You are on page 1of 12

RSUD dr Soeratno Gemolong

Sragen
A Indonesia
REV DATE MODIFICATIONS
01 - Cover Sheet 10 - Equipment Dimensions Andreas Persada
02 - Equipment Layout
03 - Structural - Electrical Layout
11 - Delivery
12 - Disclaimer - Site Readiness GE Healthcare -
04 - Floor Structural Details Andreas.persada@ge.com
05 - Radiation Protection Layout
06 - Radiation Protection Details
07 - Power Requirements - Power Distribution
08 - HVAC - Warning Light
REVOLUTION ACT
09 - Environment - Interconnections FINAL STUDY
Drawn by Verified by Concession S.O. (GON) PIM Manual Rev
A mandatory component of this drawing set is the GE Healthcare Pre Installation manual. Failure to reference the Pre Installation manual will result in
incomplete documentation required for site design and preparation.
Pre Installation documents for GE Healthcare products can be accessed on the web at: www.gehealthcare.com/siteplanning 5487127-1EN 8
GE does not take responsibility for any damages resulting from changes on drawings made by others. Errors may occur by not referring to the complete
set of final issue drawing. GE cannot accept responsibility for any damage due to the partial use of GE final issue drawings, however caused. All
Format Scale File Name Sheet
dimensions are in millimeters unless otherwise specified. Do not scale from printed pdf files. GE accepts no responsibility or liability for defective work
due to scaling from these drawings. A3 1:40 CT-A282944-FIN-XX.DWG 01/12
EQUIPMENT LAYOUT
DIMENSIONS LxWxH WEIGHT
ITEM DESCRIPTION (mm) (kg)

1 GANTRY 2050x1039x1938 1810


2 GT1700V TABLE 650x2370x1046 445
6946 3 POWER DISTRIBUTION BOX (PDB) 600x300x800 42
4 POWER DISTRIBUTION UNIT (PDU) 700x550x1062 370
5 AURORA SWS TABLE 1300x850x850 40
6 OPEN CONSOLE 672x400x576 64.2
7 ADVANTAGE WORKSTATION 1000x690 22
8 LOCAL SUPPLIED DESK - -

WALL - ACCORDING TO RECEIVED DRAWING


1 4 3
EXAM ROOM HEIGHT
FINISHED FLOOR TO SLAB HEIGHT 4m
FALSE CEILING HEIGHT 2.8m

2
5799

3172
5 8
7
6

R.OPERATOR

TOILET

Revolution ACTs CT-A282944-FIN-XX.DWG 1:40 Rev A Equipment Layout 02/12


STRUCTURAL - ELECTRICAL LAYOUT
ITEM QTY DESCRIPTION

1 Gantry anchoring (see Structural Details)


2 Table anchoring (see Structural Details)
6946 3 200x200 cable inlet through the floor slab for Gantry (see Structural Details)
4 200x70 flush floor duct
200x200 cable inlet for PDU cabling and 200x100 vertical duct from the floor to PDB
5 (h=1.1m)
3000 5 6 200x100 opening on the floor

Basic system
6 Electrical outlet 10/16A 230V + G

1 2 RJ 45 network socket
System remote control (Y), locked when power OFF "ON" and "OFF" impulse buttons with
1
indicator lamps red=ON / green=OFF located at 1.50m above floor
2 System emergency off (SEO), (recommended height 1.50m-1.85m above floor)

3000
1 System ON light (L) - 24V
1 X-Ray ON lamp (L1) - 24V

Inspector Option
1 Inspector connection point - 3Phases+N+G (Required to prepare in local)
2
5799

1 RJ 45 network socket

785 AW

3172 3 Electrical outlets for AW option: 230V 10/16A +G linked to the hospital UPS or

555
4
through a dedicated UPS of 1 kVA single phase (If available)
1 RJ45 network socket for AW option

6 Flush floor duct

R.OPERATOR

TOILET

Revolution ACTs CT-A282944-FIN-XX.DWG 1:40 Rev A Structural - Electrical Layout 03/12


