Professional Documents
Culture Documents
januar~· 1991
• CON TEN T S
I .. , .
-SECTION 1 - PROCEDURE 1
1.1 DEFINITIONS . • . . .. ....... 1
I 1.2
1.3
APPLICATION PROCEDURE
• ROAD CLOSURES . • • . . . .
..•.. 2
2
1.4 PROGRAMME OF WORK . . . 2
I 1.5
1.6
UNDERGROUND CHAMBERS . .
BRIDGES AND OTHER HIGHWAY STRUCTURES .
. .. 3
3
1.7 ROAD MARKINGS . ' .. . . . . . ... 3
I 1.8
1.9
1.10
REINSTATEMENT . .. . . . . • .
UNSATISFACTORY WORK
TRAFFIC SIGNALS
. • • . .
. • • • . . . . . ..
3
4
4
1.11 NEW ROAD SURFACES: . . • • 4
I
SECTION 2 - GENERAL REQUIREMENTS 5
I 2.1
2.2
2.3
CONTROL OF TRAFFIC
TEMPORARY ROAD ~IGNS
FENCING TO TRENCHES ..•.
5
5
5
2.4 METHOD OF WORKING 5
I 2.5
2.6
SERVICES . . . . . . . .
DAMAGE TO EXISTING ROAD SURFACES
.
.
5
6
2.7 BACKFILLING TRENCHES . . . . 6
I 2.8
2.9
DEBR IS. • . • . . . . . . . . .
SUB-CONTRACTORS . .
.
.
7
7
2.10 MAINTENANCE PERIOD . . . 7
SECTION 3 - EARTHWORKS 9
3.1
3.2
· ·
REMOVAL OF BITUMINOUS MATERIAL
PROTECTION OF EXCAVATIONS
9
9
3.3 EXCAVATION
········ · · ·· 9
3.4
3.5
MAXIMUM DRY DENSITY
BEDDING AND SURROUND.·.·. · . ·. 9
10
3.6 BACKFILLING
·· · · · · · 10
3.7
3.8
SUB-GRADE
· · · · · · ·· ··
SUB-BASE - MINOR ROADS ····
· · · · · ·
10
11
SUB-BASE - MAJOR ROADS
3.9
· · ·· ·· · · · · · 12
3.10 RECTIFICATION OF SUB-BASE
·· 12
3.11 UNSATISFACTORY COMPACTION
······ 12
. . . . · · · · ·· ·· ·· ··
· · · · ····
5.2 REMOVAL
5.3 KERBS
5.4 TEMPORARY REINSTATEMENT
·· · · ····
5.5 PERMANENT REINSTATEMENT
·· . .
5.6 CONCRETE FOUNDATION
· · ·· · ·· ·
5.7 UNPAVED AREAS · · · · · · ·· ·
SECTION 6 - COMPLIANCE TESTING 25
6.1 TOLERANCES • . • • • . . • 25
6.2 TESTING OF MATERIALS . . • 26
6.3 MATERIALS SOURCE APPROVAL 26
SECTION 7 - REINSTATEMENT 27
7.1
7.2
PHASED REINSTATEMENT · ···· ··
CEO REQUIREMENTS FOR REINSTATEMENT
27
27
7.3 MAINTENANCE PERIOD
· ·· ·· · 27
7.4 RECTIFICATION. · · · · ·· ·· · ..
, 28
7.5 FINAL INSPECTION AND ADOPTION
··· · 28
APPENDIX 4 - DRAWINGS
REINSTATEMENT OF ROAD OPENINGS
PHASE 1 MAJOR ROADS - ROAD CROSSINGS
PHASE 2 MAJOR ROADS - ROAD CROSSINGS
PHASE 1 MAJOR ROADS - TRENCH RUNS ALONG CARRIAGEWAY
PHASE 2 MAJOR ROADS - TRENCH RUNS ALONG CARRIAGEWAY
MINOR ROADS - ROAD CROSSINGS
PHASES 1 & 2 MINOR ROADS - TRENCH RUNS ALONG CARRIAGEWAY
PERMANENT REINSTATEMENT OF PAVED AREAS
MAJOR ROADS - REQUIREMENTS FOR SITING ROADWORKS SIGNS
MINOR ROADS - REQUIREMENTS FOR SITING ROADWORKS SIGNS
SECTION 1 PROCEDURE
1.1 DEFINITIONS
•
•
J ~.., '\"~~ \
1.2 APPLICATION PROCEDURE ~; P. o. ~ :"~: ,,,p \
I
- 2
-.~
'==========='-=.::.:.'' - ..-===
••. '
1. 4.2
•
effect on traffic flows.
I
1. 4.3 No .trench shall be left open for a period exceeding
I one week, unless prior written agreement has been
•~
I
received from the Road Engineer and the Traffic
Police. The Contractor shall Bubmit his programme
of work to achieve this seven day or other approved
reinstatement cycle.
