 
—   survey during installation, start up and commissioning, to ascertain that the vessel comply with the stated
 
requirements,
 
—   periodical surveys, including annual and five years surveys, consisting on the check, at different levels of detail, of all
 
the critical items to ascertain their integrity and perfect functionality,
 
—   special survey, to be performed anywhere an anomaly or a damage occur, to prove that the integrity and safety of the
 
installation is again ensured.
 
     CONTRACTOR shall agree the surveys schedule, modes and extent with the Classification Authority; survey execution shall
be noticed in advance to the Company for witness.
 
2.7 Personnel
 
     CONTRACTOR represents and warrants that CONTRACTOR’s personnel shall be adequate to properly operate and maintain
the FPSO and that all such personnel will be fully fit suitably skilled and experienced to properly perform the tasks assigned
to them in a timely and efficient manner.
 
     If the minimum operating crew requirements are not met COMPANY shall notify CONTRACTOR to remedy the default, in
accordance with Section II - “CONDITIONS of CONTRACT”.
 
     All CONTRACTOR’S key personnel, shall be fluent, able to speak, read and write competently the English language.
 
     COMPANY shall have the right at any time to object to and to require CONTRACTOR in writing to remove forthwith at its
own cost and expense any member of CONTRACTOR’S personnel who, in the opinion of COMPANY, is incompetent or
negligent in the performance of his duties or guilty of misconduct or otherwise considered by COMPANY to be unsuitable.
Any person so removed shall promptly be replaced by CONTRACTOR at its own cost and expense with a suitably skilled
and competent substitute.
 
2.8 COMPANY’s Accommodation and Facilities on Board the FPSO
 
     CONTRACTOR shall accommodate on board the vessel the permanent COMPANY’s complement plus a minimum of four
visitors. Permanent complement shall be accommodated into single bed cabins, whereas single/double beds cabins shall be
arranged for visitors.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 65/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    60 of 85  
      
      
 
  2.8.1 Accommodation Facilities
 
     CONTRACTOR shall provide cabin accommodations for 8 (double bed) + 4 (single bed) COMPANY personnel during
Hookup and Commissioning and 5 + 6 during operations. All accommodation areas shall be air conditioned and heated.
COMPANY’s accommodation’s shall comprise the following:
 
—   COMPANY Representative: One (1) single bed cabin with integral day room, shower and toilet facilities. Cabin to be
 
equipped with radio, colour television/DVD player with regular supply of movies and fridge.
 
—   DPR/Custom Representative: three (3) single bed to be equipped with radio, colour television/DVD player with
 
regular supply of movies
 
  —   Four (4) double bed cabins with integral shower/toilet.
 
     Every cabin shall have all necessary bunks, mattresses, pillows, bed linen and towels and be equipped with a locker,
wardrobe, desk and chair. The cabins shall be cleaned every day and the linen and towels changed as a minimum every other
day.
 
     CONTRACTOR shall also provide appropriately situated changing rooms with adequate lockable lockers for the storage of
working clothes. Toilet and washing facilities shall be available inside the cabin or adjacent.
 
  2.8.2 Meals
 
     CONTRACTOR shall provide, prepare, cook and serve, up to four meals per day to COMPANY’s personnel, at designated
and agreed meal times. All foodstuffs and consumables provided shall be of first class quality and freshness and shall be free
from any contamination.
 
     CONTRACTOR shall provide tea, coffee, soft drinks, cakes, biscuits etc., on a 24 hour basis.
 
  2.8.3 Laundry
 
     CONTRACTOR shall provide a laundry service for the COMPANY’s personnel within a 24 hour turn-around.
 
  2.8.4 Office Facilities
 
     CONTRACTOR shall provide offices for 8 COMPANY personnel during Hookup and Commissioning and offices for 5
during operations (1x1; 2x2 + 1 meeting room for 8) and be equipped with the appropriate desks, chairs, filing cabinets,
internal telephone, etc.
 
     The offices shall be fully equipped with good quality office furniture e.g.: desks, chairs, tables, filing cabinets etc., as required
by COMPANY.
 
     The offices shall be connected to the vessel’s internal telephone system and be able to communicate with the bridge and all
remote work stations. The offices shall be equipped with one personal computer, IBM compatible with relevant peripherals
including printer and software. The PC shall be capable of Internet connection.
 