ANCHORING/LOADING DISTRIBUTION TO THE FLOOR FLOOR REQUIREMENTS
GE SUPPLIED GANTRY ANCHORS (5479997) GE SUPPLIED TABLE ANCHORS (5479996)
1238
[48.7 in] Anchor bolt
1088 Anchor washer
[42.8 in]
Leveling screw
861 Adjuster lock ring 25 mm after proper torque Anchor bolt
[33.9 in] Gantry Anchor nut
759 stationary base

61 mm
Anchor washer

Max
[29.9 in] Leveling pad Table base
15-17 mm
705
[27.8 in]

thick concrete
Min 102 mm

80 mm
80 mm

95 mm
95 mm
533
[21 in]
479 12 mm
[18.9 in]
3
377 NOTES: NOTES:
[14.8 in] · Torque anchor to 50 Nm · Torque anchor to 50 Nm
3B 150
[5.9 in]
FINISHED FLOOR REQUIREMENTS
· Installation requires a finish floor in the scan and control rooms
[14.7 in]

Gantry · The floor surface in the scan room directly under the gantry and table must be level.
373
[20.5 in]

830 kg · The floor levelness tolerance of the floor surface that the gantry and table will rest on is 6 mm over a 3000 mm distance.
520

639 · Shims should not be used to compensate for a floor that does not meet this requirement.

[10.5 in]
[25.2 in] [1829.8 lbs]
1 · Eight or more floor covering openings that are 102 mm in diameter are made to ensure the table and gantry rest on a solid surface. These

267
[5.8 in]
[37.4 in]
[39.8 in]

floor penetrations can be sealed if required.


147
950
1010

· The distance from central line of anchor to edge of concrete basement of Gantry/table should not be less than 155 mm.
· These requirements apply to all installation types.
[59.9 in]
1521
[63.6 in]

4 NOT TO SCALE
1616

Up/Down Table
520 kg [1146 lbs]
including 180 kg TYPICAL CABLE MANAGEMENT
[2.3 in]

[396 lbs] patient


59

FLUSH FLOOR DUCT VERTICAL DUCT ON WALL


[1.8 in]
47

212
[8.3 in]

5
Waterproof joint removable cover Dividers as required Removable coverplate
Dividers as required per local code
6 per local code

(1) Scan plane


(2) Longitudinal axis
(3) Cable inlet area (700x175 mm [28x7 in])
(3B) Alternative cable inlet area
2
(4) 8 Gantry anchoring points
(5) 8 Table anchoring points
(6) 2 level areas
Center of gravity
Main anchoring point
Backup anchoring point
Remove flooring
SCALE 1:20 NOT TO SCALE

Revolution ACTs CT-A282944-FIN-XX.DWG Rev A Floor Structural Details 04/12


RADIATION PROTECTION LAYOUT

SHIELDING REQUIREMENTS SCALING

6946 mAs
CHANGED PARAMETER MULTIPLICATION FACTOR
new mAs/100
80 kV 0.24
100 kV 0.45
120 kV 0.71
140 kV 1.00
1.25 mm aperture 0.09

1.04
5 mm aperture 0.34

1.65
10 mm aperture 0.56

2.62
15 mm aperture

4.15
0.81

6.57
10.4
20 mm aperture 1.00

2
SHIELDING REQUIREMENTS:

10.4
6.57
4.15

2
2.62
Engage a qualified radiological health physicist to review your scan room shielding

1.65
requirements, taking into consideration:
1.04

· Scatter radiation levels within the scanning room


· Equipment placement.
· Weekly projected work-loads (number of patients/day technique (kvp*ma))
5799

· Materials used for construction of walls, floors, ceiling, doors, and windows.
· Activities in surrounding scan room areas.
· Equipment in surrounding scan room areas (e.g., film developer, film storage)
· Room size and equipment placement within the room relative to room size.

3172 The Illustrations on this page depict measured radiation levels within the scanning room,
while scanning a 32 cm CTDI phantom and using a large filter, with the technique shown. Use
the mAs, kV and aperture scaling factors in the table shown here to adjust exposure levels to
the scan technique used at the site.

NOTE: Actual measurements can vary. Expected deviations equals ±15%, expect for the 5 mA
and 1 mm techniques, where variations may be greater (up to a factor of 2), due to the
inherent deviation in small values. The maximum deviation anticipated for tube output
equals ±40%.