•
1.5 UNDERGROUND CHAMBERS
•I
siting, depth and accommodation, together with the
method of executing the works must be agreed with
the Road Engineer and no work shall be undertaken
I without prior approval.
.,
I 1.7 ROAD MARKINGS
I
I
l
Where trenchwork removes surface road markings such
as white lines and catseyes they shall be replaced
with similar materials by the Contractor as soon as
possible after completion of the reinstatement.
1.8 REINSTATEMENT
I 1. 8.1 The Highway Maintenance Section shall be notified in
advance of any works 1n the carriageway and they
I will inform the Contractor of the full extent of the
• '
1. 8.2
remedial works required .
I 3
I
~.~ - .
• . .,
1. 8.4 The Specification shall be implemented to ensure
satisfactory reinstatement of the highway. Highwa
q,"c····
Qj
'~bR
DOIiA
" ' ..:.'~
~ P. O. BOx 2:1
...
~
. r,
-.,.\
~
0
'
I
•I SECTION 2
REQUIREMENTS
GENERAL
I 2.5 SERVICES
I
~-----------------------
• 2.5 . ~ERVICES . (Cont'd)
6
I
I ' 2.7
2.7.4
, BACKFILLING TRENCHES (Cont'd)
-
2.7.5 Note that this Clause also applies to Bituminous
Materials.
- 2. B
2. B • 1
DEBRIS
I 2.9 SUB-CONTRACTORS
I
7
I -- -- . -.- -----~
• 2.10 MAINTENANCE PERIOD (Cont'd)
II 2.11 DEFINITIONS
o 'Subgrade' - The compacted fill beneath the
I pavement and shoulders but not including the
sub-base.
I
I
SECTION 3 EAR.THWOR.KS
I , f
'.
3.1 REMOVAL OF BITUMINOUS MATERIAL
I 3.1.1 Revolving wheel cutters attached to mechanical I
I 3.3 EXCAVATION
I Test 13.
I
I 9
I
• 3.5 BEDDING AND SURROUND
I . ' ~:r.5.1 The type and method of spreading and placing bedding
and surround materials shall be in accordance with
the requirements of the Authority.
I 3.5.2 The bedding and surround material shall be compacted
to a density of at least 95% of the maximum dry
I density of the material. Layer thickness shall not
exceed 150 mm and hand ramming or approved :
compaction plant shall be used to ensure compaction
I and that the material is free from any cavities.
3.6 BACKFILLING
II 3.6.1 Any pockets of soft soil or loose rock in the bottom
of pits and trenches shall be removed and the
II resulting cavities and any large fissures filled·
with suitable material compacted in accordance with
Clause 3.5.
I 3.6.2 Selected excavated material shall be the most
suitable portions of excavated material free from
matter harmful to other materials in the Works,
I which is capable of being compacted in the manner
specified to form stable fill.
I 3.7 SUB-GRADE
I 10
I
• 3.7.3 The soaked value of the California Bearing Ratio a
/~~ , v· s
S><-
<II
.~
po, 6DX 217
DOHA.!.t
'0
I
I
I 11
I
I
3.9 SUB-BASE - MAJOR ROADS
II, . 3.9.1 The material to be used shall be Marshall Design
I
I
i
II 3.9.2 Prime coat in accordance with Clause 4.2 shall be
applied to the sub-grade prior to laying Marshall
Design Mix Type MOl.
I
I
I
II
II 12
I - - - - ---- . -- - -
•I , SECTION 4
TREATMENT
BITUMINOUS
I
I 4.1
4 .1. 1
CLEAN SURFACES i
I
Immediately prior to the application of a prime or
tack coat all loose and objectionable material 'shall
I be removed from the surface to be treated by brushes
or compressed air. ;
i
I 4.1.2 Adjacent surfaces and kerbing shall be protected
during spraying operations •
•I 4.2
4 .2.. 1
PRIME COAT
The material to be used for prime coat shall consist
of penetration grade 60/70 bitumen, cut back t~ the
following proportions by volume, with kerosene'
solvent to provide a homogeneous liquld:-
I 60/70 Bitumen 60\
Kerosene 40%
13
/ ; r-'\_~,.' ..>'
( J ,' -(1
4.2.7 The Road Engineer may order at no extra cost, I~ ~
add! tional trial sections to be prepared, conf 1.ti${ng;; ~1 7 ~
satisfactory spraying techniques and rate of -;'6 (,,,A,, ~
application.
=
I
vehicles, or contamination of the bituminous
materials during the laying and compaction
procedures.
•I
I
4.2.9 The application of prime coat shall
when the temperature is below 15°C,
directed by the Road Engineer. The
prime and tack coat materials shall
during rainy or turbulent weather.
not be perm:itted
unless otherwise
spraying of both
not be permitted
•
I 4.3.1 The material to be used for tack coat shall be
cationic bitumen emulsion complying with BS 434,
Part 1, Class KI-40 diluted in accordance with the
manufacturer's recommendation and applied at a rate
of 0.33 to 0.45 litres per square metre by a
mechanical spraying tank or pressure hand spraying
equipment onto the bituminous surfaces.
