Professional Documents
Culture Documents
net/publication/320474751
CITATIONS READS
2 35,098
1 author:
Lutfi Al-Sharif
University of Jordan
155 PUBLICATIONS 1,138 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Lutfi Al-Sharif on 14 December 2017.
Abstract
This article discusses the elevator traffic design for high rise buildings. It starts
by listing the factors that distinguish high rise buildings from low rise buildings in
terms of traffic design as well as the technologies required to address the
problems arising from the high rated speeds necessary for high rise buildings.
The terms sector, zone and stack are defined at the beginning as they are critical
to the operation of high rise buildings. The use of elevators for the evacuation for
high rise buildings is then discussed along with the latest thinking in this area.
Two design approaches are then introduced for the design of elevator
traffic systems for high rise buildings. The first approach is the use of simulation
packages in order to develop a selection chart based on the total building
population and the number of floors above the main entrance. It identifies the
two most influential demand factors that affect the design output for vertical
transportation systems in buildings. These are the total building population and
the number of floors served above the main terminal. These are then used to
develop general guidelines to find the most optimum configuration for every pair
of such parameters. This is then transformed into a two-dimensional chart that
can visually aid the designer into using the best configuration for a building.
The second approach is based on the use of calculation and then
simulation aided with rational design rules. Six rules are introduced and
discussed for the design of high rise buildings including stacked buildings with
sky lobbies.
1. INTRODUCTION
Traditionally, the design of a vertical transportation system for a certain building
is based on the knowledge of the following parameters:
1. Building population.
2. Passenger arrival patterns.
3. Building usage (office, residential, hospital…).
4. Number of floors.
5. Car park usage.
6. Location of special floors (meeting floors, restaurants…).
Page 1 of 22
Lift Report 2017; 43(5): 46-62
3. Identifying the group control algorithm that will allocate the landing calls to
each of the elevators in a certain group (e.g., conventional group control).
4. Identifying the need for double decker elevators where appropriate ([1], [2]
and [3]).
Page 2 of 22
Lift Report 2017; 43(5): 46-62
refer to the floor from which all the incoming traffic originates. Another term that
is commonly used is the main terminal.
This approach is limited however to building heights of 40 to 50 floors only
and does not include the use of sky lobbies and stacks. This approach is
discussed in detail in section 8 of this article and mainly based on reference [6].
Buildings with more than 50 floors require a completely different approach (e.g.
sky lobbies) and are addressed in part 2 mainly based on reference [7].
• They do not provide an explanation for the rationale underlying the rule.
• Following on from the previous point, if the assumptions on which the rule
was based change, the rule cannot be changed accordingly.
• Rules of thumb cannot be used to develop a systematic design
methodology.
The aim of this part is to develop a set of rules that can guide the designer
throughout the elevator traffic system design process for high rise buildings.
Solely for clarification in this piece of work, a high rise building is defined as any
building that has floors more than those that can be accommodated in a single
zone (thus requiring multiple zones or a sky lobby, both of which are defined in
section 2 of this document).
The rules will be based on rational reasoning, whereby the rationale on
which the rule is based will be clearly stated. This ensures that where the
underlying assumptions change, the rule changes accordingly. In addition, the
rules are fully transparent showing the threshold values of the different
parameters for the different rules. The designer can thus change these
thresholds as he/she sees fit.
It will be assumed that the designer starts with a calculation that will
provide a starting point for the simulation. The design process followed in this
method has been based on the methodology found in [8]. The round trip time
calculation using equations has been based on the equations found in [9], [10]
Page 3 of 22
Lift Report 2017; 43(5): 46-62
and [11]. Under certain situations, it is necessary to use the Monte Carlo
simulation method to evaluate the round trip time [12]. The design process then
moves to simulation in order to fine tune the design. Finschi [13] states that
advanced software packages are used nowadays in the design process, rather
than simple calculation methods.
It will also be assumed that the designer possesses the required skills to
carry out the design of a single zone elevator traffic system. The design of a
single zone elevator traffic system is considered to be beyond the scope of this
document. In effect, the design of a single zone elevator traffic system is the
basic building block that will be re-used in all high rise building designs.
This second approach is presented in detail in part 2 of this article and is
based on reference [7]. It is based on definition of the average waiting time and
average travelling time that are different to those defined in [14].
Sector: A group of floors (usually, but not necessarily, contiguous) that are
grouped together in the controller software and are served by one specific
elevator in each round trip. The allocation of a sector to an elevator and the
sector’s composition are not necessarily fixed and can be dynamically changed
from one elevator trip to the next.