     CONTRACTOR shall make available one A1 size drawing board and the use of a photocopier capable of producing good
quality A3 and A4 copies, together with a supply of consumables.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 66/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    61 of 85  
      
      
 
  2.8.5 Communications
 
     CONTRACTOR shall provide access to Satellite and HF/MF/VHF Marine Radio Telephone, and Facsimile (A4 page size),
VHF Marine Radio facilities and qualified operator on a 24 hour basis for use by COMPANY personnel. These facilities may
be provided from the vessel’s standard radio equipment.
 
     CONTRACTOR shall provide the following fully equipped and commissioned radio facilities in COMPANY’s office, on the
FPSO:
 
  —  Multi-channel VHF Marine Band Radio.
 
—  Secure satellite telephone and facsimile link through Vessel satellite system. System should be controlled by
 
CONTRACTOR.
 
—  Four complete portable VHF Marine Band multi-channel radios, Motorola type or equivalent, provided with
 
sufficient batteries and battery chargers to maintain four portable radios in constant use.
 
     COMPANY shall be allowed 24 hour access to the on board facilities for the transmittal and receipt of telexes.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 67/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    62 of 85  
      
      
 
3.0 QUALITY ASSURANCE
 
     FSPO Operation Quality Management Plan: OMF-BGF-QMP-QA-PL-0001.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 68/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    63 of 85  
      
      
 
4.0 INTERFACES AND RESPONSIBILITIES
 
4.1 General
 
     The purpose of this subsection is to give the CONTRACTOR an overview of the envisaged interfaces of the WORK to allow
the full consideration of all impacts direct and indirect, on the CONTRACTOR’S scope of work.
 
     Interfaces shall, unless otherwise directed by the COMPANY, be similar to those specified for the original Oyo Field
Development Project. The work of other contractors will be coordinated by the COMPANY to achieve an integrated design
and minimize the effect of interfaces.
 
     CONTRACTOR shall clearly identify all the interfaces between the WORK and the work of other contractors and shall co-
operate with COMPANY, other contractors, government department and other related third parties to achieve continuity of all
systems forming part of the Oyo Field.
 
     The CONTRACTOR shall develop and put into operation a management interface procedure to co-ordinate those activities
within its complete control and those activities which interface and/or impinge upon the WORK.
 
     CONTRACTOR shall be responsible for all interfaces with other parties’ work and his responsibilities will include, but not be
limited to, the following:
 
  —   Give notice, provide attendance and execute any work in connection with the other parties.
 
  —   Release all drawings and technical documentation which are critical for interfaces with other contractor’s work.
 
—   To the maximum extent possible, to give other contractors unhindered access and working space and organise and
 
progress his own operations to suit and harmonise with the scope of their work.
 
—   To give information to COMPANY of any impacts that other contractor’s activities may have on CONTRACTOR’s
 
Scope of Work, programmes etc.
 
—   To give information to COMPANY of any impacts that the work may have on requirements for government permits,
 
authorisations and review and comments.
 
     For reference only, a list of envisaged interfaces is reported below.
 
4.2 Matrix of Interfaces
 
     The following matrix illustrates the responsibility limits of the CONTRACTORS for Oyo Expansion Project.
 
     The matrix allocates the responsibilities of different CONTRACTORS only for those items that are identified as interface
activities or components. The responsibilities assigned to each contractor in the area of its competence are identified in the
relevant SCOPE OF WORK documents.
 
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 69/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     64 of 85  
      
 
     The matrix contains the following information elements:
 
  a) Interface Item
 
       Description of the system interface or activity.
 
  b) CONTRACTOR Responsibility
 
     The responsibilities and deliverables for contractors and COMPANY are detailed for each Interface Item. It is
emphasized that the listed responsibilities and deliverables are minimum requirements and that the generated
 
deliverable must be presented to all of the interfacing contractors in a timely and efficient manner and properly
documented.
 