R.OPERATOR

TOILET

Revolution ACTs CT-A282944-FIN-XX.DWG 1:40 Rev A Radiation Protection Layout 05/12


RADIATION SCATTER - HEAD PHANTOM
NOTE: 140 kV
100 mAs/scan
1 sec
16 x 1.25mm 0 1 2 3
-3 -2 -1
-2.5 -1.5 -0.5 0.5 1.5 2.5

0.26 3
0.52 2.5
2
1.04
1.5 1.5
0.17 0.33 0.66 1.31 2.08
1 1
4.15
4.15 0.5 0.5
6.57
0 0
-0.5 -0.5
-1
-3 -2 -1 0 1 2 3
-2.5 -1.5 -0.5 0.5 1.5 2.5 -1.5
-2
-2.5
-3
Elevation Plan View

DETAIL NOT TO SCALE

RADIATION SCATTER - BODY PHANTOM


NOTE: 140 kV
100 mAs/scan
1 sec
16 x 1.25mm -3 -2 -1 0 1 2 3
-2.5 -1.5 -0.5 0.5 1.5 2.5

1.04 3
2.5
1.65
6.57 2
2.62 10.42
1.5 1.5
1.04 2.62 4.15
1.31 4.15 1 1
10.42
0.5 0.5
0 0
-0.5 -0.5
-1
-3 -2 -1 0 1 2 3
-2.5 -1.5 -0.5 0.5 1.5 2.5 -1.5
-2
-2.5
-3
Elevation Plan View

DETAIL NOT TO SCALE

Revolution ACTs CT-A282944-FIN-XX.DWG 1:40 Rev A Radiation Protection Details 06/12


POWER REQUIREMENTS POWER DISTRIBUTION

3 PHASES+G For Main Supply (3 phases) Feeder and


POWER SUPPLY 200/220/240/380/400/420/440/460/480 V ± 10% Ground wire size Refer to Table2
FREQUENCIES 50/60Hz ± 1Hz
SEO1 (1) Cable SUPPLIED BY CUSTOMER
MAXIMUM POWER DEMAND 40 kVA Emergency OFF
(Control room) 24 V Cable SUPPLIED BY GE
AVERAGE (CONTINUOUS) POWER DEMAND 6.3 kVA
Equipment SUPPLIED BY
POWER FACTOR 0.85
Emergency OFF SEO2 (1) CUSTOMER
(Exam room) 24 V Equipment SUPPLIED BY GE
If applicable
·
·
Power supply should come into a power distribution box (PDB) containing the protective units and controls.
The section of the supply cable should be calculated in accordance with its length and the maximum Emergency OFF SEO3 (1)
MDP MDP Main Disconnect Panel
PDU Power Distribution Unit
(Technical room) 24 V Refer to Table1 SEO Emergency OFF Button latching
permissible voltage drops. If applicable
· There must be discrimination between supply cable protective device at the beginning of the installation twist-to release style with two
(main low-voltage transformer side) and the protective devices in the PDB. Remote ON/OFF Y normally closed (NC) contacts
(2)
(Control room) 24 V Y System Remote Control with
If applicable "ON" and "OFF" buttons
SUPPLY CHARACTERISTICS
· Power input must be separate from any others which may generate transients (elevators, air conditioning, Table1:
radiology rooms equipped with high speed film changers...).
· All equipment (lighting, power outlets, etc...) installed with GE system components must be powered PDU Recommended minimum
separately. customer supplied Main
For Scan Room
· Phase imbalance 2% maximum.
Warning Light and Disconnect Panel (MDP) rating
· Transients must be less than 1500V peak. (on a 400V line)
Door Interlock Power/Voltage 40 kVA
For Sub-Feeder and Ground
Connections Detail 200, 220, 240V 115 A
GROUND SYSTEM wire size refer to Table2 (3)
refer to the next 380, 400 V 75 A
· System of equipotential grounding. page
· Equipotential: The equipotential link will be by means of an equipotential bar. This equipotential bar should 420, 440 V 70 A
be connected to the protective earth conductors in the ducts of the non GE cableways and to additional 460, 480 V 60 A
equipotential connections linking up all the conducting units in the rooms where GE system units are located.