Stack: A stack is a group of contiguous floors that are located away from the
main building entrance and is served by a sky lobby. A stack can be thought of
as a building that has been placed (or stacked) above other stacks. A stack can
contain a number of zones.
Page 4 of 22
Lift Report 2017; 43(5): 46-62
1. The target handling capacity for the local zones shall be more than or
equal to 12% and the target interval less than or equal to 30 seconds.
2. The target handling capacity for the shuttle systems shall be more than or
equal to 15% and the target interval less than or equal to 20 seconds.
3. Top down sky lobby design systems are to be avoided.
4. There shall be no more than 8 elevators in each group.
5. The number of floors in a local zone should be around 15 floors.
6. The rated car capacity should be 1600 kg (20 persons).
7. The rated car capacity of double deck elevators should be 1600/1600 kg
or 1800/1800 kg.
8. When used, a shuttle elevator shall serve no more than three local zones.
9. The passenger journey shall comprise no more than one transition
between different elevator systems (e.g., a shuttle and then a local zone).
10. For each elevator that forms part of a local zone it shall serve no more
than two floors (i.e. the ratio of floors to elevators in the local zone should
be in the ratio of 2:1).
Another rule of thumb suggested by Scott [13] attributed to Strakosch [16] is the
rule whereby one elevator is needed for every 225 people in an office building.
Jochem Wit [17] presents a number of building design examples on the use of
destination group control to remove the need for zoning a building. Destination
group control has been used as a means of segregating of the different modes of
traffic in the building.
In [6] it is shown that the two most important parameters that influence the
design of a high rise building are the number of floors above the main entrance
and the total population.
An expert system is described in Alexandris [18]. It uses forward and
backward chaining inference mechanisms in order to accept or reject certain
solutions. It has a set of if-then rules. An example of one of the rules is:
Page 5 of 22
Lift Report 2017; 43(5): 46-62
If loading is high AND passenger waiting time is normal AND system cost is
reasonable then accept solution.
He also points out that a user would like to query the software as to how the
decision was made for a certain design. He also discusses a rule base in which
the user can modify or amend existing rules or add new ones.
In [19] Barney presents a general overview of vertical transportation
systems in tall buildings. The paper contains clear definitions of low, mid and
high rise, tall and very tall and skyscrapers. It also contains an excellent
overview of the different arrangements of high rise design buildings (example:
Petronas Towers).
Browne & Kelly [20] present an overview of the simulation carried out to
assess the performance of the elevator traffic system for two of the buildings in
the World Trade Centre.
Caporale [21] suggests normalising the average journey time (AJT) in
order to allow comparison between building design and with industry standards.
He suggests dividing the average journey time by 5 minutes (which is used as
the basis for the arrival rate design) and setting a threshold of 25% (i.e., 75
seconds).
Fortune [22] states that the key to efficient high rise design is to stack the
zones on top of each other. He also suggests that a two-minute headway should
be achieved for the shuttle elevators. He also lists the seven technical problems
that face any high rise design. He then outlines a general methodology for even
going higher by effectively stacking buildings on top of each other (50 to 60 floor
high buildings stacked on top of each other).
Howkins [23] classifies buildings further as follows:
• 40-60 floors denoted as tall buildings, of which many exist and can provide
information and feedback.
• 60-80 floors denoted as very tall buildings, of which a good number exist
and can provide information and feedback.
• 80+ floors denoted as super-high-rise buildings, of which not many exist
(less than 20).
• 150+ floors denoted as super-high-rise/super-volume buildings, of which
none exist at present.
Mitric presents in [24] and [25] the concept of a total useful area in the building
and presents a set of curves that peak at a certain arrangement.
Page 6 of 22
Lift Report 2017; 43(5): 46-62
Powell uses the term banking (meaning zoning) and uses dynamic
programming to decide on the optimum arrangement ([26] and [27]).
3. The margins are very tight and hence any changes are very costly later in
the project.
4. The options available from control systems are very large. Features that
produce small incremental improvements for low rise building can make
the difference between success and failure for a high-rise building.
Examples of such features are traffic pattern recognition, self-learning and
adaptation to different passenger traffic flows.
4. The pressure difference between the topmost floor and the lower-most
floor is also an issue and has an effect on human comfort. In some cases
the elevator car internal pressure is controlled. Lauener [29] expresses
the view that the pressure change problems effectively limit the travel
distance to 300 m in one journey.