     The contractors are identified as follows:
 
DRILLING:    Drilling and completion of wells, installation of PGBs and trees, subsea tie-ins.
FPSO:    Provision and operation of Oyo FPSO FLEXIBLE:Design and manufacture of flexible system
SUBSEA:    EPC of, trees, umbilicals and subsea control system.
INSTALLATION:    Installation of FLEXIBLE and SUBSEA Scope

The following interface items have been identified:


 
Item    Category    Sub-category
1 GENERAL Field Architecture, Flow assurance and Operation Strategy, Installation
Hazid/Hazop, Operation Hazid/Hazop, Risk Assessment, Operating Philosophies
      and Procedures
2    RISER   Tieback to Oyo FPSO
3    UMBILICAL   Installation of Umbilicals and Flying Leads
4    FLOWLINE   Subsea Tie-ins
5    ROV   ROV Tooling
6 WORKOVER SYSTEM AND TREE
   INSTALLATION   
7    DHPTT   
8    SUBSEA CONTROL SYSTEM   
9    COMMISSIONING   
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 70/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     65 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
1) GENERAL Design MODU Cooperate with and Co-operate with and Design flexible Design umbilical Determine general
1.1) Field Architecture mooring patterns and provide information provide information configuration configuration field architecture.
mooring overall layout. to DRILLING, to DRILLING, Cooperate with and (dynamic section) Provide geophysical
Cooperate with and FLOWLINE, FPSO, FLOWLINE provide information Cooperate with and and geotechnical
provide information to INSTALLATION and SUBSEA to DRILLING, provide information data.
FLOWLINE, FPSO, and SUBSEA Contractors. FPSO, to DRILLING, Coordinate
SUBSEA, and contractors. Design flowline- INSTALLATION FPSO and DRILLING, FPSO,
INSTALLATION Determine riser and umbilical and SUBSEA FLOWLINE FLOWLINE,
Contractors. minimum exclusion detailed routing. Contractors. Contractors. SUBSEA, and
zones around FPSO Provide umbilicals Determine the final INSTALLATION
and safe approach routing data to configuration of the Contractors for
paths required for SUBSEA for main umbilical design flowline and
export tanker detailed length riser. umbilical routings.
berthing, definition. Determine the final
considering FPSO Determine the final length of main
rotation. lengths of the static umbilical dynamic
Design FPSO sections only of the section (from the
mooring pattern and umbilicals (from FPSO riser porch
mooring overall TDP of the Main hang-off point to
layout. umbilical to the the TDP)
         SDU and wells).         
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 71/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     66 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
1) GENERAL      Provide input to Incorporate into the Incorporate into the      Provide input to
1.2) Flow Assurance and FLOWLINES for design the design the FLOWLINE for
Operation Strategy the flo assurance requirements from: requirements from: flow assurance
analysis (slug     analysis
catcher, separator -   flow assurance -   flow assurance  
pressures, etc.)          Review flow
  -   wax management -   wax management assurance analysis
     Incorporate into      
the topsides design -   hydrate -   hydrate      Define:
and start-up management management  
procedures and
    -   hydrate
-   operation -   operation management
operating manuals strategy strategy  
the requirements     -   wax management
from: -   chemical -   chemical  
 
injection injection -   operation
-   flow assurance strategy
 
 
-   wax management     (including
 
-   hydrate pigging)
 
management -   chemical
 
-   operation injection
 
strategy      Provide input to
 
-   chemical FLOWLINE for the
injection flow-assurance
analysis (slug
catcher, separator
pressures, etc.)
 
     Incorporate into
the topsides design
and start-up
procedures and
operating manuals
the requirements
from:
 