CABLES Table2:
· Power and cable installation must comply with the distribution diagram. Feeder Table - 40 kVA
· All cables must be isolated and flexible, cable color codes must comply with standards for electrical The information below assumes the use of copper wire, rated 75 C and run in steel conduit. All ampacity is determined in accordance with the
installation. National Electrical Code (NFPA 70), Table 310-16 (2002). The ampacity of the circuit protection device listed above determines the minimum
· The cables from signaling and remote control (Y, SEO, L...) will go to PDB with a pigtail length of 1.5m, and will feeder size, except where total source regulation limits require a larger size.
be connected during installation. Each conductor will be identified and isolated (screw connector). Feeder length from Power Minimum Wire Size, AWG or MCM (mm²)/VAC
Substation to MDP - ft (m) 200 VAC 220 VAC 240 VAC 380 VAC 400 VAC 420 VAC 440 VAC 460 VAC 480 VAC
CABLEWAYS 50 (15) 2 (35) 3 (30) 3 (30) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
The general rules for laying cableways should meet the conditions laid down in current standards and regulations, 100 (30) 2/0 (70) 1/0 (55) 1/0 (55) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
with regard to:
150 (46) 5/0 (125) 3/0 (85) 3/0 (85) 3 (30) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
· Protecting cables against water (cableways should be waterproof).
· Protecting cables against abnormal temperatures (proximity to heating pipes or ducts). 200 (61) 6/0 (170) 5/0 (125) 4/0 (100) 3 (30) 3 (30) 3 (30) 3 (30) 4 (22) 4 (22)
· Protecting cables against temperature shocks. 250 (76) 6/0 (170) 6/0 (170) 5/0 (125) 1 (45) 2 (35) 2 (35) 3 (30) 3 (30) 3 (30)
· Replacing cables (cableways should be large enough for cables to be replaced). 300 (91) 7/0 (215) 6/0 (170) 6/0 (170) 1 (45) 1 (45) 1 (45) 2 (35) 2 (35) 3 (30)
· Metal cableways should be grounded. 350 (107) 8/0 (275) 7/0 (215) 6/0 (170) 1/0 (55) 1/0 (55) 1 (45) 1 (45) 1 (45) 2 (35)
400 (122) 8/0 (275) 8/0 (275) 8/0 (275) 2/0 (70) 1/0 (55) 1/0 (55) 1 (45) 1 (45) 1 (45)
Sub-Feeder length from MDP to
PDU - ft (m)
32 (9.7536) 2 (35) 3 (30) 3 (30) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
Grounding
Run a dedicated 1/0 [55 mm²] or larger insulated copper ground wire from the power source to the MDP and from MDP to the PDU. Run the
ground wire in the same raceway with the three-phase wires.

Notes :
(1) Wire size: 2x2mm² [14AWG] and 1x2mm² [14AWG] GND
(2) Wire size: 6x2mm² [14AWG] and 1x2mm² [14AWG] GND

Revolution ACTs CT-A282944-FIN-XX.DWG Rev A Power Requirements - Power Distribution 07/12


TEMPERATURE AND HUMIDITY SPECIFICATIONS SCAN ROOM WARNING LIGHT AND DOOR INTERLOCK
Facility Input Power (3)
IN-USE CONDITIONS L N
Power TS6
EXAM ROOM CONTROL ROOM TECHNICAL ROOM
Distribution 1
(1)
Min Recommended Max Min Recommended Max Min Recommended Max
Temperature Unit (1)
18°C 22°C 26°C 18°C 22°C 26°C 18°C 22°C 26°C 2
(PDU)
Temperature gradient ≤ 3°C/h ≤ 3°C/h ≤ 3°C/h 3
(1)
(1) X-RAY LIGHT
Relative humidity (1) 30% to 60% 30% to 60% 30% to 60% 4
Humidity gradient ≤ 5%/h ≤ 5%/h ≤ 5%/h 5
(1)
(1) LIGHTING CONTROL RELAY
6
STORAGE CONDITIONS (1)
7
Temperature 0°C to +30°C READY LIGHT
8
(1)
Temperature gradient ≤ 3°C/h
9
(1)
Relative humidity (1) < 70%
(1) DOOR SWITCH (2)
Humidity gradient ≤ 5%/h 10

Storage longer than 6 months is not recommended. 11/12 JUMPER, FOR N.O. 11
(1) Non-condensing CONTACT OF DOOR SWITCH
12
12/13 JUMPER, FOR N.C.
CONTACT OF DOOR SWITCH 13
AIR RENEWAL
According to local standards.

