Cumulative Cost Curve Percent Sample Data
Cumulative Cost Curve Percent Sample Data
Execution $890,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
Monthly % of cost
Control $84,000 $1,680 $1,680 $1,680 $1,680 $1,680 $4,200 $4,200 $4,200 $4,200 $4,200 $4,200
Monthly % of cost 2% 2% 2% 2% 2% 5% 5% 5% 5% 5% 5%
Close $24,000 $0 $0 $0 $0 $0 $0 $0 $0
Monthly % of cost
Cumulative Plan Cost: $4,080 $8,160 $14,640 $25,920 $40,400 $60,600 $80,800 $109,000 $137,200 $173,400 $209,600
Actual Cost: $3,840 $5,580 $7,100 $9,900 $13,000 $21,600 $18,000 $26,800 $23,700 $34,000 $32,000
Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005] Page 1 of 9 Printed on: 02/21/2023
Put your Organization
Project Cumulative Cost Data Name Here
Cumulative Actual Cost: $3,840 $9,420 $16,520 $26,420 $39,420 $61,020 $79,020 $105,820 $129,520 $163,520 $195,520
Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005] Page 2 of 9 Printed on: 02/21/2023
Put your Organization
Project Cumulative Cost Data Name Here
Instructions:
Before you enter any data, do the following:
- Determine the total cost of each project phase
- Determine the number of reporting periods that each project phase will last (e.g. 3 months)
- Determine (or guestimate) the percent of cost that will occur during each reporting period for each phase
To enter planned project values (note: all data entry cells are white):
1. Enter project name in the space provided
2. Enter reporting periods in cells D4 through AA4 (e.g. weeks, months or quarters as dates (shown) or month1, month2, etc.)
3. Enter cost of each project phase under Planned Phase Costs
4. Enter the % of phase cost planned for each Reporting Period in the white cells provided. (see Initiation and Planning for
an example of how this is done). Leave unused cells blank. Planned cost per period displays above the % you entered.
Cells in column AB will be red until the total percent for the project phase equals 100%.
5. Enter time unit of the project. This is "Months" in the example. This is used as a label on the chart in the next tab.
6. Planned cost per reporting period display in the 'Budgeted Cost per Reporting Period" line
7. Planned Cumulative Cost displays in the "Cumulative Planned Cost" line
8. Enter Actual Costs per reporting period as the data become available. The cumulative actual cost will display in the
Cumulative Actual Cost line. It is normal for the last correct cumulative cost figure to repeat through all succeeding
months. Do NOT delete these numbers!
9. Modify the graph in the Cumulative Cost Curve tab as explained on that sheet
Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005] Page 3 of 9 Printed on: 02/21/2023
Put your Organization
Project Cumulative Cost Data Name Here
6/06 7/06 8/06 9/06 10/06 11/06 12/06 1/07 2/07 3/07 4/07 5/07 6/07
$8,000 $0 $0 $0 $0 $0 $0
5%
$4,200 $4,200 $4,200 $4,200 $4,200 $4,200 $4,200 $4,200 $4,200 $4,200 $3,360 $2,520 $2,520
5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 4% 3% 3%
$56,700 $93,200 $93,200 $137,700 $182,200 $137,700 $93,200 $93,200 $48,700 $10,200 $11,760 $8,520 $6,120
$266,300 $359,500 $452,700 $590,400 $772,600 $910,300 $1,003,500 $1,096,700 $1,145,400 $1,155,600 $1,167,360 $1,175,880 $1,182,000
$49,000 $95,000 $97,000 $122,000 $166,000 $102,000 $111,000 $98,000 $62,000 $9,550 $9,900 $7,890 $5,500
Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005] Page 4 of 9 Printed on: 02/21/2023
Put your Organization
Project Cumulative Cost Data Name Here
$244,520 $339,520 $436,520 $558,520 $724,520 $826,520 $937,520 $1,035,520 $1,097,520 $1,107,070 $1,116,970 $1,124,860 $1,130,360
Template: Cumulative Cost Curve - Percent [Rev 1.0 3/29/2005] Page 5 of 9 Printed on: 02/21/2023
My Project
$1,400,000
$1,200,000
$1,000,000
Cumulative Cost
$800,000
$600,000
$400,000
$200,000
$0
05 05 05 05 05 05 06 06 06 06 06 06 06 06 06 06 06 06 07 07 07 07 07 07
7/ 8/ 9/ 10/ 11/ 12/ 1/ 2/ 3/ 4/ 5/ 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 2/ 3/ 4/ 5/ 6/
Months
Initial Setup
Once you have entered all of your Planned data in the Raw Data tab, do the following:
- Click once on the chart to select it and then click Chart on the toolbar
- Click Source Data and then Series
- Click Budgeted Cost and then in the Values box change "Raw data" to inlcude only the columns in which you have entered
For example, if your project will last 12 months you will have planned data in columns D through O, so the value for Raw
be ='Raw Data'!$D$26:$O$26
Note: this chart is easily added to a Word document. Just click on the chart, right click and Copy, then Paste into the Word do
Budget Cost
Actual Cost
ar
n which you have Actual Cost data. In this
Instructions:
Before you enter any data, do the following:
- Determine the total cost of each project phase
- Determine the number of reporting periods that each project phase will last (e.g. 3 months)
- Determine (or guestimate) the percent of cost that will occur during each reporting period for each phase
To enter planned project values (note: all data entry cells are white):
1. Enter project name in the space provided
2. Enter reporting periods in cells D4 through AA4 (e.g. weeks, months or quarters as dates (shown) or month1, month2, etc.)
3. Enter cost of each project phase under Planned Phase Costs
4. Enter the % of phase cost planned for each Reporting Period in the white cells provided. (see Initiation and Planning for an
example of how this is done). Leave unused cells blank. Planned cost per period displays above the % you entered.
Cells in column AB will be red until the total percent for the project phase equals 100%.
5. Enter time unit of the project. This is "Months" in the example. This is used as a label on the chart in the next tab.
6. Planned cost per reporting period display in the 'Budgeted Cost per Reporting Period" line
7. Planned Cumulative Cost displays in the "Cumulative Planned Cost" line
8. Enter Actual Costs per reporting period as the data become available. The cumulative actual cost will display in the
Cumulative Actual Cost line. It is normal for the last correct cumulative cost figure to repeat through all succeeding month
NOT delete these numbers!
9. Modify the graph in the Cumulative Cost Curve tab as explained on that sheet
Initial Setup
Once you have entered all of your Planned data in the Raw Data tab, do the following:
- Click once on the chart to select it and then click Chart on the toolbar
- Click Source Data and then Series
- Click Budgeted Cost and then in the Values box change "Raw data" to inlcude only the columns in which you have entered
For example, if your project will last 12 months you will have planned data in columns D through O, so the value for Raw
be ='Raw Data'!$D$26:$O$26
Note: this chart is easily added to a Word document. Just click on the chart, right click and Copy, then Paste into the Word do