Page 7 of 22
Lift Report 2017; 43(5): 46-62
An earlier piece of work by Klote [30] presented a methodology for calculating the
evacuation time from the building using elevators. It derived a set of equations
from first principles that are very similar to those used to calculate the round trip
time for the basic elevator traffic design process.
A groundswell of opinion has been forming with the view that elevators must be
used for evacuation of buildings and that most, if not all elevators, must be
designed to be able to operate for a specified period of time following an
emergency ([31], [32], [33]). The view is that total evacuation time should be in
the range of 15 to 20 minutes. Evacuation by stairs will remains preferable for
low rise buildings [32].
The Council on Tall Buildings and Urban Habitat (CTBUH) identified the following
top five priorities for the research in the area of “Circulation, Vertical
Transportation and Evacuation” (Oldfield et al., [34]). It is worth noting that all of
the top five priorities listed below are related to the topic of evacuation (shown
italicised).
Page 8 of 22
Lift Report 2017; 43(5): 46-62
It is expected that as the number of high rise buildings increases and as the
elevator hardware technology advances in order to allow the elevator to fully
operate during emergency conditions that the full or partial evacuation by
elevators will become a building standard requirement.
a. Evaluating the total evacuation time out of the building (denoted as egress
time) will become one of the user requirements for any traffic system
design in tall buildings.
b. The traffic system designer will have to ensure that the vertical
transportation system meets the egress time requirement as well as the
traditional ingress requirements. It has long been recognised that the
elevator system can carry as much as 50% extra handling capacity during
down peak as much as up-peak traffic, and this is a factor that will ensure
that elevator traffic system will not have to be enlarged to meet this
requirement.
Siikonen and Hakonen [35] carried out a simulation into the use of stairs only,
elevators only and both stairs and elevators in the evacuation of tall buildings. A
number of important conclusions are drawn from the study:
1. The study concludes that for buildings with fewer than 15 floors the use of
stairs only for evacuation is faster than using elevators only. Thus it is
only worth considering the use of elevators for evacuation for building with
15 floors or more.
2. The study also shows that it is not necessary to artificially zone or sector
the building during evacuation in order to efficiently evacuate passengers
out of building. The modern group control systems automatically optimise
the operation and thus minimise the evacuation time. It is also not
necessary to encourage passengers to gather on every other floor or
every third floor (in refuges) in order to reduce the number of stops in the
round trip and thus reduce the evacuation time.
Page 9 of 22
Lift Report 2017; 43(5): 46-62
3. The third and most important conclusion relates to the expected target
evacuation time. “If elevators are used in mega high-rise buildings during
an emergency situation, evacuation times can drop to 15-30 minutes
instead of [the current value of] 2-3 hours. In these buildings, shuttle
elevators may become a bottle-neck during the evacuation and down-
peak. Handling capacity of a shuttle elevator group with only two stops
can be considerably increased with double-deck or triple-deck elevators.”
(Siikonen and Hakonen, [35]).
Fortune [31] presents the concept of the lifeboat elevator, whereby the elevators
and the elevator shafts are fully equipped to continue operating for the full
evacuation of the building within a specified period of time (e.g., less than 60
minutes). In order for this to be possible, sufficient emergency power must be
available in order to operate the designated lifeboat elevators. A new phase 3
would be added to the standard phase 1 and phase 2 of the emergency
operation. Passengers will congregate on designated refuge floors, and the
lifeboat elevators will shuttle between each refuge floor and the building entrance
in order to complete the evacuation of the building tenants. Wit [36] presents an
overview of the work being carried out in the Netherlands to incorporate
evacuation by elevators in the national building code.
Guidelines have been provided in a CTBUH [37] study on the use of elevators for
building evacuation.
To sum up, the effect of such a requirement (i.e., the use of elevators for the
partial or full evacuation of a building using elevators) would be to transform the
elevator traffic design process for medium and high rise building such that the
egress time becomes an additional user requirement. Moreover, it is also
expected that the elevator group control system would evolve in order to meet
certain evacuation strategies.
Page 10 of 22
Lift Report 2017; 43(5): 46-62
the lobby increase. Thus, it is posited that the two most important parameters
that affect the design of the vertical transportation system are:
1. The number of passenger arriving in the lobby in the peak five minutes.
2. The number of floors above the lobby (assuming they are all populated
with equal populations).
1. The total building population (assuming a constant arrival rate of say 12%
or 15% of the building population in the busiest five minutes).