-   flow assurance
 
-   wax management
 
-   hydrate
management
 
-   operation
strategy
 
-   chemical
injection
                   
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 72/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     67 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
1) GENERAL Perform HAZID / HAZOP Participate in Incorporate the Perform HAZID / Cooperate with Participate and
1.3) Installation HAZID/HAZOP activities for HAZID HAZOP results of the HAZOP activities FLOWLINE & review HAZID /
drilling/installation for FLOWLINE, installation HAZID for FLOWLINE UMBILICAL and HAZOP
activities. SUBSEA, and /HAZOP. installation DRILLING to activities.
Cooperate with mooring activities. HAZID / HAZOP
FLOWLINE to installation activities.
HAZID/HAZOP activities. activities. Incorporate the
Incorporate the results of Incorporate the results of the
the installation HAZID / results of the installation
HAZOP. installation HAZID /
      HAZID HAZOP.          HAZOP.   
1) GENERAL Cooperate with FPSO to Perform Cooperate with Cooperate with Participate and
1.4) Operation HAZID / HAZOP perform HAZID / HAZOP. Operation FPSO to perform FPSO to perform review HAZID/
Incorporate results in HAZID /HAZOP. HAZID/ HAZOP. HAZID/ HAZOP. HAZOP carried
design. Incorporate Incorporate Incorporate out by FPSO.
results into results in design. results in design.
      design.            
1) GENERAL Participate in Risk Participate in Participate in Risk Participate in Participate in Perform Risk
1.5) Risk Assessment Assessments activities. Risk Assessments Assessments Risk Assessments Risk Assessments Assessments
Incorporate the results of activities. activities. activities. activities. activities.
all risk assessments. Incorporate the Incorporate the Incorporate the Incorporate the
results of all risk results of all risk results of all risk results of all risk
      assessments.    assessments.    assessments.    assessments.   
1) GENERAL      Develop      Provide input      Provide input      Define
1.6) Operating Philosophies and global operating to FPSO to FPSO operating
Procedures and maintenance Contractor for the Contractor for the philosophy.
procedures update of global development of  
including start-up operating and global operating      Review
and shutdown and maintenance and maintenance operating and
restart. procedures procedures maintenance
including start-up including start-up procedures and
and shutdown and and shutdown and manuals,
restart. restart including start-up
    and shutdown, for
     Review      Review SUBSEA,
operating and operating and FLOWLINE and
maintenance maintenance topsides systems.
procedures and procedures and  
manuals, manuals,      Review and
including start-up including start-up Update current
and shutdown, and shutdown, global operating
and restart for and restart for and maintenance
SUBSEA, SUBSEA, procedures and
FLOWLINE and FLOWLINE and manuals,
topsides systems. topsides systems. including start-up
Incorporate into Incorporate into and shutdown,
design. design. restart for
SUBSEA,
FLOWLINE and
                  FPSO systems.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 73/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     68 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
2) RISER Provide, install and Engineer, procure, Calculate and Prepare the
2.1) Tie-back to FPSO connect temporary construct, install document operating installation and
equipment c/w and hook-up tie- and installation commissioning
winches, rigging back equipment as hang-off loads and plan.
and installation per Table B. provide to FPSO. Review the
aides on FPSO. Provide data to Provide data to installation and
Engineer, procure, FPSO for design of FPSO for design of commissioning
construct, install riser receptacles and riser receptacles and procedure.
and hook-up tie- review FPSO design review FPSO Supervise
back equipment as Develop installation design commissioning of
per Table B. and Design, fabricate, the flowline system.
Account for loads precommissioning and install any test
and load margin in procedure. blinds as required
FPSO hull/mooring Perform riser for testing of risers
design. installation and and flowlines.
Provide FPSO hang-off. Provide pulling
motion data to Test system from heads for risers.
FLOWLINE. top of riser through
Provide space for flowline connector
temporary to PGB or
equipment provided temporary sled
by FLOWLINE. (optional).
Coordinate with Perform pre-
FLOWLINE commissioning of
installation of the flowline system
temporary with the assistance
equipment. of FPSO
Remove installation
aides and temporary
equipment and
reinstate / repair
affected areas.
Review installation
procedure and
requirements issued
by FLOWLINE and
verify the design of
existing support
      structures.            
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 74/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     69 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
3) UMBILICAL Perform subsea Engineer, procure, Engineer, procure, Perform Perform detailed Coordinate the
3.1) Installation of umbilical tie-ins of construct, install construct, install interference design of dynamic activities of
Umbilicals and Flying Leads wells, as per Table D and hook-up and hook-up analysis with risers umbilical, included SUBSEA personnel
(optional). equipment as per equipment as per and moorings. hang-off during installation,
Develop relevant Tables A and D. Tables A and D. Provide results to configuration. test and
installation and testing Account for loads Provide installation SUBSEA and Incorporate into commissioning
procedures (optional) and load margin in engineering support FPSO. design the phases.
FPSO hull/mooring to SUBSEA for interference results Review load out
design. umbilical and flying from FLOWLINE procedures
Provide FPSO leads design. Develop the developed by
motion data to Incorporate the installation SUBSEA.
SUBSEA. installation requirements and Review the pre-
Review installation requirements and provide them to commissioning
procedure and develop the FLOWLINE procedures.
requirements issued installation and Develop the load Supervise the
by FLOWLINE, subsea tie-in out requirements installation pre-
SUBSEA, and procedures. and provide them to commissioning
INSTALLATION. Review load out FLOWLINE activities.
Provide space for procedures Develop the
temporary developed by installation
equipment provided SUBSEA. requirements for
by FLOWLINE Assist, witness load flying leads and
and/or out testing and provide them to
INSTALLATION. receive the FLOWLINE and
Coordinate umbilical system DRILLING.
installation of Perform umbilical Calculate and
temporary transportation from document operating
equipment with manufacturing yard and installation
FLOWLINE and/or to the offshore site. hang-off loads and
INSTALLATION. Install and test all provide them to
Verify actual design umbilical sections FPSO.
against the and SDU.* Perform the load-
interference results Install, connect and out of umbilical
from FLOWLINE test all flying leads. onto FLOWLINE
Identify locations Perform post- installation vessel.
for TUTU and installation tests Perform loadout
provide bulk-heads with the assistance testing and
to connect TUTU of SUBSEA. handover the
with the umbilical Perform umbilical system to
pig tails precommissioning FLOWLINE
of the umbilical Provide assistance
system with the and temporary
assistance of equipment during
SUBSEA installation works,
hang-off, testing
and commissioning.
Develop the pre-
commissioning
procedures.
Provide to FPSO
information about
               the pig-tail lengths.   
                 