Cable SUPPLIED BY CUSTOMER


Notes :
(1) Wire size: 2mm² [14 AWG] at 24V Cable SUPPLIED BY GE
(2) Door Interlock circuit is jumpered out if a door switch is not provided. Equipment SUPPLIED BY CUSTOMER
NOTE Equipment SUPPLIED BY GE
In case of using air conditioning systems that have a risk of water leakage it is recommended not to install it above electric equipment or to (3) Grounding not shown on the detail, but must comply with local codes.
take measures to protect the equipment from dropping water. TS6 Terminal Block 6

HEAT DISSIPATION

MAX HEAT DISSIPATION


ROOM DESCRIPTION
kW BTU
Gantry 3.5 11945
Exam Room Up/down Table 0.2 700
TOTAL 3.7 12645

Power Distribution Unit (PDU) 0.7 2389


Exam/Technical Room*
TOTAL 0.7 2389

Operator Console (Z4G4) 0.81 2746


Control Room AW Workstation 1.0 3412
TOTAL 1.81 6158
*Technical Room is not mandatory, the placements of these elements are recommended in the Exam Room.

Revolution ACTs CT-A282944-FIN-XX.DWG Rev A HVAC - Warning Light 08/12


ENVIRONMENT INTERCONNECTIONS
ALTITUDE TECHNICAL ROOM EXAM ROOM CONTROL ROOM
· The system shall meet all functional and performance specifications when placed in a room that is at an 19.50m
elevation of -150 m to 3000 m [-492 ft to 9,843 ft] above sea level. [64']
Operator Partial UPS
Console (Option)
MAGNETIC FIELD SPECIFICATIONS 13.50m or 22.90m 4.50m
[44.2' or 75'] [14.7']
· Limit the magnetic interference to guarantee specified imaging performance. 11.50m or 22.90m
[37.7' or 75'] 3.00m
GANTRY:
[4.9']
· Ambient static magnetic fields less than 1 Gauss.
5.97m or 16.80m
· Ambient AC magnetic fields less than 0.01 Gauss peak. PDU
[20' or 55'] Gantry

OPERATOR CONSOLE:
· Ambient static magnetic fields less than 10 Gauss. Customer supply
AVIMOS
MAXIMUM GANTRY AUDIBLE NOISE LEVEL Console
PDB Table RCK (Option)
(Option)
· The maximum ambient noise level is produced by the gantry during a CT scan acquisition. It is less than Orderable from GE
70dBA when measured at a distance of one meter from the nearest gantry surface, in any direction. AVIMOS
Camera (3x) 25 m
MAXIMUM CONSOLE AUDIBLE NOISE LEVEL (Option) [82']
30 m
· Maximum Console Audible Noise Level The maximum ambient noise levels is less than or equal to 56dBA [98']
when measured 1m up and 1m away from the console at an ambient temperature of 26°C.

CONNECTIVITY REQUIREMENTS

Broadband Connections are necessary during the installation process and going forward to ensure full support
from the Engineering Teams for the customers system. Maximum performance and availability for the customers
system is maintained and closely monitored during the lifetime of the system.

Proactive and reactive maintenance is available utilizing the wide range of digital tools using the connectivity
solutions listed below:

· Site-to-Site VPN/GE Solution


· Site-to-Site VPN/Customer Solution
· Connection through Dedicated Service Network
· Internet Access - connectivity for InSite 2.0

The requirements for these connectivity solutions are explained in the broadband solutions catalogue (separate
document).