•
4.3.-3 The Contractor shall be responsible for the
application of a further tack coat should the
existin~ surface become contaminated before the
subsequent course is laid.
•
I
I
4.3.4 Before any bituminous course is laid on another
bituminous course or surfacing, the surface shall be
•
swept clean of loose material and a tack coat shall
be applied.
•
sufficiently strong to blow sand or dust onto the
exposed treated surfaces.
•
14
4.5.2 Binder
I 4.5.3 Aggregates
I
I
I 15
I
, ~
d. The total loss factor using the 10 minute
immersed rotational test shall not exceed 10
for wearing. single or friction course layers
and all other running surfaces, and 20% for
I base course layers. The test shall be carried
out in accordance with the procedure
established by the CED Materials Testing
I Laboratory.
I b.
fractured faces.
16
4 .5. 7 Selection of Job Mix - Marshall Design Mixes.
....
: C;...
a. Before surfacing begins the Contractor shall 0
'submit for approval by the Road Engineer his ~-
proposed grading of the combined aggregate :for
. each type of asphalt to be used in the works.
I
b. The grading curve of the aggregates shall not
vary from the low limit on the one size of
sieve to the high limit on adjacent sieves :or
vice versa; the particle-size distribution of
the aggregates shall give a smooth curve I
throughout the whole range of sieve sizes.
17
I
iii. As a result of the preliminary trials th
I Contractor and the Road Engineer shall ~
agree a provisional "Job Standard Mixture 0
for each mixture required. If the ~--~
I
I 18
I
• 4.6 TYPE OF CONSTRUCTION
I '. 4.6. 1 The Construction shall conform to the cross-sections
shown 1n Appendix 3 relating to Minor and Major
I r9ads as appropriate.
I 4 .7 TRANSPORTATION
, 4.7.2
and shall be covered over when in transit or
awaiting tipping.
I 1SSoC.
I
I
20
• 4.10.6 The field density shall be such that of six
/ 0'
-S!V
~
/ ; Q.$
'C'
p 0 . 8010 11
g~:"AR
'r.
9
~
: \':
, ..
~
It
; .
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I 21
1
I
SECTION 5 KER.BS, PAVED
I AND UNPAVED AR.EAS
I
I 22
I
I
5.3 KERBS
I' 5.3. 1 The units shall be laid on a concrete bed and1backed
with concrete to match with existing units or if
23
5.7 UNPAVED AREAS
I 5.7. 1 The reinstatement of unpaved areas shall be in
accordance with Section 3 of the Specification and
the material to be used shall satisfy the
I requ~rements of Clause 3.7.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I 24
I
• SECTION 6 COMPLIANCE TESTIN
i· 6.1 TOLERANCES
25
I
pavement is less than 300 rn, the measurements shall
II • r be taken in 75 m lengths .
•..
7.1 PHASED REINSTATEMENT
27
7.4 RECTIFICATION
. . All materials which do not comply with the
specif~cation shall be removed and relaid.
28
I
I
I
I
I
I
I
I
I
I
I
I 29
I
A.PPENDIX :1.
•
various departments of ~~bh ~~thority .
NOTE
• 2.
The accompanying drawings should have at least one set of
grid co-ordinates clearly marked on them to assist in the
location of the appropriate record drawings.
NOTE
30
, ,
31
•I· __ '0:
0
FORM !I.e) I
;:::Ja!~~ .
INIT. JLfJ'. STATE OF QATAR
- L . Lln L.-.J.1,
REPLY REP. ~I J.-) I • JL:.I IY-..r- ~ r - ,
i IN aoxES 0 OEl£TE DATA NOT API'L..ICAIIL£
Road Opening Application
i TO
IOU)
.r-'':'~~
.;.,~')!J.>I,) 4..oj~ ~I.;., ... ,tlal!~
1,-01' ;......,J .).)
.......... u£
;';"'1 '-oJ,,'.)
J"...u ~
("lJl .0.... ....
<-....U JI...-:.~IJ .. t:.-W i}j, jl
",VIlION ... 1.... dT ..... .., INDUSTaV ANU P'\.IlJ.tC ...u_KJ
NY"""'"
i .;rl~
"UI>O< DUr.
C!.Il:.1I.1 ~;hl
i}.1 C-uL...:..lI i }~I
Pl.0J1CT Den.
,i~ ~I}~I
~"Wl..o DkJI'T
L..1J)J "..ua .:.r:JI i
"'Nn, • ., Ot' ,",U",.Clp"'l. A,..U .,.c.:.lltC\J1.1U,AL At
,I JJ
,-.1.' ..5
i
II..Jt",NIri(.;, .4NJJ 11 EL.TlICnT
'.OJ... ·r t>£n.
"4TUN~O"'S
PUr. N~TWO ... ' DUT. ",... mav OF I.1.K"TLLLTTl' J.HO 'MA'U.