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 75/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     70 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
4) FLOWLINE Engineer, procure, Provide information Engineer, procure, Supervise tie-in
4.1) Subsea Tie-ins construct, install to SUBSEA on construct, install operations.
and hook-up tie-in loads transferred to and hook-up tie-in Provide assistance
equipment as per connector and xtree equipment as per to FLOWLINE
Table C. (or PGB if any) by Table C. during testing.
Develop tie-in and the flowline Coordinate
testing procedures Coordinate connector design
with assistance of gooseneck (if any) with FLOWLINE
SUBSEA. design with and provide with
Engineer and SUBSEA and tie-in requirements
procure all incorporate tie-in to FLOWLINE.
equipment, rigging, requirements. Supply connectors
installation aids and to FLOWLINE for
temporary sleds integration into
(optional). each flowline
Tie-in all gooseneck terminations or
(if any) connections gooseneck (if any).
to all xtree (or PGB Provide tools for
if any) and testing actuating the
with FPSO support. mechanical
connectors and
supply to
FLOWLINE and
DRILLING.
Provide assistance
to FLOWLINE
during tie-in
operations.
Provide to
FLOWLINE all
technical
information,
calculations or
analyses relevant to
xtree (or PGB if
any) hub position.
Assembly connector
onto each
               gooseneck (if any).   
5) ROV Provide ROV features Provide ROV Incorporate Provide information
5.1) ROV Tooling for interface with ROV features for COMPANY owned and requirements of
tooling. interface with ROV ROV tools features the existing
Equip the ROV spread tooling. for subsea COMPANY owned
with the tooling Equip the ROV equipment ROV ROV Tooling to
provided by spread with the interface design. SUBSEA
COMPANY. tooling provided by Provide ROV
COMPANY. tooling to
FLOWLINE and
                  DRILLING.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 76/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     71 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
6) WORKOVER SYSTEM Provide information and Incorporate Lead installation
AND TREE requirements about the information and and test of tree
INSTALLATION MODU interfaces with interface system.
Workover system. requirements from
Provide MODU and DRILLING in Tree
marine riser motion data and PGB (if any),
to SUBSEA. and workover
Design and carry out system design
required modification to Develop system
MODU layout and installation and
handling system to operation
install the workover procedures
system. Install Workover
Design and carry out system components
interface modification on the MODU,
to install the Workover operate it and
Equipment. remove it.
Provide assistance to
SUBSEA during
installation, operation
and removal of the
   Workover system.               
7) DHPTT Provide assistance to Engineer, procure, Engineer, procure,
COMPANY/SUBSEA construct, install install and hook-up
for DHPTT installation. and hook-up DHPTT equipment
DHPTT equipment as per table E.
as per table E. Provide information
Incorporate into to SUBSEA.
design information
provided by
               COMPANY   
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 77/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     72 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
8) SUBSEA CONTROL Install, hook-up and Provide support to Provide overall
SYSTEM pre-commission FPSO for the control philosophy
topsides equipment development of to FPSO and
provided by cause and effect SUBSEA.
SUBSEA diagrams.
(excluding wiring Provide to FPSO
and tubing hook-up requirements for
to the SCS side). equipment located
Engineer, procure, in the Control
construct and install Rooms and
all hook-up Instrument /
materials (i.e. Electrical buildings.
cabling, tubing, Provide to FPSO
junction boxes, requirements for
trays, etc). SCS equipment.
Incorporate into including remote
design all interfaces emergency
with subsea shutdown system.
equipment. Incorporate into
Develop overall design all interfaces
cause and effect with FPSO control
diagrams with system.
SUBSEA support. Include into design
Incorporate into the FPSO
design all requirement on
requirements for ESD system.
SCS equipment. Provide to FPSO
Provide to SUBSEA the list of hardwired
the list of hardwired i/o and serial links
i/o and serial links to FPSO DCS/ESD
with SCS. systems.
Provide suitable Perform final
space, support for wiring and tubing
SUBSEA topsides hook-up to SCS
equipment. topsides equipment.
Include the Include into design
SUBSEA topside requirements from
equipment FPSO hazardous
requirements into area classification.
the F&G and fire Provide to FPSO
fighting systems handling,
design. installation and
maintenance
manuals.
Provide technical
support to FPSO
during installation
               and hook-up   
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 78/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     73 of 85  
      