Revolution ACTs CT-A282944-FIN-XX.DWG Rev A Environment - Interconnections 09/12


GANTRY WITH TABLE POWER DISTRIBUTION UNIT (PDU)
SIDE VIEW FRONT VIEW
921
1783 TOP VIEW FRONT VIEW SIDE VIEW

[5.9 in]
120 367

150

[5.5 in]
140
Rear Front 389 389

1741
20 [15.3 in] [15.3 in]

[21.7 in]
550
895

[8.7 in]
840
Scan

220
267.2 235
Centerline [9.3 in]

[41.8 in]
1062
520 Anchorage 639 599 Anchorage

[5.1 in]
300 1213 2448

[19.4 in]
350

129
494
[13.8 in]
554
700

[35.4 in]
[27.6 in]

900
Service Area

Minimum 900 360 150


[35.4 in] [14.2 in] [5.9 in]
air flow
Seismic mounting brackets
clearance

900
Scan Weight: 10 kg [22 lbs]
Centerline
Center of Gravity
SCALE 1:50 2747 441 Center of Gravity SCALE 1:20 Indicates air flow (Convection)

AURORA SWS TABLE AND CONSOLE MAIN DISCONNECT PANEL


TOP VIEW FRONT VIEW SIDE VIEW
FRONT VIEW SIDE VIEW FRONT VIEW 0
424 Ø1 in]
4x .39
[16.69 in] 0

250
386 [9.85 in]
[15 in]
[33 in]
222 76
850
[29 in]

[3 in]

[24.59 in]
[8.75 in]
740

[22.5 in]
625

572
[20 in]
507.5
[18 in]
445

[11 in]
277.5

[12.25 in]
311
TOP VIEW
650
[26 in]
368 178
[14.5 in] [7.02 in]
[30 in]

1300
750

[33 in]
850

[51 in]

169
Table weight: 40 kg [88 lbs] [7 in] Center of gravity
SCALE 1:20 600
SCALE 1:10
[24 in]

Revolution ACTs CT-A282944-FIN-XX.DWG Rev A Equipment Dimensions 10/12


DELIVERY

THE CUSTOMER/CONTRACTOR SHOULD:


· Provide an area adjacent to the installation site for delivery and unloading of the GE equipment.
· Ensure that the dimensions of all doors, corridors, ceiling heights are sufficient to accommodate the
movement of GE equipment from the delivery area into the definitive installation room.
· Ensure that access routes for equipment will accommodate the weights of the equipment and any
transportation, lifting and rigging equipment.
· Ensure that all necessary arrangements for stopping and unloading on public or private property not
belonging to the customer have been made.

DIMENSIONS OF DELIVERY WITH DOLLY TRANSPORT EQUIPMENT


EQUIPMENT DIMENSIONS WEIGHT
LENGTH 2363 mm 93.1 in
GANTRY WIDTH 921 mm 36.3 in 1125 kg 2480 lbs
HEIGHT 1881 mm 74 in
LENGTH 2137.5 mm 84.2 in
UP/DOWN TABLE WIDTH 820 mm 32.3 in 372 kg 821 lbs
HEIGHT 1038 mm 40.8 in

GANTRY DELIVERY

W= 2363
[93 in]

L= 921
[36.3 in]
[74 in]
H= 1881

· The gantry is shipped on a dolly equipped with elevating casters (normal shipping configuration).
NOT TO SCALE