~,,:,,'jL..."'jj"U ~~~;..JI
fROM U·TU ~'J,)I,
----_ . .. _----
I I LJ--o
Q_O P.l ,
J ,;.,JI "'WI ~,wI' ' - jJI
•
Elsewhere
Failure 10 repl)' wllND Ihls period wiiJ be lakeD lhal your Autbority is not aCTwcd.
)( Iny difficulty Is antlclpaled with this timucale COnllJ:l above Engincor.
2. Lacalion or Worh _ _ _ __
I: 10.000 Location Plans musl accompany Ihi& application. (In Triplicate) •
.~ ~ ~'j! ~ \-, •• : '~J v~ ~.rU~?- ~u}r~_1
~UI (") ~ J ';"11 ~ t )1; -.. • !.pI Ji .!.-IU J P! (\ t) ';.!..o JL..;.\ JL;I I.f. .I- L-.....1rL.
N. 8. : For reapplication 14 d~ys nOlice i, ro:quircd berore clpiry uale or previous Ro 2
32
J bi LJjJ
State of Qatar I
Form Ro2.
To J! From
1/ IS~ U.,;........
5. We 100 NOT] intend 10 execute ~_MAJ
__O_A_.l--_M_'N_O_R--..J woOO J~' ~ t"~1 !f.,.;.{~J - •
~.JH- I LL "OO~..j.r-
... .J-'Y L!..J
I..
~ rWJI . . -=..II . (IL.....l ~ ,.
. ....,.......-
oo
r- .
6. Your Intended ¥tOties will1 NOT 1aHeet our apparatus
8. Further details 01 your In,ended WOI"k.tt are I NOT I requIred~~. I ~ I~l:A :.,.. ~1.41 ~I..i.: - ~
I
33
~LJJJ
State of Qatar
J Form RoJ
Inlt. Ral. :
From
Sarvi~e Aulhorlty
Supervisor: .... ... ... ... ........ ... ....... ... ..........=.11...-1
tlQIL
It is the duty 01 Ihe Servi~e Aulhorily
Supervisor 10 chad( the lIalldily 01 the RO 2
In boxes 0 delete data not IIpplicable Form prior 10 seeKing TraHIc Police approval.
II Is Intended 10
: Wt.n
unde~ake
I ., .
, -II
~.r-- ... 11
l.S~ IM·'iL
o J-.
loIl~w'
Service CQMectioo .:.L....i J..,.J
(Ros.) (~)
Road Sign and barriers will be aleclad 10 ..,..- ~l-JI .. L:../'i .:.IJL:.'iIJ ~I~I ~;. ....... -
Traffic Police Oepar1lT1ant requirements. . ..w-l \ .:.l,JL
A Copy 01 HMS approval Form Ro2 Is all acned. .:..L.J-.u .:.U)JI ~~ r-' '-UI.,.. ""ts .;r o..l.J'"4> ~>"
along with plans delalling wo~s. . J.-aJ1 .:,~ ~;.
* One copy 01 Approv&d Form to be returned 10 Highway Malnlenanca Saclion bolore commencing work.
34
J hi ~JJ
, ,
State of Qatar
Location: ·.. .. ... ..... .............. ........ .... ........ ... ... .. .... .. .
~
Operation: ................. ........................................ . · ........... .. ..... ...... .... ....... ... .. ..... ... .. " ~"Jh11 ja..L.l1
This notice Is to Inform that these excavations J ~).,.n~ ~~I r:. .u ~I t.~1 IoU ~~ ~~
are being carried out to execute emergency
1f:J1 Jb..e..1l ~~ .:..~~, .I~\j a':l/.t.l ~I JL!J.I t-iy.1
repairs to taully equipment In order to restore
service to consumers. · ~<I.-. .11 ..:.l.. ~1 L.e-aG • ..I~i ;,r. ~ .• ~'JI ~L,'
Road signs and barriers will be erecled to ~..u.;11 (S.r--l' <...~ 4...j~1 ~I"......J'J .:,.I J L!81 U' ~
Traffic Police Department requirements. . 01 aJI.I! .:.~ ~ ~,;. ~J--'
I Authorising Signature ... ......... .................................... ..... ......... ....... .... . ,....... .......... . .............................. .. . .................. ... """;'".ll1 ~,;.
TraHic Police Approval .............................................. .. .. ............ . ... .................................. .. . ............... .. ..... . ..u)1 u-r wi./'"
I 35
I
I
, M,inislry of Industry & Public Works
I Civil Engineering qepartment
State of Qatar
I Form AoS
I
In-situ Laboratory Testing Date of Date of
I Test Approval
1. Subgrade Compaction.
2. Sub-base Compaction.
Material: Source:
3. 150 mm dia. Cores Base Course.
4. '50 mm dia. Cores Wearing Course.
Remarks:
36
,Ministry of Industry & Public Works
Civil Engineering.Department
State of Qatar
Highway Maintenance Section
Form R09
Notice to Improve a Road Opening
To:
Regarding the following road openings :-
i
l.Dcallon: ........................................................................................................................................ ~ ............. .