 
 
RESPONSIBILITY
INTERFACE                        (including but not limited to)
ITEM    DRILLING    FPSO    INSTALLATION    FLOWLINE    SUBSEA    COMPANY
9) COMMISSIONING Provide assistance to Provide priority Hook-up and pre- Provide assistance Lead
COMPANY for access to work areas commission the to COMPANY for commissioning of
commissioning of for FLOWLINE flowline system. commission of the overall subsea
SUBSEA equipment. personnel and Provide assistance wells and SUBSEA production system.
equipment, as to COMPANY to equipment (on Commission wells.
required for commission the reimbursable basis). Develop wells start-
FLOWLINE to subsea system (if Provide assistance up procedures.
perform the required). to COMPANY for Lead the start-up of
required Provide assistance the start-up of the the field.
connections to the to COMPANY for field (on a
FPSO. the start-up of the reimbursable basis).
Provide other field (if required).
support assistance
(e.g. cranes,
rigging) to
FLOWLINE, as
required
Hook-up and
commission all
components
procured and/or
fabricated by FPSO.
Provide assistance
to FLOWLINE and
COMPANY to
commission
components
interconnecting
with the FPSO.
Develop start-up
procedures.
Cooperate with
COMPANY to
      start-up the field.            
10) FPSO Provide mooring Install mooring
10.1) Vessel Mooring lines and anchor lines and anchor
      system.    system.         
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 79/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    74 of 85  
      
      
 

 
4.3 Responsibility Tables
The following tables summarise the responsibilities of the contractors for all critical interface areas.
 
C    Issued for Internal Review   GBB             28 Jan 14      
B    Issued for Internal Review   GBB             27 Jan 14      
A    Issued for Internal Review   GBB             23 Jan 14      
    Rev       REASON FOR ISSUE         Prepared              VERIFIED              APPROVED        Date
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 80/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     75 of 85  
      
 

Table A: Subsea Control Umbilical – FPSO Battery Limits


 

  No.   Item   E   P   C   I   H/C


1 TOPSIDES CABLING (POWER V V V V V
AND COMMUNICATIONS)
             
2 TOPSIDES PIPING V V V V V
(INSTRUMENTS)
             
3 TUTU S S S V V
             
4 UMBILICAL S S S IC V
             
5 UMBILICAL HANG-OFF S S S IC —
ASSEMBLY
             
6 HANG-OFF BEAM V V V V —
             
7 HANG-OFF STRUCTURAL V
SUPPORT
             
8 BEND STIFFENER     S         S         S         IC           —      
             
9 BUOYANCY MODULES     S         S         S         IC           —      
             
Legend:
             