In effect this states that where two buildings have the same total populations but
a different number of floors above the lobby, then the demand of the higher rise
building will be more onerous. Moreover, where two buildings have the same
number of floors above the lobby, but different total populations, then the
demand of the higher population building will be more onerous.
Obviously, other parameters will have an effect, but are less important.
For example, the floor to floor height in an office building will generally be in the
order of 4 m and will not deviate dramatically from that figure for a real life
building (3.6 to 4.2 m). In a similar manner, passenger transfer times will always
be in the range of 1.2 second per passenger, and will not deviate dramatically
from this figure. Passenger transfer time is the time taken by one passenger to
board (or alight) from the elevator.
The analysis in this section will be limited to the following for simplicity and
brevity:
2. Up peak traffic pattern (incoming traffic): The traffic design will be based
on an up-peak traffic pattern (incoming traffic into the building from the
lobby).
Page 11 of 22
Lift Report 2017; 43(5): 46-62
3. A limit has been placed on the number of floors above the lobby of around
50 floors. Above 50 floors the classical design of travelling ‘direct-from-
ground’ ceases to be feasible due to the increase in core space used for
elevators, and sky lobbies have to be introduced. This is addressed in the
second part in this article and in [7].
4. Repeat the design procedure in 3 above until designs have been found for
all the 34 combinations.
5. The results are then plotted on a chart to show the most suitable
configuration for each combination.
The following numbers of floors above lobby have been used: 10 floors, 20
floors, 30 floors and 40 floors.
The following numbers of total building populations have also been used
based on an arrival rate of 15%: 500, 1000, 1500, 2000, 2500, 3000, 3500,
4000, 4500 and 5000 persons. These would be equivalent to total populations of
625, 1250, 1875, 2500, 3125, 3750, 4375, 5000, 5625 and 6250 persons
respectively at an arrival rate of 12%. As far as the elevator system is concerned
a total building population of 2000 person with an arrival rate of 15% is identical
to a building with a total building population of 2500 person with an arrival rate of
12%. In both cases, 300 passengers will arrive in the lobby in the busiest five
minute period.
Page 12 of 22
Lift Report 2017; 43(5): 46-62
1. A basic traffic analysis based on the interval and the handling capacity is
carried out to determine the required number of elevators with their
capacity and speed. A target interval of 30 seconds or less is used. An
arrival of 15% in the busiest five minutes is used along with the total
building populations of 500/1000/1500/2000/2500/3000/3500/4000/4500
and 5000 persons.
2. A further analysis is then carried out to assess the average waiting time,
average transit time and the average time to destination. The average
waiting time is the average time spent by passengers waiting for the
elevator in the lobby. The average transit time is the average time spent
travelling in the car by the passengers. The average time to destination is
the sum of the average waiting time and the average transit time. A target
of 30 s for average waiting time, 60 s for the average transit time and 90 s
for the average time to destination has been used based on the current
industry de facto standard of 30/60/90 [41], [42].
Elevate software revision 7.18 TC has been used for the traffic analysis above
[42]. Default values within elevate have been used unless otherwise specified
below. Step 1 above is carried out using the enhanced up peak calculation
mode. Step 2 above is carried out using the simulation mode with the Group
Collective mode (up peak 2). Under this simulation mode, the system is exposed
to a constant arrival of 15% for 15 minutes with pure incoming (up peak) traffic
only.
The following values have been assumed for traffic analysis parameters:
Page 13 of 22
Lift Report 2017; 43(5): 46-62
The example below shows how one configuration was arrived at using
calculation and then simulation.
Example 1
The following example is used to illustrate the design process.
Let us assume a building with a total population of 2000 persons equally spread
over 10 floors above the lobby (200 persons per floor). The traffic analysis is first
carried out using calculation to arrive at the interval.
Using 8 elevators rated at 2000 kg (26 persons) and running at 2.5 m/s, gives an
interval of 20.9 seconds at a car loading of 80.5%. Under the classical
assessment criterion of using the interval only, this arrangement would be
satisfactory and would provide an excellent level of service.
A second assessment is then carried out to assess the performance from
the point of view of the passenger. Under this scenario, the performance shows
that under up peak (incoming traffic) conditions at a constant arrival rate of 15%
for a duration of 15 minutes, the average waiting time, average transit time and
average time to destination are 105.1 s, 102.5 s and 207.6 s respectively. These
are unacceptable figures and well exceed the industry de facto standard of 30 s,
60 s, 90 s (average waiting time, average transit time, average time to
destination) [43].