II has been broughlto my attention that works in connection with Ihe above road opening are in breach
of specification. The following works are necessary to bring the road opening 10 a satisfactory standard.
I
I
I
I
I
I
I In this instance I hereby instruct you to stop all site works until remedial works have
been completed and the specification is adhered to .
I
I Please arrange for remedial works to be undertaken within ======1/
L!::II Days
I 37
I
I
TABLE 1 - STANDARDS
Part 1 Requirements
Part 1 sampling
Part 2 Testing
I Part 100
Part 101
Methods of sampling
I bollarda
38
I
-. ' ,
-
-
-II
_I
-II
APPEND.::r:X. .2
II
_I
(;
/ ---~~
~ '.)':,\ . "'. ~~
'(1
' .
/ .....c- .
I
j, f!.' .";1
.. BS . 1449
.
- . St~~~ ...I?! ~.~~ . L...~ heet and strip
Part 2
I
I
Stainless and heat resisting' steel
!~
\ 1:.
o ~
QAll>R !7l
e,
sheet and strip I
I
.
BS 1470 Wrought aluminium and aluminium alloys fbr general
enginee~lng purposes - plate, sheet and strip
BS 6088 Solid glass beads for uee with road marking compounds
and for other industrial uses
39
.,
• /.'~;;-~
c ·c·
Soundness of aggregates by use of sodium au' l~~'a 't~S~"7'0~
i· ASTM C 88
.
magnesium sulphate
<b
~
0
~~, QATAR
r
>C'j
",
iii
II
II
II
I
I
I
I
I
I
I 40
I
TABLE 2 - SPECIFICATION FOR TESTS TO BE CARRIED OUT BY
LABORATORY
A~N~~~~~'6~'I~
r.:\- P 0 . 60X'P
DOHA. -I
.
<)
~O
aATAR
.9 177
STANDARD DESCRIPTION
BS 812 PART 1
PART 2
Determination of relative densities and water absorption.
PART 3
Determination of 10\ fines value.
Determination of aggregate crushing value.
41
- ,~
.
TABLE J COMBINED AGGREGATE AND BINDER CONTENT FOR BITUMI/tp
MATERIALS - MARSHALL DESIGN MIXES ~
s ..~
p :;l L'~' 217 '?
1"-' r ::\ \~ -I
' ~" OA1 " " ,to
'~~
PERCENTAGE PASSING BY WEIGHT OF AGGREG
I . MARSHALL DESIGN MIXES
I
I
I as SIEVE
37.5 mm
65\ STONE
ROAD BASE /
20 IM\
55\ STONE
B1\SECOURSE
20 mm
50\ STONE
WEARING
I
I
14 mm
50\ STONE
r WEARING
50.0 100 - - -
I 37.5 93-100 - - -
-
I 28.0
20.0
85-100
70-90
100
90-100
100
94-100 100
I 14 .0 - 78-90 -
!
eO-l 00
3.35 - - - -
I 2.36 22-36 35-50 45-55 34-50
-I LIB
0.6
0.3
.
18-30
10-20
-
25-40
15-26
-
34-44
17-27
-
:
17-27
10-20
-
0.15 6-15 - - -
I 0.075
-
CEMENT CONTENT .. 2 , 2 % 2
2
" "
I STABILITY (MIN) 8kN 8 kN 4 kN 4 kN
I
,-
42
.J . FLOW (MAX) 6mm 6mm 5 nun
!
~IR VOIDS . 3 to 5 \ 3 to 5 \ 3 to 4 ,
I
VOIDS FILLED WITH 61-77 67-71 75-82
I BITUMEN l') .
INDICATIVE LAYER 75-150 45-55 nun 50 mm 40 mm
I
DIm
THICKNESS (Engineer
will instruct)
,
* Cement content to be inc reased to 3\ with limestone aggregate.
I
I
I
I
I
I
I
I
..
I -
I
I
I
II
I
I 43
I
• TABLE 4 - LIMITS OF PLANT MIXTURE TOLERANCES
. REQUIREMENT BASE
COURSE
WEARING
ICOURSE
I
,
Binder content ± 0.3 ± 0.3 \
"
II voids total mixture :!: 1.0 \ ± 1.0 \
1111
II
I
•III
.. _.. . _-- -------
44
, --:;==---
TABLE 5 - MINIMUM FREQUENCY OF TESTING : SUB-GRADE, SUB-BAg?~,~' 0
BASE OTHER THAN BITUMINOUS COATED MATERIAL (:,~~po. nc~ 217 ·'9
~ t"~'~ ..,
'0~,
. ~
OU':'R
('
",
I classification test
(see Table 2) 1000 600 300
I Heavy compaction
(4.5 kg rammer method) 900 750 750
BS 812
900
I Flakiness index
I
I
I
I
I
I
I
II 45
I
I c,v
0(\\ · O·S
.~
TABLE 6 - MINIMUM FREQUENCY OF TESTING : BITUMINOUS MATERIA ,.-
. ;0
""Q
po.eOX217
OOHk
QATAR
0
~
~
(:)
C
.