Revolution ACTs CT-A282944-FIN-XX.DWG Rev A Delivery 11/12


DISCLAIMER GLOBAL SITE READINESS CHECKLIST (DI)
DOC1809666 Rev. 7
GENERAL SPECIFICATIONS Site Ready Checks at Installation
EHS Site Requirements
· GE is not responsible for the installation of developers and associated equipment, lighting, cassette trays and Overall access route to the scan room free from obstruction / high hazards.
protective screens or derivatives not mentioned in the order.
Enough space to store tools, equipment, parts, install waste and the general area free from obstruction and trip hazards.
· The final study contains recommendations for the location of GE equipment and associated devices, electrical
wiring and room arrangements. When preparing the study, every effort has been made to consider every Enough necessary facilities for the GE employees available.
aspect of the actual equipment expected to be installed. No 3rd parties working in the area that may affect the safety of the installation activity.
· The layout of the equipment offered by GE, the dimensions given for the premises, the details provided for Area free from any chemical, gas, dust, welding fume exposure and has painting been completed and dry.
the pre-installation work and electrical power supply are given according to the information noted during All emergency routes identified, signed and clear from obstruction.
on-site study and the wishes expressed by the customer. Accessible single source lockable panel that LOTO can be applied to for GE equipment installation (MDP and/or PDU).
· The room dimensions used to create the equipment layout may originate from a previous layout and may not There are no other conditions or hazards that you have observed or have been made aware of by the customer or contractors on site.
be accurate as they may not have been verified on site. GE cannot take any responsibility for errors due to
Required for Mechanical Install start
lack of information.
· Dimensions apply to finished surfaces of the room. Room dimensions, including ceiling height, for all Exam, Equipment/Technical & Control rooms meets GE specifications.
· Actual configuration may differ from options presented in some typical views or tables. Ceiling support structure, if indicated on the GE drawing, is in the correct location and at the correct height according to the Original
· If this set of final drawings has been approved by the customer, any subsequent modification of the site must Equipment Manufacturer specifications.
be subject to further investigation by GE about the feasibility of installing the equipment. Any reservations Levelness and spacing has been measured, and is ready for the installation of any GE supplied components.
must be noted. Overhead support Structure (unistrut) has been confirmed with customer/contractor to meet required GE provided criteria.
· The equipment layout indicates the placement and interconnection of the indicated equipment components. Finished ceiling is installed. If applicable ceiling tiles installed per PMI discretion.
There may be local requirements that could impact the placement of these components. It remains the
Floor levelness/flatness is measured and within tolerance, and there are no visible defects per GEHC specifications.
customer's responsibility to ensure that the site and final equipment placement complies with all applicable
local requirements. Entry door threshold meets PIM requirement.
· All work required to install GE equipment must be carried out in compliance with the building regulations and Rooms that will contain equipment, including staging areas if applicable, are construction debris free. Precautions must be taken to prevent
the safety standards of legal force in the country concerned. debris from entering rooms containing equipment.
· These drawings are not to be used for actual construction purposes. The company cannot take responsibility Cable ways (floor/wall/ceiling/Access Flooring) are available for installation of GE cables are of correct length and diameter.
for any damage resulting therefrom.
Cable ways routes per GE Final drawings and cable access openings areas installed at a time determined by GEHC PM. Surface floor duct can
be installed at time of system installation.
CUSTOMER RESPONSIBILITIES
Adequate room illumination installed and working.
· It is the responsibility of the customer to prepare the site in accordance with the specifications stated in the Customer supplied countertops where GE equipment will be installed are in place.
final study. A detailed site readiness checklist is provided by GE. It is the responsibility of the customer to Required for Calibration Start
ensure all requirements are fulfilled and that the site conforms to all specifications defined in the checklist and HVAC systems Installed, and the site meets minimum environmental operational system requirements.
final study. The GE Project Manager of Installation (PMI) will work in cooperation with the customer to follow System power & grounding (PDB/MDP) is available as per GE specifications.
up and ensure that actions in the checklist are complete, and if necessary, will aid in the rescheduling of the System power & grounding (PDB/MDP) is installed at point of final connection and ready to use. Lock Out Tag Out is available.
delivery and installation date.
PMI to confirm all feeder wires and breaker are size appropriately. EPO installed if needed.
· Prior to installation, a structrual engineer of record must ensure that the floor and ceiling is designed in such a
PMI to confirm with electrician all power and signal cables are well terminated ensuring there are no loose connections.
way that the loads of the installed system can be securely borne and transferred. The layout of additional
structural elements, dimensioning and the selection of appropriate installation methods are the sole Network outlets installed.
responsibility of the structural engineer. Execution of load bearing structures supporting equipment on the Computer network available and working.
ceiling, floor or walls are the customer's responsibility. Lead doors and windows complete or scheduled to be installed. If applicable, radiation protection (shielding) finished & radioprotection
regulatory approval for installation obtained.
RADIO-PROTECTION Note: The details shown here are only an extract from DOC1809666. For the complete document please contact your PMI.

· Suitable radiological protection must be determined by a qualified radiological physicist in conformation with
local regulations. GE does not take responsibility for the specification or provision of radio-protection.

THE UNDERSIGNED, HEREBY CERTIFIES THAT I HAVE READ AND APPROVED THE PLANS IN THIS DOCUMENT.

DATE NAME SIGNATURE

Revolution ACTs CT-A282944-FIN-XX.DWG Rev A Disclaimer - Site Readiness 12/12

You might also like