Page 14 of 22
Lift Report 2017; 43(5): 46-62
One method to reduce the transit time and hence the time to destination is to
zone the elevators during the morning up peak. Zoning restricts one group of the
elevators to serving a group of lower contiguous floors and the other group of
elevators to serving a group of upper contiguous floors.
The results of such zoning are shown in Table 2 below. The zones have
been set to an equal number of floors in this case (lower zone serving 1 to 5;
upper zone serving 6 to 10; all elevators serving Ground). This is not necessarily
the optimum solution and it is generally accepted that the lower zone could cover
a larger number of floors to account for the fact of the longer distance the
elevator serving the upper zone would have to travel.
The zoned solution with eight elevators in total, whereby four elevators
serve the lower zone (1 to 5) and the other four elevators serve the upper zone
(6 to 10) provides an excellent performance. However, dropping the number of
total elevator to seven provides a good performance that is within the 30/60/90
criterion, even though the average transit time slightly exceeds the 60 second
mark. Using six elevators in total exceeds the 30/60/90 criterion. Hence using
seven elevators in two zones is the selected configuration that uses the smallest
number of elevators while approximately meeting the 30/60/90 criterion.
The analysis above has only been based on the morning up peak. It is generally
accepted that if the configuration meets the 15% morning arrival rate, it can
comfortably meet a mixture of inter-floor lunchtime patterns. This however must
be confirmed for any specific building.
Page 15 of 22
Lift Report 2017; 43(5): 46-62
8.4 Results
The design methodology followed in the example in the last section has been
used as the basis for compiling the data in the graph shown in Figure 1.
Page 16 of 22
Lift Report 2017; 43(5): 46-62
No feasible
solution
Figure 1: Graphical representation of the most suitable elevator configurations for the various combinations of
total building population and number of floors.
Page 17 of 22
Lift Report 2017; 43(5): 46-62
The following conclusions can be drawn from the graph shown in Figure 1:
1. The number of passengers arriving in the lobby in the busiest five minutes
is an important factor in deciding the design of the vertical transportation
system that can achieve the required performance. Based on either a
15% arrival rate or 12% arrival rate, this can be expressed as the total
building population. In fact that x-axis could be expressed as the number
of passengers arriving in the lobby in five minutes. However, it is more
convenient to use the total building population and assume a certain
arrival rate as a percentage of that population (e.g., 12% or 15%).
3. It has been assumed that the lowest realistic floor population for an office
building is 50 persons per floor. This results in the shaded area that is
labeled as improbable floor areas. For example, for a total building
population of 1000 persons over 40 floors is an improbable combination
as it implies an unrealistic floor population of 25 persons.
4. It can be seen from the graph that the maximum number of floors that can
be served by a single group of elevators in one zone is around 16 floors.
This confirms the widely known rule of thumb in the industry.
9. CONCLUSIONS
The vertical transportation design for a building requires the finding a suitable
elevator configuration. Each configuration specifies the number, speed and
Page 18 of 22
Lift Report 2017; 43(5): 46-62
capacity of the elevators in each group. It also specifies the grouping of the
elevators and floors into zones, as well as any special features in terms of the
use of double decker elevators and group control algorithms.
A number of relevant issues have been discussed in the article including
the use of elevator for the evacuation for high rise buildings, the definition of
sectors, zone and stacks, and the special features that make the design for high
rise buildings much more involved as compared to low rise buildings.
Two approaches have been suggested for the design of elevator traffic
systems for high rise buildings. The first approach is based on using simulation
to develop a two-dimensional chart that depends on the building population and
the number of floors above the main entrance. The second approach is based
on applying rational rules to the results of calculation and simulation in order to
arrive at suitable designs for the elevator traffic systems for high rise buildings.
The two most important parameters that drive demand in a vertical
transportation system in a building are the total building population and the
number of floors served above ground. For a certain total building population,
the arrival rate for the busiest five minutes results in a certain number of
passengers arriving in the lobby in a five-minute period. Each configuration has
been arrived at by using the classical performance parameter, the interval, with a
target value of 30 seconds. The analysis is then also carried out using simulation
to assess the passenger-centric parameters of waiting time, transit time and total
time to destination with a target value of 30 seconds, 60 seconds and 90
seconds respectively. Using the two demand parameters and the results from
the analysis, a chart has been developed that can be used to guide the selection
of the best vertical transportation configuration.