MIXED MATERIAL COMPACTED
TYPE-OF TEST MATERIAL
2 ' 2
m m
and
-
I Laying and rolling temperature Each load
I
I
I
I
I
I 46
I
I
TABLE 7 - TOLERANCES IN SURFACE LEVELS
I
I
I
TOLERANCE FROM MAX DE~RESSION
SURFACE DESIGNED LEVEL UNDER A: 3 METRE
STRAIGHTEDGE
I mm
!
mm
I
Formation + 15
I - 25 -
I Sub-base + 10
- 20 -
I Road base + 15
- 15 15
I
I
I
I
I
I 47
I
I
TABLE 8 - MAXIMUM PERMITTED NUMBER OF SURFACING
I . WEARING COURSE
ROAD SURFACE
I -
I
IRREGULARITY 4 mrn 7 mm
I
Length (m) 300 7S 300 7S
I
I
Hinor Roads 40 18 4 2
I Major Roads 20 9 2 1
I
I
I
I
I
I
I
I
I
I 48
I
•
i.
-I
I APPENDIX 3
I
I
I
I
I
I
I
I
I
I
I
II
_. '-
~
P.O. Box 38, Doha
Tel: 420667
•
I TRAFFIC POLICE DEPARTMENT
P.O. Box 920, Doha
Tel: 870075
•I
EMERGENCY (POLICE CONTROL)
Tel: 330000
-~ DOHA MUNICIPALITY
P.O. Box B20, Doha
Tel: 413535
i
I MINISTRY OF ELECTRICITY AND WATER
P.O. Box 41, Doha
Tel: 326622 / 443222
49
APPENDIX 4
DR..A.WINGS
· I
REINSTATEMENT OF ROAD OPENINGS
Phase 1 Major Roads Road Crossings
,~-----------------------------------------------------------------------
c
- ~j - - - -
=== =-==tf=----
~.
CENTRAL RESC:RVATlmi CENTRAL R~SC:~VATION
/;0
I I
I
I :OOrnm
ml'T". .'1~: =csec.:r..:rse
1!!itu/Tlln'us sv,,"cces
io ~e sprQyeC w,:~
/ I /" I
) 200 mm cui ~oc~ ):);f\_S
to "" '/crJe:1 and ?crcilel
tcc~-coot !'mlJ js; c.~ end pcir.led ',,;\1\ toc~-coct
150,.,..", MOl
em:Jl.sion
SL:~-:cs.
·1 /
Sub-Qrcce su.-fece
to be prir:'\"~ w,:h ~C I S"b-grcco
Mil''IImum Dry OonSl:Y
95:<
?Iocd c:er..,ac!e~
)
"
in Icyc," riot
,xc!eiinc..; ISOI'!'.r';"I
[________________ ._A_p_p_e_nd_·_I~__4_____D_rO_v_/_in_g_S______~] ~
/ .." ' . ': '0'
REI NST ATE MENT OF ROAD OPE Nl NGS ./ :'. ". - .~;::'7'~
. ..:. .;;.~ ,."
.I ,~----~~------------------------------------------------~
I'
: I
I: ,
!. !
i
,
I
Ii
, I
CENI?,;.L R::SE::'NA"7"iON
I:I
j
:::DGE OF CAR~!AG2NAY EDGE O.=- C.AR:=?IJ...G"C'/VAY
II
I i
PLAN ARE.il. OF CARR!AG~WAY TO BE REINSTATED
K == I \ STAT E ~I E NT
r.,
rnase t~ c i 0 r Roo d s y
.-..._- - -_ ... --.--_ . . _------ ... _-_ .... ----- -_._- ._----- - - - . ._- -_.- ---- ._ . _ - - - - - - - - - -
, / / ./ " / / / 7 / / ' ( ~7"'7 / 7 .' 7 .7 ( r-:- / / / .' / / 7 Z Z ? / 7 Z " Z .7 / /
--
1..-
-- -
__ .
- -- .-- -- -- -
__ _ _ _ .
- -
__
- -- -
_ _ _ _ _ _ _ . _ _.
"- - .- - -.-
_ _ _ _ _ _ _ _ _ _
- - - - .- _
' 7 / / / / / / / / 7 / / / 7~~
======== <~~~;~;~~~~
I! ./9G",.m IOOr:1."T1
~mt.:lsJor.
to ':>e ~e,...~c::;1 Jtld ~crc:lel
tCCl<-C:;'ct Qn~ ~ci"te:: wa~ tcc\(--:=c~
150r-:r;- ~_!CI
elT'.ulsicn
St.::: - :cse
~.::e:n.:ls to ser:lce
REINSTATEMENT OF TRE~ICH
. '-----------------------------------------------------------------------------------~
~_______________A__p_p_e_n_d_ix__ 4_.____D_r_O_W_in_g__
S ______ ~] ~
&. .