V FPSO Vessel Contractor E Engineering
S Subsea Contractor P Procurement
F Flowline Contractor C Construction/Fabrication
D Drilling Contractor I Installation
Co Company H/C Hook-up & Commissioning
IC Installation Contractor

       
 
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 81/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     76 of 85  
      
 

Table B: Flexible Risers – FPSO Battery Limits


 
  No.   ITEM         E              P              C              I              H/C      
1 TOPSIDES PIPING V V V V V
                   
2 TOPSIDE TIE-IN SPOOL V V V IC V
                   
3 RISER END FITTING F F F IC —
                   
4 HANG OFF ASSEMBLY F F F IC —
                   
5 HANG OFF V V V V —
STRUCTURAL SUPPORT          
              
6 BEND STIFFENER F F F IC —
                   
7 HANG-OFF BEAM V V V V —
                   
8 FLEXIBLE RISER F F F IC V
                   
  Legend:           
V FPSO Vessel Contractor E Engineering
S Subsea Contractor P Procurement
F Flowline Contractor C Construction/Fabrication
D Drilling Contractor I Installation
Co Company H/C Hook-up & Commissioning
  IC   Installation Contractor    
 
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 82/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     77 of 85  
      
 

Table C: Flexible Flowlines – Xtree or PGB (if any) Battery Limits –


 

 
No.    ITEM          E                P                C                I              H/C    

1    ELECTRICAL FLYING LEAD    S    S    S    IC    V


2    HYDRAULIC FLYING LEAD    S    S    S    IC    V
3    UMBILICAL IUTA    S    S    S    IC    V
4    TEMPORARY SLED    S    S    S    IC    —
5    SUBSEA XMT    S    S    S    D    D
6    VCM W/GOOSENECK&FLANGE    S    S    S    IC    —
7    FLEXIBLE SUBSEA END FITTING    F    F    F    IC    —
8    FLEXIBLE BENDING RESTRICTORS    F    F    F    IC    —
9    FLEXIBLE ANODES    F    F    F    IC    —
10    UMBILICAL BENDING RESTRICTORS    S    S    S    IC    —
Legend:                  
V FPSO Vessel Contractor E Engineering
S Subsea Contractor P Procurement
F Flowline Contractor C Construction/Fabrication
D Drilling Contractor I Installation
Co Company H Hook-up & Commissioning
IC    Installation Contractor      
 
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 83/85
12/9/22, 4:25 PM EX-10.3

   Date       Doc. N°.   Page


   28 Jan 2014               OYO2-FPSO-SOW-0001                     78 of 85  
      
 

Table D: DHPTT – Tree Battery Limits


 
  No.   ITEM         E              P              C              I              H      
1 DHPTT Co Co Co Co Co
                   
2 DHPTT CABLE AND CLAMPS Co Co Co Co Co
                   
3 GLAND S S S S S
                   
4 CABLE INSIDE THE TUBING Co S S S S
         
HANGER
              
5 PENETRATOR - DRILLING TO S S S S D
         
PROVIDE ROV FOR FINAL HUC
              
6 JUMPER(HARNESS) S S S S S
                   
7 POD S S S S S
                   
8 INTERFACE CARD Co Co Co S Co
                   
9 TUBING PUP JOINT AND Co Co D D D
         
CROSSOVER REQUIRED WILL BE
PROVIDED BY COMPANY. A-K TH
PIN 5- 1⁄2” VAM TOP 23 LB-FT X
(TBD PIN)
              
10 TUBING HANGER S S S D D
                   
  Legend:           
V FPSO Vessel Contractor E Engineering
S Subsea Contractor P Procurement
F Flowline Contractor C Construction/Fabrication
D Drilling Contractor I Installation
  Co   Company  H   Hook-up & Commissioning
 
This document is property of Allied Energy. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 84/85
12/9/22, 4:25 PM EX-10.3

Date     Doc. N°. Page


      
28 Jan 2014             OYO2-FPSO-SOW-0001                    79 of 85  
      
      
 

 
5.0 HEALTH, SAFETY AND ENVIRONMENT (HSE)
(Note: This Section to be deleted provided there is an approved HSE plan covering the Operations phase. Need Reference.)

APPENDIX 1 – FPSO ACTION TRACKING REGISTER


 

https://www.sec.gov/Archives/edgar/data/1402281/000156459014002000/d724993dex103.htm 85/85