REFERENCES
[1] Fortune J W. Modern Double-Deck Elevator Applications and Theory.
Elevator World, 1996;44(8): 63.
[2] Peters R D, Mehta P and Haddon J. Lift Traffic Analysis: General
Formulae for double deck lifts. Building Services Engineering Research
and Technology 1996; 17(4): 209-213.
[3] Al-Sharif L, AlOsta E, Abualhomos N and Suhweil Y. Derivation and
Verification of the Round Trip Time Equation and Two Performance
Coefficients for Double Deck Elevators under Incoming Traffic Conditions.
Building Services Engineering Research and Technology 2017; 38(2):
176-196.
[4] Al-Sharif L. Introduction and Assessing Demand in Elevator Traffic
Systems (METE I). Lift Report 2014; 40(4): 16-24. July/August 2014.
[5] Al-Sharif L. Calculating the Elevator Round Trip Time for the Most Basic
of Cases (METE II). Lift Report 2014; 40(5): 18-30. Sep/Oct 2014.
[6] Al-Sharif L and Seeley C. The effect of the building population and the
number of floors on the vertical transportation design of low and medium
rise buildings. Building Services Engineering Research and Technology
2010; 31(3): 207-220.
Page 19 of 22
Lift Report 2017; 43(5): 46-62
Page 20 of 22
Lift Report 2017; 43(5): 46-62
[21] Caporale B. Editor’s Overview, Calling all Cars and Traffic Analysts.
Elevator World 2004; 52(9): 4. September 2004.
[22] Fortune J. Mega High Rise Elevators. Elevator World 1995; 43(7): 63-69.
July 1995.
[23] Howkins R. Elevator Core Areas, A comparison with Existing Structures
and those of the Future. Elevator World 1998; (11):58-64. November
1998.
[24] Mitric S. Elevator Systems for Tall Buildings, Part I, Single Mode Elevator
Systems. Transportation Science 1975; 9(1): 54-73. February 1975.
[25] Mitric S. Elevator Systems for Tall Buildings, Part II, Mixed Mode Elevator
Systems. Transportation Science 1975; 9(1): 74-85. February 1975.
[26] Powell B. Elevator Banking for High Rise Buildings. Transportation
Science 1975; 9(3): 200-210.
[27] Powell B. Optimal Elevator Banking under Heavy Up-Traffic.
Transportation Science 1971; 5(2): 109-121.
[28] Wit J. Elevator Planning for High-Rise Buildings. Deerns Consulting
Engineers Publication, The Netherlands, Amsterdam, www.deerns.com.
Access on 30th July 2017.
[29] Lauener J. Notes on Elevatoring Design. Elevator World 2008;
56(10):128-135.
[30] Klote J H. A method for calculation of elevator evacuation time. J. of Fire
Prot. Engr., 1993; 5(3): 83-95.
[31] Fortune J W. Emergency Building Evacuations via Elevators, CTBUH
2010, Remaking Sustainable Cities in the Vertical Age, 3rd to 5th February
2010, Mumbai, India.
[32] Barney G C. Behaviour of Lift and their use for Evacuation, Elevatori
2002; 31. November/December 2002.
[33] Barney G C. Emergency Egress (note to the editor). Elevator World,
March 2005; 53(3).
[34] Oldfield P, Trabucco D and Wood A (eds.). Roadmap on the Future
Research Needs of Tall Buildings. Council on Tall Buildings and Urban
Habitat: Chicago. 2014.
[35] Siikonen M L and Hakonen H. Efficient Evacuation Methods in Tall
Buildings. Elevator Technology 12, 202; 12: 237-246. Proceedings of
Elevcon 2002, Milan, Italy, June 2002, IAEE.
[36] Wit J. Evacuating Using Elevators, Enhancing the CTBUH Approach for
the Dutch High-Rise Covenant. Elevator Technology 18, 2010; 18: 419-
430. Proceedings of Elevcon Lucerne 2010, June 2010, IAEE.
[37] CTBUH. Emergency evacuation elevator systems guideline. Council on
Tall Buildings and Urban Habitat, 2004. 47 pages.
[38] Al-Sharif L and Al-Adem M D. The current practice of lift traffic design
using calculation and simulation. Building Services Engineering Research
and Technology 2014; 35(4): 438-445.
[39] Strakosch G. The Vertical Transportation Handbook. John Wiley & Sons,
1998.
Page 21 of 22
Lift Report 2017; 43(5): 46-62
Page 22 of 22