RE; !\
;
S-: ;. T M
E ~ ~ T 0 FRO ADO PEN I NGS 4G::'~:::7~~
Phase 2 tA a 0 ( Rca d s - T r en c h (u n salon 9 car pic
;1 tttlP Yr' . '/
\ ".:'_~ 'V_1'.:ri\ ." •
'\...0 '-
-
,-,-
---_ .._ - - - - - - - - - - - -- -- - . - - -
..-.r:-,"'7~ ; ' -:-~ --:-;- - r-:" "":~"':~"'~. -.-0-~~,-~ r--i-~~ -: -: --~r:.-- ' ~~~. --~-- _:r_;-,~ .~ .- - - - -../:- - -
~-r:
r; /, / //, / / / .·/ /r-7-~:7 -~ 7 / .' /.. / / / 0/ / 7 . / - " /. ' / / . .', ",' / 0' . / / ' / / ( / / / 7, ..',/ . 7/ .' . > . /
,/ /. '" L/L / / _.' 1 I_ ,', L.....
/ . / _ /_L
/ L /_L.:.-.L
/ L......../..-.J....
/ I / I / I _
' / /__ / I / I /L ./---'--/ _7.
/ / L /' / .:......J
__
'-
.
.- '- -- ' - - -- -
,~ -L
-- - -- - - / -- -- .-- -- --- -- .- ,-_ L__-- -- - -- /-L.. .
I
i i
I
I I
i
E:)GE OF CARRiAGEWAY
~----------Ay,---------------------------------~
_________________R_E_IN_S_T_A-~IE-~-IE-N-T-O_F__T_R_E_N~C-H_R_U_N_S____________------~J
[ Appendix 4 - Drawings
J
4/4
,~ Ei t'i ST A "I EM E~J T OF ROAD
Minor Roads Road Crossings
/
':-'~'=-;}r",:~C' s-~r..;.:e'
/ :00 m""" c\,,:: :ccx. ~ojr",!.~
~:::> ~I') ·/~r:~CC~ ::"".c ~c/cl'el
':.~ ~ :.n~~r; A'~'.:"': I..(C:
:t\~ ~ci(\lo<1 ~i~~ ~cck-coct
i
I
: ~Cr:"".~ .5t..::::1- :'CS8
.l.lin,,,",um _ rj Cen"'tj
: C~;;
emUlSIon
95 __
\
Ptc.c~c de c!)m~l!c!e<S
;1"1 leye,... I"Ict
)
\
e.xceeeinty 1 :Cr."\m
~
i;et!cic'9 & ."~,,r.C
r:"'.c: :~cls to servic: e
Au:'.... ol7'Jes (~;..:i(-: [.'}4! n~s
TYPICAL R.'::INSTATENIENT
DETAIL TYPE 1
o
I
/
/90 ~" , , ,. "'o~.
I / _ _ _ _.--_----J~ ____
: ,
o
Nolo 2: 'Sharo ~~o exi3tjf"l~ (OOC cor.:IItruc:tion conJj~l::;
~t ¢ ::iil";;:! ~ Couf::l 0 of c.!pJ\ol~ laid en
.ub-Qrc~& then roinste\omel\\ Typ" \ sholl
ep:>ly. ;';1 olher typ,,' of con.t.ructio", .noll
TYPICAL REINSTATEtvlENT ~& r&'n~t:tcd in accorconce with Type 2
~n toil ur,le S~ "lh~""is& .pe<1 rio<! by
DETAIL TYPE 2 ':.he ro-oc eln9ir'lt!ier.
~
---
[
-----------------------------------------------~---------
---------------------------------
Appendix 4 Drawings ]
,
.=<EI,~STATEMENT OF ROAD OPENINGS
< •
Phases 1 & 2 ~lin 0 r Roads
Trench runs along carriageway
r~-------------------------------------------------------------~-----------------
)
, . 7 / ' .) (' . / ( ,/ (r / /) ) / ) (
I
! I
1 GlOm.,.. !
: ;tu."":'Iif'\eus su~ cc es
~ ~-grcc.
Ie :>e sprcy~ w,,~
tce~-c~ct emu~si.on
(
SU~-9roee
MInimum Or/ Cen,i~1
.' .L..,~~ 95;:
::>('" Oens Jty
1
/
~L.::-grcee ~u~~c~ -!.--I
)
) P!",eed &.
9S~
com~ccle-C
to ~~ ;:>n..,~ ,.i\h ),IC: (
(
01 ... ,_
. CCe_ '" c"",;>oc e
I d \
\
I
;("'; ~ .:yers .'\c~
n:HC:.-.C; 1~Cmm t( in Icy.'" nc:
exceeCinc; lS0..,m
(
1 ,~
5edt:;nQ dl n:rrcu"d Oecc;nl; .l<. SVrTo\:f\d
mt:: ~er.alS' ~o sel""'Jice IT.o!er.c13 ~o ser.tice
A\.::r-onijes re<::.uirenenls ':"vthori'J ~s reqvirem~n~
PHASE 2 REINSTATEMENT
NOl e 1: '.Vher ••• isl i"Q rood COMI/1Jc:ion ~nsislS or c .ingl~ cou/S~ or c.pho ll lokI on .ub -9rc~e :r, CI'l rei"gtctemont Typo I "noli QPp ly.
,:,,]1 other \ypus of co"str\lctlon sMoll co r~'r.• tC\ed In ~CCO(CC~C~ w;\n Type :>. detol! u" I ~.s oth~rwis~ •• ocir,ed by the Rood En91"eer.
") . The ·.id~~ 0' t~o ~r"I,ae 2 .,..eorirH~ c:>ur:l': IClnstotemer-.l will :>0 dclerminted by the Rood ~"t;.ne~r on on tl'drvid\Jot bosi, depe~don' upc n
~h. loc.:liol"l of ~he "JCr'lc!i 11"'1 tho rOQ~ . Howe .... or ~Mo mInImum wiC'th ot roil"slctlClmont will be Or\u lone wld!M ond in m..lny COlO will bo
(vii carriaQewoy "i<:I~ _
~______________A__p_p_e_n_a_'i _X__4_____D_r_O_W~i_n_g_S________~J ~
~C::!!\JSTATEMENT OF ROAD OPENINGS
Pert'Ylonent Reinstatement Of Paved Areas
.~~----------------------------------------------------------------~~--~~--~
I ~
, !,
I
c..ncret~ Fcvin~ Sic:.
! i
I :
I !
f I 50,."m Cleo" Sene 56,,<!j~~
I II ' S"Q-gr:~6
,\.(;ni,.,wr.o C"I Ccns, tl
i ! 95~
1 I
{I
i
I
;olcccC (J c: m:oc :cc
1 cX'c.eecin; 1 ~Cmr.'\
i
11
~ I
cec'd;"9 .!< surnund
IT".C h:ricl! :,:) St:f';~C: e
At,;:~OtitH~S re~uire~en~
L j
--~----------------------------------------------------------------------------~
~________________A_p_p~e_n_d_iX___4____D_r_a_V_;i_n_g_S______~) ~
n
2W
nf F UOIP q .7 mttr
_ Jln. pm 111
. '8" ..Ih~2 7P. 1
r l',;',.rw'·
-' , tt?---e._-"1'_'s
,--- ~ - -- .. -- .•
t : \ - ,•. ,.S, I,." ....
r' •• 2 • p :8i f.r !;dI"."C '. , . ' , 2 " ;' -
'\
~.
:C.
:J
B A o
"" rl>! ..z - .----- .- ""---- - , -.. ~.
-,
o
;u
~rJ;l
~
I
o I'
~~ <EJ o
0...
(f)
I
!
~+. ~ .-t~. ~
'"
,;~:,~;:,~:,~
._ .
~ -- --~ - - D -- -
-/
»
u I
o 0 0 MIl) 45' EXIT TAI'[I<$
c
3
--I
p-
-I
-0 ~J l::::::::J c...:. -.J 1-: -' , ~ c_::=.J ~ r:::::=;J ~ c:::=l c:::::=J r==J £::::=l ~~ [ .. . :.-:-
. ....,:.1 c:::::::=I C):.J l..:-::) c:::::.=.l ":"=.::J r::::::=.J r==:::.J t-.....: :"'"J r::- ~ L.:....-...J I.':"~:.J l '':''':':'.1 c-:-~, c_- _) I. ' I \. _l l ., ,I l • I
f'1
(t) ;u
:J ID ~
0, G.OIA (MII-t) ..0 rrl
X
c Z
..p..
1=================== ===============_ I. __ r_ 1- ___ : '_-_ =-:::='_= _'=--=-::. _-_~:=: ~ : . -,
(l)
4
~-El ~~l
EDGE OF CI\RRIAGEWAY
~+- -I 3
(])
...,0
:J
......
r.iil~
~ B;> ~
;0
-
(/)
o
---. tJj~ 0
o o
»
-, 0
~ A 13
k- - -".
:J (f) 0
to -+- --0
(f)
:J r'l
to Z
- - - - - -- -----, --- ------, -
II u Z
C)
SHin,) f)lslonco MI" No of 519'" (j)
01 fi. ~I SI~n I" Auv"nco 01
In Advo"ce 01 Roou ... or~9
TruHlc 51'00<1 Roo<.lworlui Spocud 0\ [<luol lenglh
KPH I~blr ,,:I Inl.,vol. (III)
--------1-------- .- - - -.- - -.- .----- - - -
Up 10 15 Nol lo s. thu" 50 2 10 - )0
45 - 60 50 - 1'20 2. or J )0 - 40
120 JOO J or 1 4() - 50
..p.. 60 -
Ovor 80
BO
JOO - 500 4 50 - 00
'"
1O
CD :J
(f)